SOLICITATION.pdf
PDF 2 MB Posted
- Attached to
- Replace Water Tank at Camp Oliver Federal contract opportunity
- Solicitation number
- W9124M20B0012
About this file
This solicitation seeks replacement of a potable water tank and installation of an emergency water source tank at Camp Oliver in Fort Stewart, Georgia. Required work includes removal of an existing potable water supply and replacement with a new hydro-pneumatic potable water tank, appurtenances, and piping. An emergency water source tank must also be installed with new appurtenances and piping. Interested offerors must submit bids by 2 July 2020. The award date is scheduled for 7 July 2020. Pricing is to be provided using the bid price schedule format. The solicitation is set aside for HUBZone small businesses. The Department of the Army Materiel Command Mission and Installation Contracting Command is the contracting agency. The period of performance is 180 days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Copy of ABSTRACT - 20-B-0012-Replace Water Tanks at Camp Oliver. 3.pdf | ||
| Amendment 3.pdf | ||
| Questions- Answers.pdf | ||
| FS-26 Camp Oliver Drawings 1956.pdf | ||
| Coronavirus disease 2019 (COVID-19) Factsheet.pdf | ||
| ENCL 4 200405_DoD Guidance on the Use of Cloth Face Coverings.pdf | ||
| Amendment 2.pdf | ||
| Amendment 1.pdf | ||
| DRAWINGS 3777 Combined.pdf | ||
| Q5A-8-5J Env Asbestos Report.docx | DOCX document | |
| Camp Oliver Tank Replacement Design Change 3 Dec 2019.pdf | ||
| Webex Instructions.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011426014
PROJECT NO: Q5A-8-5J
PROJECT LOCATION : FORT STEWART
SET ASIDE: 100% HUBZONE
NAICS CODE : 237110 SIZE STANDARD : 36,5000,000.00
MAGNITUDE OF CONSTRUCTION PROJECT : $ 500,000- $ 1,000,000
All w ork shall be completed per Scope of Work, Terms and Conditions, Provisions, Clauses , Draw ings and Specif ications.
BONDS: Bid Bonds, Payment Bonds, and Performance Bonds w ill be required.
VISUAL SITE VISIT : Virtual Site Visit, 11 June 2020, 9:00 am (EST) through w ebex.com. Interested Bidders must sign in to w ebex using access code 126 332 5964 code 1234.
DUE DATE FOR ALL QUESTIONS: 16 June 2020 ,11:00 am (EST)
BID OPENING : 07 July 2020 at 1400 hrs ( 2:00 PM EST) at the Parking lot of Paul R. Smith Education Center, 100 Know ledge Drive, Fort Stew art, GA 31314.
X
TATJANA M. FISHER 912-767-3747
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
03-Jun-2020
(RFP)
(IFB)
CALL:
REPLACE WATER TANK AT CAMP OLIVER
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________180 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________02 Jul 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
MICC - FORT STEWART
976 WILLIAM H. WILSON AVE SUITE 100
FORT STEWART GA 31314
W9124M
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
Q5A-8-5J
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: (912)767-8420 TEL: FAX:
W9124M20B0012 75
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9124M20B0012
Section A - Solicitation/Contract Form
NOTICE TO BIDDERS
1. Bidder must complete and return the SF 1442 (2 pages), the Bid Price Schedule, and Section K by the date/time specified in Block 13A. Offerors must acknowledge receipt of all amendments to the solicitation by giving number and date for each as required in block 19.
2. MICC-Fort Stewart is operating a paperless contracting file system. A minimum of one copy of each Document submitted to the contracting office shall be in an electronic format. Acceptable formats are PDF, DOC(x), XLS(x), TXT, JPG and XPS. All submissions shall include one (1) CD with all required documents and one (1) paper copy of each bid.
3. Bids submitted by Facsimile (FAX) will not be accepted.
4. Bids submitted by E-mail will not be accepted.
5. Please enter your CAGE code, Tax Identification Number (TIN), and DUNS in Block 14 of page 2.
6. Offeror must acknowledge receipt of all amendments by giving number and date as required in block 19.
7. Hard copy of the bid shall be mailed to : MICC – Fort Stewart, 976 William H. Wilson Ave, Suite 100, Fort Stewart, GA .The envelop shall be marked IAW FAR Clause 52.214-5 and ATTENTION: Mary L. Hightower/Tatjana Fisher. BID OPENING WILL BE HELD 07 JULY 2020 at 1400hrs (2PM EST) at Paul R. Smith Education Center Parking Lot. All interested parties can hand deliver their bids to this location.
8. Virtual Site visit/Pre-bid conference of Camp Oliver will be held on 0900, 11 June 2020 to all interested parties.
9. Written questions shall be submitted to mary.l.hightower2.civ@mail.mil and tatjana.fisher.civ@mail.mil no later than 2:00PM (EST), 16 June 2020 at 1100 (11Am
EST).
