Amendment 0001 BID OPENING REMAINS ON 30 AUG 2017 @ 2:00 P.M. LOCAL TIME

View the file

Other files

File Type Posted
C1_ABSTRACT_W9126G-17-B-0026(2).pdf PDF
B3_AMEND-0007_W9126G17B0026.pdf PDF
Amend0006.pdf PDF
g17b0026_0005.pdf PDF
g17b0026_0004.pdf PDF
B3_Amendment_0003-W9126G17B0026.pdf PDF
B3_AMEND-0002_W9126G17B0026.pdf PDF
B3_W9126G17B0026-Specs.pdf PDF
B3_W9126G17B0026-Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W45VAK70174178

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is stated on the pages follow ing See pages follow ing:

BID OPENING REMAINS ON 30 AUG 2017 @ 2:00 P.M.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9126G-17-B-0026

X 9B. DATED (SEE ITEM 11)

31-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Aug-2017

CODE

US ARMY CORPS OF ENGINEERS FORT WORTH

2000 FORT POINT ROAD

GALVESTON TX 77550-1229

W9126G 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9126G17B0026 Page 2 of

A0001-2

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

1. The specifications for Solicitation No. W9126G17B0026, Sabine –Neches Waterway, Texas, Port Arthur Canal Junction Area and Sabine Pass Channel, in Jefferson County, Texas, and Cameron Parish, Louisiana, Pipeline Dredging, are hereby amended as follows:

a) Specifications.

(1) COVER SHEET – The enclosed COVER SHEET supersedes that issued with this Solicitation.

(2) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.

(3) SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 01 10 00.01 45, entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD, supersedes that issued with this Solicitation.

(4) SECTION 01 22 00.10. MEASUREMENT AND PAYMENT – The enclosed SECTION 01 22 00.10, entitled MEASUREMENT AND PAYMENT, supersedes that issued with this Solicitation.

(5) SECTION 35 20 23.17 45, PIPELINE DREDGING - The enclosed SECTION 35 20 23.17 45, entitled PIPELINE DREDGING, supersedes that issued with this Solicitation.

(6) SECTION 35 20 23.17 45 PIPELINE DREDGING, APPENDIX I – QUANTITY

SUMMARY TABLE – The enclosed SECTION 35 20 23.17 45, entitled PIPELINE DREDGING, APPENDIX I – QUANTITY SUMMARY TABLE, supersedes that issued with this Solicitation.

b) Drawings.

(1) DRAWINGS NO. G-02, G-03, C-02, AND C-05 THROUGH C-10 - The enclosed Drawings No. G-02, G-03, C-02, and C-05 through C-10, supersede that issued with this Solicitation.

(2) DRAWINGS NO. C-11, AND C-12 - The enclosed Drawings No. C-11, and C-12, are in addition to that issued with this Solicitation.

2. This amendment shall be attached to and become a part of the solicitation.

7 Encls:

1. COVER SHEET

2. SECTION 00 11 00.00 45, BID SCHEDULE

3. SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD

4. SECTION 01 22 00.10, MEASUREMENT AND PAYMENT

5. SECTION 35 20 23.17 45, PIPELINE DREDGING

6. SECTION 35 20 23.17 45, PIPELINE DREDGING, APPENDIX I – QUANTITY SUMMARY

TABLE

7. DRAWINGS NO. G-02, G-03, C-02, and C-05 through C-12

SOLICITATION NO. W9126G17B0026

SABINE-NECHES WATERWAY, TEXAS

SABINE-NECHES WATERWAY, PORT ARTHUR CANAL

JUNCTION AREA, AND SABINE PASS CHANNEL

IN JEFFERSON COUNTY, TEXAS,

AND CAMERON PARISH, LOUISIANA

PROJECT MANUAL FOR

PIPELINE DREDGING

JULY 2017

DEPARTMENT OF THE ARMY

GALVESTON DISTRICT, CORPS OF ENGINEERS

P.O. BOX 1229

GALVESTON, TEXAS

"INCREASE PROFIT - SUBMIT VECP'S"

This project was designed by the Galveston District of the U.S. Army Corps of Engineers.

The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.

