SEE ADDENDUM
(No Collect Calls)
W9126G19R0047 07-Mar-2019
b. TELEPHONE NUMBER
817 886 1110
8. OFFER DUE DATE/LOCAL TIME
12:00 PM 08 Apr 2019
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W9126G9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MATTHEW S DICKSON
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
US ARMY ENGINEER DISTRICT, FORT WORTH
ATTN: CESWF-CT
819 TAYLOR ST, ROOM 2A17
FORT WORTH TX 76102-0300
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
817-886-6403FAX:
TEL: 817-886-1043 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$38,500,000
NAICS:
561210
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF217
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 1449 - CONTINUATION SHEET
CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE
The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$2,500.00 $5,000,000.00
DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE
The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
$2,500.00 $700,000.00
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
0001 $ $
1001 $ $
2001 $ $
3001 $ $
4001 $ $
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 1001 N/A N/A N/A Government 2001 N/A N/A N/A Government 3001 N/A N/A N/A Government 4001 N/A N/A N/A Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
1001 N/A N/A N/A N/A
2001 N/A N/A N/A N/A
3001 N/A N/A N/A N/A
4001 N/A N/A N/A N/A
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 UNDEFINED Job Facitlity Maintenance Whitney/Aquilla
FFP
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform facility maintenance services as defined in this Performance Work Statement.
Period of Performance: 1 April 2019 - 31 March 2020
POC: Matthew S. Dickson, 817-886-1110, matthew.s.dickson@usace.army.mil FOB: Destination
MAX
NET AMT
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
1001 UNDEFINED Job OPTION Facitlity Maintenance Whitney/Aquilla
FFP
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform facility maintenance services as defined in this Performance Work Statement.
Period of Performance: 1 April 2020 - 31 March 2021
POC: Matthew S. Dickson, 817-886-1110, matthew.s.dickson@usace.army.mil FOB: Destination
MAX
NET AMT
UNIT UNIT PRICE MAX AMOUNT
2001 UNDEFINED Job OPTION Facitlity Maintenance Whitney/Aquilla
FFP
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform facility maintenance services as defined in this Performance Work Statement.
Period of Performance: 1 April 2021 - 31 March 2022
POC: Matthew S. Dickson, 817-886-1110, matthew.s.dickson@usace.army.mil FOB: Destination
UNIT UNIT PRICE MAX AMOUNT
3001 UNDEFINED Job OPTION Facitlity Maintenance Whitney/Aquilla
FFP
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform facility maintenance services as defined in this Performance Work Statement.
Period of Performance: 1 April 2022 - 31 March 2023
POC: Matthew S. Dickson, 817-886-1110, matthew.s.dickson@usace.army.mil FOB: Destination
UNIT UNIT PRICE MAX AMOUNT
4001 UNDEFINED Job OPTION Facitlity Maintenance Whitney/Aquilla
FFP
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform facility maintenance services as defined in this Performance Work Statement.
Period of Performance: 1 April 2023 - 31 March 2024
POC: Matthew S. Dickson, 817-886-1110, matthew.s.dickson@usace.army.mil FOB: Destination
INSTRUCTIONS TO OFFERORS
INSTRUCTIONS TO
OFFEROR
QUOTER DUE DATE/LOCAL TIME: see block 8, SF 1449 Central Standard Time (CST) POINT OF CONTACT: Matthew S. Dickson Phone: (817) 886-1110 Email POC: matthew.s.dickson@usace.army.mil
Quotes shall be accepted via “EMAIL ONLY,” no fax, mail, express mail, or hands carry, “NO EXCEPTIONS.” EMAIL your proposal to: matthew.s.dickson@usace.army.mil
Subject line of email: Include the solicitation number, W9126G19R0047, and your name.
For additional help contact your local Procurement Technical Assistance Centers (PTAC). Centers were created by Congress to assist businesses seeking to compete on federal contracts. Services are generally free;
however, a small fee may be charged for certain services. Please use website http://www.aptac-us.org/new/ to contact a center to assist you in the preparation for a federal contract, registering in SAM or other required systems.
SYSTEM FOR AWARD MANAGEMENT (SAM) is REQUIRED to receive an award on all federal government contracts. Therefore, contractors are encouraged to begin this process sooner rather than later. If already registered, please ensure your registration is ACTIVE. The website to register with SAM is: www.sam.gov.
