Total Cost Schedule
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Bidding Schedule |
| For all Fixed Price and Cost Plus Technical Provisions |
| SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| BASE YEAR | 1 | Year | | |
| Operation and Maintenance of Government-owned Facilities and Equipment at Black Warrior-Tombigbee (BWT) and Alabama River Projects located in Washington, Clarke, Marengo, Choctaw, Sumter, Hale, Greene, Tuscaloosa, Monroe, Wilcox, Dallas, Lowndes, and Autauga Counties in Alabama, in accordance with the Technical Provisions as stated in Section C. Period of performance: 12 months from date of award. | |
| TOTAL AMOUNT OF ALL TPs (1-21) | $ - 0 |
OPTION YEAR ONE 1 Year
| Operation and Maintenance of Government-owned Facilities and Equipment at Black Warrior-Tombigbee (BWT) and Alabama River Projects located in Washington, Clarke, Marengo, Choctaw, Sumter, Hale, Greene, Tuscaloosa, Monroe, Wilcox, Dallas, Lowndes, and Autauga Counties in Alabama, in accordance with the Technical Provisions as stated in Section C. Period of performance: 12 months from date of award. | |
| TOTAL AMOUNT OF ALL TPs (1-21) | $ - 0 |
OPTION YEAR TWO 1 Year
| Operation and Maintenance of Government-owned Facilities and Equipment at Black Warrior-Tombigbee (BWT) and Alabama River Projects located in Washington, Clarke, Marengo, Choctaw, Sumter, Hale, Greene, Tuscaloosa, Monroe, Wilcox, Dallas, Lowndes, and Autauga Counties in Alabama, in accordance with the Technical Provisions as stated in Section C. Period of performance: 12 months from date of award. | |
| TOTAL AMOUNT OF ALL TPs (1-21) | $ - 0 |
OPTION YEAR THREE 1 Year
| Operation and Maintenance of Government-owned Facilities and Equipment at Black Warrior-Tombigbee (BWT) and Alabama River Projects located in Washington, Clarke, Marengo, Choctaw, Sumter, Hale, Greene, Tuscaloosa, Monroe, Wilcox, Dallas, Lowndes, and Autauga Counties in Alabama, in accordance with the Technical Provisions as stated in Section C. Period of performance: 12 months from date of award. | |
| TOTAL AMOUNT OF ALL TPs (1-21) | $ - 0 |
OPTION YEAR FOUR 1 Year
| Operation and Maintenance of Government-owned Facilities and Equipment at Black Warrior-Tombigbee (BWT) and Alabama River Projects located in Washington, Clarke, Marengo, Choctaw, Sumter, Hale, Greene, Tuscaloosa, Monroe, Wilcox, Dallas, Lowndes, and Autauga Counties in Alabama, in accordance with the Technical Provisions as stated in Section C. Period of performance: 12 months from date of award. | |
| TOTAL AMOUNT OF ALL TPs (1-21) | $ - 0 |
GRAND TOTAL (Base and Option Years 1, 2, 3, & 4) $ - 0
Cert of Final Indirect Costs
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Certificate of Final Indirect Costs |
This is to certify that I have reviewed this proposal to establish final indirect cost rates and to the best of my knowledge and belief:
1. All costs included in this proposal for __________________________ to establish final indirect cost rates for __________________________ are allowable in accordance with the cost principles of the Federal Acquisition Regulation (FAR) and its supplements applicable to the contracts to which the final indirect cost rates will apply.
2. This proposal does not include any costs which are expressly unallowable under applicable cost principles for the FAR or its supplements.
| _____________________________ | _________________ | |
| | Date |
Home Office OH Allowance
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Home Office Overhead Allowance |
| Volume II Cost/Price Proposal |
| HOME OFFICE OVERHEAD ALLOWANCE |
| Home office overhead for cost plus portions of this contract will not exceed (________%) of estimated contract cost. In no event will allowance for home officer overhead exceed the dollar amount of $ ________________________. |
| Note: As cost plus portions of this contract are modified and the direct cost is increased, ___________________________ |
| the amount filled in here by the offeror will also increase by the same amount. |
| The name of the Government auditing Agency (if any) that has approved the use of these rates for bidding purposes. _________________ |
Fixed priced portions of this contract will have overhead costs included in contract line item bid price.
