Solicitation_Amendment__W9124M-19-R-0015-0002_Q&A.docx
DOCX document 12 KB Posted
- Solicitation number
- W9124M-19-R-0015
About this file
Solicitation Amendment 0002 Questions & Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Synopsis-Solicitation_USMA_Shelter_Support_Services_-_Amendment_0002.docx | DOCX document | |
| Concrete_Pad_Example_4.jpg | JPG image | |
| Overflow_Tent_Lot_-_South_CNB.jpg | JPG image | |
| Solicitation_Amendment__W9124M-19-R-0015_Questions_&_Answers.docx | DOCX document | |
| Concrete_Pad_Example_2.jpg | JPG image | |
| Concrete_Pad_Example_5.jpg | JPG image | |
| Concrete_Pad_Example_3.jpg | JPG image | |
| Synopsis-Solicitation_USMA_Shelter_Support_Services_-_Amendment_0001.docx | DOCX document | |
| Concrete_Pad_Example_1.jpg | JPG image | |
| Exhibit_A_-_Bid_Schedule_-_USMA_SSSs_V1.xlsx | XLSX spreadsheet | |
| Synopsis-Solicitation_Shelter_Support_Services_-_USMA_V3.docx | DOCX document | |
| Attachment_A_-_Map_of_Approved_Tent_Locations_V1.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0002 Questions & Answers to Solicitation #: W9124M-19-R-0015 – 29 April 2019
Question (Q) = Contractor Answer (A) = Government
*Note. See Solicitation Amendment 0002 containing lined out red font (deletions) and blue font (additions) to highlight the changes incorporated into the revised PWS within the Solicitation document. All questions and answers provided as part of Amendment 0001 are valid and still in effect. Below are the new questions and answers:
Q1: Do you have any salient characteristics for the tent floors?
A1: Yes. The Requiring Activity approved the revision of the tent floor salient characteristics to bring clarity to expectations of floor quality. See Paragraph 5.4 of Solicitation Amendment 0002 for the revised changes to the PWS.
Q2: Have there been any changes as to when the 450 Soldiers are scheduled to arrive and occupy the tents?
A2: Yes. The Requiring Activity stated today that a phased arrival plan for all 450 Soldiers is in effect. See Paragraph 1.3 – Objectives for the revised dates and numbers of personnel arriving at Camp Natural Bridge.
-------------------------END OF QUESTIONS AND ANSWERS FOR AMENDMENT 0002--------------------------