This is Section 02 41 00 of a federal construction specification for the Sacramento River Contract 3, detailing demolition and removal requirements for existing facilities at a levee project site.
The specification establishes comprehensive procedures for demolishing and removing identified structures, materials, and utilities prior to new construction. Key work items include removal of existing boat docks and gangways (with piles remaining in place), disconnection and removal of utilities and related equipment, removal of paving and concrete slabs, and disposal of resulting debris. The contractor must submit a detailed Removal Plan for government approval before work commences, including procedures for careful material handling, utility disconnection sequencing, equipment specifications, and safety protocols. All demolition and removal work must comply with EM 385-1-1 Section 23, ASSP A10.6 safety standards, and 40 CFR 61-SUBPART M asbestos emission standards. The contractor is required to provide daily notification to Federal, State, regional, and local environmental authorities at least ten working days before commencing work and must prevent dust and debris migration to surrounding areas. Materials resulting from demolition become contractor property upon government approval of demolition procedures and authorization to begin work; however, burning materials on-site is prohibited. All removed debris must be transported off-site for legal disposal in compliance with applicable federal, state, and local regulations specified in the project's Waste Management Plan. The contractor bears all costs for removal and disposal of materials not reused in the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OF_1419 - 3 of 4.pdf | ||
| OF_1419 - 2 of 4.pdf | ||
| OF_1419 - 1 of 4.pdf | ||
| OF_1419 - 4 of 4.pdf | ||
| Solicitation Amendment W9123826BA0060003 SF 30.pdf | ||
| 01 22 00 Price and Payment.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sacramento River Contract 3 Specification # 2485
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION AND REMOVALS
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 PROJECT DESCRIPTION
1.3.1 Definitions
1.3.1.1 Demolition
1.3.1.2 Removal
1.3.1.3 Demolition Plan
1.3.1.4 Removal Plan
1.3.2 Removal Plan
1.3.3 General Requirements
1.4 ITEMS TO REMAIN IN PLACE
1.4.1 Existing Construction Limits and Protection
1.4.2 Utility Service
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.6.1 Dust and Debris Control
1.7 PROTECTION
1.7.1 Traffic Control Signs
1.7.2 Protection of Personnel
1.8 RELOCATIONS
1.9 EXISTING CONDITIONS
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Boat Dock Removal and Disposal
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Paving and Slabs
3.1.4 Concrete
3.2 DISPOSITION OF MATERIAL AND CLEANUP
3.2.1 Title to Materials
3.3 CLEANUP
3.4 DISPOSAL OF REMOVED MATERIALS
3.4.1 Regulation of Removed Materials
3.4.2 Burning
3.4.3 Removal from the site of construction
-- End of Section Table of Contents --
16 January 2025 SECTION 02 41 00 Page 12 Amended 1/16/2025
SECTION 02 41 00
DEMOLITION AND REMOVALS
PART 1 GENERAL
1.1 SCOPE
The work includes demolition or salvage of identified items and materials, removal of resulting rubbish and debris, and removal of identified items and materials. Remove items identified for demolition from the site daily, unless otherwise directed by the Contracting Officer, to avoid accumulation at the site of construction. Materials that cannot be removed daily must be stored in areas provided by the Contractor. In the interest of occupational safety and health, perform work in accordance with EM 385-1-1 , Section 23, DEMOLITION, and other applicable requirements.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61-SUBPART M National Emission Standard for Asbestos
1.3 PROJECT DESCRIPTION
1.3.1 Definitions
1.3.1.1 Demolition
Demolition is the process of wrecking or taking apart materials on the levee surface prior to removal.
1.3.1.2 Removal
Removal is the process of removing materials that impact the improvements to the project site and are no longer needed for site functionality.
16 January 2025 SECTION 02 41 00 Page 13 Amended 1/16/2025
1.3.1.3 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.3.1.4 Removal Plan
Removal Plan is the planned steps and processes for managing the removal of all or portions of materials to be improved upon during the construction of the project sites.
1.3.2 Removal Plan
Submit a Removal Plan for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Coordinate with Waste Management Plan in accordance with Section 01 57 19 . Provide procedures for safe conduct of the work in accordance with EM 385-1-1 .
1.3.3 General Requirements
Do not begin demolition or removals until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site;
do not allow accumulations. The work includes removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas identified by the contractor. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.4 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
1.4.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.4.2 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When
16 January 2025 SECTION 02 41 00 Page 14 Amended 1/16/2025 used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Removal Plan ;
Existing Conditions
SD-07 Certificates
Notification
1.6 QUALITY ASSURANCE
Submit timely notification of demolition and removal projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61-SUBPART M . Notify the State's environmental protection agency, local air pollution control district/agency, and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61-SUBPART M . Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris from removals to avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
1.7 PROTECTION
1.7.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Contracting Officer prior to beginning such work.
1.7.2 Protection of Personnel
Before, during and after the demolition and removal work continuously evaluate the condition of the structure being demolished and removed and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.8 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items
16 January 2025 SECTION 02 41 00 Page 15 Amended 1/16/2025 as approved by the Contracting Officer.
1.9 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse must be disassembled.
Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified. Use designated materials for reuse onsite whenever possible.
3.1.1 Boat Dock Removal and Disposal
Remove and dispose of existing docks and gangways shown on the plans.
Existing piles are to remain in place.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities, as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.
16 January 2025 SECTION 02 41 00 Page 16 Amended 1/16/2025
3.1.3 Paving and Slabs
Remove ground concrete and asphaltic concrete paving as indicated and directed by the Contracting Officer. Remove pavement and slabs not to be used in this project from the Installation at Contractor's expense.
3.1.4 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch . Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.