(End of Notice to Bidders)
Section B - Supplies or Services and Prices
BID PRICE SCHEDULE
CLIN MAX AMOUNT
0001 $
0002 $
TOTAL $
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Replace Potable Water Tanks
FFP
Removing of existing failed potable water tank and install a new potable water tank at Camp Oliver , Fort Stewart FOB: Destination
PURCHASE REQUEST NUMBER: 0011426014
PSC CD: 4510
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Job
Install Emergency Supply Water Tank
FFP
Installation of New Emergency Supply Water Tank FOB: Destination
PURCHASE REQUEST NUMBER: 0011426014
PSC CD: Z1NZ
NET AMT
Section C - Descriptions and Specifications
TECHNICAL PROVISIONS GENERAL
REPLACE WATER TANK AT CAMP OLIVER
CAMP OLIVER, FORT STEWART
IJO # Q5A-8-5J
1. DESCRIPTION OF WORK:
1.1 Work to be done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with REPLACE WATER TANK AT CAMP OLIVER IJO #Q5A-8-5J complete in strict accordance with specifications and drawings. The work includes, but is not necessarily restricted to, the following items.
Removal of existing potable water supply for Camp Oliver and replace with new hydro-pneumatic potable water tank, appurtenance, and piping.
Installation of New Emergency Water Source Tank with new appurtenance and piping.
1.1.1. Demolition
1.1.1.1 Removal of existing storage tank.
1.1.1.2 Removal of storage tank building all items including foundation.
1.1.1.3 Removal of underground lines as indicated in the plans
1.1.1.4 Removal of Power from existing locations demolished back to feeder panels.
1.1.1.5 Site surface grade removal as needed to install new slabs and to coordinate removal of objects listed above.
1.1.2 Site
1.1.2.1 Re-grade to promote positive drainage away from new concrete pads.
1.1.3 Concrete
1.1.3.1 Slab on grade, concrete pads with thickened footings at new tank locations.
1.1.4 Tanks & Appurtances
1.1.4.1 Hydro-pneumatic Potable water storage tank
1.1.4.1.1 Chlorination treatment system
1.1.4.1.2 Potable water storage tank level controls
1.1.4.1.3 Electrical grounding system
1.1.4.2 AWWA Emergency water source storage tank
1.1.4.2.1 Including backflow preventer
1.1.4.2.2 Fire hydrant for fire department connection
1.1.4.2.3 Electrical grounding system
1.2 Additives N/A
1.3 Government Furnished – Government Installed (GF-GI) Furniture and Equipment: - N/A
1.6 WORK BY OTHERS: The Contractor shall afford the Government and separate contractors’ reasonable opportunity for the introduction and storage of their materials and equipment and the execution of their work, and shall connect and coordinate the contractor’s work with separate contractors’ as required by the Contract Documents.
1.7 DRAWINGS AND SITE VISITS
1.7.1 The drawings indicate the extent of the general location and arrangement of existing conditions. It is strongly recommended that the Contractor visit the site to determine the complexity of the work and the amount of material required to perform this project. Field measurements may be necessary to determine the size and quantity of materials. Conditions which are obvious/visible or which should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions provision of the contract.
1.8 ENVIORNMENTAL REQUIREMENTS
1.8.1 Contractor shall comply with “Attachment A - Environmental Requirements” for the following items:
Recycling, Salvage and Disposal of Materials Fort Stewart and Hunter Army Airfield
Toxic Substances Control Act (TSCA) Requirements Installing Storage Tanks on Fort Stewart and Hunter Army Airfield Removing Aboveground Storage Tanks (ASTs) on Fort Stewart and
Hunter Army Airfield
Potable Water Utility Environmental Compliance Requirements
Wells and Water Storage Tanks o Georgia EPD Letter of Approval is attached to the Contract Documents
Water / Waste Water Systems
Stormwater / Erosion and Sedimentation Control (E & S) Requirements
Painting Operations
2. CONSTRUCTION CONSTRAINTS
2.1. Time of Performance
2.1.1 Access to Buildings – All work requiring access to building interiors excluding attics, crawl spaces, etc. and all other work shall be performed between 7:30 a.m. and 4:00 p.m. excluding official holidays, unless otherwise indicated or approved by the Contracting Officer. Requests to work during other than these normal hours shall be made in writing at least 36 hours in advance. For example, a request to work on a Saturday should be made no later than noon on Thursday.
2.1.2 Work Requiring Outages – Work requiring outages of utilities or building systems will be accomplished in accordance with prior approved schedules.
2.2. Outages – The contractor’s work requiring outages of utility or building systems will require 15 day advance notice and will be subject to the approval of the Contracting Officer. Notice shall include type of outage, date, and time outage will commence and estimated duration of outage.
2.3. Continuity – All tools, labor, and materials required to complete any item of work within a given work area or requiring an outage of any building utility or system, shall be available at the site prior to commencement thereof.
Once work has commenced on an item of work said work shall be continuously and diligently performed to completion and acceptance.
2.4. Road and/or Railroad Closures – Road and/or railroad closures will require a 15-day advance written notice and be subject to the Contracting Officer’s approval. Notice shall state reason for closure, date and time closure will commence and estimated duration of closure. A sketch shall be provided showing location of closure area and placement of barricades and signs. Closures shall be limited to a maximum of 5 calendar days.
