Text version
ATTACHMENT 1 OPTION YEAR III
BIDDING SCHEDULE OPTION YEAR III UNIT
ITEM NO. DESCRIPTION UNIT Quantities PRICE
3001 Clearing and Grubbing (AHS DOC 201) Completion Time (CT): 3 days/2 Acre Acre 4 $ -
3002 Removing Trees (AHS DOC 201) CT: 3 Trees/day Each 4 $ -
3003 Removing Concrete Sidewalk (AHS DOC 206) CT: 25 SY/day
Square Yard 120 $ -
3004 Removing Concrete Pavement (AHS DOC
206) CT: 25 SY/day
Square Yard 400 $ -
3005 Removing Asphalt Pavement (AHS DOC 206) CT: 25 SY/day
Square Yard 1750 $ -
3006 Removing Pipe (6"-24") (AHS DOC 206) CT: 50 LF/day Linear Foot 20 $ -
3007 Removing Large Pipe (30"-60") (AHS DOC
206) CT: 50 LF/day Linear Foot 5 $ -
3008 Removing X-Large Pipe (>60") (AHS DOC 206) CT: 50 LF/day Linear Foot 4 $ -
Removing Old Box Culvert (AHS DOC 206)
CT: 10 LF/day Note: Maximum culvert size:
10'x10'
Linear Foot 4
3010 Removing Curb (AHS DOC 206) CT: 50 LF/day Linear Foot 230 $ -
3011 Removing Combination Curb & Gutter (AHS DOC 206) CT: 50 LF/day Linear Foot 55 $ -
3012 Removing Guardrail (AHS DOC 206) CT: 50 LF/day Linear Foot 125 $ -
3013 Removing Rail Road Track (AHS DOC 206) CT: 25 LF/day Linear Foot 25 $ -
3014 Removing Headwall (6"-24") (AHS DOC 206) CT: 2 days/ea Each 4 $ -
3015 Removing Large Headwall (30"-60") (AHS DOC 206) CT: 3 days/ea Each 4 $ -
3016 Removing Inlet (6"-24") (AHS DOC 206) CT:
3 days/EA Each 4 $ -
3017 Removing Large Inlet (30"-60") (AHS DOC
206) CT: 3 days/ea Each 4 $ -
(This CLIN Information Only) 3018 UNCLASSIFIED EXCAVATION (AHS DOC 210)
3019 Unclassified Excavation (0-100 CY) CT: 100 CY/day Cubic Yard 60 $ -
3020 Unclassified Excavation (101-1000 CY) CT: 100 CY/day Cubic Yard 200 $ -
3021 Unclassified Excavation (>1,000 CY) CT: 100 CY/day Cubic Yard 5750 $ -
3022 Muck Excavation (AHS DOC 210) CT: 25 CY/day Cubic Yard 13 $ -
(This CLIN Information Only) 3023 BORROW EXCAVATION (AHS DOC 210) (Note: All Testing Included in Unit Price)
3024 Borrow Excavation (0-100 CY) CT: 100 CY/day Cubic Yard 120 $ -
3025 Borrow Excavation (101-500 CY) CT: 100 CY/day Cubic Yard 130 $ -
3026 Borrow Excavation (>500 CY) CT: 100 CY /day Cubic Yard 3650 $ -
Machine Grading Shoulders (AHS DOC 212)
(Note: 1 STA=100 LF) CT: 3 STA/day
Station 135
3028 Structure Excavation (AHS DOC 214) CT: 75 CY/day Cubic Yard 100 $ -
3029 Foundation Backfill (AHS DOC 214) CT: 10 CY/day Cubic Yard 25 $ -
ITEM NO. DESCRIPTION UNIT Quantities PRICE
(This CLIN Information Only) 3030 ROADBED PROCESSING (AHS DOC 230)
3031 Roadbed Processing (0-2,000 SY) CT: 100 SY/day
Square Yard 500 $ -
3032 Roadbed Processing (>2,000 SY) CT: 100 SY/day
Square Yard 3850 $ -
3033 Pneumatic Roller Compaction CT: 250 SY/day
Square Yard 4 $ -
3034 Roadbed Stabilizing Material (AHS DOC 231) CT: 5 Tons/day Ton 20 $ -
(This CLIN Information Only) 3035
GRANULAR SOIL BASE COURSE (6"
Compacted Thickness) (AHS DOC 301) (Note: All Testing Included in Unit Price)
3036 Granular Soil Base Course (0-2,000 SY) CT: 250 SY/day
Square Yard 1750 $ -
3037 Granular Soil Base Course (>2,000 SY) CT: 250 SY/day
Square Yard 3500 $ -