| The allowance for home office overhead will be established after award by the Government audit. The Contractor will not be |
| reimbursed by expense incurred in excess of the above-stated not-to-exceed percentages, even though actual Government audit reveals |
| that home office overhead expenses exceed the Offeror's proposed not-to-exceed percentages. |
| END OF FORM |
Limit on Sub
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Limitations on Subcontracting |
| | Base Year | OPTION 1 | OPTION 2 | OPTION 3 | OPTION 4 | TOTAL |
| A | Total Prime Labor Cost (NOT INCLUDING SUBCONTRACT LABOR) | $ | $ | $ | $ | $ | $ |
| B | Total Subcontracting Labor | $ | $ | $ | $ | $ | $ |
| C | Total Labor Cost | $ | $ | $ | $ | $ | $ |
| D | Limitation on Subcontracting Percentage | % | % | % | % | % | % |
| EXAMPLE: |
| A = Total Prime Labor = $3,000,000.00 |
| B = Total Subcontract Labor = $5,000,000.00 |
| C = Total Labor Costs = A + B = $8,000,000 |
| D = Limitation on Subcontracting Percentage = (B / C) = $5,000,000.00 / $8,000,000.00 = 62.5% |
| NOTE: |
| This percentage shall not be more than 50% for the offeror to be considered |
| for award. Therefore, the example given is NOT an acceptable bid. |
Summary Sheet
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Summary Sheet |
| ALL YEARS |
Cost Element Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
| Fixed Price Technical Provision | | | | | | | |
| TP-1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| A | TOTAL FIXED PRICE | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Cost Plus Fixed Fee (TP-2 to TP-11): | | | | | | | |
| Direct Labor: | | | | | | | |
| B | Total Direct Labor Salary: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| C | Total Direct Labor Hourly: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| D | Total Direct Labor (Hourly + Salary) | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden: | | | | | | | | |
| E | Labor Burden Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| F | Labor Burden Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| G | Total Labor Burden (Hourly + Salary) | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| H | Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| I | Other Direct Costs | | | | | | | |
| J | Subcontract Costs: | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
K Total Direct Costs: $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
L G&A Costs % $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
M Total Direct Cost + G&A $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Fee: | | | | | | | | |
| N | Fixed Fee | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
O TOTAL COST PLUS FIXED FEE $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
P CONTRACT TOTAL $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| A = Total Fixed Price Cost |
| D = Total Direct Labor = B + C |
| E = Labor Burden Salary = B (Labor Burden Salary Percentage %) |
| F = Labor Burden Hourly = C (Labor Burden Hourly Percentage %) |
| G = Total Labor Burden = E + F |
| K = Total Direct Costs = (D + G + H + I + J) |
| L = G&A Costs = K (G&A %) |
| M = Total Direct Costs + G&A = K + L |
| N = Fixed Fee = M (Fixed Fee %) |
| O = Total Cost Plus Fixed Fee = M + N |
| P = Contract Total = A + O |
Cost by TP
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Total Costs by Technical Provision |
| Technical Provision | Base Year | Option Yr 1 | Option Yr 2 | Option Yr 3 | Option Yr 4 | Total |
| TP-1 Management and Base Labor | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-2 Management Reimbursable Requirements | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-3 Cleaning and Refuse Removal | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-4 Grass Mowing | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-5 Boundary Line Clearing and Maintenance | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-6 Maintenance of Buildings, Recreation Faciliteis and Associated Infrastructure | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-7 Lock and Dam Maintenance | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-7 Lock Closures | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-7 Coffeeville Spillway Repair | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-8 Maintenance of Upland Dredged Material Disposal Areas | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-9 Protection and Enhancement of Natural Resources | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-10 Maintenance of Government Vehicles, Boats & Equipment | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| TP-11 Grounds Maintenance | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
Direct Labor Hours by Labor C
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Direct Labor Hours by Labor Classification |
| List All Labor Classifications That Apply |
| BASE YEAR | | | | | | | | | | | | | | | |
| A | B | C | D | E | F | G | H | I | J | K | L | M | | | | |
| Labor Classification | TP 1 | TP 2 | TP 3 | TP 4 | TP 5 | TP 6 | TP 7 | TP 8 | TP 9 | TP 10 | TP 11 | Total Direct Labor Hours | TP 7 Lock Closures Temp (OY 3) | TP 7 Lock Closures OT (OY 3) | TP 7 Coffeeville Spillway Gates Temp (OY 1&2) | TP 7 Coffeeville Spillway Gates OT (OY 1&2) |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Labor Classification | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
| Total | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | | | | |
M = Total Direct Labor Hours = B + C + D + E + F + G + H + I + J + K + L
Subcontracts by TP
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| Subcontracts Costs Breakdown by Technical Provision |
| ALL YEARS |
| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O |
| Subcontract Description | TP 1 | TP 2 | TP 3 | TP 4 | TP 5 | TP 6 | TP 7 | TP 7 Lock Closures | TP 7 Coffeeville Spillway Gates | TP 8 | TP 9 | TP 10 | TP 11 | Total Subcontracts |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Subcontract Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Total | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
O = Total Subcontracts = B + C + D + E + F + G + H + I + J + K+ L + M + N
M&S and ODC by TP
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| M&S and ODC Breakdown by Technical Provision |
| ALL YEARS |
| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O |
| Subcontract Description | TP 1 | TP 2 | TP 3 | TP 4 | TP 5 | TP 6 | TP 7 | TP 7 Lock Closures | TP 7 Coffeeville Spillway Gates | TP 8 | TP 9 | TP 10 | TP 11 | Total M&S and ODC |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Material & Supplies Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| ODC Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| ODC Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| ODC Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| ODC Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| ODC Item | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
| Total | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - |
O = Total M&S + ODC = B + C + D + E + F + G + H + I + J + K+ L + M + N
TP-1
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-1 Management and Base Labor |
| Firm Fixed Price |
| CLIN Number | | Annual Total |
| 0001 | Base Year | $ - 0 |
| 0002 | Option Year 1 | $ - 0 |
| 0003 | Option Year 2 | $ - 0 |
| 0004 | Option Year 3 | $ - 0 |
| 0005 | Option Year 4 | $ - 0 |
| Total All Years | | $ - 0 |
| Base | Option Year 1 | Option Year 2 | Option Year 3 | Option Year 4 | Extension (Annual) |
| January | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| February | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| March | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| April | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| May | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| June | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| July | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| August | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| September | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| October | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| November | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| December | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
TP-2
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-2 Management Reimbursable Requirements |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-3
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-3 Cleaning and Refuse Removal |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-4
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-4 Grass Mowing |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-5
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-5 Boundary Line Clearing and Maintenance |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-6
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-6 Maintenance of Buildings, Recreation Faciliteis and Associated Infrastructure |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-7
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-7 Lock and Dam Maintenance |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-7 Lock Closures
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-7 Lock Closures |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-7 Coffeeville Spillway Gates
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-7 Coffeeville Spillway Repair |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-8
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-8 Maintenance of Upland Dredged Material Disposal Areas |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-9
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-9 Protection and Enhancement of Natural Resources |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-10
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-10 Maintenance of Government Vehicles, Boats & Equipment |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Repalcement Equipment | $ 18,000.00 | $ 18,000.00 | $ 18,000.00 | $ 18,000.00 | $ 18,000.00 | $ 90,000.00 | $ 18,000.00 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Floating Plant Repairs | $ 40,000.00 | $ 40,000.00 | $ 40,000.00 | $ 40,000.00 | $ 40,000.00 | $ 200,000.00 | $ 40,000.00 |
| Survey Boat Service/Repair | $ 20,000.00 | $ 20,000.00 | $ 20,000.00 | $ 20,000.00 | $ 20,000.00 | $ 100,000.00 | $ 20,000.00 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0
TP-11
| Black Warrior-Tombigbee (BWT) and Alabama River Projects |
| Solicitation No. W91278-20-R-0103 |
| Section L - Cost Worksheets |
| TP-11 Grounds Maintenance |
| Cost Plus Fixed Fee |
Cost Element Hours Rate OT Hours OT Rate Base Year Option Yr 1 Option Yr 2 Option Yr 3 Option Yr 4 Total Extension (Annual)
Direct Labor (List all that apply):
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Salary: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| List Each Labor Classification | - 0 | $ - 0 | - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Labor Hourly: | | | | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Labor (Hourly + Salary): $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Labor Burden: | | | | | | | | |
| Labor Burden - Salary | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Labor Burden - Hourly | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Labor Burden (Hourly + Salary): | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials & Supplies (List all that apply): | | | | | | | |
| List Each M&S Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Material & Supplies | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Other Direct Costs (ODC), (List all that apply): | | | | | | | |
| List Each ODC Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total ODC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Subcontracts (List all that apply) | | | | | | | |
| List Each Subcontract Item | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Subcontracts | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Total Direct Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| G&A Costs | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Total Direct Cost + G&A | | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Fee: | | | | | | | | |
| Fixed @ | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0
| Extension |
| January | $ - 0 |
| February | $ - 0 |
| March | $ - 0 |
| April | $ - 0 |
| May | $ - 0 |
| June | $ - 0 |
| July | $ - 0 |
| August | $ - 0 |
| September | $ - 0 |
| October | $ - 0 |
| November | $ - 0 |
| December | $ - 0 |
Total $ - 0 image1.emf