W45VAK61419915 088910
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Unrestricted Procurement for Houston Ship Channel, Texas in Chambers County, Texas, Houston Ship Channel at Bayport Flare, Oyster Mitigation in w hich bid opening is scheduled for 15 Aug 17 @ 2:00 PM CST is hereby amended as follow s:
Continued on Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
W9126G17B0013
X 9B. DATED (SEE ITEM 11)
14-Jul-2017
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Aug-2017
CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
2000 FORT POINT ROAD
GALVESTON TX 77550-1229
W9126G 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
M3ODXMAN
Text Box
W9126G17B0013
A0001-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. The specifications for Solicitation No. W9126G17B0013, Houston Ship Channel, Texas, Houston Ship Channel at Bayport Flare in Chambers County, Texas, Oyster Mitigation, are hereby amended as follows:
THE PROPOSAL DUE DATE IS HEREBY RESCHEDULED FOR 21 AUGUST 2017, AT 3:00
P.M. CDT.
a) Specifications.
(1) SECTION 01 35 26.01 45, GOVERNMENTAL SAFETY REQUIREMENTS – The enclosed SECTION 01 35 26.01 45, entitled GOVERNMENTAL SAFETY REQUIREMENTS, supersedes that issued with this Solicitation.
(2) SECTION 01 45 01.00, QUALITY CONTROL – The enclosed SECTION 01 45 01.00, entitled QUALITY CONTROL, supersedes that issued with this Solicitation.
b) Drawings.
(1) NONE
2. This amendment shall be attached to and become a part of the solicitation.
2 Encls:
1. SECTION 01 35 26.01 45, GOVERNMENTAL SAFETY REQUIREMENTS
2. SECTION 01 45 01.00, QUALITY CONTROL
SWG FILE NO.:HSC 401-554 SOLICITATION NO.: W9126G17B0013
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
1.2.2 Competent Person, Cranes and Rigging
1.2.3 Competent Person, Fall Protection
1.2.4 Competent Person (CP) Trainer
1.2.5 High Risk Activities
1.2.6 High Visibility Accident
1.2.7 Load Handling Equipment (LHE)
1.2.8 Medical Treatment
1.2.9 Near Miss
1.2.10 Operating Envelope
1.2.11 Qualified Person (QP)
1.2.12 Recordable Injuries or Illnesses
1.2.13 USACE Property and Equipment
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling
Equipment Mishap
1.3 SUBMITTALS
1.4 MONTHLY EXPOSURE REPORTS
1.5 REGULATORY REQUIREMENTS
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
1.6.1.2 Contractor Quality Control (QC) Manager
1.6.1.3 Competent Person Qualifications
1.6.1.4 Crane Operators/Riggers
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
1.6.3.2 Safety Meetings
1.7 ACCIDENT PREVENTION PLAN (APP)
1.7.1 Names and Qualifications
1.7.2 Plans
1.7.2.1 Standard Lift Plan (SLP)
1.7.2.2 Critical Lift Plan - Crane or Load Handling Equipment
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
1.8.1 AHA Management
1.8.2 AHA Signature Log
1.9 DISPLAY OF SAFETY INFORMATION
1.9.1 Safety Bulletin Board
1.9.2 Safety and Occupational Health (SOH) Deficiency Tracking System
1.10 SITE SAFETY REFERENCE MATERIALS
1.11 EMERGENCY MEDICAL TREATMENT
1.12 NOTIFICATIONS AND REPORTS
1.12.1 Mishap Notification
SECTION 01 35 26.01 45 Page 1
(TO ACCOMPANY AMENDMENT NO.0001 TO SOLICITATION NO. W9126G17B0013)
1.12.2 Accident Reports
1.12.3 LHE Inspection Reports
1.12.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
1.13 SEVERE STORM PLAN
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
3.1.1 Worksite Communication
3.1.2 Unforeseen Hazardous Material
3.2 EQUIPMENT
3.2.1 Material Handling Equipment (MHE)
3.2.2 Load Handling Equipment (LHE)
3.2.3 Machinery and Mechanized Equipment
3.2.4 Use of Explosives
-- End of Section Table of Contents --
SECTION 01 35 26.01 45 Page 2
SECTION 01 35 26.01 45
GOVERNMENTAL SAFETY REQUIREMENTS
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSE/SAFE Z359.0 (2012) Definitions and Nomenclature Used for Fall Protection and Fall Arrest
ASME INTERNATIONAL (ASME)
ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-Hook Lifting Devices
ASME B30.22 (2010) Articulating Boom Cranes
ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging Hardware
ASME B30.3 (2012) Tower Cranes
ASME B30.5 (2014) Mobile and Locomotive Cranes
ASME B30.8 (2010) Floating Cranes and Floating Derricks
ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2013) Standard for Portable Fire Extinguishers
NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction,Alteration, and Demolition Operations
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2 2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
NFPA 70E (2015; ERTA 1 2015) Standard for Electrical Safety in the Workplace
SECTION 01 35 26.01 45 Page 3
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1926.1400 Cranes and Derricks in Construction
29 CFR 1926.16 Rules of Construction
1.2 DEFINITIONS
1.2.1 Competent Person (CP)
The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.
1.2.2 Competent Person, Cranes and Rigging
The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.3 Competent Person, Fall Protection
The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSE/SAFE Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
1.2.4 Competent Person (CP) Trainer
A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.
SECTION 01 35 26.01 45 Page 4
1.2.5 High Risk Activities
High Risk Activities are activities that involve work at heights, crane and rigging and electrical work.
1.2.6 High Visibility Accident
A High Visibility Accident is any mishap which may generate publicity or high visibility.
1.2.7 Load Handling Equipment (LHE)
LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).
1.2.8 Medical Treatment
Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.2.9 Near Miss
A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).
1.2.10 Operating Envelope
The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.
1.2.11 Qualified Person (QP)
The QP is a person designated in writing, who, by possession of a recognized degree, License certificates, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.
1.2.12 Recordable Injuries or Illnesses
Recordable Injuries or Illnesses are any work-related injury or illness that results in:
a. Death, regardless of the time between the injury and death, or the length of the illness;
b. Days away from work (any time lost after day of injury/illness onset);
c. Restricted work;
SECTION 01 35 26.01 45 Page 5
d. Transfer to another job;
e. Medical treatment beyond first aid;
f. Loss of consciousness; or
g. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (a) through (f) above.
1.2.13 USACE Property and Equipment
Interpret "USACE" property and equipment specified in USACE EM 385-1-1 as Government property and equipment.
1.2.14 Load Handling Equipment (LHE) Accident or Load Handling Equipment Mishap
A LHE accident occurs when any one or more of the eight elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment;
two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, or roll over). Document any mishap that meets the criteria described in the Contractor Significant Incident Report (CSIR).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with the SECTION 01 33 00 SUBMITTAL PROCEDURES:
Government acceptance, as defined in EM 385-1-1, is required for submittals with a "G,A" designation.
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G,A
SD-06 Test Reports
Monthly Exposure Reports Notifications and Reports Accident Reports LHE Inspection Reports
SD-07 Certificates
Crane Operators/Riggers Standard Lift Plan
SECTION 01 35 26.01 45 Page 6
Critical Lift Plan Activity Hazard Analysis (AHA) Certificate of Compliance License Certificates
1.4 MONTHLY EXPOSURE REPORTS
Provide a Monthly Exposure Report for the previous month's work and submit to the Government not later than the fifth day of each month. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. Failure to submit the report may result in retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, and the following federal, state, and local laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
Provide an SSHO that meets the requirements of EM 385-1-1 Section 1. The SSHO must ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one
(1) person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Alternate SSHO must be at the work site at all times to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO and Alternate SSHO must have the required training, experience, and qualifications in accordance with EM 385-1-1 Section 01.A.17, and all associated sub-paragraphs. (AM#1)The SSHO and Alternate SSHO may not have other collateral duties.