(This CLIN Information Only) 3038
SOIL AGGREGATE BASE COURSE (6"
Compacted Thickness) (AHS DOC 301)
(Note: All Testing Included in Unit Price)
3039 Soil Aggregate Base Course (0-2,000 SY) CT:
100 SY/day
Square Yard 100 $ -
3040 Soil Aggregate Base Course (>2,000 SY) CT: 100 SY/day
Square Yard 400 $ -
(This CLIN Information Only) 3041
CRUSHED AGGREGATE BASE COURSE
(6" Compacted Thickness) (AHS DOC 301) (Note: All Testing Included in Unit Price)
Note: 1 Ton = 3 SY 3042 Crushed Aggregate Base Course (0-2,000 SY)
CT: 100 SY/day Square Yard 500 $ -
3043 Crushed Aggregate Base Course (>2,000 SY) CT: 100 SY/day
Square Yard 5250 $ -
3044 Compaction Test (Nuclear Method (AHS DOC
306) CT: N/A Each 4 $ -
3045 Proctor Density Test (AHS DOC 306) CT: 2 Ea/day Each 4 $ -
3046 Bituminous Treatment Prime Coat A (AHS
DOC 401) CT: N/A
Square Yard 1250 $ -
3047 Bituminous Surface Treatment J (AHS DOC
401) CT: 250 SY/day
Square Yard 7250 $ -
3048 Bituminous Surface Treatment K (AHS DOC
401) CT: 250 SY/day
Square Yard 4 $ -
3049 Bituminous Surface Treatment L (AHS DOC
401) CT: 250 SY/day
Square Yard 4 $ -
3050 Slurry Seal Coat Type 1 (AHS DOC 402) CT: 10 days/5,000 SY
Square Yard 4 $ -
3051 Slurry Seal Coat Type 2 (AHS DOC 402) CT: 10 days/5,000 SY
Square Yard 4 $ -
3052 Tack Coat (AHS DOC 405) CT: 200 GA/day Gallon 5500 $ -
(This CLIN Information Only) 3053
PLANNING (MILLING) OF EXISTING
PAVEMENT (TO 1" THICKNESS) (AHS DOC
408)
3054 Planning (Milling) of Existing Pavement (To 1" Thickness) (0-5,000 SY) CT: 500 SY/day
Square Yard 1500 $ -
3055 Planning (Milling) of Existing Pavement (To 1" Thickness (>5,000 SY) CT: 500 SY/day
Square Yard 33000 $ -
ITEM NO. DESCRIPTION UNIT Quantities PRICE
(This CLIN Information Only) 3056
ADDITIONAL PLANNING (MILLING)
PAVEMENT (From 1" to 3") (AHS DOC 408) (1" Thick per SY, Orderable in 2" thick per
SY increments)
3057 Additional Planning (Milling) Pavement (From 1" to 3") (0-5,000 SY) CT: 500 SY/day
Square Yard 1500
3058 Additional Planning (Milling) Pavement (From 1" to 3") (>5,000 SY) CT: 500 SY/day
Square Yard 22500
(This CLIN Information Only) 3059 AIRFIELD PAVEMENT (TS DOC) (UFGS 32 12 15)
3060 Airfield Pavement (0-500 Tons) CT: 250 Tons/day Ton 100 $ -
3061 Airfield Pavement (>500 Tons) CT: 250 Tons/day Ton 4250 $ -
(This CLIN Information Only) 3062
SUPERPAVE BITUMINOUS CONCRETE
UPPER BINDER LAYER (1"), ESAL RANGE
C/D (AHS DOC 424)
Superpave Bituminous Concrete Upper Binder
Layer (1"), ESAL Range C/D (0-100 Tons) CT: 10 Tons/day
Ton 25
Superpave Bituminous Concrete Upper Binder
Layer (1"), ESAL Range C/D (>100 Tons) CT: 10 Tons/day
Ton 225
(This CLIN Information Only) 3065
SUPERPAVE BITUMINOUS CONCRETE
UPPER BINDER LAYER, PATCHING (1"),
ESAL RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Upper Binder Layer, Patching (1"), ESAL Range C/D (0-25
Tons) CT: 5 Tons/day Ton 25
Superpave Bituminous Concrete Upper Binder Layer, Patching (1"), ESAL Range C/D (>25
Tons) CT: 5 Tons/day Ton 100
(This CLIN Information Only) 3068
SUPERPAVE BITUMINOUS CONCRETE
UPPER BINDER LAYER, WIDENING (1"),
ESAL RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Upper Binder Layer, Widening (1"), ESAL Range C/D (0-100
Tons) CT: 5 Tons/day Ton 15
Superpave Bituminous Concrete Upper Binder Layer, Widening (1"), ESAL Range C/D (>100
Tons) CT: 5 Tons/day Ton 100
(This CLIN Information Only) 3071
SUPERPAVE BITUMINOUS CONCRETE
WEARING SURFACE LAYER (1/2"), ESAL
RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Wearing
Surface Layer (1/2"), ESAL Range C/D (0-200 Tons) CT: 250 Tons/day
Ton 125
Superpave Bituminous Concrete Wearing
Surface Layer (1/2") (201-500 Tons) CT: 250 Tons/day
Ton 400
Superpave Bituminous Concrete Wearing
Surface Layer (1/2"), ESAL Range C/D (>500 Tons) CT: 250 Tons/day
Ton 2760
(This CLIN Information Only) 3075
SUPERPAVE BITUMINOUS CONCRETE
WEARING SURFACE LAYER (3/8"), ESAL
RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Wearing
Surface Layer (3/8"), ESAL Range C/D (0-200 Tons) CT: 250 Tons/day
Ton 50
ITEM NO. DESCRIPTION UNIT Quantities PRICE
Superpave Bituminous Concrete Wearing
Surface Layer (3/8") (201-500 Tons) CT: 250 Tons/day
Ton 100
Superpave Bituminous Concrete Wearing
Surface Layer (3/8"), ESAL Range C/D (>500 Tons) CT: 250 Tons/day
Ton 225
(This CLIN Information Only) 3079
SUPERPAVE BITUMINOUS CONCRETE
WEARING LAYER - PATCHING (1/2"), ESAL
RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Wearing
Layer-Patching (1/2"), ESAL Range C/D (0-25 Tons) CT: 5 Tons/day
Ton 5
Superpave Bituminous Concrete Wearing
Layer-Patching (1/2"), ESAL Range C/D (>25 Tons) CT: 5 Tons/day
Ton 30
(This CLIN Information Only) 3082
SUPERPAVE BITUMINOUS CONCRETE
WEARING LAYER-LEVELING (3/8"), ESAL
RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Wearing
Layer-Leveling (3/8"), ESAL Range C/D (0-250 Tons) CT: 25 Tons/day
Ton 175
Superpave Bituminous Concrete Wearing Layer-Leveling (3/8") (>250 Tons) CT: 25
Tons/day Ton 350
(This CLIN Information Only) 3085
SUPERPAVE BITUMINOUS CONCRETE
WEARING LAYER-WIDENING (1/2"), ESAL
RANGE C/D (AHS DOC 424)
Superpave Bituminous Concrete Wearing
Layer-Widening (1/2"), ESAL Range C/D (0- 100 Tons) CT: 25 Tons/day
Ton 25
Superpave Bituminous Concrete Wearing
Layer-Widening (1/2"), ESAL Range C/D (>100 Tons) CT: 25 Tons/day
Ton 120
3088 Aggregate Surfacing (AHS DOC 430) (Note: 1 Ton = 4.45 SY @ 6" thick) CT: 100 Tons/day Ton 100
Plain or Reinforced Cement Concrete
Pavement 4" Thick (AHS DOC 450) CT: 25 SY/day
Square Yard 525
Plain or Reinforced Cement Concrete
Pavement 6" Thick (AHS DOC 450) CT: 25 SY/day
Square Yard 450
Plain or Reinforced Cement Concrete
Pavement 8" Thick (AHS DOC 450) CT: 25 SY/day
Square Yard 550
Plain or Reinforced Cement Concrete
Pavement 12" Thick (AHS DOC 450) CT: 25 SY/day
Square Yard 50
3093 6"x6"-W4.0xW4.0 Welded Wire Fabric (AHS
DOC 502) CT: N/A
Square Yard 1500 $ -
3094 4"x4" - W4.0xW4.0 Welded Wire Fabric (AHS
DOC 502) CT: N/A
Square Yard 400 $ -
3095 ASTM Standard Reinforced Bars Steel Reinforcement (AHS DOC 502) CT: 300 lb/day Pound 400
Reinforced Culvert Concrete (Precast or C.I.P.