ROBERT C. THOMAS, P.E.

CHIEF, ENGINEERING AND CONSTRUCTION DIVISION

THOMAS.ROBERT.CHARL

ES.III.1062686924

Digitally signed by THOMAS.ROBERT.CHARLES.III.1062686924 DN: c=US, o=U.S. Government, ou=DoD, ou=PKI, ou=USA, cn=THOMAS.ROBERT.CHARLES.III.1062686924 Date: 2017.08.14 15:37:44 -05'00'

SWG FILE NO.:SN 101-300 SOLICITATION NO.: W9126G17B0026

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 11 00.00 45

BID SCHEDULE

PART 1 GENERAL

1.1 BID SCHEDULE

1.1.1 Schedule No. 1

1.1.2 Option No. 1

1.1.3 Option No. 2

1.1.4 Option No. 3

1.2 MODIFICATIONS (CESWG)

1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

-- End of Section Table of Contents --

DOCUMENT 00 11 00.00 45 Page 1

(TO ACCOMPANY AMENDMENT NO. 0001 TO SOLICITATION NO . W9126G17B0026)

SECTION 00 11 00.00 45

BID SCHEDULE

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 BID SCHEDULE

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.1 Schedule No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

SCHEDULE NO. 1

0001 Mobilization and Demobilization

1 JOB SUM $___________

0002 Pipeline Management 1 JOB SUM $___________

0003 Dredging Section Nos. 3 and 4

1,086,000 C.Y. $_________ $___________

0004 Dredging Section Nos. 5 and 6

1,582,000 C.Y. $_________ $___________

TOTAL SCHEDULE NO. 1 $___________

NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.

DOCUMENT 00 11 00.00 45 Page 2

BID SCHEDULE (CONT'D)

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.2 Option No. 1

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 1

0005 Dredging Section No. 1 127,000 C.Y. $_________ $___________

0006 Pipeline Management 1 JOB SUM $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE FOR OPTION NO. 1: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. Award of this Option is contingent upon availability of funds. An additional time of 14 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 3

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.3 Option No. 2

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 2

0007 Dredging Section No. 2 115,000 C.Y. $_________ $___________

0008 Pipeline Management 1 JOB SUM $___________

0009 Standby for Port of Port Arthur Dredging

72 HOUR $_________ $___________

TOTAL OPTION NO. 2 $___________

TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2 $___________

NOTE FOR OPTION NO. 2: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. Award of this Option is contingent upon availability of funds. An additional time of 14 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 4

(TO BE ATTACHED TO STANDARD FORM 1442)

1.1.4 Option No. 3

Item No.

Description Estimated Quantity

Unit Unit Price Estimated Amount

OPTION NO. 3

0010 Dredging Section No. 7 239,000 C.Y. $_________ $___________

0011 Pipeline Management 1 JOB SUM $___________

TOTAL OPTION NO. 1 $___________

TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________

NOTE FOR OPTION NO. 3: The Government may exercise this Option by written notice to the Contractor prior to completion of all authorized work. Award of this Option is contingent upon availability of funds. An additional time of 21 calendar days will be added to this Contract for completion of this Option.

DOCUMENT 00 11 00.00 45 Page 5

(TO BE ATTACHED TO STANDARD FORM 1442)

1.2 MODIFICATIONS (CESWG)

If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment of each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the bid schedule.

1.3 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

-- End of Document --

DOCUMENT 00 11 00.00 45 Page 6

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 00.01 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)

1.5 (SCR-S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR

PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011)

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

DOCUMENT 00 73 00.01 45 Page 1

SECTION 00 73 00.01 45

SPECIAL CONTRACT REQUIREMENTS, STANDARD

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR

52.211-10)

The Contractor shall be required to:

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives Notice to Proceed;

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than 206(AM#1)229 calendar days. The time stated for completion shall include final cleanup of the premises.

1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,406.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys. The general shape of the existing section of channel to be dredged is shown by cross sections on the Contract drawings.

(b) Weather Conditions. Under ordinary conditions, the mean tidal range is about 1.5 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than 2.0 feet below Mean Lower Low Water (MLLW), while southerly winds may raise the water surface as much as, and in some instances more than

3.0 feet above MLLW.

