DURAMAX_MARINE_Instruction_-_Air_Seal_Ring_Replacement.pdf
PDF 629 KB Posted
- Attached to
- FY20 Dredge Vessel Yaquina Overhaul
- Solicitation number
- W9127N19R0059
About this file
Drawing
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
© 2016 Duramax Marine®
17990 Great Lakes Parkway Hiram, Ohio 44234 U.S.A.
PHONE: 440.834.5400 FAX: 800.497.9283 USA & Canada or 440.834.4950 info@DuramaxMarine.com www.DuramaxMarine.com
COMMERCIAL STUFFING BOXES
AIR SEAL RING REPLACEMENT INSTRUCTIONS
1. Remove stuffing box assembly from shaft.
2. Remove air valve extension from stuffing box housing.
3. Use a screw driver to pry out old air seal ring.
4. Coat new air seal ring with mild soap solution for lubrication.
5. Using a blunt object, force the ears of the replacement air seal ring into the machined grooves of the air seal ring slot.
6. Screw 1/4” NPT drill jig fitting, supplied in repair kit, into air valve hole on stuffing box housing.
7. Drill through the air valve hole into the rubber air seal ring using a 13/64” (5.159mm) diameter drill.
CAUTION! Take care that the drill penetrates only the outer surface of the air seal ring into the air cavity, but not into or through the inner surface. The drill can be felt with a finger on the air seal inner surface when it has penetraded the outer surface. (See Figure B)
8. Remove drill jig fitting.
9. Install the air valve extension.
10. Place a cylindrical object the same diameter as the shaft journal into the stuffing box and inflate the air seal ring to a test pressure of 80 P.S.I. The air seal ring should hold air pressure for 24 hours.
NOTE: When replacing packing ring an adequate seal should be obtained with about 15 P.S.I.G. air pressure.
AIR VALVE
EXTENSION
OUTER SURFACE
INNER SURFACE
AIR SEAL
RING
FIGURE A.
FIGURE B.
FIGURE C.
AIR VALVE
AIR SEAL RING