Ordering Period 1
| CLIN # | Description | Extended Price | Hours | Fully Burden Rate | |
| 0001 | Phase In | Progam Manager | 1,880 | ||
| 0002 | PM Support Services | Communication Specialist | 1,880 | ||
| 0003 | Other Direct Costs/DO NOT PROPOSE | $ 52,000.00 | Program Analyst | 20,680 | |
| 0004 | Contract Manpower Reporting | $ - 0 | |||
| 0005 | BRAC Round Ppreparation & LSIA | $ - 0 | |||
| 0006 | Other Direct Costs/DO NOT PROPOSE | $ 5,000.00 |
Total Tasks (Ordering Period 1) $ 57,000.00
W9124J-18-R-0001/BRAC PM & LSIA
Ordering Period 1 Pricing Sheet 1 December 2018 - 30 November 2019
NOTE 1: CLINs 0001, 0002, 0003 and 0004 are the core of the Task Order 1.
NOTE 2: the goverment may or may not award CLIN 0005 and 0006 during any ordering period. The vendor needs to calualte CLIN 0005 by inseriting fully burden rates above. Any escalation rate should be included.
NOTE 3: For evaluation purposes, the Government will utilize Offeror’s total proposed pricing for CLINs 0001 thorugh 0006. The offeror’s total proposed price will be evaluated for reasonableness and balance.
Ordering Period 2
| CLIN # | Description | Extended Price | Hours | Fully Burden Rate | |
| Progam Manager | 1,880 | ||||
| 0002 | PM Support Services | Communication Specialist | 1,880 | ||
| 0003 | Other Direct Costs/DO NOT PROPOSE | $ 52,000.00 | Program Analyst | 20,680 | |
| 0004 | Contract Manpower Reporting | $ - 0 | |||
| 0005 | BRAC Round Ppreparation & LSIA | $ - 0 | |||
| 0006 | Other Direct Costs/DO NOT PROPOSE | $ 5,000.00 |
Total Tasks (Ordering Period 1) $ 57,000.00
1 December 2019 - 30 November 2020
NOTE 1: CLINs 0001, 0002, 0003 and 0004 are the core of the Task Order 1.
NOTE 2: the goverment may or may not award CLIN 0005 and 0006 during any ordering period. The vendor needs to calualte CLIN 0005 by inseriting fully burden rates above. Any escalation rate should be included.
NOTE 3: For evaluation purposes, the Government will utilize Offeror’s total proposed pricing for CLINs 0001 thorugh 0006. The offeror’s total proposed price will be evaluated for reasonableness and balance.
Ordering Period 3
| CLIN # | Description | Extended Price | Hours | Fully Burden Rate | |
| Progam Manager | 1,880 | ||||
| 0002 | PM Support Services | Communication Specialist | 1,880 | ||
| 0003 | Other Direct Costs/DO NOT PROPOSE | $ 52,000.00 | Program Analyst | 20,680 | |
| 0004 | Contract Manpower Reporting | $ - 0 | |||
| 0005 | BRAC Round Ppreparation & LSIA | $ - 0 | |||
| 0006 | Other Direct Costs/DO NOT PROPOSE | $ 5,000.00 |
Total Tasks (Ordering Period 1) $ 57,000.00
1 December 2020 - 30 November 2021
NOTE 1: CLINs 0001, 0002, 0003 and 0004 are the core of the Task Order 1.
NOTE 2: the goverment may or may not award CLIN 0005 and 0006 during any ordering period. The vendor needs to calualte CLIN 0005 by inseriting fully burden rates above. Any escalation rate should be included.
NOTE 3: For evaluation purposes, the Government will utilize Offeror’s total proposed pricing for CLINs 0001 thorugh 0006. The offeror’s total proposed price will be evaluated for reasonableness and balance.
CLIN Summary-Total Eval Price
| CLIN # | Description | Extended Price |
| 0001 | Phase In | $ - 0 |
| 0002 | PM Support Services (Ordering period 1-3) | $ - 0 |
| 0003 | Other Direct Costs/DO NOT PROPOSE (Oredering period 1-3) | $ 156,000.00 |
| 0004 | Contract Manpower Reporting (Ordering period 1-3) | $ - 0 |
| 0005 | BRAC Round Ppreparation & LSIA (Ordering period 1-3) | $ - 0 |
| 0006 | Other Direct Costs/DO NOT PROPOSE (Ordering Period 1-3) | $ 15,000.00 |
CLIN Summary-Total Evaluated Price $ 171,000.00