If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed. Note that the DR is a collateral duty safety position, with safety duties in addition to their full time occupation.
1.6.1.2 Contractor Quality Control (QC) Manager
The Contractor Quality Control Manager cannot be the SSHO on this project,even though the QC has safety inspection responsibilities as part of the QC duties.
SECTION 01 35 26.01 45 Page 7
1.6.1.3 Competent Person Qualifications
Provide Competent Persons in accordance with EM 385-1-1, Appendix Q and herein. Competent Persons for high risk activities include cranes and rigging, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e. competent person, fall protection).
The Competent Person identified in the Contractor's Safety and Health Program and accepted Accident Prevention Plan, must be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the the Contracting Officer for information in consultation with the Safety Office.
1.6.1.4 Crane Operators/Riggers
Provide Operators meeting the requirements in EM 385-1-1, Section 15.B for Riggers and Section 16.B options 1 or 4 for Crane Operators.
1.6.2 Personnel Duties
1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)
The SSHO must:
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily production report.
b. Conduct mishap investigations and complete required accident reports.
Report mishaps and near misses.
c. Use OSHA's Form 300 to log work-related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors. Post and maintain the Form 300 on the site Safety Bulletin Board.
d. Maintain applicable safety reference material on the job site.
e. Attend the pre-construction conference, pre-work meetings including preparatory meetings, and periodic in-progress meetings.
f. Review the APP and AHAs for compliance with EM 385-1-1, and approve, sign, implement and enforce them.
g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking System that lists and monitors outstanding deficiencies until resolution.
h. Ensure subcontractor compliance with safety and health requirements.
i. Maintain a list of hazardous chemicals on site and their material Safety Data Sheets (SDS).
j. Maintain a weekly list of high hazard activities involving energy, equipment, and elevation, and be prepared to discuss details during QC
SECTION 01 35 26.01 45 Page 8
Meetings.
k. Provide and keep a record of site safety orientation and indoctrination for Contractor employees, subcontractor employees, and site visitors.
Superintendent, QC Manager, and SSHO are subject to dismissal if the above duties are not being effectively carried out. If Superintendent, QC Manager, or SSHO are dismissed, project work will be stopped and will not be allowed to resume until a suitable replacement is approved and the above duties are again being effectively carried out.
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project must attend the preconstruction conference. This includes the project superintendent, Site Safety and Occupational Health officer, quality control manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, and Government review of AHAs to preclude project delays.
c. Deficiencies in the submitted APP, identified during the Contracting Officer's review, must be corrected, and the APP re-submitted for review prior to the start of construction. Work is not permitted to begin work until an APP is established that is acceptable to the Contracting Officer.
1.6.3.2 Safety Meetings
Conduct safety meetings to review past activities, plan for new or changed operations, review pertinent aspects of appropriate AHA (by trade), establish safe working procedures for anticipated hazards, and provide pertinent Safety and Occupational Health (SOH) training and motivation.
Conduct meetings at least once a month for all supervisors on the project location. The SSHO, supervisors, foremen, or CDSOs must conduct meetings at least once a week for the trade workers. Document meeting minutes to include the date, persons in attendance, subjects discussed, and names of individual(s) who conducted the meeting. Maintain documentation on-site and furnish copies to the Contracting Officer on request. Notify the Contracting Officer of all scheduled meetings 7 calendar days in advance.