2.5. Entry – Entry to all areas, except the cantonment area, shall be coordinated with Range Control, Building 8302 (intersection of Highway 144 and Fort Stewart Road 47) and the Provost Marshal’s Office.
2.6. Fire Zone – The contractor is required to provide 72-hour notice to the Contracting Officer prior to the final programming of the fire zone information at the main fire station.
2.7. Foreign Object Debris (FOD) – The Contractor shall take special precautions to contain Foreign Object Debris (FOD) in and around any runways, taxi ways and aprons.
2.8 Operational Safety on the Airfield During Construction – N/A
2.8.1 Contractor shall be responsible for implementing construction – phasing plan included in the Contract Documents.
3. CONSTRUCTION ACTIVITIES:
3.1 Contractor shall submit a Safety Plan and Construction Schedule to the Contracting Officer’s Representative (COR) 10 days in advance of any construction activities to arrange specific schedule for performing work as required by this Contract.
4. FACTORS AFFECTING PERFORMANCE UNDER THIS CONTRACT:
4.1 The Contractor shall coordinate use of the site for access, staging, and parking with the Contracting Officer.
4.2 Contractor shall be responsible for limiting access of contractors’ employees and subcontractors to the area of work defined in the Contract.
Contractor shall not have access to restrooms and amenities such as vending machines unless granted permission by the Contracting Officer.
4.3 Contractor shall maintain haul routes to and from the job sites and the borrow pits, to include the borrow pit. In addition it is the contractor’s responsibility to meet all Local, State and Federal regulations for the operation of a borrow pit. Contractor shall control runoff and erosion on all excavation and backfilling operations.
5. AS-BUILT RECORD DRAWINGS:
5.1 The Contractor shall be responsible for maintaining one set of master/record construction drawing prints on the job site on which the contractor shall keep a neat and accurate record of all deviations from the original contract documents as the work progresses. The contractor is responsible for noting all changes and correction on these master/record construction drawing prints promptly as the changes occur in red ink(redline prints) and note date when these changes occurred, but in no case less often than on a weekly basis. Notify the COR of all changes that are made. The master/record construction drawing prints which are maintained in red ink shall indicate all the changes and modifications incorporated into the work as well as the following:
5.1.1 Actual locations of all subsurface and concealed utility lines, type of materials used, sizes, etc. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the master/record construction drawings shall show by offset dimensions to two permanently fixed surface features. Valves, splices boxes and similar appurtenances shall be located by dimensions along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.
5.1.2 Any shop drawings that constitute part of the design shall be included with the record drawings.
5.2 At the completion of construction, the master/record (redline construction drawings) prints with corrections, such as field changes and contract modifications, shall be certified by the Contractor as to their correctness and submitted to the Contracting Officer’s Representative for approval.
Once these provisional master/record (redline construction drawing) prints have been approved by the COR, the COR will obtain a compact disc (CD) of computer generated construction drawings from the DPW Engineering Service Division, Building 1141 at Ft. Stewart or Building 1021 at Hunter AAF, as applicable. The contractor shall then transfer all corrections from redline construction drawing prints to the compact disc (CD) of computer generated construction drawings. Corrections done shall be in Micro Station “.dgn” format. The Contractor shall note on the computer generated construction drawings the words “AS-BUILT” in the revision block with the next revision number to identify any changes made.
Also, revision number identification will be placed where any changes were made. The contractor shall then submit AS-BUILT compact disc (CD) of computer generated drawing and one (1) AS-BUILT hardcopy with contractor’s redline corrections to the COR to insure accuracy that all corrections made were transferred from redline construction drawing prints to AS-BUILT hardcopy prints. Once the COR approves the AS-BUILT hardcopy prints the COR will then turn over to DPW/ ESD/ Drafting section for final approval of AS-BUILT compact disc (CD) of computer generated drawings and at this time the Contractor can receive final payment.
6. SECURITY REQUIREMENTS.
6.1 All contractor employees, to include subcontractor employees, requiring access to government installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or the Contracting officer (if a COR has not been designated) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:
https://jkodirect.jten.mil/.
The contractor and all sub-contractors shall brief all employees on the local iWATCH program. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
The Contractor and all sub-contractor employees shall comply with applicable Installation, facility, and area Commander’s local access and security policies and procedures. If required by this contract, the contractor shall also provide all information for background checks to meet Installation access requirements to be accomplished by Installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.
In addition to the changes otherwise authorized by the changes clause of this solicitation/contract, should the Force Protection Condition (FPCON) at any individual facility or Installation change, the Government may require changes in contractor security matters or processes.
ATTACHMENT A – ENVIRONMENTAL REQUIREMENTS
1. RECYCLING, SALVAGE, AND DISPOSAL OF MATERIALS
FORT STEWART AND HUNTER ARMY AIRFIELD
1.1 Disposal: All waste generated from construction, demolition, and renovation contracts must be disposed of off the installation in a permitted disposal facility and in accordance with all Federal, State, and Local rules and regulations unless otherwise stated in the contract. At the end of each month, the contactor will provide copies of all disposal weight/scale tickets to the Contracting Officer’s Representative (COR) showing the in, out, and tare weights of each load taken from the installation. The COR will provide copies of these tickets to the DPW Environmental Division, Solid Waste Management Section for tracking and regulatory reporting requirements.
