AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04 EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Solicitation for USDA Fruit Fly Rearing and Release Facility Phase 1; Moore Air Base, TX is amended as follows.
See SF30 Continuation Sheet(s)
NOTE: Bid Receipt date is 19 July 2021; at 1:00 p.m.,CT, as previously announced.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer) (Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G21B0006
X 9B. DATED (SEE ITEM 11)
02-Jun-2021
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09 -July-2021
CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A19
P.O. BOX 17300
FORT WORTH TX 76102-0300
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODE CODE
EMAIL: TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
CHANGES TO SOLICITATION W9126G21B0006
1. Replacement Sections: Replace the following section with the accompanying new section of the same number and title bearing the notation W9126G21B0006 0003:
00 11 00.01 - SOLICITATION, OFFER AND AWARD, SF-1442
00 21 00 - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
03 41 33 PRECAST STRUCTURAL PRETENSIONED CONCRETE
08 11 13 STEEL DOORS AND FRAMES
08 13 73 SLIDING METAL DOORS
08 33 23 OVERHEAD COILING DOORS
08 71 00 DOOR HARDWARE
11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 63 00.00 10 COLD STORAGE REFRIGERATION SYSTEMS
31 63 29 DRILLED CONCRETE PIERS AND SHAFTS
2. New Sections - The following sections are being added bearing the notation W9126G21B0006-0003:
07 13 53 ELASTOMERIC SHEET WATERPROOFING
08 71 00_Appendices HARDWARE SCHEDULE
. 09 65 13 RESILIENT BASE AND ACCESSORIES
11 41 11 REFRIGERATED AND FROZEN FOOD STORAGE EQUIPMENT
11 71 00 STERILIZERS AND GROWTH CHAMBER
11 90 13 PRODUCTION EQUPMENT
CHANGES TO THE DRAWINGS
3. Replacement Drawings – Replace the following Drawings with the accompanying new drawings bearing the notation W9126G21B0006-0003:
C-513-CIVIL DETAILS
C-514-CIVIL DETAILS
C-530-EROSION CONTROL DETAILS
CP-601-PAVING PLAN - AREA H
CS-101 - DIMENSION CONTROL PLAN - AREA H
CU-105-GAS PLAN - AREA I
CU-120-STORM PLAN - AREA H
CU-121-STORM PLAN - AREA I
CU-140 -DRAINAGE AREA MAP
S-001 - ABBREVIATIONS SYMBOLS & GENERAL NOTES
S-112 - WALKABLE CEILING - AREA 1
S-113 - WALKABLE CEILING - AREA 2
S-114 - WALKABLE CEILING - AREA 3
S-501 - FOUNDATION SECTIONS AND DETAILS
S-502 - SECTIONS AND DETAILS
S-512 - ROOF FRAMING SECTIONS AND DETAILS
S-515 - TILT WALL SECTIONS AND DETAILS
S-601 – SCHEDULES
A-101 - FLOOR PLAN - AREA 1
A-102 - FLOOR PLAN - AREA 2
A-530 - INTERIOR SECTION DETAILS
A-540 - INTERIOR CEILING DETAILS
A-610 - DOOR SCHEDULE AND DETAILS
A-612 - INTERIOR DOOR DETAILS
A-620 - FINISH LEGEND & ROOM FINISH SCHEDULE
P-102 - PLUMBING FLOOR PLAN - AREA 2
P-103 - PLUMBING FLOOR PLAN - AREA 3
P-104 - PLUMBING FLOOR PLAN - AREA
P-502 - PLUMBING DETAILS
P-601 - PLUMBING SCHEDULES
P-902 – PLUMBING RISERS
M-001 - HVAC GENERAL NOTES AND DESIGN DATA
M-122 - HVAC SENSOR PLAN - AREA 2
M-123 - HVAC SENSOR PLAN - AREA 3
M-510 - HVAC DETAILS
M-512 - HVAC DETAILS
M-601 - HVAC SCHEDULES
M-602 - HVAC SCHEDULES
M-603 - HVAC SCHEDULES
M-604 - HVAC SCHEDULES
M-605 - HVAC SCHEDULES
M-606 - HVAC SCHEDULES
M-607 - HVAC SCHEDULES
M-608 - HVAC SCHEDULES
E-001 - GENERAL NOTES, LEGEND, AND SYMBOLS
E-112 - COMMUNICATION PLAN - AREA 2
E-131 - LIGHTNING PROTECTION PLAN
E-501 - ELECTRICAL DETAILS
E-601 - ELECTRICAL ONE-LINE DIAGRAM
E-701 - EQUIPMENT AND WIRE SCHEDULES
5. Clarifications to Bidder Inquiries
The response to Bidder Inquiry 9309616 stated, “The pipe material has been modified to be entirely PVC. Refer to the forthcoming Amendment 0003 for the revision to the drawings.” This change was actually issued via Amendment # 0002.
