About this file
This document appears to be an example boiler inspection form that details the annual calibration service and scheduled preventive maintenance inspections required for boilers. The key elements include securing and draining the boiler, opening it for cleaning and inspection, checking for corrosion or damage, disassembling and cleaning the low water cutoff controls, performing a hydrostatic test, testing the safety/relief valve, cleaning fuel components, checking ignition and burner operation, and lubricating motor and shaft bearings. The scheduled preventive maintenance inspections focus on reviewing the operating log, testing the low water cutoff and pressure relief valve, checking for leaks, testing the flame safeguard control, and performing other operational checks. This form appears to be an attachment to the related federal contract opportunity for Boiler Inspection and Labeling Service at Fort Campbell, KY/TN, which is a non-personal services contract solicitation issued by the Department of the Army Materiel Command Mission and Installation Contracting Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 3 - Boiler Inspection form - NB-6.pdf | ||
| W9124825Q2000.pdf | ||
| Questions and Answers 1 to 10 for Boiler Inspections Post-Wide.pdf | ||
| Attachment 1 - Service Contract Act Wage Determination.pdf | ||
| Attachment 4 - Boiler Inspection form - NB-7.pdf | ||
| Attachment 5 - Master Boiler List.xlsx | XLSX spreadsheet | |
| W9124825Q2000 P0001.pdf | ||
| Attachment 6 - Pricing Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3
EXAMPLE BOILER INSPECTION FORM
1. ANNUAL CALIBRATION SERVICE: Inspection(s) per year will be performed during machine non-operation including the following:
0. Secure and drain boiler.
0. Open fireside and water side for cleaning and inspection.
0. Check heating surfaces and water side for: corrosion, pitting, scale, blisters, bulges, and soot.
0. Clean or replace water column sight glass.
0. Clean fire inspection glass.
0. Disassemble, clean, and inspect low water cutoff control(s).
0. Reassemble boiler and low water cutoff control(s) with new gaskets.
0. Check blow-down valve packing and lubricate.
0. Refill boiler.
0. Perform hydrostatic test, if required.
0. Test safety/relief valve(s) after startup (full pressure test).
0. Clean or replace fuel filters.
0. Clean fuel nozzles.
0. Clean burner fan wheel and air dampers.
0. Clean flame safeguard scanner.
0. Clean and adjust ignition electrodes.
0. Check all burner linkage for excessive wear.
0. Tighten all linkage set screws.
0. Lubricate motor and shaft bearings.
0. Check gas valves against leakage (where test cocks are provided).
0. Replace vacuum tubes (if used) in flame safeguard control.
0. Clean contacts in program timer.
0. Check operation of flame safeguard control.
0. Check operation of modulating motor.
1. Perform pilot turn down test.
1. Check operation of low water cutoff and feed control(s).
1. Check settings and test all operating and limit controls.
1. SCHEDULED PREVENTIVE MAINTENANCE: Inspection(s) per year will be performed during machine operation including the following:
1. Review owner's log. Log all operating conditions.
1. Inspect boiler and burner. Adjust as required.
1. Test low water cutoff and pressure relief valve.
1. Blow down and test low water cutoff and feed control(s).
1. Check for water, steam, and fuel leaks.
1. Check sequence and operation of flame safeguard control.
1. Check setting and test operating and limit controls.
1. Check operation of modulating motor.
1. Lift safety/relief valves with at least 70 percent rated pressure.
1. Blow down gauge cocks and try cocks to confirm glass water level.
1. Check and test boiler blow-down valve.
1. Lubricate motor and shaft bearings as required.
1. Check customer's log with operator and discuss operation of boiler.