(c) Transportation Facilities. The immediate vicinity is served by railroad, highway, and deep and shallow draft channels.

DOCUMENT 00 73 00.01 45 Page 2

(d) Other Information. Channel traffic consists of deep draft ships, small boats of various sizes, fishing vessels, tugs, and tows consisting of a tug and one or more barges. Traffic will interfere with dredging operations to some extent.

Contractor should expect to encounter strong currents in all the dredging sections.

1.4 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)

(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con-tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:

http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx.

1.5 (SCR-S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR

PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011)

The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE

WITH DAVIS-BACON AND RELATED ACT REGULATIONS.

DOCUMENT 00 73 00.01 45 Page 3

If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations. When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.

The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://rms.usace.army.mil/) for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government's Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data;

ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.

All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Document --

DOCUMENT 00 73 00.01 45 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

1.1.1 Mobilization and Demobilization

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.2 Pipeline Management

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 Dredging

1.2.1.1 Payment for Dredging Section Nos. 3 through 7

1.2.1.2 Payment for Dredging Section Nos. 1 and 2

1.2.1.3 Dredging Partial Payment

1.2.1.4 Measurement

1.2.1.5 Electronic Positioning

1.2.1.6 Unit of Measurement

1.2.2 Standby for Port of Port Arthur Dredging

1.2.2.1 Payment

1.2.2.2 Measurement

1.2.2.3 Unit of Measure

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 22 00.10 Page 1

SECTION 01 22 00.10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 LUMP SUM PAYMENT ITEMS

Payment items for the work of this Contract for which Contract lump sum payments will be made are listed in the BID SCHEDULE and specified below.

All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, will be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed will constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for which separate payment is not otherwise provided.

1.1.1 Mobilization and Demobilization

1.1.1.1 Payment

The Contract price for "Mobilization and Demobilization" in Schedule No. 1 will include the costs in connection with mobilization and demobilization of the plant necessary to perform work under the various bid items. The Contract price will include transportation and other costs incidental to delivery of the plant and other equipment to the general work area in condition ready for operation and, after the completion of the work, for removal of the plant and equipment from the work site(s). Payment for mobilization and demobilization will be pursuant to the conditions as defined in the SECTION 00 72 00 CONTRACT CLAUSES.

1.1.1.2 Unit of Measure

Unit of measure: Job.

1.1.2 Pipeline Management

1.1.2.1 Payment

Payment for "Pipeline Management" in Schedule No. 1 and Option Nos. 1, and 2,(AM#1)2, and 3, will be made for costs associated with laying, handling of dredge pipelines, from the dredge to the Placement Area, procurement of materials, and for construction of ramps or installation of culvert pipes that may be necessary in connection with placing and removal of pipeline and final clean up of pipeline route. Monthly partial payments will be based on the estimates of work completed during the period up to 80 percent of the Contract price and the remaining 20 percent will be paid in the first monthly partial payment after removal of the pipeline and the final clean-up of the pipeline route.

SECTION 01 22 00.10 Page 2

1.1.2.2 Unit of Measure

Unit of measure: Job.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work in this Contract on which the Contract unit price payments will be made are listed in the BID SCHEDULE and specified below. The unit price and payment made for each item listed will constitute full compensation for furnishing plant, labor, materials, and equipment, and performing any associated Contractor Quality Control, administrative requirements, environmental protection, meeting safety requirements, tests and reports, and for performing the work required for each of the unit price items.

1.2.1 Dredging

1.2.1.1 (AM#1)Payment for Dredging Section Nos. 3 through 76

Payment for "Dredging Section Nos. 3 and 4" and "Dredging Section Nos. 5 and 6" in Schedule No. 1 (AM#1), and "Dredging Section No. 7" in Option No.

3, will be made for costs associated with the removal of dredged material, transportation, and placement at the Placement Area.

1.2.1.2 Payment for Dredging Section Nos. 1 and 2

Payment for "Dredging Section No. 1" in Option No. 1 and "Dredging Section No. 2" in Option No. 2 will be made for costs associated with the removal of dredged material, transportation, and placement at the Placement Area and for cost associated with breached dike repair work.