The response to Bidder Inquiry 930503 stated, “Demarcation of gas line work has been added to the drawings via Amendment #3. It is the Contractor's responsibility to construct the line from the meter to the building. The utility provider will install the meter, regulator and bypass. Contractor shall coordinate with the local gas provider for the installation of the gas meter, regulator and bypass. Contractor is responsible for payment of all connection fees required for the installation. The natural gas provider is Gulf Gas Utilities Co., 281-334-6335. This information will be provided in a forthcoming amendment.” Clarification was received from the gas utility that all lines inside the fence are the responsibility of the contractor to provide and install. The Contractor must construct the gas per the drawings provided in Amendment #3.
End of Summary of Changes
Project Title: USDA Fruit Fly Rearing and Release Facility Phase 1
Funds are not presently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available.
Firm-Fixed Price project to provide construction services to build the facility to support the USDA Fruitly Rearing, Eclosion, and Release mission located at Edinburg, Texas.
This is an UNRESTRICTED Design-Bid-Build procurement. The magnitude of this project is betw een $25,000,000 and $100,000,000.
NAICS Code: 236220 Product or Service Code: Y1EC
POC:benjamin.j.aldrich@usace.army.mil, (817) 886-1181.
X
BENJAMIN ALDRICH 817-886-1181
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
NEGOTIATED
02-Jun-2021
(RFP)
(IFB)
CALL:
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________660 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________01 00 00.0044
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________19 Jul 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______30 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
W9126G
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
466271
8. ADDRESS OFFER TO (If Other Than Item 7)
(817) 886-6403FAX:TEL: TEL: FAX:
W9126G21B0006 57
<AM#0003>01:00 PM<AM#0003>
W9126G21B0006-0003 m2ct9ba9 Cross-Out
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9126G21B0006-0003
USDA Fruit Fly Rearing and Release Facility Phase 1 USDAFF
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 11 00.01 SOLICITATION, OFFER AND AWARD, SF-1442
00 11 00.02 CONTRACT LINE ITEM SCHEDULE
00 21 00 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
00 45 00 REPRESENTATIONS AND CERTIFICATIONS
00 72 00 CONTRACT CLAUSES
00 73 00 SPECIAL CONTRACT REQUIREMENTS
00 73 46 WAGE DETERMINATION SCHEDULE
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 44 CONSTRUCTION SCHEDULE
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 56 00.00 44 DUST CONTROL
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
03 41 33 PRECAST STRUCTURAL PRETENSIONED CONCRETE
03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
03 47 13 TILT-UP CONCRETE
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 51 00 METAL STAIRS
05 51 33 ALTERNATING TREAD DEVICES
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
PROJECT TABLE OF CONTENTS Page 1
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 36 SPRAY FOAM AIR BARRIERS
07 54 19 POLYVINYL-CHLORIDE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 13 73 SLIDING METAL DOORS
08 14 00 WOOD DOORS
08 22 20 FIBERGLASS REINFORCED PLASTIC (FRP) DOORS AND FRAMES
08 31 00 ACCESS DOORS AND PANELS
08 33 23 OVERHEAD COILING DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 51 13 ALUMINUM WINDOWS
08 53 00 PLASTIC WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 13 RESILIENT BASE AND ACCESSORIES
09 67 23.14 CHEMICAL RESISTANT RESINOUS FLOORING
09 73 00 INTERIOR METAL CEILING SYSTEM
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 26 23.13 IMPACT RESISTANT WALL PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 26 SOLID PLASTIC LOCKERS
DIVISION 11 - EQUIPMENT
11 31 13 ELECTRIC KITCHEN EQUIPMENT
11 41 11 REFRIGERATED AND FROZEN FOOD STORAGE EQUIPMENT
11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS
11 71 00 STERILIZERS AND GROWTH CHAMBER
11 90 13 PRODUCTION EQUIPMENT
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 31 00 MANUFACTURED METAL CASEWORK
