W9127824Q0015 Solicitation Amnd 0002.pdf
PDF 838 KB Posted
- Solicitation number
- W9127824Q0015
About this file
This document is an amendment to a solicitation for the Bayou Caddy Ecosystem Restoration (Shoreline Stabilization) project located in Hancock County, Mississippi. The project involves an herbicide treatment of phragmites, an invasive plant, within four areas of the 22-acre restored marsh. The contractor will be required to develop a work plan, apply the herbicide treatment, and provide reporting. The treatment is intended to be a one-time application, with potential follow-up treatments if necessary. Key details include the project location, objectives, tasks, and deliverables schedule. The solicitation is being administered by the U.S. Army Corps of Engineers, Engineering District Mobile.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9127824Q0015 Solicitation Amnd 0005.pdf | ||
| W9127824Q0015 Solicitation Amnd 0004.pdf | ||
| W9127824Q0015 Solicitation Amnd 0003.pdf | ||
| W91278234Q0015 Solicitation Section L.docx | DOCX document | |
| W9127824Q0015 - BayouCaddy Combined synopsis_solicitation.docx | DOCX document | |
| W9127824Q0015 - BayouCaddy Combined synopsis_solicitation.docx | DOCX document | |
| W9127824Q0015 Solicitation Amnd 0001.pdf | ||
| 04_SOW Invasive Control_ Revised.docx | DOCX document | |
| PIEE_Solicitation_Module_Vendor_Access_Instructions.docx | DOCX document | |
| PIEE Vendor_Submit_Offer (1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a. The purpose of this ammendment is to Modify the SOW to include the approximate acreage of the phragmites at site location.
b. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127824Q0015
X 9B. DATED (SEE ITEM 11)
17-Sep-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0002
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Oct-2024
CODE
ENDIST MOBILE CONTRACTING DIVISION
109 ST JOSEPH ST
MOBILE AL 36602
W91278 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9127824Q0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been modified:
SOW
Changes are in RED.
SCOPE OF WORK
INVASIVE VEGETATION CONTROL
BAYOU CADDY, MARSH RESTORATION PROJECT
April 2024
The Bayou Caddy Ecosystem Restoration (Shoreline Stabilization) project is located in southwestern Mississippi near Waveland, in Hancock County. The project site is adjacent to and west of the federally authorized Cadet Bayou navigation project. Cadet Bayou is about 21 miles to the west of the Port of Gulfport and is about 44 miles to the east of New Orleans, Louisiana. The Bayou Caddy Ecosystem Restoration Project consists of a 22-acre site of restored marsh contained by a 2,000-foot-long geotextile tube (Figure 1). The most recent portion of the project consists of a 1,000-foot-long by 25-foot-wide rock breakwater combined with a 1,700-foot-long segmented living shoreline system consisting of prefabricated concrete wave attenuation devices (WADs) that protect the ecosystem restoration project from excessive wave action and storm damage as seen in the figures below. Based on the preivous field survey team, the acreage of the phragmites was approximately 1.2 acres but may have changed since last field visit in Spring ’24.
Figure 1: Bayou Caddy Ecosystem Restoration Beneficial Use Site Location
Area 1
Area 4
Figure 2: Drone Ortho mosaic View of Identified Phragmites Areas
PROJECT DESCRIPTION
This project entails an herbicide treatment of phragmites, an invasive plant identified during recent post-construction monitoring events, within four areas of the 22-acre restored marsh (Figure 2). The goal is to remove phragmites without causing damage to restored marsh plantings. This is intended to be a one-time spray treatment, after which additional follow-up or annual control treatments may be required, depending upon the results. Contractor shall provide all equipment, materials, transportation, and personnel required to accomplish the tasks described herein.
PROJECT OBJECTIVES
The objectives of the restoration project are to: 1) Extend the longevity and enhance the ecosystem within four areas of the 22-acre restored marsh at the site through decreased density of the invasive phragmites plant that will (i) Increase native vegetation, and (ii) improve the functional quality of the habitat.
Task 1. Development of a Work Plan The contractor will develop a Draft Project Work Plan based on a site visit of the areas indicated on Figure 2. This Draft Plan will provide information on equipment to be used by the contractor and herbicide treatment methodology. The project work plan shall include the proposed locations as recommended by the contractor. The Project Work Plan shall also include project description, description of treatment application, anticipated schedule for the project, proposed report outline, proposed equipment used, name and quantity of proposed herbicide used for treatment, and name and qualifications of Forman and applicators.
Task 2. Invasive Vegetation Control The contractor will apply herbicide treatment to phragmites growth at the four areas of the restored marsh. The contractor’s crew will treat along advancing edges and within dense phragmites clusters. Foliar applications will be made to the leaves and stems of the phragmites in the monoculture areas by walking transects through the dense stands and spraying adjacent to each transect. Basal application, applied near the base of the sown crop, will be made to individual phragmites stems and clusters where the cane is just beginning to advance into the desirable marsh vegetation. Herbicide will be applied as slower, targeted spot treatments to prevent off-target application.
Three days of herbicide treatment will be sufficient, but spraying cannot be performed when raining or in windy conditions, therefore the project duration could take up to several weeks. This task will ideally be performed in the spring.
Task 3. Reporting The contractor is required to submit reports to Valerie Powe, Lead Biologist via email.
The draft report shall include a description of spray treatment and completion date of application, equipment used, name and quantity of herbicide used for treatment, and a complete summary of findings and photos for submittal within 10 days after treatment application. The Lead Biologist and other members of the Project Delivery Team (PDT) will review the report within three (3) days. If there are revisions, contractor will revise and finalize report for submittal within five (5) days.
Task 4 Deliverables Schedule Description
1. Draft Project Work Plan Schedule Ten (10) days after the Notice to Proceed
2. Final Project Work Plan Schedule Within five (5) days of the PDT review
3. Draft reports with photos Within 10 days of spray application
3. Final reports with photos Within five (5) days of PDT review
(End of Summary of Changes)