1.2.1.3 Dredging Partial Payment

Partial payment will be based on approximate quantities determined by fathometer soundings or sweepings taken behind the dredge. The Contractor may use its own hydrographic surveys to determine quantities for pay requests, but final quantities will be based on Government Before-Dredging and After-Dredging surveys.

1.2.1.4 Measurement

The material removed will be measured by cubic yard in place, by means of soundings taken before and after dredging. The total quantity of dredged material will be the theoretical quantity between the bottom surface shown by fathometer soundings of the last survey made "before-dredging" and the bottom surface shown by the fathometer soundings of a survey made "after-dredging", within the limits of the overdepth and side and end slopes, less deductions that may be required for misplaced material.

1.2.1.5 Electronic Positioning

The horizontal control points shown are the control points the Government will use to perform electronic surveys on the waterway. The Government does not guarantee permanent access to these control points, therefore, it may be necessary for the Contractor to establish its own network of survey points from these survey points or from other U.S. Coast and Geodetic Survey (USCGS) monuments. Location and description of the horizontal control points which the Government plans to use to perform electronic surveys on the channels are available at the Port Arthur Resident Office.

SECTION 01 22 00.10 Page 3

The Contractor will be responsible for establishing its own reference line to conduct hydrographic surveys and dredging operations if electronic positioning equipment is not used.

1.2.1.6 Unit of Measurement

Unit of measure: cubic yard.

1.2.2 Standby for Port of Port Arthur Dredging

1.2.2.1 Payment

Payment for standby time will be made at the Contract unit price for "Standby for Port of Port Arthur Dredging" in Option No. 2, which will include required standby time at the port docks associated with idle time for ships to move from the dock to allow for dredging. No separate payment will be made for standby or down time incurred while dredging the federal channels.

1.2.2.2 Measurement

Standby time will be measured to the nearest 0.25 hour and recorded in the daily report.