1.7 ACCIDENT PREVENTION PLAN (APP)
A qualified person must prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of EM 385-1-1, Appendix A, and as supplemented herein. Cover all paragraph and subparagraph elements in EM 385-1-1, Appendix A. The APP must be job-specific and address any unusual or unique aspects of the project or activity for which
SECTION 01 35 26.01 45 Page 9 it is written. The APP must interface with the Contractor's overall safety and health program referenced in the APP in the applicable APP element, and made site-specific. Describe the methods to evaluate past safety performance of potential subcontractors in the selection process. Also, describe innovative methods used to ensure and monitor safe work practices of subcontractors. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP must be signed by an officer of the firm (Prime Contractor senior person), the individual preparing the APP, the on-site superintendent, the designated SSHO, the Contractor Quality Control Manager, and any designated Certified Safety Professional (CSP) or Certified Health Physicist (CIH). The SSHO must provide and maintain the APP and a log of signatures by each subcontractor foreman, attesting that they have read and understand the APP, and make the APP and log available on-site to the Contracting Officer. If English is not the foreman's primary language, the Prime Contractor must provide an interpreter.
Submit the APP to the Contracting Officer no later than 15 calendar days after award for acceptance. Work cannot proceed without an accepted APP.
Once reviewed and accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP is cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Continuously review and amend the APP, as necessary, throughout the life of the contract. Changes to the accepted APP must be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and Quality Control Manager. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered. Should any severe hazard exposure ( i.e. imminent danger) become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery. Eliminate and remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34), and the environment.
1.7.1 Names and Qualifications
Provide plans in accordance with the requirements outlined in Appendix A of EM 385-1-1, including the following:
a. Names and qualifications (resumes including education, training, experience and certifications) of site safety and health personnel designated to perform work on this project to include the designated Site Safety and Health Officer and other competent and qualified personnel to be used. Specify the duties of each position.
b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: fall protection; health hazard recognition, evaluation and control of chemical, physical and biological agents; and personal protective equipment and clothing to include selection, use and maintenance.
SECTION 01 35 26.01 45 Page 10
1.7.2 Plans
Provide plans in the APP in accordance with the requirements outlined in Appendix A of EM 385-1-1, including the following:
1.7.2.1 Standard Lift Plan (SLP)
Plan lifts to avoid situations where the operator cannot maintain safe control of the lift. Prepare a written SLP in accordance with EM 385-1-1, Section 16.A.03, using Form 16-2 for every lift or series of lifts (if duty cycle or routine lifts are being performed). The SLP must be developed, reviewed and accepted by all personnel involved in the lift in conjunction with the associated AHA. Signature on the AHA constitutes acceptance of the plan. Maintain the SLP on the LHE for the current lift(s) being made.
Maintain historical SLPs for a minimum of 3 months.
1.7.2.2 Critical Lift Plan - Crane or Load Handling Equipment
Provide a Critical Lift Plan as required by EM 385-1-1, Section 16.H.01, using Form 16-3. Critical lifts require detailed planning and additional or unusual safety precautions. Develop and submit a critical lift plan to the Contracting Officer 30 calendar days prior to critical lift. Comply with load testing requirements in accordance with EM 385-1-1, Section 16.F.03.
In addition to the requirements of EM 385-1-1, Section 16.H.02, the critical lift plan must include the following:
a. For lifts of personnel, demonstrate compliance with the requirements of 29 CFR 1926.1400 and EM 385-1-1, Section 16.T.
b. For barge mounted mobile cranes, provide a Naval Architecture Analysis and include an LHE Manufacturer's Floating Service Load Chart in accordance with the criteria from the selected standard in EM 385-1-1, Section 16.L.02. The Floating Service Load Chart must provide a table of rated load versus boom angle and radius. The Floating Service Load Chart must also provide the maximum allowable machine list and trim associated with the tabular loads and radii provided. If the Manufacturer's Floating Service Load Chart is not available, a floating service load chart may be developed and provided by a qualified Registered Professional Engineer (RPE), competent in the field of floating cranes. The Load Chart must be in accordance with the criteria from the selected standard in EM 385-1-1, Section 16.L;
provide a table of rated load versus boom angle and radius; provide the maximum allowable machine list and machine trim associated with the tabular loads and radii provided; and be stamped by a RPE qualified and competent in the field of floating cranes. The RPE, competent in the field of floating cranes must stamp and certify (sign) that the Naval Architectural Analysis (NAA) meets the requirements of EM 385-1-1, Section 16.L.03.
c. Multi-purpose machines, material handling equipment, and construction equipment used to lift loads that are suspended by rigging gear, require proof of authorization from the machine OEM that the machine is capable of making lifts of loads suspended by rigging equipment.