PROJECT TABLE OF CONTENTS Page 2
<AM#0003> </AM#0003>
<AM#0003> </AM#0003>
<AM#0003> </AM#0003>
<AM#0003> </AM#0003>
<AM#0003> </AM#0003>
<AM#0002> </M#0002>
</AM#0002><AM#0002>
<AM#0002> </AM#0002>
<AM#0002> </AM#0002>
<AM#0002> </AM#0002>
12 34 00 MANUFACTURED PLASTIC CASEWORK
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 METAL BUILDING SYSTEMS
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 PLUMBING PIPING INSULATION
22 13 29 SANITARY SEWERAGE PUMPS
22 15 14.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS, LOW PRESSURE
22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)
22 66 53.00 40 LABORATORY CHEMICAL-WASTE AND VENT PIPING
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 22 26.00 20 STEAM SYSTEM AND TERMINAL UNITS
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 52 00 HEATING BOILERS
23 52 53.00 20 STEAM BOILERS AND EQUIPMENT (18,000,000 - 60,000,000
BTU/HR)
23 63 00.00 10 COLD STORAGE REFRIGERATION SYSTEMS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 65 00 COOLING TOWERS AND REMOTE EVAPORATIVELY-COOLED CONDENSERS
DIVISION 26 - ELECTRICAL
26 05 73.13 SHORT-CIRCUIT STUDIES
26 05 73.16 COORDINATION STUDIES
26 05 73.19 ARC-FLASH HAZARD ANALYSIS
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 28 21.00 40 AUTOMATIC TRANSFER SWITCHES
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW
26 33 53 STATIC UNINTERRUPTIBLE POWER SUPPLY (UPS)
26 41 00 LIGHTNING PROTECTION SYSTEM
26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
26 51 00 INTERIOR LIGHTING
PROJECT TABLE OF CONTENTS Page 3
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 31 16.13 CHEMICAL TERMITE CONTROL
31 63 29 DRILLED CONCRETE PIERS AND SHAFTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 33 00 SITE FURNISHINGS
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 05 23 TRENCHLESS UTILITY INSTALLATION
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 11 23 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 30 00 SANITARY SEWERAGE
33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING
33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS
33 40 00 STORM DRAINAGE UTILITIES
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
<AM#0002> </AM#0002>
W9126G21B0006
Section 00 21 00 - Instructions, Conditions and Notices to Offerors
INSTRUCTION TO OFFERORS
SEALED BIDDING
INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS
1. INQUIRIES BIDDER'S QUESTIONS AND COMMENTS
All questions and comments are to be submitted via ProjNet at: http://www.projnet.org/projnet To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login.
Fill in all required information and click create user. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgment of their question via email, followed by an answer to their question after it has been processed.
The Solicitation Number is: W9126G21B0006 The Bidder Inquiry Key is: N6X8CI-5U5WCD The last day to submit ProjNet inquiries is <AM#0003> 17 days prior to the bid due date <AM002> 7 July 2021 </AM002> 12 July 2021 at 03:00 pm CT<AM#0003>in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Bidders are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is (833) 389-1097 and (217) 367-3273.
2. INSTRUCTIONS TO BIDDERS SPECIAL INSTRUCTIONS PERTAINING TO
ELECTRONIC BIDS SUBMISSION (FAR 14.302 & 14.304)
a. SUBMITTAL REQUIREMENT: In an effort to reduce paperwork and cost, submit ALL bids electronically through DoD SAFE at https://safe.apps.mil. It is the Bidders responsibility to submit the required information by the established deadline. For an outside user (the contractor) to submit through DoD SAFE, they must receive a drop-off request from an inside user (the Government). To request and receive a drop-off request for this solicitation, email the request not later than two (2) working days before the due date to: CESWF-IIS@usace.army.mil, Benjamin.J.Aldrich@usace.army.mil and eric.j.hurtado@usace.army.mil.
When the inside user generates the drop-off request, you will receive an email with a link to submit your drop-off. Optionally, the Government may provide you with a request code. In that case, click the Drop-off button on the SAFE home page and enter the Request Code.
