B.08_W9127N21B00180001-Bid Validity 90 Days.pdf

PDF 379 KB Posted

Attached to
Rogue River Mechanical Dredging 2021
Solicitation number
W9127N21B0018
Issued by

About this file

This document provides an amendment to an invitation for bids for mechanical dredging services on the Rogue River in Gold Beach, Oregon. Key details include:

The amendment changes the bid validity period from 60 days to 90 days from the bid due date. It also requires bidders to submit all inquiries regarding the solicitation through the ProjNet-Bidsm website. Bids are due no later than 2:00 pm on an unspecified date and must be submitted electronically to the named contracting officer and contract specialist. The bid opening will be held telephonically at 3:00 pm on the bid due date, with bidders required to submit a list of participants in advance. The services required include clamshell maintenance dredging of the Rogue River to unspecified depths and quantities. The solicitation is being conducted by the Department of the Army Corps of Engineers Portland District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is to change 00 21 00 Submission of Bids to reflect the bid validity period stated on the SF 1442 of 90 days.

POC: Carl Schmurr 503-808-4613

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Apr-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N21B0018

X 9B. DATED (SEE ITEM 11)

07-Apr-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Apr-2021

CODE

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N21B0018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

BIDDER INQUIRIES

All inquiries regarding this solicitation are to be submitted via ProjNet-Bidsm. Telephone and email inquiries will not be accepted. ProjNet-Bidsm is a web-based program that allows bidders to post questions regarding the solicitation and to view all questions by other bidders and answers by USACE. ProjNet-Bidsm can be accessed through ProjNetsm at https://www.projnet.org/projnet/. To access the ProjNet-Bidsm website the first time:

1) Click the Bid tab

2) Click Bidder Inquiry. (The Agency is USACE.)

3) Enter the following information for access:

The Bidder Inquiry Key Y68WJM-59X7TQ

Valid business contact information (e.g. Company name, contact person, business address, phone number and email address). (required on first project only)

Establish secret question and answer which will be used as a password. (required on first project only)

4) For subsequent access use your email address, the Bid Inquiry Key and response to the secret question to access the ProjNet-Bidsm Module.

5) Submit questions or review questions and answers. (A bidder who submits a question will receive an automated email notification that their question has been received. When an answer is posted to a question, the question and answer is then available for all other bidders to review.

6) For a specific step-by-step for POSTING YOUR INQUIRIES, is available in the Reference link on the Contract Viewer.

7) For questions about the ProjNet-Bidsm, please contact the Call Center help desk toll free at 1-800-428- HELP, which operates from 8AM to 5PM (Central US time zone). ProjNet-Bidsm questions can also be emailed to the helpdesk at staff@rcesupport.com. No response will be posted to inquiries after the Close of Business on the third business day preceding the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet-Bidsm prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.

SUBMISSION OF BIDS

Bidders shall submit their bids via email to the following individuals by no later than the date and time established in Block 13 of the Standard Form (SF) 1442, or Block 14 of the most recently issued SF 30 as applicable:

Carl Schmurr, carl.r.schmurr@usace.army.mil

Each email shall contain the following information:

W9127N21B0018

Solicitation No. W9127N21B0018 Bid Due Date and Time: ______ Bid Validity Date: ______ (90 days from the bid due date)

Bids received after the date and time stated within Block 13 of the SF1442, or Block 14 of the most recently issued SF 30 as applicable, will be considered late and will not be considered for award. To avoid rejection of a bid, the offeror must make every effort to ensure its electronic submission is virus-free. Bids, or portions thereof, submitted with the presence of a virus or which are otherwise unreadable will be treated as unreadable pursuant to FAR 15.207(c).

Bidders should enter a description for every file submitted. For files over 20 megabytes (MB) the bidders shall break the file into smaller files sent via separate emails with each email marked to identify which number the email is relative to the total number of emails submitted (i.e. “email one of four”). Once all of the emails submitted have been received the Government will confirm receipt via responsive email. If a bidder submits multiple bids the Government will only consider the last bid submitted prior to the bid due date and time.

Do not assume submission will be instantaneous. File size and number of files submitted shall be considered.

Bidder/Teammate/Subcontractors should allow adequate time for submission completion because the entire bid (i.e.

bidders’ submission and all teammate/subcontractor(s) independent submissions) must be received by the bid due date and time specified in Block 13 of SF 1442, or SF 30 as applicable.

Electronic submission of bids satisfies the requirement set forth in Block 13A of the SF 1442 (‘…in original and ___ copies…”). Additionally, electronic submission of the bid guarantee, when a bid guarantee is required, is due with the bid submission. Mailing a bid guarantee for submission is not allowed.

BID OPENING

Bidders are advised there will NOT be a physical bid opening held for this invitation for bids. The bid opening will be held telephonically via conference call at 3:00 pm on the date bids are due. Due to the requirement that bids be submitted electronically only, the bid opening is scheduled to take place one hour following the bid due date and time of 2:00 pm in order to allow the contracting office time to download all bid documents submitted. The USACE Portland District will not accept any hard copy documentation submitted in response to this invitation for bids.

Bidders wishing to participate in the telephonic bid opening shall email a list of participants to both Contracting Officer (mitchell.j.johnson@usace.army.mil) and Contract Specialist (carl.r.schmurr@usace.army.mil) no later than the close of business 24 hours prior to the bid due date and time. Please reference “W9127N21B0018 Rogue River Dredging Bid Opening” in the email subject line. A responsive email will be sent to the bidder which will include confirmation of the list of participants, the conference call-in telephone number, and the security passcode for participants to utilize for the telephonic bid opening.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .