Submittal Register
| TITLE: | Sam Rayburn Powerhouse Inverter/Battery System Replacement | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | ||||||||||||||||||
| LOCATION: | Sam Rayburn Powerhouse, Jasper, TX | |||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Trans-mittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Revwr | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Revwr | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01010 | 01 | Preconstruction Submittals | Contractor Employee Eligibility | 1.7.2 | G | ||||||||||||||
| 2 | 01010 | 01 | Preconstruction Submittals | Employee Identification and Control Procedures | 1.7.4 | G | ||||||||||||||
| 3 | 01010 | 01 | Preconstruction Submittals | Location of Contractor's Off-Site Disposal Area and Plan for Safe Disposal | 1.24 | G | ||||||||||||||
| 4 | 01010 | 01 | Preconstruction Submittals | Scaffolding, Ladder, Stairway or Other Access Schemes | 1.25 | G | ||||||||||||||
| 5 | 01010 | 01 | Preconstruction Submittals | Contractor's Work Supervisor(s) Qualifications | 1.30.1 | G | ||||||||||||||
| 6 | 01010 | 01 | Preconstruction Submittals | Dust and Fume Control Plan | 1.34 | G |
| 7 | 01320 | 01 | Preconstruction Submittals | Preliminary Schedule | 1.6.1 | G |
| 8 | 01320 | 01 | Preconstruction Submittals | Initial Schedule | 1.6.2 a. | G |
| 9 | 01320 | 01 | Preconstruction Submittals | Periodic Schedule Updates | 1.6.2 b. | G |
10 01330 01 Preconstruction Submittals Submittal Register 1.14 G
| 11 | 01355 | 01 | Preconstruction Submittals | Environmental Protection Plan | 1.6.1 | G |
| 12 | 01355 | 01 | Preconstruction Submittals | Hazardous Waste Handling Plan | 1.14 | G |
| 13 | 01451 | 01 | Preconstruction Submittals | Quality Control Plan | 3.2.1 | G |
| 14 | 01451 | 01 | Preconstruction Submittals | Contractor Quality Control System Manager Qualifications | 3.2.2 | G |
| 15 | 01525 | 07 | Certificates | EM 385-1-1, Section 1 Documentation | 1.1 | G |
| 16 | 01525 | 09 | Manufacturer's Field Reports | Incident Reports | 1.13 | |
| 17 | 01525 | 09 | Manufacturer's Field Reports | Confined Space Entry Permit | 1.10 |
| 18 | 01781 | 01 | Preconstruction Submittals | O&M Manual Execution Plan | 1.2.1 | G |
| 19 | 01781 | 10 | Operation and Maintenance Data | Operation and Maintenance (O&M) Manual | 1.3 | G |
| 20 | 01782 | 01 | Preconstruction Submittals | Record Drawings Execution Plan | 1.4 | G |
| 21 | 01782 | 11 | Closeout Submittals | Preliminary Record Drawings | 1.7 | G |
| 22 | 01782 | 11 | Closeout Submittals | Preliminary CAD Drawings | 1.7.2.2 | G |
| 23 | 01782 | 11 | Closeout Submittals | Final Inspection Drawings | 1.7.2.3 | G |
| 24 | 01782 | 11 | Closeout Submittals | Final Record Drawings | 1.8 | G |
| 25 | 01783 | 07 | Certificates | Instructor Qualifications | 1.3 | G |
| 26 | 01783 | 07 | Certificates | Resume of the Technician and Associated Video Production Company | 3.3.2 | G |
| 27 | 01783 | 07 | Certificates | Training Schedule | 3.1 | G |
| 28 | 01783 | 11 | Closeout Submittals | Training Course Plan | 3.1 | G |
| 29 | 01783 | 11 | Closeout Submittals | Training Course Agenda | 3.1 | G |
| 30 | 01783 | 11 | Closeout Submittals | DVD Training Videos | 3.3.2 | G |
| 31 | 03600 | 01 | Preconstruction Submittals | Concrete Removal and Disposal Plan | 3.4.1 | G, HDC |
| 32 | 03600 | 01 | Preconstruction Submittals | Core Drilling Procedure | 3.4.4 | G, HDC |
| 33 | 03600 | 01 | Preconstruction Submittals | Concrete Imaging Report | 3.4.4 | G, HDC |
| 34 | 03600 | 01 | Preconstruction Submittals | Repair Procedure of Concrete Surfaces | 3.4.12 | G, HDC |