All bids MUST be received by the Government via DOD SAFE to no later than due date and time. Bidders should use the DOD SAFE system and input the following emails when using their drop-off request: CESWF-IIS@usace.army.mil, Benjamin.J.Aldrich@usace.army.mil and eric.j.hurtado@usace.army.mil. In accordance with FAR 14.403 Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bid (IFB) by the time specified in the IFB. Late bids will not be considered and will be held unopened, unless opened for identification and notification of the bidder. LATE BIDS WILL NOT BE READ AT THE ELECTRONIC BID OPENING.
b. Electronically submitted bids must include the completed SF 1442 (in accordance with FAR 52.214-18), Acknowledgement of all amendments, completed CLIN schedule, a copy of the
W9126G21B0006-0003 m2ct9ba9 Cross-Out original Bid Bond, completed representations and certifications, the financial institution POC from paragraph k(1) of this section, and the references from paragraph k(3) of this section and a small business subcontracting plan (LARGE BUSINESSES ONLY) as outlined in paragraph l.
To be considered for award, a bid must comply in all material respects with the invitation for bids. Such compliance enables bidders to stand on an equal footing and maintain the integrity of the sealed bidding system. Bids that do not provide each of the items above will be considered non-responsive and in accordance with FAR 14.402 any bid that fails to conform to the essential requirements of the invitation for bids shall be rejected.
c. SENDING FILES. All submissions paragraph (b) should be in Adobe PDF format. Title and group the file(s) in the following format:
W9126G21B0006_COMPANY NAME_SF1442/Amendments/CLIN Schedule W9126G21B0006_COMPANY NAME_Bid Guarantee Bond W9126G21B0006_COMPANY NAME_Reps and Certs W9126G21B0006_COMPANY NAME_Financial POC and References W9126G21B0006_COMPANY NAME_subcontracting plan (as required for Large Business)
d. Original copies of the Bid Bond documents shall also be submitted separately to the following point of contact postmarked NLT bid due date and received NLT two (2) business days after the bid due date.
US Army Engineer District, SWF District, Fort Worth ATTN: Benjamin Aldrich 819 Taylor St, Room 2A17 Fort Worth, TX 76102-0300
e. Bids received will be publicly opened “Electronically” at the following location:
US Army Engineer SWF District, Fort Worth 819 Taylor St, Room 2A17 Fort Worth, TX 76102 “Electronically” Date & Time: 19 July 2021 <AM#0003> 1:00 PM 03:00 pm <AM#0003>(CT)
f. Teleconference Dial-in and Webex Conference Information for the public is:
Call-in: +1-844-800-2712 US Toll Free +1-669-234-1177 US Toll Access Code: 199 278 2952 https://usace1.webex.com/meet/eric.j.hurtado
g. BIDS BY TELEGRAPH. Bids received by telegraph, modifications thereto, or cancellations of bids WILL NOT BE ACCEPTED.
h. FACSIMILE BIDS. Facsimile bids, modifications thereto, or cancellations of bids WILL
NOT BE ACCEPTED.
i. EMAIL. Cancellations of bids will be accepted if received through email by the bid due date and time specified in the solicitation. Bid cancellations shall be sent to CESWF- IIS@usace.army.mil, Benjamin.J.Aldrich@usace.army.mil and eric.j.hurtado@usace.army.mil.
Initial bids and bid modifications submitted through email WILL NOT BE ACCEPTED.
W9126G21B0006-0003
j. MODIFICATIONS. Bid modifications will only be accepted through DOD SAFE by the bid due date and time specified in the solicitation. A bidder must follow the process in paragraph (a) to receive another drop-off request. Modifications received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered.
k. RESPONSIBILITY. Award will be made to the lowest, responsible bidder whose bid, conforming to the invitation for bids, will be the most advantageous to the Government. To be determined responsible, the bidder shall:
(1) Have adequate financial resources to perform the contract, or the ability to obtain them.
The contractor will be required to provide the Name of the Financial Institution, POC, and phone number.
(2) Bidders will be required to provide at least three (3) references for like work, to include Business Name, Point of Contact, and telephone number. The Government will use these references to determine responsibility.
(3) Have a satisfactory performance record. The contractor shall have no performance annotated with an individual rating of less than SATISFACTORY in the Contractor Performance Assessment Reporting System (CPARS) within the last six years.
(4) Have a satisfactory record of integrity and business ethics.