Demonstrate that the operator is properly trained and that the equipment is properly configured to make such lifts and is equipped with a load chart.
SECTION 01 35 26.01 45 Page 11
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work. Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the Contracting Officer. Submit the AHA for review at least 15 working days prior to the start of each activity task, or DFOW.
The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.
AHAs must identify competent persons required for phases involving high risk activities, including crane and rigging, electrical work, and fall protection, and scaffolding.
1.8.1 AHA Management
Review the AHA list periodically (at least monthly) at the Contractor supervisory safety meeting, and update as necessary when procedures, scheduling, or hazards change. Use the AHA during daily inspections by the SSHO to ensure the implementation and effectiveness of the required safety and health controls for that work activity.
1.8.2 AHA Signature Log
Each employee performing work as part of an activity, task or DFOW must review the AHA for that work and sign a signature log specifically maintained for that AHA prior to starting work on that activity. The SSHO must maintain a signature log on site for every AHA. Provide employees whose primary language is other than English, with an interpreter to ensure a clear understanding of the AHA and its contents.
1.9 DISPLAY OF SAFETY INFORMATION
1.9.1 Safety Bulletin Board
Within one calendar day after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, may be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, Section 01.A.06.
1.9.2 Safety and Occupational Health (SOH) Deficiency Tracking System
Establish a SOH deficiency tracking system that lists and monitors the status of SOH deficiencies in chronological order. Use the tracking system to evaluate the effectiveness of the APP. A monthly evaluation of the data must be discussed in the QC or SOH meeting with everyone on the project.
The list must be posted on the project bulletin board and updated daily, SECTION 01 35 26.01 45 Page 12 and provide the following information:
a. Date deficiency identified;
b. Description of deficiency;
c. Name of person responsible for correcting deficiency;
d. Projected resolution date;
e. Date actually resolved.
1.10 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in paragraph REFERENCES. Maintain applicable equipment manufacturer's manuals.
1.11 EMERGENCY MEDICAL TREATMENT
Contractors must arrange for their own emergency medical treatment.
Government has no responsibility to provide emergency medical treatment.
1.12 NOTIFICATIONS AND REPORTS
1.12.1 Mishap Notification
Notify the Contracting Officer as soon as practical, but no more than twenty-four hours, after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 Appendix Q, any report of injury, illness, load handling equipment (LHE) or rigging mishaps, or any property damage. The Contractor is responsible for obtaining appropriate medical and emergency assistance and for notifying fire, law enforcement, and regulatory agencies. Immediate reporting is required for electrical mishaps, to include Arc Flash; shock; uncontrolled release of hazardous energy (includes electrical and non-electrical); load handling equipment or rigging; fall from height (any level other than same surface); and underwater diving. These mishaps must be investigated in depth to identify all causes and to recommend hazard control measures.
Within notification include Contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (for example, type of construction equipment used and PPE used). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted. Assist and cooperate fully with the Government's investigation(s) of any mishap.
1.12.2 Accident Reports
a. Conduct an accident investigation for recordable injuries and illnesses, property damage, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident. Complete the applicable The Contracting Officer will provide copies of any required or special forms.
b. Near Misses: Near miss reports are considered positive and proactive
SECTION 01 35 26.01 45 Page 13
Contractor safety management actions.
1.12.3 LHE Inspection Reports
Submit LHE inspection reports required in accordance with EM 385-1-1 and as specified herein with Daily Reports of Inspections.
1.12.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging
Provide a FORM 16-1 Certificate of Compliance for LHE entering an activity under this contract and in accordance with EM 385-1-1. Post certifications on the crane.