| 35 | 13080 | 02 | Shop Drawings | Detail Drawings | 1.3 | G, HDC |
| 36 | 13080 | 03 | Product Data | Concrete Anchors | 1.3 | G, HDC |
| 37 | 13080 | 03 | Product Data | Seismic Equipment Certification | 1.3 | G, HDC |
| 38 | 13080 | 05 | Design Data | Structural Design Calculations for Seismic Restraints | 1.3 | G, HDC |
| 39 | 13080 | 06 | Test Reports | Concrete Anchor Test Reports | 3.5.2.1 | G, HDC |
| 40 | 13080 | 06 | Test Reports | Contractor Qualification Testing | 1.3 | G, HDC |
| 41 | 13280 | 01 | Preconstruction Submittals | Sampling Plan | 3.2 | G, EC-R |
| 42 | 13280 | 01 | Preconstruction Submittals | Asbestos Hazard Abatement Plan | 3.3.2 | G, EC-R |
| 43 | 13280 | 01 | Preconstruction Submittals | Respirators | 1.10 | |
| 44 | 13280 | 01 | Preconstruction Submittals | Encapsulants | 2.1.5 | |
| 45 | 13280 | 01 | Preconstruction Submittals | Surfactants | 2.1.6 | |
| 46 | 13280 | 01 | Preconstruction Submittals | Local Exhaust System | 1.11 | |
| 47 | 13280 | 01 | Preconstruction Submittals | Recording Manometer | 1.11 | |
| 48 | 13280 | 06 | Test Reports | Work Site Entry Log | 1.7.2 | |
| 49 | 13280 | 06 | Test Reports | Daily Narrative Log | 1.18.1 | |
| 50 | 13280 | 06 | Test Reports | Asbestos Bulk Sample Results | 3.2 | |
| 51 | 13280 | 06 | Test Reports | Personnel and Area Air Monitoring | 3.6 | |
| 52 | 13280 | 07 | Certificates | Qualifications | 1.8 | |
| 53 | 13280 | 07 | Certificates | Asbestos Abatement Worker Training | 1.9.1 | |
| 54 | 13280 | 07 | Certificates | Asbestos Abatement Contractor | 1.14 | |
| 55 | 13280 | 07 | Certificates | Bulk Sampling Personnel | 1.16 | |
| 56 | 13280 | 07 | Certificates | Asbestos Abatement Supervisory Personnel Training | 1.9.2 | |
| 57 | 13280 | 07 | Certificates | Respirator Fit Test Results | 1.10.2 | |
| 58 | 13280 | 07 | Certificates | Medical Examinations | 1.12 | |
| 59 | 13280 | 07 | Certificates | Permits and Notifications | 1.13 | |
| 60 | 13280 | 07 | Certificates | Certified Industrial Hygienist (CIH) | 1.15 | |
| 61 | 13280 | 07 | Certificates | Air Monitoring Personnel | 1.17 | |
| 62 | 13280 | 07 | Certificates | Testing Laboratory | 1.17 | |
| 63 | 13280 | 07 | Certificates | Waste Disposal Site (WDS) | 1.18.2 | |
| 64 | 13280 | 07 | Certificates | Waste Shipment Record (WSR) | 3.9 |
| 65 | 16050 | 02 | Shop Drawings | Drawing Index | 1.4.1 | G |
| 66 | 16050 | 02 | Shop Drawings | Bill of Materials | 1.4.2 | G |
| 67 | 16050 | 02 | Shop Drawings | Main One-Line Drawing | 1.4.3 | G |
| 68 | 16050 | 02 | Shop Drawings | Schematic Drawings | 1.4.4 | G |
| 69 | 16050 | 02 | Shop Drawings | Interconnecting Diagrams | 1.4.5 | G |
| 70 | 16050 | 02 | Shop Drawings | Electrical Installation Drawings | 1.4.6 | G |
| 71 | 16050 | 02 | Shop Drawings | Cable and Conduit Schedule | 1.4.7 | G |
| 72 | 16050 | 02 | Shop Drawings | Nameplates | 2.13.2 | G |
| 73 | 16050 | 03 | Product Data | Catalog Data | 1.4.9 | G |
| 74 | 16050 | 03 | Product Data | Conduit, Fittings, and Hangers | 1.4.9 | G |
| 75 | 16050 | 03 | Product Data | Boxes and Enclosures | 1.4.9 | G |
| 76 | 16050 | 03 | Product Data | Junction and Outlet Boxes | 1.4.9 | G |
| 77 | 16050 | 03 | Product Data | Molded Case Circuit Breakers | 1.4.9 | G |
| 78 | 16050 | 03 | Product Data | Enclosed Switches | 1.4.9 | G |
| 79 | 16050 | 03 | Product Data | Terminal Blocks | 1.4.9 | G |
| 80 | 16050 | 03 | Product Data | Pushbuttons and Switches | 1.4.9 | G |
| 81 | 16050 | 03 | Product Data | Relays | 1.4.9 | G |
| 82 | 16050 | 03 | Product Data | Spare Parts and Special Tools | 2.14.5 | G |