1.2.2.3 Unit of Measure

Unit of measure: Hour

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 01 22 00.10 Page 4

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 20 23.16 45

PIPELINE DREDGING

PART 1 GENERAL

1.1 SUMMARY

1.2 MEASUREMENT AND PAYMENT

1.3 WORK COVERED BY CONTRACT PRICE

1.3.1 Existing Conditions

1.4 REFERENCES

1.5 SUBMITTALS

1.6 CHARACTER OF MATERIAL

1.6.1 Debris Within the Dredging Limits

1.7 EASEMENTS

1.8 UTILITIES ACROSS THE LIMITS OF DREDGING

1.8.1 Known Pipeline/Utility Crossings

1.9 (AM#1)ORDER OF WORK

1.9.1 Dredging Options

1.10 OBSTRUCTION OF CHANNEL

1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION

1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

1.13 SIGNAL LIGHTS (CESWG)

1.14 PLANT

1.14.1 General Requirements

1.14.2 Capacity

1.14.3 Inspectors (Government Agents) Transportation

PART 2 PRODUCTS

2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT

2.2 LOOKOUTS AND RADIO COMMUNICATIONS

PART 3 EXECUTION

3.1 ESTIMATED QUANTITY OF MATERIAL

3.1.1 Quantity Summary

3.1.2 Required Dredging Prism

3.1.3 Allowable Overdepth

3.1.4 Side And End Slopes

3.1.5 Excessive Dredging

3.2 AREAS TO BE DREDGED

3.3 CONDUCT OF DREDGING WORK

3.3.1 Pre-Operations Safety Coordination Meeting

3.3.2 Protection of Existing Waterways

3.3.3 Adjacent Property and Structures

3.4 PLACEMENT OF EXCAVATED MATERIAL

3.4.1 General

3.4.1.1 Confined Placement Area No. 5A

3.4.1.2 Confined Placement Area No. 8

3.4.1.3 Misplaced Material

3.4.1.4 Placement Operations Inspection

SECTION 35 20 23.17 45 Page 1

3.4.1.5 Placement Area Drainage

3.4.1.6 Maintenance of Existing Dikes and Drop-outlet Structures

3.4.2 Spillway Operations

3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY

3.5.1 Damages

3.5.2 Accountability and Restoration

3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER

AWARD OF CONTRACT

3.6.1 Data Submittal

3.7 METHOD OF PLACEMENT

3.7.1 Pipeline Route

3.8 DISPOSAL IN PLACEMENT AREA

3.8.1 Utilities within the Placement Area

3.8.2 Unauthorized Placement of Material

3.8.3 Debris Disposal

3.9 DREDGE PIPELINES

3.9.1 Submerged Pipeline

3.9.2 Submerged Pipeline Lighting Requirements

3.9.3 Floating Pipeline

3.9.4 Pipeline Leaks

3.10 PORT ARTHUR VESSEL TRAFFIC SERVICE AREA

3.10.1 General

3.10.2 Report Changes

3.10.3 Vessel Traffic Service Location

3.10.4 Communications

3.11 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS

3.12 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)

3.13 AUTOMATIC IDENTIFICATION SYSTEM

3.14 DREDGE PLANT INSTRUMENTATION

ATTACHMENTS:

Appendix 1 - QUANTITY SUMMARY TABLE

-- End of Section Table of Contents --

SECTION 35 20 23.17 45 Page 2

SECTION 35 20 23.16 45

PIPELINE DREDGING

AMENDMENT NO. 0001

PART 1 GENERAL

1.1 SUMMARY

The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto.

1.2 MEASUREMENT AND PAYMENT

Measurement and payment for pipeline dredging will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND

PAYMENT.

1.3 WORK COVERED BY CONTRACT PRICE

Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE entitled CHANGES. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: CHARACTER OF MATERIAL and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging shall include the costs for maintenance of dikes and ditches necessary to confine the material within the areas shown.

1.3.1 Existing Conditions

The drawings already prepared as specified in the CONTRACT CLAUSES Paragraph entitled CONTRACT DRAWINGS AND SPECIFICATIONS represent conditions existing as of the date of their preparation using average existing conditions. However, to reflect anticipated shoaling occurring between the dates of preparation of the drawings and the dates of the "before-dredging" sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging. The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used.

Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.

SECTION 35 20 23.17 45 Page 3

1.4 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 1110-2-5027 (1987) Confined Disposal of Dredged Material

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Notification Prior To Commencement of Dredging Operations; G

Indicate commencement of dredging operations, and location of dredge(s).

Temporary Removal of Aids To Navigation; G

Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.

SD-02 Shop Drawings

Submerged Pipeline; G

Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.

Pipeline Route; G

A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations shall be submitted prior to commencing work on this project.

1.6 CHARACTER OF MATERIAL

The material to be removed is shoals which have accumulated over a period of time. However, some virgin material may be encountered in allowable overdepth, or side slope dredging. Bidders are expected to examine the worksite and the records of previous dredging, which are available in the Port Arthur Resident Office and after investigation decide for themselves the character of materials.

1.6.1 Debris Within the Dredging Limits

Debris including but not limited to, metal bands, pallets, pieces of broken

SECTION 35 20 23.17 45 Page 4 cable, rope, stumps, and broken piles may be encountered. Debris removed from the dredged area shall be removed from the water. Disposal shall be the responsibility of the Contractor and disposal shall be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE entitled

DIFFERING SITE CONDITIONS.

1.7 EASEMENTS

Permits authorizing the laying of shore pipe, and for placement of dredge material in the Placement Areas are on file and available for examination in the Port Arthur Resident Office of the U.S. Army Corps of Engineers, 8737 (AM#1)9th9nth Avenue, Port Arthur, Texas. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor shall strictly comply with the terms thereof.

1.8 UTILITIES ACROSS THE LIMITS OF DREDGING

It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor shall take precautions against damages which can result from dredging operations in the vicinity of the utility crossings. If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved. Costs of these repairs and downtime of the dredge and attendant plant shall be at the Contractor's expense.

1.8.1 Known Pipeline/Utility Crossings

APPROX.

STATION

OWNER PHONE PIPE SIZE CONTENTS PERMIT NO.

SABINE PASS CHANNEL

158+00 Plains Marketing, L.P.

1-10" Gas 20725

242+27.5 Kinder Morgan Pipeline Co.