1.2 Recycling/Salvage: Fort Stewart and Hunter Army Air Field has a mandatory recycling program. The Installation Command Policy Letter #30 and Command Recycling SOP can be accessed at http://www.stewart.army.mil/info/?id=443&p=1. All recyclable materials (listed in the recycling SOP) generated during the entire term of any construction, demolition, or renovation contract will be turned over to the Fort Stewart or HAAF Recycling Program. Contractors must contact the COR who will coordinate with the DPW Environmental Waste Management Section (912-767-2010) to arrange for turn-in of recyclable/salvageable materials. In areas where large amounts of scrap metal or cardboard will be generated, it is possible that a collection bin/container could be provided to the Contractor at no cost to deposit these materials. Salvage materials, unless otherwise specified, become the property of the contractor upon removal from the job site and should be taken into consideration in formulating bids.
1.3 Hauling/Transport Requirements: All vehicles and containers used to transport waste or recyclables on or off the Installations will meet all Federal and State DOT requirements. All waste or recyclable materials being transported will be loaded, tied, and covered in such a manner that will prevent any of the materials from leaking, spilling, falling or blowing from/off the vehicle or container. It is the contractor’s responsibility to ensure immediate pick-up/clean-up of any material that is accidentally dropped, spilled or blown from a vehicle or container while in transit on and off the Installation.
1.4 Custodial Contract: (N/A) If this contract is for custodial services or will include a custodial service requirement, the Contractor shall empty or otherwise transfer the contents from the blue recycling containers located inside buildings/facilities to the nearest blue recycling dumpster located outside. The contactor will ensure that all recycled paper products are first placed inside a clear plastic bag and the top is tied closed before it too is placed inside the nearest blue recycle dumpster.
1.5 Payment/Funding: If any of the conditions listed under the Recycling, Salvage, and Disposal section are not met, it will be considered a failure to comply with the terms of the contract as discussed in the inspection clause herein.
1.6 Guidance/Question: Anyone requiring further guidance, recycling training for contractors, or has additional questions on this section should contact the DPW Environmental Division, Solid Waste Management Section at 912-767-2010.
1.7 Chillers, pumps, HVAC units, and similar equipment: (N/A) Equipment must be logged on an applicable inventory/certification document prior to turn-in to recycling yard (on DD Form 1348). The form will be used to track the removal of units from facilities, refrigerant removal certification (if applicable), and a chain of custody from removal technician thru supply manager to recycling technician. The serial number and facility number will be listed on each form and one form may contain more than one like item.
Recycling Yard personnel will verify document to items turned in, sign the document, and retain a file copy. Contractor shall submit this form to the Contracting Officer (KO) and the COR. Additionally, damaged HVAC system may be accepted as scrap metal at the FSGA Recycling Scrap Metal Yard, Building 1143, or the HAAF Recycling Yard, Building 728, provided any and all freon has been certified as being removed from the system.
2. Toxic Substances Control Act (TSCA) Requirements
2.1 Asbestos Containing Materials (ACM)
2.1.1 If ACM will either be disturbed or removed, the contractor must perform asbestos abatement, containment, disposal and a 10-day notification to the Georgia Environmental Protection Division (GA EPD), as required by the Georgia Asbestos Safety Act, Official Code of Georgia Annotated Section 12-12-1. The disposal of ACM must be in accordance with both the GA EPD and Occupational Safety and Health Administration regulations.
2.1.2 REQUIRED SUBMITTAL ITEM: The Installation TSCA POC (Craig Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil) must be provided a copy of the 10-day notification at the time the contractor informs GA EPD of their intent to properly abate the ACM. A copy of the Georgia asbestos shipment record must also be provided to the TSCA POC.
2.2 Lead-Based Paint (LBP)
2.2.1 If survey results, as reviewed by the Installation TSCA POC (Craig Christopher at 912-767-1234 / Craig.W.Christopher.civ@mail.mil), indicate LBP removal is necessary, the contractor will be required to collect, contain, and dispose of the LBP off-Post in accordance with local, state, and Federal regulations. The contractor will be required to provide the disposal manifest to the TSCA POC.
2.2.2 REQUIRED SUBMITTAL ITEM: LBP survey must be provided to the TSCA POC, as applicable. The LBP disposal manifest must be provided to the TSCA POC if LBP removal was determined necessary by the TSCA POC.
3 Installing Storage Tanks on Fort Stewart and Hunter Army Airfield - (N/A)
3.1 Underground Storage Tank Moratorium.
3.1.1 The installation of any underground storage tank and associated piping for the purpose of containing regulated and/or hazardous substances is strictly prohibited in the case where at least 10% of the total volume (tank + piping) is below the surface of the ground. Similarly, tanks in vaults for the purpose of installing tanks below grade are not acceptable.