DATA UNIVERSAL NUMBERING SYSTEM (DUNS) is REQUIRED. Dun & Bradstreet (D&B) provides a DUNS Number, a unique nine digit identification number, for each physical location of your business.
DUNS Number assignment is FREE for all businesses required to register with the US Federal government for contracts or grants in the System for Award Management (SAM see below).
The website to obtain your DUNS number: http://fedgov.dnb.com/webform for technical difficulties, contact govt@dnb.com
ONLINE REPRESENTATIONS AND CERTIFICATIONS APPLICATIONS (ORCA)
allows contractors to complete a one-time certification and representations for your use on any solicitation. The website to complete ORCA is available at the System for Award Manager (SAM): www.sam.gov. The information previously maintained in CCR, FedReg and ORCA now is contained within the Entity Management area in SAM. Legacy EPLS information resides in the Performance Information area of SAM. Contractors MUST be certified in the NAICS Code and Size Standard applicable with this solicitation.
ATTENTION TO OFFEROR(s)/CONTRACTOR(s): On July 14, 2014, Small Business Administration (SBA) increased the monetary-based industry size standards to account for inflation. You must update your Representations (Reps) and Certifications (Certs) for the impacted North American Industry Classification System (NAICS) codes identified with an exclamation point "!" next to the "Small Business" value in the System for Award Management (SAM). Please log into SAM, review, and resubmit your registration to apply the new size standard.
WAGE RATES: The Service Contract Act applies (see attached wage rates).
Below is a checklist to assist you to ensure all the proper documents are returned for consideration on this solicitation. Only those items checked below as “required” must be returned
Required Contractor Item
Complete page 1 of Solicitation (SF 1449-Sign and date in block 30).
Complete Bid Schedule(s)
Complete Contractor Information Sheet below: Include your SSN or firm’s Tax ID Number (TIN) and active email address.
You may be notified of your selection by this method!!!
Offerors shall complete ORCA profile on line in SAMS:
Clause 52.212-3 paragraph (b) OR submit complete ORCA profile.
Offerors shall submit an active SAM registration (Attach first page).
The System for Award Management (SAM) is the Official U.S. Government system that consolidated the capabilities of CCR/FedReg, ORCA and EPLS. Website: www.sam.gov
Ensure NAICS Code 561210 is listed in SAMS.
Past Performance Questionnaire from a former employer or person who can vouch for your work capability or volunteer work. Ensure former employer returns the form and references the solicitation number in the email subject line.
Scan all documents into a single.pdf file. (For Help contact your local Library, copy centers or PTACs-http://www.aptac-us.org/new/
EMAIL your proposal to: matthew.s.dickson@usace.army.mil Subject line of email: Include the solicitation number, W9126G19R0047 and your name
Contractor Information Sheet
IN THE EVENT OF AWARD, ISSUE CONTRACT TO:
NAME
(Last, First Middle)
ADDRESS
(Number & Street) (City, State and Zip)
HOME PHONE NUMBER MOBILE
(Area code and number) (Area code and number)
EMAIL ADDRESS
DUNS NUMBER CAGE CODE NUMBER
SSN/TIN NUMBER
PAST PERFORMANCE QUESTIONNAIRE
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY
ANY AND ALL INFORMATION ON THIS FORM.
RATING DEFINITION NOTE
(E) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
(VG) Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.
There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative.
TO BE COMPLETED BY CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS YOUR
EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards specified for technical performance E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
E VG S M U N
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project?
E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
d) Overall customer satisfaction E VG S M U N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
b) Ability to hire, apply, and retain a qualified workforce to this effort
E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel
E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed price(s)? E VG S M U N
b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No
6. SAFETY/SECURITY
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?
(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N
c) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N
W9126G19R0047
Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):
KO STATEMENT
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.
INSURANCE REQUIREMENT
Prior to commencement of work, the Contractor shall furnish the original of his Insurance Certificate directly to the Contracting Officer, Fort Worth District, Corps of Engineers, ATTN: CECT-SWF, P.O. Box 17300, Fort Worth, Texas 76102-0300 and one copy directly to the Lake Project Office.
