This document is an amendment to a solicitation for replacing water tanks at Camp Oliver. The amendment provides clarification on several items. The required response date is changed from July 7th to July 9th at 2:00 PM. Additional drawings of the site from 1956 are included as an attachment. Contractors must submit questions by a certain date and answers are provided. Recycling and disposal of construction debris must follow the installation's requirements, including a 60% minimum diversion. Concrete and asphalt removed must be disposed of off-site. The signage detail for an emergency water source is clarified to be on drawing C-2.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Copy of ABSTRACT - 20-B-0012-Replace Water Tanks at Camp Oliver. 3.pdf | ||
| Questions- Answers.pdf | ||
| FS-26 Camp Oliver Drawings 1956.pdf | ||
| Coronavirus disease 2019 (COVID-19) Factsheet.pdf | ||
| ENCL 4 200405_DoD Guidance on the Use of Cloth Face Coverings.pdf | ||
| Amendment 2.pdf | ||
| Amendment 1.pdf | ||
| Q5A-8-5J Env Asbestos Report.docx | DOCX document | |
| DRAWINGS 3777 Combined.pdf | ||
| SOLICITATION.pdf | ||
| Camp Oliver Tank Replacement Design Change 3 Dec 2019.pdf | ||
| Webex Instructions.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011426014 Q5A-8-5J
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
a. This amendment is issued to provide a Question/ answ er sheet .
b. A second set of draw ings ,FS-26 Camp Oliver Draw ings 1956,w ill be uploaded separately.
c. The bid opening is changed to Thursday, 09 July 2020 at 1400 2 PM EST.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9124M20B0012
X 9B. DATED (SEE ITEM 11)
03-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Jun-2020
CODE
MICC - FORT STEWART
976 WILLIAM H. WILSON AVE SUITE 100
FORT STEWART GA 31314
W9124M 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9124M20B0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS- ANSWERS
W9124M-20- B-0012- Replace Water Tanks at Camp Oliver
1. Question :
Is the Government supplying a metal container in which the concrete is to be placed as concrete structures are being demolished or after concrete structures have been demolished by the contractor?
DPW ANSWER:
FSGA/HAAF has a mandatory recycling program. Unless otherwise specified, the Government retains all salvage rights. Contractors shall recycle construction & demolition debris as required by the Installation's recycling clause, 52.000-4061:
RECYCLING, SALVAGE, AND DISPOSAL OF MATERIALS FORT STEWART AND
HUNTER ARMY AIRFIELD.
Source Reduction is required to reduce the initial input to the solid waste stream.
Ensure minimum packing and packaging materials are used for items shipped to the Installation. Also, all military construction, renovation and demolition projects shall include performance requirements for a 60% minimum diversion of C&D waste by weight. Contractor must provide all weight tickets to demonstrate meeting the performance standard. Specifications must include submission of a contractor’s C&D Waste Management Plan.
Concrete and asphalt material shall be hauled and disposed of off of government property. Recycle materials will be broken down when delivered to the Recycling Center (to include metal equipment). Scrap metal will be cut down to no larger than 4 square feet in size.
Please read environmental requirement located in Technical Provisions General (TPG) for disposal and recycle.
2. Question:
What is the thickness of the concrete slab under building 15003A? It is important to know this, in order to determine the cost of the demolition.
W9124M20B0012
RECORD DRAWINGS INDICATE BUILDING 15003A IS A 4” CONCRETE SLAB.
SEE ATTACHED REFERENCE DRAWINGS FROM 1956. PROJECT NUMBER FS-26
3. Question: What is the PSI for the Pressure Relief Value (PRV) on the potable water tank on Site 1?
SEE DRAWING M-6.
4. Question: Do the pipe, fittings, and all other materials have to be manufactured in the USA?
ALL MATERIALS SHALL MEET “THE BUY AMERICAN ACT” AND REQUIRED CODES
AND STANDARDS INDICATED ON THE DRAWINGS AND SPECIFICATIONS.
5. Question: On Drawing M-2, and EMERGENCY WATER SOURCE sign is called out with a reference to Drawing C-2 for details. There is no description or dimensions of such sign on Drawing C-2 or on any other Drawing so far as we can ascertain. Please provide that information in order to determine the cost of this signage.
EMERGENCY WATER SOURCE SIGN DETAIL IS LOCATED ON DRAWING C-2. IT IS
LOCATED ABOVE THE GATE POST SCHEDULE.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 07-Jul-2020 02:00 PM to 09-Jul-2020 02:00 PM.