W9127827RA002_Attach 8_FY27 FLPHORC_MPS Structure Template.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- W9127827RA002
About this file
This is a Military Munitions Response Program (MMRP) and Installation Restoration Program (IRP) Master Project Schedule (MPS) structure template for the FY 2027 Florida Panhandle Optimized Remediation Contract. The template is designed to organize and track environmental remediation activities across 58 IRP sites and 5 MMRP sites located at Eglin Air Force Base, Hurlburt Field, and Tyndall Air Force Base in Florida. The MPS structure template serves as a framework for contractors to schedule and manage performance-based environmental remediation deliverables, including site investigations, remedial design, construction of remedial systems, operation and maintenance of established remedies, remedy optimization, and achievement of site-specific Performance Objectives (POs). This template provides the standardized format and organizational structure that contractors must utilize when planning and executing their comprehensive remediation activities under this Army Corps of Engineers contract, enabling consistent tracking and reporting of project milestones and resource allocation across multiple installations and site categories.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127827RA002_Solicitation Amend 0001 FY27 FL Panhandle ORC (Signed).pdf | ||
| W9127827RA002_Attach 5_Entry Authorization List (EAL) Request V2.xlsx | XLSX spreadsheet | |
| W9127827RA002_Solicitation FY27 FL Panhandle ORC (Signed).pdf | ||
| W9127827RA002_Attach 6_CLIN Structure_9.10.26.xlsx | XLSX spreadsheet | |
| W9127827RA002_Attach 18_Bid Sheet.xlsx | XLSX spreadsheet | |
| W9127827RA002_Attach 5_Entry Authorization List (EAL) Request.xlsx | XLSX spreadsheet | |
| W9127827RA002_Attach 7_FY27 FL PHORC_IMS Structure Template.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FL Panhandle Group
| Latest Version: | mm/dd/yyyy | 001 | 002 | 003 | 004 | 005 | ||||||||||||||||
| Revision: | # | Invoice Date | mm/dd/yyy | |||||||||||||||||||
| Period End | mm/dd/yyy | |||||||||||||||||||||
| Installation | Site | USACE CLIN | AFCEC CLIN/Sub-CLIN Number | Milestone Payment Identification Number | AFCEC CLIN/Sub-CLIN Description | Award Date or Projected Award Date (Pending availability of funding and bona fide need) | CLIN/ SubCLIN Amount | Payment Milestone Amount | Payment Percentage | Completion Date | Percent Complete | Invoice Number | Current Invoice Amount | Previously Invoiced Amount | Total Invoiced Amount to Date | Total Invoice % | Remaining to Invoice | Invoiced Amount | Invoiced Amount | Invoiced Amount | Invoiced Amount | Invoiced Amount |
| N/A | N/A | 0001 | Complete Project Management Plan (PMP) | $100.00 | ||||||||||||||||||
| N/A | N/A | 0001 | 0001CA | Complete PMP | 05/10/2027 | $50.00 | 50% | |||||||||||||||
| N/A | N/A | 0001 | 0001CA | 0001CA.01 | Air Force/CESAM Approval of Final PMP | $50.00 | 50% | |||||||||||||||
| N/A | N/A | 0002 | 0001CB | Update PMP #1 | 05/10/2030 | $15.00 | 15% | |||||||||||||||
| N/A | N/A | 0002 | 0001CB | 0001CB.01 | Air Force/CESAM Approval of Final PMP Update #1 | $15.00 | 15% | |||||||||||||||
| N/A | N/A | 0003 | 0001CC | Update PMP #2 | 05/10/2033 | $15.00 | 15% | |||||||||||||||
| N/A | N/A | 0003 | 0001CC | 0001CC.01 | Air Force/CESAM Approval of Final PMP Update #2 | $15.00 | 15% | |||||||||||||||
| N/A | N/A | 0004 | 0001CD | Complete ORC Transition Plan | 05/10/2035 | $20.00 | 20% | |||||||||||||||
| N/A | N/A | 0004 | 0001CD | 0001CD.01 | Air Force/CESAM Approval of ORC Transition Plan | $20.00 | 20% | |||||||||||||||
| Note: The last AFCEC Sub-CLIN must be at least 20% of the total AFCEC CLIN Amount and the last task within that AFCEC Sub-CLIN must be at least 20% of the total AFCEC Sub-CLIN Amount. |