| 83 | 16080 | 01 | Preconstruction Submittals | Equipment Removal, Installation, and Testing Plan and Schedule | 1.5.2 | G |
| 84 | 16080 | 05 | Design Data | Commissioning Test Plans | 1.7 | G |
| 85 | 16080 | 05 | Design Data | Field Test Plans | 3.2 | G |
| 86 | 16080 | 06 | Test Reports | Field Test Reports | 3.2 | G |
| 87 | 16080 | 06 | Test Reports | Conductor Insulation Resistance Test Report | 3.3.1 | G |
| 88 | 16080 | 06 | Test Reports | Conductor Continuity and Labeling Test Report | 3.3.2 | G |
| 89 | 16080 | 06 | Test Reports | Circuit Functionality Test Report | 3.3.3 | G |
| 90 | 16120 | 03 | Product Data | Insulated Wire and Cable | 1.4 | G |
| 91 | 16120 | 03 | Product Data | Special Wire and Cable | 1.4 | G |
| 92 | 16120 | 03 | Product Data | Installation Instructions | 3.1.1 | G |
| 93 | 16120 | 06 | Test Reports | Tests, Inspections, and Verifications | 3.2 | G |
| 94 | 16240 | 02 | Shop Drawings | Drawings of the Seismic Battery Racks and Barriers | 2.3 | G |
| 95 | 16240 | 03 | Product Data | Battery | 1.4 | G |
| 96 | 16240 | 03 | Product Data | Proof of Battery Service Life Record | 2.1.5 | G |
| 96 | 16240 | 03 | Product Data | Seismic Racks | 1.4 | G |
| 97 | 16240 | 03 | Product Data | Battery Terminal Shrouds | 1.4 | G |
| 98 | 16240 | 03 | Product Data | Battery Monitoring System | 1.4 | G |
| 99 | 16240 | 03 | Product Data | Spill Barrier and Absorbent | 1.4 | G |
| 100 | 16240 | 03 | Product Data | Hydrogen Gas Detector | 1.4 | G |
| 101 | 16240 | 03 | Product Data | Temporary DC Power Supply | 1.4 | G |
| 102 | 16240 | 03 | Product Data | Upper Battery Cell Access | 1.4 | G |
| 103 | 16240 | 03 | Product Data | Battery Cell Lifting Device | 1.4 | G |
| 104 | 16240 | 05 | Design Data | Battery Hydrogen Concentration Calculation | 3.2.4 | G |
| 105 | 16240 | 06 | Test Reports | Battery Capacity Test Results | 3.3.4 | G |
| 106 | 16240 | 07 | Certificates | Battery Capacity Test Procedures | 3.3.4 | G |
| 107 | 16240 | 07 | Certificates | Certification of Compliance for the Seismic Battery Racks | 2.3 | G |
| 108 | 16240 | 07 | Certificates | Certificate of Recycling | 3.1 | G |
| 109 | 16260 | 03 | Product Data | Inverter | 1.4 | G |
| 110 | 16260 | 03 | Product Data | Battery Chargers | 1.4 | G |
| 111 | 16345 | 02 | Shop Drawings | Outline Drawings | 1.5.1 | G |
| 112 | 16345 | 02 | Shop Drawings | Connection/Assembly Drawings | 1.5.2 | G |
| 113 | 16345 | 03 | Product Data | Motor Control Center | 1.7 | G |
| 114 | 16345 | 03 | Product Data | Control Center Assemblies | 1.7 | G |
| 115 | 16345 | 03 | Product Data | Bus Phasing | 1.7 | G |
| 116 | 16345 | 03 | Product Data | Operating Unit | 1.7 | G |
| 117 | 16345 | 03 | Product Data | Air Circuit Breakers | 1.7 | G |
| 118 | 16345 | 03 | Product Data | Transformer | 1.7 | G |
| 119 | 16345 | 06 | Test Reports | Factory Test Procedure | 3.4.1 | G |
| 120 | 16345 | 06 | Test Reports | Factory Test Reports | 3.4.2 | G |
| 121 | 16345 | 10 | Operation and Maintenance Data | Motor Control Center O&M Data Package | 1.4 | G |
| 122 | 16403 | 02 | Shop Drawings | 125 volt DC and 120 volt AC Distribution Panelboard Arrangement Drawings | 2.1.5 | G |
| 123 | 16403 | 03 | Product Data | Panelboards | 1.4 | G |
| 124 | 16403 | 03 | Product Data | Indicating Instruments | 1.4 | G |
| 125 | 16403 | 03 | Product Data | Instrument Current Transformers | 1.4 | G |
| 126 | 16403 | 03 | Product Data | Ground Detectors | 1.4 | G |
| 127 | 16403 | 06 | Test Reports | Identification of Existing Battery System Grounds | 3.1 | G |
| 128 | 16403 | 07 | Certificates | Panelboard Factory Tests | 2.6 | G |