(AHS DOC 524) CT: 1 CY/day Note:
Reinforcement will be paid separate under Item
Cubic Yard 14
ITEM NO. DESCRIPTION UNIT Quantities PRICE
Reinforced Culvert Concrete Extension (Precast or C.I.P. (AHS DOC 524) CT: 1 CY/day Note: Reinforcement will be paid separate under Item 3095
Cubic Yard 4
3098 12" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3099 18" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3100 24" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3101 30" Roadway Pipe Class 3 R. C. Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3102 36" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3103 48" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
3104 60" Roadway Pipe, Class 3 R.C., Class C Bedding (AHS DOC 530) CT: 16 LF/day Linear Foot 48 $ -
(This CLIN Information Only) 3105 6" UNDERDRAIN PIPE, TYPE 9 OR 10 (AHS
DOC 606)
3106 Bottom of Trench Below Existing Ground Less Than or Equal to 3' CT: 20 LF/day Linear Foot 45 $ -
Bottom of Trench Between 3' and No More
Than 6' CT: 20 LF/day (max bid less than or = 120% of Item 0105)
Linear Foot 150
Bottom of Trench Between 6' and No More
Than 9' CT: 20 LF/day (max bid less than or = 150% of Item 0105)
Linear Foot 55
Bottom of Trench Between 9' and No More
Than 12' CT: 20 LF/day (max bid less than or = 175% of Item (0105)
Linear Foot 25
3110 Paving Geotextiles (AHS DOC 607) CT: 250 SY/day
Square Yard 12 $ -
3111 Asphalt Sealant (AHS DOC 607) CT: N/A Gallon 100 $ -
3112 Loose Riprap, Class 1 or 2 (AHS DOC 610 CT: 15 Tons/day Ton 450 $ -
3113 Filter Blanket, Geotextile Non-Woven (AHS
DOC 610) CT: N/A
Square Yard 470 $ -
3114 Slope Paving (AHS DOC 614) CT: 2 CY/day Cubic Yard 200 $ -
Reinforced Slope Paving (AHS DOC 614), included reinforcement is Item 0093 CT: 2
CY/day Cubic Yard 125
Reinforced Concrete Sidewalk 4" Thick (AHS
DOC 618), included reinforcement is Item 3093 CT: 10 SY/day
Square Yard 300
Reinforced Concrete Driveway 6" Thick (AHS
DOC 618) CT: 10 SY/day, included reinforcement is Item 3093
Square Yard 110
3118 12" Pipe End Treatment, Class 1 (AHS DOC
619) CT: 1 day/EA Each 12 $ -
3119 12" Pipe End Treatment, Class 2 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3120 18" Pipe End Treatment, Class 1 (AHS DOC
619) CT: 1 day/EA Each 6 $ -
3121 18" Pipe End Treatment, Class 2 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3122 24" Pipe End Treatment, Class 1 (AHS DOC
619) CT: 1 day/EA Each 5 $ -
ITEM NO. DESCRIPTION UNIT Quantities PRICE
3123 24" Pipe End Treatment, Class 2 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3124 30" Pipe End Treatment, Class 1 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3125 30" Pipe End Treatment, Class 2 (AHS DOC
619) CT: 1day/EA Each 4 $ -
3126 36" Pipe End Treatment, Class 1 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3127 36" Pipe End Treatment, Class 2 (AHS DOC
619) CT: 1 day/EA Each 4 $ -
3128 Minor Structure Concrete (0-5 CY) (AHS DOC
620) CT: 1 CY/day Cubic Yard 7 $ -
3129 Minor Structure Concrete (>5 CY) (AHS DOC
620) CT: 1 CY/day Cubic Yard 21 $ -
3130 Junction Boxes, Type 1 (AHS DOC 621) CT: 3 EA/day Each 4 $ -
3131 Junction Box Unit, Type 1 (AHS DOC 621) CT: N/A Each 4 $ -
3132 Inlets, Type B (AHS DOC 621) CT: 3 days/EA Each 4 $ -
3133 Inlet Units, Type B (AHS DOC 621) CT: N/A Each 4 $ -
3134 Inlets, Type C (AHS DOC 621) CT: 3 days/EA Each 5 $ -
3135 Inlet Units, Type C (AHS DOC 621) CT: N/A Each 7 $ -
3136 Inlets, Type S-3, One Wing (AHS DOC 621) CT: 3 days/EA Each 4 $ -
3137 Inlets, Type SE-Two Wings (AHS DOC 621) CT: 3 days/EA Each 4 $ -
3138 Inlet Units, Type S3 (AHS DOC 621) CT: N/A Each 4 $ -
3139 Manholes, Type M (AHS DOC 621) CT: N/A Each 4 $ -
3140 Manhole Units, Type M (AHS DOC 621) CT:
N/A Each 5 $ -
3141 Manhole Covers Reset (AHS DOC 622) CT: 1 day/EA Each 4 $ -
3142 Gratings Reset (AHS DOC 622) CT: 1 day/EA Each 4 $ -
3143 Concrete Gutter (AHS DOC 623) CT: 15 LF/day Linear Foot 100 $ -
(This CLIN Information Only) 3144 CONCRETE CURB, TYPE N (AHS DOC 623)
3145 Concrete Curb, Type N (0-250 LF) CT: 50 LF/day Linear Foot 120 $ -
3146 Concrete Curb, Type N (>250 LF) CT: 50 LF/day Linear Foot 400 $ -
(This CLIN Information Only) 3147 COMBINATION CURB AND GUTTER, TYPE
C (AHS DOC 623)
3148 Combination Curb and Gutter, Type C (0-250 LF) CT: 50 LF/day Linear Foot 60 $ -
3149 Combination Curb and Gutter Type C (>250 LF/day) CT: 50 LF/day Linear Foot 378 $ -
3150 Steel Beam Guardrail, Class A (AHS DOC
630) CT: 50 LF/day Linear Foot 300 $ -
3151 Steel Beam Guardrail, Class B (AHS DOC
630) CT: 50 LF/day Linear Foot 300 $ -
3152 Guardrail End Anchor, Type 10 (AHS DOC
630) CT: 2 days/EA Each 4 $ -
ITEM NO. DESCRIPTION UNIT Quantities PRICE
3153 Guardrail End Anchor, Type Special (AHS DOC 630) CT: 5 days/EA Each 4 $ -
3154 Water Meters Reset (AHS DOC 643) CT: 1 day/EA Each 4 $ -
3155 Valve Boxes Reset (AHS DOC 643) CT: 1 day/EA Each 4 $ -
3156 Topsoil (AHS DOC 650) CT: 10 CY/day Cubic Yard 75 $ -
3157 Seeding (AHS) DOC 652) CT: 2 Acre/day Acre 5 $ -
3158 Solid Sodding (AHS DOC 654) CT: 100 SY/day
Square Yard 3150 $ -
3159 Mulching, Class A Type 1 (AHS DOC 656) CT:
2 Acre/dy Acre 5 $ -
3160 Erosion Control Netting, Class B (AHS DOC
659) CT: 120 SY/day
Square Yard 1700 $ -
3161 Hay Bales (AHS DOC 665) CT: 10 EA/day Each 25 $ -
3162 Silt Fence, Type A (AHS DOC 665) CT: 50 LF/day Linear Foot 3600 $ -
3163 Wattles (AHS DOC 665) CT: 100 LF/day Linear Foot 400 $ -
3164 Floating Basin Boom Type 1 (AHS DOC 665) CT 50 LF/day Linear Foot 400 $ -
(This CLIN Information Only ) 3165 TRAFFIC AND AIRFIELD STRIPE (AHS DOC 701)
3166 Solid 4" Class 1, Type A CT: 5 MI/day (Note:
Reflective Paint for Roadways) Miles 67 $ -
3167 Solid 4" Class 1, Type A CT: 400 LF/day (Note: Reflective Paint for Parking Lots) Linear Foot 32000 $ -
3168 Solid 6" Class 1, Type A CT: 5 MI/day (Note:
Reflective Paint for Roadways or Airfields) Miles 20
3169 Solid 6" Class 1, Type B CT: 5 MI/day (Note:
Non-reflective Paint for Airfields) Miles 8 $ -
3170 Solid 4" Class 2, Type A CT: 3 MI/day (Note:
Reflective Thermoplastic for Roadways) Miles 12 $ -
3171 Solid 5" Class 2, Type A CT: 3 MI/day (Note:
Reflective Thermoplastic for Roadways) Miles 15 $ -
3172 Broken 4" Class 1, Type A CT: 5 MI/day (Note: for roadways) Miles 4 $ -
3173 Broken 4" Class 2, Type A CT: 3 MI/day (Note: for roadways) Miles 5 $ -