3.2 Design Requirements for Aboveground Storage Tanks
3.2.1 Provide appropriate secondary containment (40 CFR 112.8(c)(2)). All aboveground storage tanks used for the purpose of storing regulated and/or hazardous substances must be double-walled. In order for a tank to be considered double-walled, the interstitial space between the inner and outer wall must be able to be inspected visually or the interstitial space must be equipped with a sensor capable of alarming in case of liquid in the interstice (access to the interstice must also allow for the periodic removal of liquids).
3.2.2 Provide tertiary containment (in accordance with 40 CFR 112.8(c)(3)). All aboveground storage tanks must be placed on an impervious diked concrete housekeeping pad designed to catch spills caused from transferring substance to/from the tank. This housekeeping pad must come with a valve that allows for the discharge of rainwater from the diked pad after a visual inspection has been done to determine that the water is clean.
3.2.3 Provide Instrumentation (Provide good engineering practices to avoid unwanted discharges, 40 CFR 112.8(c)(8)))
3.2.3.1 All aboveground storage tanks must come with a high liquid level alarm that emits both an audible and visual signal to alert operators that the tank must be emptied before further use.
3.2.3.2 The tank must also be equipped with a level gauge that allows for determining the level of liquid in the tank.
3.2.3.3 In the case of any tank equipped with a pump for the purpose of dispensing of a stored substance, the pump must have an automatic cutoff to prevent overfilling of a container.
3.2.4 Provide Labeling. All aboveground storage tanks should be labeled IAW all applicable local, state, federal laws, or industry standard. At a minimum, the tank should display an appropriate hazard warning, material ID, and storage capacity.
4. Removing Underground Storage Tanks (USTs) on Fort Stewart and Hunter Army Airfield - (N/A)
4.1 Tank Removal.
Note to ENGINEER - The Georgia Underground Storage Tank Management Program (GA USTMP) requires the removal of tanks after they have fulfilled their useful purpose and have been out of service for a period of twelve (12) months. Be aware that some tanks do NOT meet current tank standards but have an exemption from those standards based on their current use (e.g, heating oil tanks). If the use changes, those exemptions may no longer apply and the tank must be removed and if still needed will require replacement with an above ground tank.
4.2 Removal must follow the standards for removal and closure of registered tanks as outlined in the Georgia Underground Storage Tank Management Program (GA USTMP) guidance document (ref GA Rules 391-3-15-.11).
As a minimum oil samples must be taken and analyzed from the excavated pit’s walls and floor. A groundwater sample must be taken if a soil sample is not possible from beneath the UST. Soil and groundwater samples must be tested for benzene, toluene, ethylbenzene and xylenes (BTEX), total petroleum hydrocarbons-diesel range organics (TPH-DRO), and polynuclear aromatic hydrocarbons (PAHs). The USTs and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil/rinseate) must be coordinated with the Installation DPW Environmental Division. See 1.0 for Recycling of cut up tank.
4.3 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice and a POC / telephone number prior to UST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time the tank(s) is being removed from the ground. Installation DPW Environmental POC: Algeana Stevenson at 912-315-5144; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with Installation DPW Environmental Division is required).
Letter and photo documentation (hard copy and digital) of the UST removal process is required of the UST removal contractor; and (c) confirmation cut up tank was delivered to the Recycling Center.
5. Removing Aboveground Storage Tanks (ASTs) on Fort Stewart and Hunter Army Airfield
5.1 Tank Removal.
5.1.1 The AST(s) and associated piping must be removed and triple rinsed with water. Rinse water must be containerized (in drums or a tank) and analytical testing conducted by a certified Georgia laboratory, so the product can be correctly coded/classified on a Non-hazardous Manifest signed by an authorized representative from the Installation DPW Environmental Division. Disposal of materials (soil / rinseate) must be coordinated with the Installation DPW Environmental Division. See Section 1 for Recycling of cut up tank.
5.1.2 REQURED SUBMITTAL ITEM: Contractor shall provide (a) 24- hour notice (and a POC/telephone number) prior to AST removal activities to allow time for Installation DPW Environmental Division representation at the site during the time the tank(s) is being removed. Installation DPW Environmental Division POC: Veronica Frazier at 912-767-2400; (b) All lab tests and manifests for disposal of any contaminated soil/rinseate (pre-coordination with the Installation DPW Environmental Division is required);
and (c) confirmation cut up tank was delivered to the Recycling Center.
6 Potable Water Utility Environmental Compliance Requirements
6.1 REQUIRED SUBMITTAL ITEM: Extending a water main: The contractor must submit applications for GA EPD’s approval through the Installation DPW Environmental Division POC: Stanley Thomas at 912-767-4139. At least 100 days prior to construction, the contractor must submit the following items to the Installation DPW Environmental Division:
6.1.1 Three copies of the design plans and specifications for the proposed water main extension.
6.1.2 Every sheet of the drawings must be stamped by a GA certified P.E.;
the cover page of the specifications must also be stamped with document.
6.1.3 Water Extension Submittal Forms will be required for any project that has more than one service connection or if the water line tapping off the main is at least 6 inches in diameter.