Develop a Standard Lift Plan (SLP) in accordance with EM 385-1-1, Section 16.H.03 using Form 16-2 Standard Pre-Lift Crane Plan/Checklist for each lift planned. Submit SLP to the Contracting Officer for approval within 15 calendar days in advance of planned lift.
1.13 SEVERE STORM PLAN
In the event of a severe storm warning, the Contractor must:
a. Secure outside equipment and materials and place materials that could be damaged in protected areas.
b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.
c. Ensure that temporary erosion controls are adequate.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
Comply with EM 385-1-1, NFPA 70, NFPA 70E, NFPA 241, the APP, the AHA, Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
PPE is governed in all areas by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous areas or when performing noise hazardous tasks. Safety glasses must be worn or carried/available on each person. Mandatory PPE includes:
a. Hard Hat
b. Long Pants
c. Appropriate Safety Shoes
d. Appropriate Class Reflective Vests
3.1.1 Worksite Communication
Employees working alone in a remote location or away from other workers
SECTION 01 35 26.01 45 Page 14 must be provided an effective means of emergency communications (i.e., cellular phone, two-way radios, land-line telephones or other acceptable means). The selected communication must be readily available (easily within the immediate reach) of the employee and must be tested prior to the start of work to verify that it effectively operates in the area/environment. An employee check-in/check-out communication procedure must be developed to ensure employee safety.
3.1.2 Unforeseen Hazardous Material
Contract documents identify materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e. 29 CFR Part 1910.1000). If material(s) that may be hazardous to human health upon disturbance are encountered during construction operations, stop that portion of work and notify the Contracting Officer immediately. Within calendar days the Government will determine if the material is hazardous.
If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4, "Changes" and FAR 52.236-2, "Differing Site Conditions."
3.2 EQUIPMENT
3.2.1 Material Handling Equipment (MHE)
a. Material handling equipment such as forklifts must not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.
Material handling equipment fitted with personnel work platform attachments are prohibited from traveling or positioning while personnel are working on the platform.
b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions. Material Handling Equipment Operators must be trained in accordance with OSHA 29 CFR 1910, Subpart N.
c. Operators of forklifts or power industrial trucks must be licensed in accordance with OSHA.
3.2.2 Load Handling Equipment (LHE)
a. Equip cranes and derricks as specified in EM 385-1-1, Section 16.
b. Notify the Contracting Officer 15 working days in advance of any LHE entering the activity, in accordance with EM 385-1-1, Section 16.A.02, so that necessary quality assurance spot checks can be coordinated.Contractor's operator must remain with the crane during the spot check. Rigging gear must comply with OSHA, ASME B30.9 Standards safety standards.
c. Comply with the LHE manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Perform erection under the supervision of a designated person (as defined in ASME B30.5). Perform all testing in accordance with the manufacturer's recommended procedures.
d. Comply with ASME B30.5 for mobile and locomotive cranes, ASME B30.22
SECTION 01 35 26.01 45 Page 15 for articulating boom cranes, ASME B30.3 for construction tower cranes, ASME B30.8 for floating cranes and floating derricks, ASME B30.9 for slings, ASME B30.20 for below the hook lifting devices and ASME B30.26 for rigging hardware.
e. Under no circumstance must a Contractor make a lift at or above 90 percent of the cranes rated capacity in any configuration.
f. When operating in the vicinity of overhead transmission lines, operators and riggers must be alert to this special hazard and follow the requirements of EM 385-1-1 Section 11, and ASME B30.5 or ASME B30.22 as applicable.
g. Do not use crane suspended personnel work platforms (baskets) unless the Contractor proves that using any other access to the work location would provide a greater hazard to the workers or is impossible. Do not lift personnel with a line hoist or friction crane. Additionally, submit a specific AHA for this work to the Contracting Officer. Ensure the activity and AHA are thoroughly reviewed by all involved personnel.