The Contractor shall maintain, during the entire period of his performance under this contract, the following minimum insurance requirements:
Submit a copy of Insurance Certificate directly to:
U.S. Army Corps of Engineers, Whitney Project Office, 285 CR 3602 Clifton, TX 76634 And email to: matthew.s.dickson@usace.army.mil, 817-886-1110
(a) Comprehensive general liability insurance for bodily injury in the minimum limits of $500,000 per occurrence. No property damage liability is required.
(b) Comprehensive automobile liability insurance covering the operation of all automobiles used in connection with the performance of the contract in the minimum limits of $200,000 per person and $500,000 per accident for bodily injury and $20,000 per accident for property damage.
(c) Workmen's Compensation and Employer's Liability Insurance in the minimum amount of $100,000.00, or in compliance with applicable State statutes.
(d) An endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer.
NOTE:
(1) It is recommended that the contractor furnish a copy of the foregoing requirements to his insurance company in order to assure that an Insurance Certificate is issued meeting the minimum requirements shown. The Insurance Certificate shall also show the contract number to which it applies as well as a brief description and location of the work.
(2)
TASK ORDER OMBUDSMAN
USACE Task and Delivery Order Ombudsman:
Acquisition Support Division U.S. Army Corps of Engineers 7701 Telegraph Road, Casey Building, Room 2115 Alexandria, VA 22315 Phone: 703‐428‐6323 Email: Jacqueline.C.Woodson@usace.army.mil
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT
TECHNICAL PROVISIONS
General
1.1 SCOPE OF WORK: The Contractor shall furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, and vehicles, except as otherwise provided for herein, required to perform the operation and maintenance service within the area of responsibility of the Whitney-Aquilla Lakes Project Office, as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by the reference. Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.
Estimated quantities and/or the work to be performed is described herein and listed on separate sheets an Exhibits.
These quantities are approximate and are provided only for the Contractor’s information to assist in preparation of bids. They are not guaranteed and the actual quantities may be more or less than shown. Variations in these estimated quantities shall not be justification for or request for additional payment. The services required in this contract are in addition to the routine operation and maintenance performed by Government personnel, however the Government reserves the right to perform any or all of the service described herein with its own personnel or volunteers. Contractor work and responsibility shall include, but shall not be limited to: all planning, programming, administration and management necessary to assure that all services are conducted in accordance with the contract and all applicable laws, regulations, codes, or directives. Contractor shall ensure that all work meets or exceeds critical Contractor administrative services necessary to perform the work such as supply, procurement, quality control, Contractor financial control, and maintenance of accurate and complete records and files.
1.2 BACKGROUND: Whitney and Aquilla Lakes are flood control and water supply Lakes.
The Whitney-Aquilla Lakes Project Office is responsible for the maintenance and operations of two (2) dams and spillways, and eleven (11) parks/public use areas. Maps of the Lake Area and Major Park Areas are attached in Exhibit A. Minor repair, renovation or high Lake levels may cause the temporary closing of parts of some parks.
The Contractor’s work schedule shall be sufficiently flexible to meet these changing needs.
1.3. DELIVERY ORDERS. All work under this contract will be ordered by issuance of individual Task Orders.
The COR will order work using this contract by issuing a Task Item Delivery Order. The Delivery Order will list those items from the bid section that are to be performed or used to perform the work.
1.4. PAYMENT: The Contractor will be paid only for work accomplished and performed in accordance with these specifications and requirements of Delivery Orders (see 1.3). The Contractor will be paid monthly for work accomplished after submittal of an invoice (see Exhibit B for sample invoice). The Contractor will furnish a copy of the invoice to the Whitney-Aquilla Lake Project Office by the 25th of each month.
a. Task Items: The Contractor will include all labor, materials, supplies, parts, tools, equipment, transportation to and from the work site, profit overhead, and vehicles except as otherwise provided for herein, required to perform the service listed in the applicable bid item.
b. Disposal of Debris. The Contractor shall dispose of all materials and/or debris from the installation or replacement of work under this contract. Disposal shall be off Government property and in strict accordance with all applicable laws and ordinances. No separate payment for the disposal of materials and debris will be made.
c. The Contractor’s administrative costs to set up office, prepare estimates for task job requests, report results of normal and emergency service calls, and complete all the necessary paper work required in this scope of work will not be considered as work for payment.