6.1.4 All water lines must be disinfected and sampled IAW the most current edition of AWWA’s C651.
7. Wells and Water Storage Tanks
7.1 The contractor must follow the specific guidance as stated in the GA EPD’s “Minimum Standards For Public Water Systems”. This document can be Found on the GA EPD’s web site:
http://www.gaepd.org/Files_PDF/techguide/wpb/standards.pdf .
7.2 Additional guidance can be found in the following documents:
7.2.1 Water Storage Tanks: The latest edition of the AWWA’s D102 (Coating Steel Water-Storage Tanks) and M42 (Steel Water-Storage Tanks).
7.2.2 Wells: AWWA’s C654 (Disinfections of Wells)
A well permit application must be submitted prior to constructing a well.
7.2.2.2 Well drilling logs, source sampling data, and P.E. construction certification statement must be submitted upon completion of all wells.
7.3 Lead Requirements
7.3.1 Reference the Safe Drinking Water Act (as amended 4 JAN 2014) regarding standard for the lead content in plumbing materials. Lead content in solder and flux will not exceed 0.2% and lead content in the wetted surface of pipes, pipe fittings, plumbing fittings, and fixtures used in public potable water systems will not exceed 0.25%.
7.4 Meters. All new water service connections must be metered.
8. Electrical Meters and Instrument Transformers
8.1 Electrical meters and instrument transformers shall meet or exceed the minimum
Measure quantities. Electrical meter quantities measured are Power average demand over 15 minute intervals and Energy
System Accuracy. System accuracy for the meter product devices instrument transformers shall not exceed 1% as calculated using the Root Sum (RSS) method and assuming normal
Meter
For facilities with connected load equal to or greater than one (1) volt-ampere (MVA), meter certification shall be NEMA/ANSI C12.20, class
For facilities with load less than 1MVA, meter certification shall IEEE/ANSI C12.16, Accuracy class
Communication Protocol. Meters shall communicate via either Modbus RTU (LonTalk) protocols or as otherwise
Auxiliary data ports. Unless otherwise specified, electrical meters shall have minimum of two pulse inputs for incorporation and transmission of other external
Surge Protection. IEEE/ANSI C37.90.1, Standard surge withstand (SWC) tests for relays and relay systems associated with electric power
Current transformers (CTs) sized properly so that the meter secondary of transformer shall output current to ensure at least a plus or minus
0.6% accuracy current when measured between 10% and 90% of full amperage
CTs shall not exceed 5 amps on the secondary
Burden on CTs shall not exceed rated burden for the accuracy
CTs shall be provided in split core 1.7.4 CTs shall be provided in the appropriate ranges to meet the service amperage
For facilities with a connected load equal to or greater than 1MVA, certification shall be IEC 185 or ANSI/IEEE C57.13 for 0.3% accuracy class
For facilities with a connected load less than 1MVA, CTs shall grade and certified per IEEE/ANSI C57.13 or IEC
Current sensors shall be sized properly for the application and provide a (normally 0-2 volts) to the meter that results in at least a plus or minus 0.6% accuracy current when measured between 10% and 90% of full amperage
Voltage or Potential Transformers (PTs) sized properly so that the transformer shall output voltage to ensure at least a plus or minus accuracy of voltage when measured from zero to the IEEE/ANSI C57.13 or IEC specified standard burden, at the specified standard burden power factor, and at any from 90% to 110% of rated
For facilities with a connected load equal to or greater than 1MVA, certification shall be IEC 185 or IEEE/ANSI C57.13 for 0.3% accuracy class
For facilities with a connected load less than 1MVA, PTs shall be grade and certified per IEEE/ANSI C57.13 or IEC
Burden on PTs shall not exceed rated burden for accuracy
Data Storage. Unless otherwise specified, the meter must be capable providing and storing required interval data for a minimum of 30
Environmental Tolerances
Meters shall be installed in indoors/interior locations and rated operation and storage from 0° - 50° C or better and 5 to 90% relative humidity condensing). Interior meters shall be provided with or installed within a NEMA
Advanced Metering Data Management System front end computer requirements
Data encapsulation format shall be Extensible Markup Language (XML) Simple Object Access Protocol (SOAP) for future output to a remote centralized data management
Storage of metered data for at least 2
Display of data upon request and selectable from 1 minute to 15 minutes
Final install of front end equipment shall, at minimum, display accurate readings for each meter in a text format. Customization of the user interface is required. Two hardcopies and two electric copies (DVD or CD) of shall be provided for customization and integration of additional features that are not prepared at the time of final
Display capability shall include multiple graphical formats such as data time (minutes, hours, days, weeks, months, and year) comparison between data from two or more meters and other standard meter
System expansion capability of 50 times for incremental future growth of data to include water, gas and
Data Transmission Media is LAN, Radio Frequency, or Power Lines for of metered data to the Advanced Metering Data Management
System, whichever is economical for the
9.2 Water Conservation Requirements. IAW the Georgia Water Stewardship Act (GWSA), Section 8, water fixtures will meet the following minimum water conservation standards (note – Section 8 of the GWSA can be found on the bottom of the Georgia Environmental Protection Division’s website:
http://www.gaepd.org/Documents/outdoorwater.html
9.2.1 Toilets will not exceed 1.28 gallons per flush.
9.2.2 Showerheads will not exceed an average of 2.5 gallons of water per minute at 60 pounds per square inch of pressure.