3174 Broken 6" Class 1, Type A CT: 5 MI/day (Note: for roadways) Miles 4 $ -
3175 Broken 5" Class 2, Type A CT: 3 MI/day (Note: for roadways) Miles 6 $ -
3176 Dotted 4" Class 2, Type A CT: 750 LF/day Linear Foot 980 $ -
3177 Dotted 5" Class 2, Type A CT: 750 LF/day Linear Foot 1200 $ -
3178 Solid or Broken Temporary Traffic Stripe CT: 2 MI/day Miles 38 $ -
3179 Solid or Broken Stripe Removed CT: 2 MI/day Miles 4 $ -
ITEM NO. DESCRIPTION UNIT Quantities PRICE
(This CLIN Information Only) 3180 TRAFFIC CONTROL MARKINGS AND
LEGENDS (AHS DOC 703)
Traffic Control Markings, Class 1 Type A CT:
500 SF/day (Note: Reflective paint for roadways and parking lots)
Square Foot 6500
Traffic Control Markings, Class 1 Type B CT:
500 SF/day (Note: Non-reflective paint for airfields)
Square Foot 20000
Traffic Control Markings, Class 2 Type A CT:
500 SF/day (Note: Reflective thermoplastic for roadways) Square Foot 1800
Traffic Control Legends, Class 1 Type A CT:
500 SF/day (Note: Reflective paint for roadways and parking lots)
Square Foot 100
Traffic Control Legends, Class 1 Type B CT:
500 SF/day (Note: Non-reflective paint for airfields)
Square Foot 50
Traffic Control Legends, Class 2 Type A CT:
500 SF/day (Note: Reflective thermoplastic for roadways)
Square Foot 75
3187 Removal of Traffic Control Markings or Legends CT: 1,500 SF/day Square Foot 40 $ -
3188 Temporary Traffic Control Markings or Legends CT: 500 SF/day Square Foot 9000 $ -
3189 Pavement Markers, Class A, Type 1 or 2 (AHS DOC 705) CT: 500 SF/day Each 400 $ -
(This CLIN Information Only) 3190 ROADWAY SIGNS (AHS DOC 710)
3191 Class 4, Aluminum Flat Sign Panels CT: 15 SF/day Square Foot 45 $ -
3192 Roadway Sign Post (Green Baked) CT: 100 LF/day Linear Foot 100 $ -
3193 Removal of Existing Roadway Signs CT: 10 EA/day Each 90 $ -
3194 Roadway Sign Relocation (AHS DOC 711) CT: 5 EA/day Each 12 $ -
(This CLIN Information Only) 3195
PC WHEEL STOP PARKING BARRIER-
INCLUDING DOWELS (6"x10"x6'x-0" precast concrete)
3196 Furnish and Install PC Wheel Stop Parking Barrier Including Dowels CT: 15 EA/day Each 50 $ -
Remove and Reset Existing Precast Concrete Wheel stop Parking Barrier Including Dowels
CT: 15 EA/day Each 25
Replace Traffic Activator Loops as required (AHS DOC 730) CT: 2 EA/day (Note: saw cut
2" depth, install #12 AWG activator loop conductor, and seal with a weatherproof epoxy resin sealer; work includes pulling conductor through conduit, and all service connections to return to full service).
Each 4
3199 Asphalt Coring Investigation (1 Set=5 Cores) CT: 2 SETS/day Set 4 $ -
Static Ground Device Installed and Tested
(UFC 3-260-01) CT: 2 EA/day (Note: Closed Eye Static Ground Only. See Figure B11-12)
Each 4
Mooring Device Installed (UFC 3-260-01) CT: 6 EA/day (Note: Device Shall Be Cast in Ductile
Iron 80-55-06 or Equal with No holes) Each 6
ITEM NO. DESCRIPTION UNIT Quantities PRICE
NPDES Notice of Intent/Inspection/Corrections/NOT/ CBMPP
Prepared (Project Location only under 5 acres) (AHS DOC 107) 14 days/each
Each 4
PRIORITY CONSTRUCTION SITES NPDES
Notice of Intent/Inspection/Corrections/NOT/
CBMPP Prepared and Certified (Project Location only under 5 acres) (AHS DOC 107) 45 days/each
Each 4
TOTAL -$
OPTION YEAR 3