1.4.1 GUARANTEED MINIMUM: The guaranteed minimum work to the awardee for this contract is equal to 3% of the total dollar value for the base year. The guaranteed minimum will be met via naturally occurring task orders.
1.5 WORK AREA: The work required under this solicitation will be located at the sites described in 1.2. The work sites, located at the Lakes, are located around the perimeter of the project, this will necessitate that the Contractor include costs for travel time in the bid amount.
1.6. WORKING HOURS:
Normal Working Hours. Normal working hours and days, except as otherwise specified or approved in advance by the Representative of the Contracting Officer (COR), shall be Monday through Friday, 7:30 a.m. to 5:00 p.m. The ten Federal Holidays observed are:
New Years Day (January 1st) Martin Luther King’s Birthday (3rd Monday in January) Presidents’ Day (3rd Monday in February) Memorial Day (Last Monday in May) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
When one of the above designated holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the proceeding Friday is observed as a holiday.
Work that interferes with other ongoing functions at Whitney-Aquilla Project shall be scheduled around normal working hours, as specified by the COR. Work shall be scheduled around the above listed Federal Holidays except as specified herein or as approved by the COR. Refer to individual sections of this specification for specific sections of work.
1.7. PERMITS AND LICENSES. The Contractor shall, as his/her own expense, obtain any licenses or permits required to perform the contract. The Contractor shall comply with all current federal, state, and local laws and regulations and shall comply with any subsequent changes.
1.7.1 REQUIRED INSURANCE. Any successful offeror under this solicitation shall procure and maintain during the entire period of his performance under this contract the following minimum insurance in accordance with FAR
52.228-5, INSURANCE--WORK ON A GOVERNMENT INSTALLATION:
(1) Workmen's Compensation in amounts required by applicable jurisdictional statutes. (FAR 28.307-2a).
(2) Employers Liability Insurance of at least $100,000. (FAR 28.307-2a).
(3) Comprehensive general liability insurance for bodily injury in the minimum limits of $500,000 per occurrence. No property damage liability insurance is required. (FAR 28.307-2(b)).
(4) Comprehensive vehicle liability insurance covering the operation of all automobiles used in connection with the performance of the contract in the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. (FAR 28.3072(c)).
1.8. IDENTIFICATION OF CONTRACT EMPLOYEES AND VEHICLES. The Contractor shall provide ball caps/hats with the company name or logo to be worn by all employees and subcontractors while working on public recreation areas. Appearance of all employees will be neat and clean at the beginning of each work day.
Contractor’s vehicles and major subcontractor’s vehicles shall be identified with the company name prominently displayed (minimum two inch letters) on the outside of both front doors of each vehicles in such a manner as to provide a readily visible means of identification. Extreme caution should be exercised at all times and especially when operating vehicles to prevent accident and injuries to the contractor and visitors. Vehicles and equipment must be kept in proper mechanical order and clean and neat in appearance.
1.9 SAFETY AND SECURITY REQUIRMENTS. The Contractor shall comply with all current provisions of the Occupational Safety and Health Act (OSHA) in addition to the standards of the Corps of Engineers manual, EM 385-1-1, “Safety and Health Requirements Manual”. If the Contractor fails or refuses to promptly comply with the safety and security requirements as specified herein, the COR may issue an order stopping all or part of the work for each delivery order affected by the infraction until satisfactory corrective action has been taken. No part of the time lost due to any such stop shall be made subject to claim for extension of time or for excess costs or damages to the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
The Contractor will be furnished a set of keys to those buildings and areas where access is necessary to perform the work described herein or as determined to be necessary by the COR. No duplicates of the keys are authorized to be obtained in any manner by the Contractor or by any Contractor employee. Any additional keys required by the Contractor will be furnished by the COR. Security of the keys shall be the responsibility of the Contractor. The failure of the Contractor to provide adequate key security will result in a deduction from payment due the Contractor in the amount of $20.00 per lost or damaged key and a deduction for setting new combinations for any affected locks at the rate charged by the manufacturer per lock.