9.2.3 Urinals will not exceed 0.5 gallons per flush.
9.2.4 Lavatory faucets will not exceed 1.5 gallons per minute flow.
9.2.5 Kitchen faucets will not exceed 2.0 gallons per minute flow.
9.3 Sanitary Inspections Prior to Government acceptance, the Contractor, through the COR, must coordinate with Installation Environmental Health,
(912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure drinking water lines (e.g. Drinking fountain, utility sink, etc.) have been super-chlorinated with positive chlorine residuals and are free of any bacteria.
9.4 Outdoor Sprinkler Systems
Sprinkler systems must be isolated from potable drinking water lines (no cross-connection) to allow for easy conversion to non-potable water sources in the future. If a non-potable water source is within 200 feet of the site at the time of construction, tying into the non-potable lines is required.
If connected to a potable water source, a backflow preventer is required.
The sprinkler system must include timers and rain gauges to ensure the system is not running while there is a rainstorm.
9.5 Fire Hydrants
Prior to placing into service, the Contractor, through the COR, must coordinate with Installation Environmental Health, (912) 435-5721 or (912) 257-1220, for bacteriological testing to ensure potable water lines have been super-chlorinated with positive chlorine residuals and are free of any bacteria.
9.6 Hydrant models specified should be those equipped with an anti-terrorism device.
9.7.1 Ensure all water service connections with discontinued service due to abandonment or demolition are properly and permanently capped and sealed to prevent the escape of potable water or possible contamination.
9.7.2 Remove all asbestos lines that are abandoned as a result of a project.
9.8 Wastewater Requirements
9.8.1 REQUIRED SUBMITTAL ITEM: If a new sewer main, septic tank, and/or lift station will be installed, it is required that the contractor submit applications for GA EPD approval through the Installation DPW Environmental Division. At least 100 days prior to construction, the Contractor must submit the following through the COR to the DPW Environmental Division, Prevention and Compliance Branch to the attention of the Wastewater Program Manager (912-767-4937 or 767-2010).
9.8.1.1 The contractor must submit three copies of the sewer main extensions, septic tank, and/or lift station drawings and specifications.
9.8.1.2 All drawings and specification shall be stamped by a GA certified P.E.
9.8.1.3 Sanitary Sewer Extension Submittal Forms or Underground Injection Control Non-Domestic Septic System Forms will be submitted for any project that extends the sanitary sewer main, includes installation of a lift station or installation of septic tank/ leach field or septic system.
9.8.2 Lift Stations. The following are required:
9.8.2.1 High level alarm (visual & audible).
9.8.2.2 Perimeter fencing.
9.8.2.3 A Supervisory Control and Data Acquisition (SCADA) System compatible with the current system used on the Installation (thermostat controlled panel heaters will need to be included on transmitter units).
9.8.2.4 Emergency bypass.
9.8.2.5 Electric generator. The standby generator must be commissioned in accordance with applicable OSHA, EPA, NEC and NFPA 110 Section 16620 Sanitary Sewer Pump Station Emergency Pump Station Standards.
If diesel fuel generators are used (rather than natural gas) the fuel storage tanks must be double walled ASTs.
9.8.3 Demolition
9.8.4 Ensure all sewer service connections are properly disconnected prior to demolition. Permanently cap and seal service connections to prevent the infiltration of groundwater or surface water into the sanitary collection system.
9.8.5 (N/A) The contents of septic tanks will be pumped out and properly disposed of at a wastewater treatment plant. The septic tank will be removed from its current location and the tank must be either recycled or otherwise properly disposed. After removal, backfill will be placed and compacted.
The leach field soil may remain in place to naturally attenuate after abandonment of the site.
10 Stormwater / Erosion and Sedimentation Control (E&S) Requirements
10.1 Requirements for Sites with Soil Disturbance Greater Than 0.75 Acres
10.1.1 A Notice of Intent (NOI) for coverage under the Georgia National Pollution Discharge Elimination System (NPDES) Permit must be applied for through the DPW Environmental Office Stormwater POC (Russell Moncrief at 912- 767-0271). The land disturbance calculation must include project entrances /exits, material lay down areas, equipment storage areas, soil stockpile, fill, and muck out areas. The NOI package has a mandatory 14-day waiting period once mailed to the Georgia Environmental Protection Division (EPD).