3.2 DISPOSITION OF MATERIAL AND CLEANUP
3.2.1 Title to Materials
All materials and equipment removed and not reused or salvaged, become the property of the Contractor and will be removed from Government property.
Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.4 DISPOSAL OF REMOVED MATERIALS
3.4.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan. Storage of removed materials on the project site is prohibited.
3.4.2 Burning
Burning of materials removed from demolished and deconstructed structures will not be permitted on the site of construction.
3.4.3 Removal from the site of construction
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from the site of construction for legal disposal. Dispose of waste soil as directed.
-- End of Section --
16 January 2025 SECTION 02 41 00 Page 17 Amended 1/16/2025
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 22 00 - PRICE AND PAYMENT PROCEDURES |
| 01 22 00 - PRICE AND PAYMENT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 SINGLE JOB PAYMENT ITEMS |
| 1.2.1 Mobilization and Demobilization 0001 |
| 1.2.1.1 Payment |
| 1.2.1.2 Unit of Measure |
| 1.2.2 Temporary Storm Water Pollution Control 0002 |
| 1.2.2.1 Payment |
| 1.2.2.2 Unit of Measure |
| 1.2.3 Clearing and Grubbing 0003 |
| 1.2.3.1 Payment |
| 1.2.3.2 Unit of Measure |
| 1.2.4 Option Item: Boat Dock Removal Sta 1370+20 1 of 6 1001 |
| 1.2.4.1 Payment |
| 1.2.4.2 Unit of Measure |
| 1.2.5 Option Item: Boat Dock Removal Sta 1373+70 2 of 6 1002 |
| 1.2.5.1 Payment |
| 1.2.5.2 Unit of Measure |
| 1.2.6 Option Item: Boat Dock Removal Sta 1375+30 3 of 6 1003 |
| 1.2.6.1 Payment |
| 1.2.6.2 Unit of Measure |
| 1.2.7 Option Item: Boat Dock Removal Sta 1380+80 4 of 6 1004 |
| 1.2.7.1 Payment |
| 1.2.7.2 Unit of Measure |
| 1.2.8 Option Item: Boat Dock Removal Sta 1383+00 5 of 6 1005 |
| 1.2.8.1 Payment |
| 1.2.8.2 Unit of Measure |
| 1.2.9 Option Item: Boat Dock Removal Sta 1429+20 6 of 6 1006 |
| 1.2.9.1 Payment |
| 1.2.9.2 Unit of Measure |
| 1.3 UNIT PRICE PAYMENT ITEMS |
| 1.3.1 Graded Stone Type C 0004 |
| 1.3.1.1 Payment |
| 1.3.1.2 Measurement |
| 1.3.1.3 Unit Measure |
| 1.3.2 Soil-Filled Graded Stone Type C 0005 |
| 1.3.2.1 Payment |
| 1.3.2.2 Measurement |
| 1.3.2.3 Unit of Measure |
| 1.3.3 Aggregate Base 0006 |
| 1.3.3.1 Payment |
| 1.3.3.2 Measurement |
| 1.3.3.3 Unit of Measure |
| 1.3.4 Topsoil 0007 |
| 1.3.4.1 Payment |
| 1.3.4.2 Measurement |
| 1.3.4.3 Unit of Measure |
| 1.3.5 Grass Seeding and Erosion Control 0008 |
| 1.3.5.1 Payment |
| 1.3.5.2 Measurement |
| 1.3.5.3 Unit of Measure |
| 1.3.6 In-Stream Wood Material 0009 |
| 1.3.6.1 Payment |
| 1.3.6.2 Measurement |
| 1.3.6.3 Unit of Measure |
| 1.3.7 Beaver Barrier Fence 0010 |
| 1.3.7.1 Payment |
| 1.3.7.2 Measurement |
| 1.3.7.3 Unit of Measure |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 INVOICE SUBMISSION PROCEDURES |
| 3.1.1 Required Procedure |
| 3.1.2 Required Documents |
| DIVISION 02 - EXISTING CONDITIONS |
| 02 41 00 - DEMOLITION AND REMOVALS |
| 02 41 00 - DEMOLITION AND REMOVALS |
| PART 1 GENERAL |
| 1.1 SCOPE |
| 1.2 REFERENCES |
| 1.3 PROJECT DESCRIPTION |
| 1.3.1 Definitions |
| 1.3.1.1 Demolition |
| 1.3.1.2 Removal |
| 1.3.1.3 Demolition Plan |
| 1.3.1.4 Removal Plan |
| 1.3.2 Removal Plan |
| 1.3.3 General Requirements |
| 1.4 ITEMS TO REMAIN IN PLACE |
| 1.4.1 Existing Construction Limits and Protection |
| 1.4.2 Utility Service |
| 1.5 SUBMITTALS |
| 1.6 QUALITY ASSURANCE |
| 1.6.1 Dust and Debris Control |
| 1.7 PROTECTION |
| 1.7.1 Traffic Control Signs |
| 1.7.2 Protection of Personnel |
| 1.8 RELOCATIONS |
| 1.9 EXISTING CONDITIONS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 EXISTING FACILITIES TO BE REMOVED |
| 3.1.1 Boat Dock Removal and Disposal |
| 3.1.2 Utilities and Related Equipment |
| 3.1.2.1 General Requirements |
| 3.1.2.2 Disconnecting Existing Utilities |
| 3.1.3 Paving and Slabs |
| 3.1.4 Concrete |
| 3.2 DISPOSITION OF MATERIAL AND CLEANUP |
| 3.2.1 Title to Materials |
| 3.3 CLEANUP |
| 3.4 DISPOSAL OF REMOVED MATERIALS |
| 3.4.1 Regulation of Removed Materials |
| 3.4.2 Burning |
| 3.4.3 Removal from the site of construction |