W9123822B0004 Amendment 0003.pdf

PDF 163 KB Posted

Attached to
Sacramento River Erosion Contract 1 Federal contract opportunity
Solicitation number
W9123822B0004
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

This document provides an amendment to solicitation W9123822B0004 for Sacramento River Erosion Contract 1. The amendment updates specifications, provides responses to two additional bidder inquiries, and modifies the pricing schedule and Davis Bacon wage determinations. The purpose of the solicitation is to repair riverbank erosion on the Sacramento River. Bids are due by January 25, 2022. The amendment clarifies that a minimum 6-inch layer of soil cover is required over soil-filled quarry stone to facilitate grass establishment. It also confirms that construction equipment can be delivered and operated within construction limits via barge to place and grade materials, if the equipment is also removed from the site by barge. The solicitation is a 100% small business set-aside issued by the Department of the Army Corps of Engineers Sacramento District.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Provide the updated Specif ications attachment.

2. Provide 2 additional reponses to inquiries.

3. Provide updated Price Schedule.

4. Update Davis Bacon Wage Determinations.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jan-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123822B0004

X 9B. DATED (SEE ITEM 11)

17-Dec-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jan-2022

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123822B0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

ADDTIONAL INQUIRIES

Additional Inquiries

As discussed, the Government responses to inquiry No.s 9560436 and 9560436 warrant additional clarification. Historically the Corps of Engineers bank repair projects include a six inch layer of soil cover placed over the soil filled quarry stone (SFQS) to facilitate erosion control seeding/grass establishment. However, there is no soil cover shown over the SFQS on this project. The only soil shown for this project is located at the Planting Bench. The response to # 9560436 states areas to be seeded “includes all areas receiving top soil over soil filled quarry stone.” This response, combined with the response to inquiry no. 9560443, leads us to believe that the Government desires grass establishment over the SFQS. Grass will not grow directly on SFQS, which consists of 70% quarry stone and 30% soil. There has to be soil cover over the SFQS for the grass to grow. We submitted inquiry no. 9560443 anticipating that grass will not grow on the SFQS, and that another method of stabilization would be needed given that grass establishment is not achievable. I have also attached a photo from a previous project that shows soil cover partially over SFQS to illustrate what the surface of the SFQS will look like.

Government Response:

Concur, a minimum 6 inch layer of soil cover is needed over the soil filled quarry stone to establish grass. The plans and the price schedule have been updated to reflect both the planting bench mix (Top Soil Material), grass seeding, and erosion control measures.

Contractor Question:

Specification 01 50 00, Temporary Construction Facilities, Section 3.5 includes the statement that “All work must be done via barge only.” We interpret this that all quarry stone, trees for IWM, and soil would be delivered to the site via barge. We seek confirmation that it would be acceptable to deliver construction equipment, such as a doze and hydraulic excavator, to the site via barge which would then be set atop the QS and SFQS after these materials were delivered by barge. This equipment would finish grade the materials, and would only work within the footprint of the repair. All such equipment would be demobilized from the site via barge upon completion. This method significantly reduces the cost of the project. Will it be acceptable to use equipment working from the surface of the QS and SFQS to place and finish grade materials delivered by barge?

Government Response:

It will be acceptable to use construction equipment only inside the construction limits, on top of placed materials, and only if the equipment is delivered and removed via barge.

The following have been deleted:

BIDDER INQUIRIES/RESPONSES

SECTION 00 01 10 - TABLE OF CONTENTS

W9123822B0004

The following have been modified:

ATTACHMENT TABLE OF CONTENTS

DOCUMENT

TYPE

DESCRIPTION PAGES DATE

Attachment 1 Specifications 406 07-OCT-2021 Attachment 2 Plans 21 08-OCT-2021 Attachment 3 Davis Bacon Wage

Determination

49 20-JAN-2022

Attachment 4 Pricing Schedule 1 24-JAN-2022 Attachment 5 Pre-Award Survey

(End of Summary of Changes)