h. Inspect, maintain, and recharge portable fire extinguishers as specified in NFPA 10, Standard for Portable Fire Extinguishers.
i. All employees must keep clear of loads about to be lifted and of suspended loads.
j. Use cribbing when performing lifts on outriggers.
k. The crane hook/block must be positioned directly over the load. Side loading of the crane is prohibited.
l. A physical barricade must be positioned to prevent personnel access where accessible areas of the LHE's rotating superstructure poses a risk of striking, pinching or crushing personnel.
m. Maintain inspection records in accordance by EM 385-1-1, Section 16.D, including shift, monthly, and annual inspections, the signature of the person performing the inspection, and the serial number or other identifier of the LHE that was inspected. Records must be available for review by the Contracting Officer.
n. Maintain written reports of operational and load testing in accordance with EM 385-1-1, Section 16.F, listing the load test procedures used along with any repairs or alterations performed on the LHE. Reports must be available for review by the Contracting Officer.
o. Certify that all LHE operators have been trained in proper use of all safety devices (e.g. anti-two block devices).
p. Take steps to ensure that wind speed does not contribute to loss of control of the load during lifting operations. At wind speeds greater than 20 mph, the operator, rigger and lift supervisor must cease all crane operations, evaluate conditions and determine if the lift may proceed. Base the determination to proceed or not on wind calculations per the manufacturer and a reduction in LHE rated capacity if applicable. Include this maximum wind speed determination as part of the activity hazard analysis plan for that operation.
SECTION 01 35 26.01 45 Page 16
3.2.3 Machinery and Mechanized Equipment
a. Proof of qualifications for operator must be kept on the project site for review.
b. Manufacture specifications or owner's manual for the equipment must be on-site and reviewed for additional safety precautions or requirements that are sometimes not identified by OSHA or USACE EM 385-1-1.
Incorporate such additional safety precautions or requirements into the AHAs.
3.2.4 Use of Explosives
Explosives will not be allowed on this contract.
-- End of Section --
SECTION 01 35 26.01 45 Page 17
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 01.00
QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 QUALITY CONTROL PLAN
3.2.1 Content of the CQC Plan
3.2.2 Acceptance of Plan
3.2.3 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 Contractor Quality Control (CQC) System Manager
3.4.3 Contractor Quality Control (CQC) Personnel
3.4.4 Additional Requirement
3.4.5 Organizational Changes
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Laboratory Validation Requirements
3.7.2 Laboratory Validation Procedures
3.7.3 Coordination
3.8 COMPLETION INSPECTION
3.8.1 Punch-out Inspection
3.8.2 Pre-final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.10 NOTIFICATION OF NON-COMPLIANCE
-- End of Section Table of Contents --
SECTION 01 45 01.00 Page 1
SECTION 01 45 01.00
QUALITY CONTROL
AMENDMENT NO. 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-261 (1999) Quality Assurance of Laboratory Testing Procedures
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program, and all associated costs will be included in the applicable Bid Schedule unit or lump-sum prices.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Establish and maintain an effective Quality Control (QC) system that complies with the CONTRACT CLAUSE titled INSPECTION OF CONSTRUCTION. QC consists of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system must cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements
SECTION 01 45 01.00 Page 2 specified in the Contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production, is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 QUALITY CONTROL PLAN
Submit no later than 10 calendar days from the award date, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the CONTRACT CLAUSE entitled INSPECTION OF CONSTRUCTION. The Government will consider an interim plan for the first 30 calendar days of operation.
Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.
3.2.1 Content of the CQC Plan
Include, as a minimum, the following to cover all operations, both on-site and off-site, including work by:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals. These procedures shall be in accordance with SECTION
01 33 00 SUBMITTAL PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
f. Procedures for tracking deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
SECTION 01 45 01.00 Page 3
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
3.2.2 Acceptance of Plan
Acceptance of the Contractor's Plan is required prior to the start of construction.