(409) 658-0848

1-30" Gas 12504

243+73.5 Kinder Morgan Pipeline Co.

1-30" Gas 12504

243+83 Kinder Morgan Pipeline Co.

(This pipeline may no longer exist.)

1-30" Gas 12504

SABINE-NECHES CANAL

APPROX.

STATION

OWNER PHONE PIPE SIZE

CONTENTS

PERMIT NO.

SECTION 35 20 23.17 45 Page 5

APPROX.

STATION

OWNER PHONE PIPE SIZE CONTENTS PERMIT NO.

183+40 City of Port Arthur

409-983-822 Two Waterlines (Abandoned?)

195+37 City Of Port Arthur

One 16-inch Waterline

14114

EVERY EFFORT HAS BEEN MADE TO GIVE ALL PERTINENT DETAILS ON THE LOCATION OF

PIPELINES/UTILITIES. THE DATA FURNISHED ON THE PLANS ARE BELIEVED TO BE

SUBSTANTIALLY CORRECT. HOWEVER, THE EXACT LOCATIONS MAY VARY FROM THAT

SHOWN: THEREFORE THE CONTRACTOR SHALL COOPERATE WITH THE RESPECTIVE OWNERS

TO ESTABLISH THE ACTUAL POSITION OF THE PIPELINES/UTILITIES.

IF DREDGING OVER A PIPELINE OR PIPELINE CORRIDOR CANNOT BE ACCOMPLISHED

WITH A SPUDDING METHOD, THE CONTRACTOR SHALL FIND AN ALTERNATIVE METHOD TO

SAFELY DREDGE OVER THOSE PIPES.

THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE OWNERSHIPS:

Lonestar Notification Center 1-713-223-4567 or 1-800-669-8344

Texas 811 (Dig-Tess) 1-800-344-8377

1.9 (AM#1)ORDER OF WORK

The Conractor shall commence dredging at the Port Arthur Canal Junction Area, Taylors Bayou Entrance Channel and West Turning Basin, Sabine Pass Channel, Port of Port Arthur Dock and Sabine-Neches Canal Turning Basin, in that order. The Government reserves the right to change the order of work at any time.The Contractor shall commence dredging at the the Port Arthur Canal Junction Area, Port of Port Arthur Docks, Sabine-Neches Canal Turning Basin and Sabine Pass Channel in that order. The Government reserves the right to change the order of work at any time.

1.9.1 Dredging Options

The Government will award Dredging Options as specified.

1.10 OBSTRUCTION OF CHANNEL

The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant shall be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage.Upon completion of the work, the Contractor shall promptly remove its plant, including ranges, buoys, piles, and other marks placed under

SECTION 35 20 23.17 45 Page 6 this Contract.

1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION

The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. The Contractor shall notify the Contracting Officer at least 21 days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.

The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation.

1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS

Notify the Port Arthur Resident Engineer, Northern Area Office, in writing, at least 10 days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE entitled SCHEDULE FOR CONSTRUCTION

CONTRACTS.

1.13 SIGNAL LIGHTS (CESWG)

The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the U.S. Coast Guard governing the:

i) lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations;

ii) lights to be displayed on dredge pipe lines;

iii) day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel;

iv) and the passing by other vessels of floating plant working in navigable channels, as set forth in United States Coast Guard publication entitled Navigation Rules and Regulations Handbook. Web site location:

http://www.navcen.uscg.gov/?pageName=navRuleChanges

1.14 PLANT

1.14.1 General Requirements

Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in specifications and shall be subject to inspection by the Contracting Officer's representative at all times.

SECTION 35 20 23.17 45 Page 7

1.14.2 Capacity

No reduction in the capacity of the dredge equipment and attendant plant employed to execute the work shall be made except by written direction of the Contracting Officer. The measure of the "Capacity of the Dredge and Attendant Plant" shall be its actual performance on the work to which these specifications apply.