1.10 ACCIDENT REPORTING. All serious accidents (those resulting in death or injury requiring medical attention) shall be reported to the COR immediately. The Contractor shall maintain an accurate record of, and shall report to the COR, all accidents within 24 hours of the occurrence.
1.11 CONTRACT EMPLOYEES CONDUCT AND COMPETENCY. All contract employees and subcontractors shall conduct themselves in a proper manner at all times. Since the majority of work will be performed in the presence of the general public, the conduct of all employees and/or subcontractors is critical and will be closely monitored. No alcoholic or intoxicating beverages, illegal drugs, controlled substances or drugs not prescribed by a physician shall be possessed or consumed while on duty.
The Contractor shall remove from the site any individual whose continued employment is deemed by the COR to be contrary to the public interest or inconsistent with the best interests of the U.S. Army Corps of Engineers.
1.12 DAMAGES OR LOSS OF CONTRACTOR’S SUPPLIES AND PROPERTY. The Contractor is responsible for taking the action necessary to protect all Contractor property and the personal property of Contractor employees from loss, damage, or theft. The Government assumes no responsibility for theft, damage, etc. of the above.
1.13 SUPERVISION. The Contractor shall personally supervise the work or provide a qualified Contractor Representative who is responsible for quality control whenever the work specified herein is being performed. The Contractor Representative shall conduct overall management coordination and be the central point of contact with the Government for performance of all work under this contract. The Contractor Representative shall have full authority to contractually commit the Contractor for prompt action on matters pertaining to administration of the entire contract. The Contractor Representative shall deal directly with the COR or designated representatives, for normal day-to-day administration of the contract provisions.
1.14 ENVIRONMENTAL PROGRAMS. The Contractor shall comply with Federal, State, and local laws, regulations and standards regarding environmental protection. All environmental protection matters shall be coordinated with the COR. Any of the facilities operated by the Contractor may be inspected by the COR, or other Federal, State and local officials on a non-notice basis. Access for inspection shall be granted upon request.
Citations against Government facilities operated by the Contractor for noncompliance with environmental standards are a matter for resolution between the Government and the issuing office. Payment of fines or penalty charges associated with citations issued by Federal, State, or local officials shall be paid by the Government. If the citations are issued due to faulty operation or maintenance practices, the COR shall deduct the fine from any money due the Contractor.
1.15 PERFORMANCE EVALUATION MEETINGS. The Contractor, the Contractor Representative, or both, shall meet with the COR (or a designated representative) weekly or as determined necessary by the COR. However, a meeting shall be held not later than one normal workday after a Contract Deficiency Report (CDR) is issued. Mutual effort will be made to resolve any and all problems identified.
1.16 QUALITY CONTROL PROGRAM.
a. General. The Contractor shall be responsible for maintaining adequate quality control to satisfactorily meet the specifications of the contract through the development of a Quality Control Plan. The Government will assure quality performance according to a Quality Assurance Surveillance Plan.
Combined, these two programs form the Government’s Quality Assurance Program.
b. Quality Control. The Contractor shall establish a complete quality control program to assure the requirements of the contract are provided as specified. The program shall include, but not be limited to the following:
An inspection system covering all the services stated in the contract. It must specify areas to be inspected on either a scheduled or unscheduled basis or the individuals who will do the inspection.
Inspectors shall be employees of the Contractor; not employees of a subcontractor. The contractor shall provide a daily Quality Control Report to the COR on each active Delivery Order. This report shall list the Contract and Delivery Order numbers, name of Contractors and Subcontractors, the date, weather conditions, all delays, a detailed description of the work performed, progress of work, items inspected and time of inspections, any deficiencies. The reports shall also provide factual evidence that continuous quality control inspections and tests were performed including, but not limited to the following: type and number of tests involved; results of inspections or tests including all computations;
nature of defects found; causes for rejections; proposed remedial actions; and corrective actions taken to avoid repetition of faulty work. All reports shall be legible and furnished to the Government on a daily basis or as designated by the COR.
c. Testing. Upon completion of services involving parts or replacement or repair, the total system shall be tested to confirm that all portions, including the replaced or repaired parts, are functioning properly.
The COR will be notified of any malfunctions created by the directed parts replacement or repair to the overall system.