Land disturbing activities cannot occur until the 14-day waiting period has ended. The NOI package includes an Erosion & Sedimentation and Pollution Control (ESPC) Plan, fees in the amount of $80/acre, the fee form, and the NOI application. In addition to meeting those requirements under the Georgia Erosion and Sedimentation Control Act, the contractor must also follow Federal and local E&S control regulations. A summary of the applicable stormwater / E&S requirements are provided below:
10.1.1.1 E&S Control Best Management Practices (BMPs) will be identified in the ESPC Plan and must be utilized by the contractor. The ESPC Plan will include those requirements identified in the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia), the Coastal Stormwater Supplement, the Energy Independence and Security Act Section 438, the US Environmental Protection Agency (EPA) Technical Guidance (EPA 841-B-09-001 December 2009), the United Facilities Criteria (UFC) Manual for Low Impact Design, and those additional applicable Federal and local requirements found at the following web link:
http://www.stewart.army.mil/info/?id=443&p=1 and a summary of how these materials apply is provided in the three sub-bullets below. Reference DPW Stormwater Management Policy Letter #11 and the USACE Hydrology and Low Impact Development site: https://mrsi.erdc.dren.mil/sustain/cx/lid is used to house official documents, planning and design tools for use in development of Army projects. Army LID implementation will be accomplished using Army LID guidance "Army Stormwater Management Using Low Impact Development" (this document), the Army Low Impact Development Technical User Guide (see Best Practices section of the mrsi site), and the Army's LID Planning Tool and LID Cost Planning Tool (see Design Tools section of Army Stormwater Management Using Low Impact Development the mrsi site).
10.1.1.2 The ESPC Plan must also include flow calculations demonstrating concentrated runoff flows from peak rain events will not impact (a) any existing stream, (b) upstream systems and (c) downstream systems of the site as required for Total Maximum Daily Loads to maintain water quality standards by the removal of any potential pollutants.
10.1.1.3 When preparing the ESPC Plan, refer to the following web link:
http://www.stewart.army.mil/info/?id=443&p=1 for a copy of two Installation Policies (#10 and #11) that require engineers / proponents to take a more holistic approach to stormwater management of individual construction projects. Specifically, engineers must use Low Impact Development (LID) and Green Infrastructure (GI) stormwater control practices along with water quantity management practices found in the Georgia Stormwater Management Manual and the Coastal Stormwater Supplement. This is necessary to completely satisfy aquatic resource protection, overbank flood protection, and extreme flood protection which are criterion found in these documents for post-construction BMPs. In addition, it is required the utilization of the following guidance at the following site for DoD facilities:
https://mrsi.erdc.dren.mil/sustain/cx/lid
10.1.2 Dry detention basins must be located downstream of other LID/GI structural controls. Hydraulic considerations are necessary to ensure dry detention basins are sized to store the entire water quality design volume or have adequate structural controls to meet the minimum criteria for a 1-year, 24-hour storm event. PLEASE NOTE: Wet retention ponds are not a BMP option for FSGA/HAAF; reference DPW Policy Letter #10.
10.1.3 Site dewatering requires prior approval from the Environmental Office.
10.1.4 The site operator for the proposed action is required to continuously maintain all BMPs through the duration of site disturbing activities (regardless of NOI requirement). In order for the Army to accept the project as complete, the site must be stabilized to prevent silts and sediments from leaving the construction site. The Installation, through its Contracting Officer Representative, NRCS, and the DPW Environmental Office, must agree that the project site meets necessary site stabilization parameters as required by the State of Georgia prior to project acceptance by the Army.
10.1.5 At a minimum, a Level 1A E&S Control Certified individual must be on the site during any land disturbance activity in the State of Georgia.
10.1.6 Cross drainage facilities that transport stormwater runoff under roadways must meet the 25- to 100-year design storm, or be in accordance with GA Department of Transportation requirements, whichever is more stringent.
The design must ensure that the structure(s) will not impact any facilities upstream or downstream during heavy rain events. Culverts, bridges, and/or roadway drainage structures require bank stabilization to prevent erosion during rain events.
10.1.7 Equipment cleanout (brushes, rollers, spray guns/lines, etc.) must occur in designated areas (sink basins or washracks which discharge to sanitary or industrial wastewater treatment plants) and must not discharge to the stormwater conveyance system. Ensure all washouts of trucks and equipment is controlled and is discharged with adequate E&S control BMPs.
10.1.8 Ensure proper drip pans and secondary containment are utilized for staging, storing, loading, fueling, maintenance, repairs, etc.
10.1.9 Place all fuel storage tanks within plastic lined earthen berms, drive-on, or drive-over containment. The containment area must have a minimum capacity of 110% of the fuel storage tanks capacity for spill prevention, and to capture incidental spills.
10.2 Requirements for Sites with Soil Disturbance Less Than 0.75 Acres
10.2.1 An NOI for coverage under the Georgia NPDES will not be necessary. The following requirements still apply:
10.2.2 The site operator must utilize and implement Best Management Practices (BMPs) in accordance with the “Green Book” (Manual for Erosion & Sedimentation Control for the State of Georgia-most current edition).
10.2.3 Site dewatering requires prior approval from the Installation Environmental Office.
10.2.4 The site operator is required to continuously maintain all BMPs through the duration of site disturbing activities (regardless of NOI requirement). In order for the Army to accept the project as complete, the site must be stabilized to prevent silts and sediments from leaving the construction site.
The Installation, through its Contracting Officer Representative, NRCS, and the DPW Environmental Office, must agree that the project site meets necessary site stabilization parameters as required by the State of Georgia prior to project acceptance by the Army.
10.2.5 At a minimum, a Level 1A E&S Control Certified individual must be on the site during any land disturbance activity in the…
This is the start of the file's text. The full file is on GovTribe.