1.14.3 Inspectors (Government Agents) Transportation

Furnish, throughout the Contract period, for the exclusive use of the Government: a motorboat, minimum 18 feet in length, with enclosed cabin, a minimum of a 50 horsepower motor and equipped with safety equipment as required by EM 385-1-1. Furnish fuel, oil, and maintenance for the motorboat throughout the Contract period. Assume full responsibility for the storage and security of the motorboat when not in use by the Government employees. There shall be no separate payment for these items and the cost shall be distributed throughout the existing bid items. Equipment which fails to perform because of insufficient power or other mechanical deficiencies shall be replaced and inexperienced operators unable to operate the equipment shall be replaced within 12 hours after the Contractor is directed to do. No smoking shall be allowed inside the cabin and operator's space while occupied by Government personnel. No Smoking signs shall be posted.

PART 2 PRODUCTS

2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT

Dredge and self-propelled attendant floating plant shall be radiotelephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radiotelephone Act (Public Law 92-63). This will require, as a minimum, the radiotelephone equipment capable of transmitting and receiving on

156.65 MHz (Channel 13). Multi-channel equipment will also require 156.8 MHz (Channel 16). Dredge tugs and tenders will be considered towing vessels within the meaning of the Act.

2.2 LOOKOUTS AND RADIO COMMUNICATIONS

When working in the Sabine-Neches Waterway, the Contractor shall have a lookout person posted in the dredge control room at all times to visually monitor the movement of vessels around the dredge plant; to perform radio communications with company workboats; and to deliver passing arrangements with other commercial, fishing and recreational vessels. The lookout shall be competent in U.S. Coast Guard and Federal Communications Commission radio communications procedures and requirements and shall be trained in the Vessel Bridge to Bridge Radiotelephone Act. The lookout shall maintain up to the minute information on the status of each company workboat and approaching vessels, and will communicate this information as required to prevent collisions. Each company workboat shall check in with the lookout when arriving at the dredge and shall receive radio clearance from the lookout before departing the dredge.

FAILURE TO COMPLY WITH THIS REQUIREMENT WILL BE CONSIDERED A VIOLATION OF

THE SAFETY PROTOCOL ESTABLISHED HEREIN. PURSUANT TO THE DIRECTION OF THE

CONTRACTING OFFICER, THE CONTRACTOR MAY BE REQUIRED TO CEASE OPERATIONS

UNTIL THIS PROVISION IS COMPLIED WITH. A SUSPENSION, DELAY OR INTERRUPTION

OF WORK ARISING FROM NON-COMPLIANCE OF THIS PROVISION SHALL NOT CONSTITUTE

A BREACH OF THIS CONTRACT AND SHALL NOT ENTITLE THE CONTRACTOR TO A PRICE

SECTION 35 20 23.17 45 Page 8

ADJUSTMENT IN ACCORDANCE WITH THE CONTRACT CLAUSE ENTITLED SUSPENSION OF

WORK OR ANY OTHER PROVISION UNDER THIS CONTRACT.

PART 3 EXECUTION

3.1 ESTIMATED QUANTITY OF MATERIAL

Within the limits of available funds, the Contractor will be required to excavate the entire quantity of material necessary to complete the work specified whether the quantities involved are greater or less than those estimated. The work is to be done in accordance with this Contract and at the Contract price or prices, subject to the provisions of the SECTION 01 10 00.01 45 NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph entitled VARIATIONS IN ESTIMATED QUANTITIES - DREDGING.

3.1.1 Quantity Summary

The quantities listed in Appendix 1 - QUANTITY SUMMARY TABLE include the volumes present at the time of the surveys indicated on the Contract drawings, plus anticipated shoaling before dredging begins. For the purpose of acceptance, the pipeline dredging work in the Bid Item(s) of the Bidding Schedule are divided into Sections.

3.1.2 Required Dredging Prism

The total estimated amount of material to be removed from within the specified limits, including side and end slopes and including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys but excluding overdepths, in cubic yards is listed in Appendix 1 - QUANTITY

SUMMARY TABLE.

3.1.3 Allowable Overdepth

To cover unavoidable inaccuracies of the dredging process, material actually removed from the designated areas to be dredged, will be measured and paid for at full Contract price. The maximum amount of allowable overdepth dredging is estimated, including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys in cubic yards is listed in Appendix 1 - QUANTITY SUMMARY TABLE.