1.17 QUALITY ASSURANCE. The Government will monitor the Contractor’s performance in each functional are under this contract and reserves the right to use whatever additional surveillance procedures are deemed appropriate.
If the Contractor fails to perform according to the performance standards, a Notification of Contract Deficiency or Contract Deficiency Report will be issued by the COR. The Contractor shall explain, in writing, why performance was not satisfactory and how recurrence of the problem will be prevented in the future.
The COR, or his representative will make periodic inspections of the Contract's work. The Contractor’s QC will be advised as soon as possible of any deficiencies found. Upon being advised of deficiency the Contractor shall take immediate action to correct these deficiency or submit a written plan addressing correction of the deficiency and ensure that they do not recur. The COR or the QA will be available for inspection specifically called for in the contract specifications. The Government also reserves the right to use whatever additional surveillance and testing procedures necessary to ensure or verify the quality of the Contractor's performance. Payment will not be made until all work has been completed, inspected and accepted by the COR. See Exhibit C, Quality Assurance Surveillance Plan.
1.18 WORK SITE REPORTING. The Contractor shall report to the designated work site with necessary personnel, vehicles, supplies, tools, materials and parts to accomplish the specified work within specified time limits as noted in the delivery order.
1.19 INTERRUPTION TO SYSTEMS. All work that would necessitate an interruption of the use of the project or to the utility systems or otherwise disrupt building occupants and/or the visiting public shall be fully coordinated and approved in advance by the COR. Interruptions shall be kept to an absolute minimum and all repairs or replacements of equipment or components shall be accomplished in an expeditious and efficient manner.
1.20 GOVERNMENT FURNISHED ITEMS
a. General - The amount and type of government furnished items is specified in the Technical Provision of this contract. The Contractor shall be responsible for the proper security of all Government furnished items. All Government furnished property or items are provided in an “as is” condition and shall be used only in connection with performance under this contract consistent with all Federal, Department of Defense, and Environmental Act Policies, standards, codes, or directives. The Contractor should inspect this property prior to installation to ascertain safe condition. The Contractor shall assume all liability for claims arising from its use or misuse while in the Contractor’s possession and shall hold the Government harmless from any claims by the Contractor employees or others.
b. Utilities - The Contractor may use Government utilities where available. The Contractor shall make a dedicated effort to conserve utilities and shall comply with all Government regulations regarding energy conservation. Government furnished utilities shall be used only in the performance of work specified in this contract. Where water and electricity are not provided, the Contractor must obtain them from other sources at no additional expense to the Government.
c. Forms -All Department of Defense forms required by the Government to be used under this contract will be provided by the Government.
d. Operating Manuals - Equipment or facility operating manuals and suppliers’ catalogs presently maintained by the Government will be made available to the Contractor on an as needed basis.
e. Control - Contractor shall establish a control system to ensure that Government furnished items are utilized only for contract purposes. Upon completion (including any extension of contract terms) or termination of the contract, for any reason, and except for fair wear and tear, the Contractor shall return all Government furnished items and any unused material, supplies or parts in the same condition as received. Any discrepancies (except for fair wear and tear), damages or deficiencies in the inventory shall be chargeable against the Contractor.
1.21 CONTRACTOR FURNISHED ITEMS.
a. General - Except as described elsewhere in this contract, the Contractor shall furnish all personnel, management, inspections, facilities, vehicles, transportation, equipment and operators, supplies, tools, materials, and parts necessary to accomplish all required services. All Contractor furnished items shall meet all applicable Federal, State, and local laws or regulations. When a Delivery Order requires the use of the equipment or vehicles specified, such items shall include a qualified and competent operator.
Unless otherwise specified, when the Contractor provides services under a Delivery Order, the Contractor shall provide all the necessary “tools of the trade” to accomplish the work. This includes the vehicles necessary to transport government furnished items, any other materials, equipment, supplies, and/or Contractor personnel to and from the job site.
b. Quality - All Contractor furnished supplies, parts and materials used shall be new and the same brand and model as the existing facilities listed in Exhibit H or of a quality equal or better than the items to be replaced; or in accordance with the Government’s specifications. The items used shall be standard products of manufacturers regularly engaged in the production of such items. All Contractor furnished items are subject to approval by the COR prior to being used.
