This amendment modifies an invitation for bids for the Coos Bay North Jetty Repair project. The modification updates the period of performance, extending both the final completion date and contract end date by one month for the base award. It also extends the final completion date for optional line items by one year if exercised. The project scope involves repairing approximately 2,000 feet of the north jetty trunk and head above the -18 foot elevation, with an estimated stone volume of 24,430 cubic yards. Optional repairs include 3,000 additional feet of the trunk and root with a stone volume of 33,770 cubic yards. The U.S. Army Corps of Engineers, Portland District is the contracting agency. The estimated value of the contract is between $25-100 million. The period for stone placement is April 1 through October 31, 2022 for the base and April 1 through October 31, 2023 for any options.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1) Update Section 01 11 00.00 25 Page 3,
2) Update Section 35 31 26.40 25, and
3) Update FAR Clause 52.211-10.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N21B0022
X 9B. DATED (SEE ITEM 11)
28-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Aug-2021
CODE
USACE, PORTLAND DISTRICT
333 SW 1ST AVE
PORTLAND OR 97204
W9127N 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127N21B0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The contractor shall be required to (a) commence work within TEN (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work for use not later than September 30, 2023 October 31, 2023 for the Base (Reach 1 and Reach 2). If any optional CLINs are awarded, then the associated work between Reach 3 and Reach 5 is to be completed no later than October 31, 2024. The time stated for FINAL CONSTRUCTION PHYSICAL COMPLETION shall include physical completion of all site work, final cleanup of the premises, and demobilization.
FINAL CONSTRUCTION PHYSICAL COMPLETION DATE for all jetty work: September 30, 2023 October 31, 2023 for the Base CLINs and September 30, 2024 for all Optional CLINs.
CONTRACT END DATE: December 31, 2023 if only the Base is awarded or December 31, 2024 if any Optional CLINs are awarded.
The time stated for CONTRACT END DATE shall include submission and approval of all final remaining work documents to include closeout submittals, As-Constructed Drawings, and all other requirements submitted and approved. (See Section 01 33 00 SUBMITTAL PROCEDURES and 01 78 39.10 25 AS-BUILT DRAWINGS).
(End of clause)
(End of Summary of Changes)
File details come from the government source that posted it. Updated .