Solicitation Amendment W9123826BA0060003 SF 30.pdf
PDF 4 MB Posted
- Attached to
- Sacramento River Erosion Contract 3 Federal contract opportunity
- Solicitation number
- W9123826BA006
About this file
This is Amendment 0003 to Solicitation W9123826BA006, issued by the W075 Endist Sacramento KO Contracting Division on 20 January 2026. The amendment modifies optional contract line items related to boat dock disposal and removal services at various locations along a waterway (STA 1370+20, 1373+70, 1375+30, 1380+80, 1383+00, and 1429+20).
The primary changes add "and disposal" language to six optional contract line items (1001–1006) and their corresponding payment procedure specifications. Previously, payment was specified for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and appurtenances, with existing piles to remain in place. The revised language now explicitly includes "and disposal" in both the line item descriptions and payment terms. All six options maintain the same exercise timeline requirement: options must be exercised within 180 days after issuance of the Notice to Proceed, with no additional days added to the Period of Performance upon exercise. The amendment also introduces new Specification Section 02 41 00 addressing "Demolition and Removals" and revised Specification Section 01 22 00 "Price and Payment Procedures." These revised sections will be incorporated into conformed specifications upon award. Offerors must acknowledge receipt of this amendment prior to the solicitation deadline through one of three methods: completing items 8 and 15 and returning copies, acknowledging on each offer copy, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF_1419 - 3 of 4.pdf | ||
| OF_1419 - 2 of 4.pdf | ||
| OF_1419 - 1 of 4.pdf | ||
| OF_1419 - 4 of 4.pdf | ||
| 02 41 00 Demolition and Removal.pdf | ||
| 01 22 00 Price and Payment.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is to Block 14 (Description of Amendment/Modification):
accomplish the following:
1. Provide revised Specification Section 01 22 00, "Price and Payment Procedures" to include "and disposal" in the Payment sections for the optional CLINs.
2. Revised Optional CLIN descriptions to include "and disposal".
3. Provide new Specification Section 02 41 00, "Demolition and Removals".
These revised sections will be incorporated into the conformed specifications upon award.
No other changes are made or implied.
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
The following CLIN(s) / SLIN(s) / ELIN(s) were modified:
Option Line Item 1001
INFORMATION FROM TO CHANGED
BY
Description Disposal/ Removal of
Boat Dock STA 1370+20
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be
Disposal/ Removal of Boat Dock STA 1370+20
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
W9123826BA0060003
added to the Period of Performance upon exercise of this option.
Option Line Item 1002
INFORMATION FROM TO CHANGED
BY
Description Disposal/Removal of Boat
Dock STA 1373+70
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Disposal/Removal of Boat Dock STA 1373+70
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Option Line Item 1003
INFORMATION FROM TO CHANGED
BY
Description Disposal/Removal of Boat
Dock STA 1375+30
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to
Disposal/Removal of Boat Dock STA 1375+30
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Option Line Item 1004
INFORMATION FROM TO CHANGED
BY
Description Disposal/Removal of Boat
Dock STA 1380+80
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Disposal/Removal of Boat Dock STA 1375+30
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Option Line Item 1005
INFORMATION FROM TO CHANGED
BY
Description Disposal/Removal of Boat
Dock STA 1383+00 Disposal/Removal of Boat Dock STA 1375+30
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Option Line Item 1006
INFORMATION FROM TO CHANGED
BY
Description Disposal/Removal of Boat
Dock STA 1429+20
Payment will be made for demolition of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances.
Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
Disposal/Removal of Boat Dock STA 1429+20
Payment will be made for demolition and disposal of boat docks including dock, buoy support, anchor, shore connection, handrails, and any appurtenances. Existing piles are to remain in place.
If option is exercised, option must be exercised within 180 days after the issuance of the Notice to Proceed. No additional days will be added to the Period of Performance upon exercise of this option.
| IDCode: J |
| Page: 1 |
| Pages: 6 |
| AmendNo: 0003 |
| EffDate: 20 JAN 2026 |
| ReqNo: |
| ProjNo: 456852 |
| IssCode: W91238 |
| AdmCode: |
| IssuedBy: W075 ENDIST SACRAMENTO |
KO CONTRACTING DIVISION, 1325 J STREET
SACRAMENTO, CA 95814-2922
UNITED STATES
JULIE MAXWELL, EMAIL: JULIE.MAXWELL@USACE.ARMY.MIL TELEPHONE: (916) 557-7989
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W9123826BA006 |
| SolDate: 16 DEC 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: JENNIFER WHEELIS |
| ContDate: |
| CODate: 20 JAN 2026 |
File details come from the government source that posted it. Updated .