3.1.4 Side And End Slopes

Dredging of the side and end slopes shall follow, as closely as practicable, the lines indicated or specified. Material actually removed from within the limits as approved, to provide for final side and end slopes as specified, but not in excess of the amounts originally above the limiting side and end slopes will be estimated and paid for, whether dredged in original position or by dredging the space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut. In computing the limiting amount of side and end slope dredging, net dimensions, without allowance for overdepth, will be used.

3.1.5 Excessive Dredging

Material taken from beyond the limits specified will be deducted from the total amount dredged as excessive overdepth dredging or excessive side or end slope dredging, for which payment will not be made. Nothing herein shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of the SECTION 01 10 00.01 45

SECTION 35 20 23.17 45 Page 9

NON-REGULATED SPECIAL CONTRACT REQUIREMENTS, Paragraph FINAL EXAMINATION AND ACCEPTANCE or Paragraph SHOALING.

3.2 AREAS TO BE DREDGED

Based on information currently available to the Government, areas known to require dredging are shown.

3.3 CONDUCT OF DREDGING WORK

3.3.1 Pre-Operations Safety Coordination Meeting

Prior to arrival on location and commencing dredge operations, the Contractor shall attend a pre-dredging safety coordination meeting between the dredge operators, pilots, towing industry representatives, VTS, and the affected port.

3.3.2 Protection of Existing Waterways

Conduct dredging operations using a method that will ensure that material or other debris are not pushed outside of the dredging limits or otherwise deposited in existing side channels, basins, docking areas, or other areas being used by vessels. The Contractor will be required to change its method of operations as may be required to comply with the above requirements. If bottom material or other debris is pushed into areas noted above, as a result of the Contractor's operations, the same shall be promptly removed by and at the expense of the Contractor to the satisfaction of the Contracting Officer.

3.3.3 Adjacent Property and Structures

Dredging adjacent to a structure will not be permitted closer than that shown. At the Port of Port Arthur Dock, no deep dredging will be permitted within 10 feet of the dock face in Berth Nos. 3, 4 and 5, as there is inter-locking slope protection below 45 foot in those areas. All pipeline and pontoons must be continuously secured and maintained away from all dock face, support piles, cluster piles, etc. Damage to private or public property or structures resulting from the disposal or dredging operations shall be repaired promptly by and at the Contractor's expense. Damage to structures as a result of Contractor's negligence will result in suspension of dredging and require prompt repair at the Contractor's expense as a prerequisite to the resumption of dredging.

3.4 PLACEMENT OF EXCAVATED MATERIAL

3.4.1 General

Material excavated shall be transported to and deposited in the Placement Area designated. All existing drop-outlet structures shall be repaired as necessary, as a minimum, replacing damaged or missing weir boards. The Contractor shall take precautionary measure to ensure boards are not removed by the public. Particular statutes which the Contractor shall consider include, but are not limited to, the Federal Migratory Bird Treaty Act and the Endangered Species Act of 1973.

3.4.1.1 Confined Placement Area No. 5A

Confined Placement Area No. 5A shall be used to deposit material to be dredged from Section Nos. 5 and 6. The perimeter dike shall be maintained

SECTION 35 20 23.17 45 Page 10 and repaired as necessary for the duration of this Contract. Repairs to the breaches or low areas shall be constructed to the lines and grades of the existing adjacent dikes. A spreader shall be used to reduce scouring and to distribute the material evenly. The Contractor shall monitor and control movement of the discharge point to insure an even build-up of material throughout the Placement Area and to prevent overflowing the dike. Dikes shall be maintain to the lines and grades shown. The effluent ditch shall be maintained and excavated, as nessesary, to prevent overflowing of the ditch.

The laying of dredge pipelines to the Placement Area No. 5A will require crossing a private gravel road. Contractor will be required to coordinate with the land owner to determine requirements/permits for the pipeline ramp crossing to PA 5A.

3.4.1.2 Confined Placement Area No. 8

The south discharge corridor of the Confined Placement Area No. 8 shall be used to deposit material to be dredged from Section Nos. 3 and 4 in Schedule No. 1 (AM#1), and Section No. 7 in Option No.