1.22 SAFEGUARDING GOVERNMENT PROPERTY. The Contractor shall cooperate with Government personnel in safeguarding Government property. The Contractor shall be responsible for reporting all acts of vandalism, larceny, or pilferage to the COR. The Contractor shall establish security procedures and safeguards that are compatible with the Government’s existing procedures to protect all equipment, materials, supplies, tools, and other resources. The Contractor shall cooperate with and provide any assistance necessary to the Government during any audits, usage checks of expendable property and inventories of non-expendable property. The Contractor shall maintain accurate records and make them available to the Government upon request.
1.23 NOTIFICATION OF WORK TO BE DONE. When the Contractor is notified of work required under these specifications, the Contractor shall begin work in accordance with 1.18. The notification to the Contractor of work to be performed will be by issuance of Delivery Orders (DD1449), absolutely no work will begin prior to issuance of a Delivery Order.
Upon issuance of a task item Delivery Order, the Delivery Order becomes a firm, fixed-price order for work specified, based on the contract bid prices. The Contractor shall, upon invoicing, be paid the amount shown on the Delivery Order.
1.24 MINIMUM MAN-POWER REQUIREMENTS. The Contractor shall provide an adequate number of fully qualified personnel to perform the work specified herein. Personnel required to handle emergency situations shall be available on call.
1.25 MINIMUM PERSONNEL QUALIFICATIONS. Employees, technical personnel, and subcontractors shall have the education, experience or knowledge as evidenced by license, certificate, diploma, etc., to provide a comprehensive understanding of the systems, components, equipment, and facilities to be serviced, operated, maintained, repaired, renovated and constructed under this contract. Only properly trained and qualified employees or subcontractors shall be used in the performance of this contract. All employees shall be subject to such Government regulations as are applicable during the time spent performing work under this contract.
A file containing the qualifications (education and experience) and/or certification and/or licenses of each employee and subcontractor shall be maintained by the Contractor. These files shall be submitted to the COR and will be used as part of the basis for determining the qualifications of personnel. In the event the Contractor does not have a qualified employee to perform the specific work, the Contractor will be required to immediately provide qualified personnel or to subcontract the work to a specialist familiar with the type of work to be accomplished.
1.26 OTHER CONTRACTS. The Government may undertake or award other contracts or have lessees or volunteers performing certain work, and the Contractor shall fully cooperate with such other Contractors, lessees, volunteers and Government employees and carefully fit their own work to such other additional work as may be directed by the COR. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another Contractor, by a lessee, by volunteers or by Government employees. The COR can alter the work schedules of the Contractor to avoid possible conflicts. Any such change or failure to make such a change by the COR shall not be the basis for a claim by the Contractor.
1.27 APPLICABLE PUBLICATIONS. The Contractor shall perform technical work in accordance with applicable publications. They include but are not limited to:
A. Manufacturer’s Recommendations
1. Operating Manuals
2. Repair Manuals
3. Maintenance Manuals
B. Industrial Standards and Codes (latest editions):
1. Underwriter’s Laboratories Inc.
2. National Electrical Code
3. National Fire Protection Association
4. Sheet Metal Manufacturers
5. American Welding Society
6. American National Standards Institute
7. American Concrete Institute
8. Portland Concrete Association
9. Asphalt Institute
10. American Institute of Steel Construction
11. National Association of Architectural Metal Manufacturers
12. Architectural Aluminum Manufacturers Association
13. The Aluminum Association
14. American Society for Testing and Materials
15. State of Texas Standard Specs for Highway Construction
1.28 DAMAGE TO GOVERNMENT PROPERTY. The Contractor shall use reasonable care to avoid damaging buildings, equipment, vegetation and other Government property. If the Contractor damages or loses any of this property, the Contractor shall replace or repair the damage, at no cost to the Government, as the COR directs. A written report of the incident and extent of such damage shall be submitted to the COR within 2 working days (less weekends and holidays) of the occurrence. If the Contractor fails or refuses to make such repairs or replacements, the Contractor shall be liable for the cost, which will be deducted from the contract bid price.
1.29 DEFINITIONS. As used throughout descriptions/specification/work statement, the following terms shall have the meaning set forth below:
a. Contractor. The term Contractor…