(5) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
(6) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(7) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
l. Each Large Business bidder shall provide a Small Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-9 Alt I (DEV) and meets or exceeds the following small business subcontracting goals: Small Business: {36.4%} of the total subcontracted dollars; Small Disadvantaged Business (SDB): {7.2%} of the total subcontracted dollars; Woman-Owned Small Business (WOSB): {5.6%} of the total subcontracted dollars;
Historically Underutilized Business Zone (HUBZone) Small Business: { 2.6%} of the total subcontracted dollars; Veteran Owned Small Business (VOSB): {5%} of the total subcontracted dollars; and Service Disabled Veteran Owned Small Business (SDVOSB): {3.7%} of the total subcontracted dollars. The subcontracting plan of apparent low bidder will be reviewed in accordance with the guidance at FAR19.705-4, and DFARS PGI 219.705-4. Bidders that provide subcontracting plans not meeting goals may be rejected. The Contracting Officer reserves the right to have an Offeror revise their subcontracting plan prior to award in accordance with 52.219-9(c)(1) Alt I.
3. GOVERNMENTWIDE POINT OF ENTRY (GPE). All contract soliciation documents, amendments, and award information for this project will be published electronically on SAM website at www.sam.gov under Solicitation Number W9126G21B0006.
4. NOTIFICATION OF UNSUCCESSFUL BIDDERS. Written unsuccessful bidder letters will be issued in accordance with FAR 14.409-1.
5. PREPROPOSAL CONFERENCE / SITE VISIT
See FAR clause 52.236-27 Site Visit (Construction) (Feb 1995) – Alternate I (Feb 1995)
NOTE: Remarks and explanations addressed during the conference shall not qualify or alter the terms and conditions of the solicitation.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017
CLAUSES INCORPORATED BY FULL TEXT
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
(End of provision)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
(End of provision)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of provision)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
(End of provision)
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
(End of provision)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
(End of provision)
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
72.8% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is State of Texas, Hildalgo County, and City of Edinburg.
(End of provision)
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE Fort Worth Contracting Divisions Attention: Eric J. Hurtado 819 Taylor St.
Fort Worth, TX 76102 SWF-Protest@usace.army.mil eric.j.hurtado@usace.army.mil
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- Date: Thursday, 10 JUN 2021
Time: 1:00 PM (CT) POC: Frederick McGee;
Phone: (409) 766-3060 or (409) 370-5100 (Mobile) Email: frederick.j.mcgee@usace.army.mil
Contractors planning to attend the site visit shall RSVP with the POC above NLT than close of business on 8 June 2021 by sending an email with list of the names of all persons attending the site visit.
(c) Participants will meet at-- USDA Moore Air Base (MAB) 22675 N. Moorefield Road Edinburg, Texas 78541
(End of provision)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/
(End of provision)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any DFARS (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
USDA (FFRRF) - Phase 1 Solicitation No. W9126G21B0006
MOORE AIR BASE, EDINBURG, TEXAS
SECTION 03 41 33
PRECAST STRUCTURAL PRETENSIONED CONCRETE
11/16
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 200 (1973; R 2012) Standard Specification for Epoxy Protective Coatings
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)
ACI 318M (2014; ERTA 2015) Building Code Requirements for Structural Concrete & Commentary
ACI SP-66 (2004) ACI Detailing Manual
ACI/MCP-2 (2015) Manual of Concrete Practice Part 2
ACI/MCP-3 (2015) Manual of Concrete Practice Part 3
ACI/MCP-4 (2015) Manual of Concrete Practice Part 4
AMERICAN HARDBOARD ASSOCIATION (AHA)
AHA A135.4 (1995; R 2004) Basic Hardboard
AMERICAN WELDING SOCIETY (AWS)
AWS A5.1/A5.1M (2012) Specification for Carbon Steel Electrodes for Shielded Metal Arc Welding
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
SECTION 03 41 33 Page 1 AM#0003
ASME INTERNATIONAL (ASME)
ASME BTH-1 (2014) Design of Below-the-Hook Lifting Devices
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A240/A240M (2020a) Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications
ASTM A283/A283M (2013) Standard Specification for Low and Intermediate Tensile Strength Carbon Steel Plates
ASTM A322 (2013) Standard Specification Steel Bars, Alloy, Standard Grades
ASTM A370 (2018) Standard Test Methods and Definitions for…