P a g e | 1
MOTCO Pier II Restoration PWS
PERFORMANCE WORK STATEMENT (PWS)
MOTCO Pier II Restoration
& Enhancement
Contra Costa County, California
July 24, 2019 REV July 29, 2019
US ARMY CORPS
OF ENGINEERS
SACRAMENTO DISTRICT
P a g e | 2
1.0 GENERAL:
1.1 Introduction: This scope of work covers restoration and enhancement for intertidal, upland, and buffer habitats on the south side of Suisun Bay in Clyde CA. The major work elements described herein includes: Providing Storm Water Pollution Prevention Plan (SWPPP), Accident Prevention Plan (APP), General Safety, noxious/invasive weed control, plans, salvaging and temporary storage of emergent vegetation, collecting propagules, providing container plants, installing container and salvaged plants, installing and maintaining BMPs, grass seeding, installing and maintaining water fowl deterrents, wave action disbursement, and installation year with 4 subsequent establishment years to effectively restore the site. Maintenance and establishment tasks includes: Weeding, mowing, herbicide application, monitoring and reporting, replacing dead plants, BMPs/adaptive management, monthly update meetings, and restoration and cleanup. The Contractor shall design, plan, coordinate, organize, manage, and perform the activities described herein.
1.2 Description of Services/Introduction: The described herein is restoration and enhancement for the impacts of MOTCO Pier II Upgrade and Retrofit project. The restoration and enhancement activities described herein are being developed at one site divided by Pier II proposed west ramp.
1.1 Background: The Military Ocean Terminal Concord (MOTCO) is located in the East San Francisco Bay region, approximately 10 nautical miles inland past the Carquinez Strait that connects Suisun Bay to San Pablo Bay. The Pier II Upgrade and Retrofit Construction contract is to restore functionality to MOTCO for sending and receiving ocean bound commodities for continued military operations. The work scoped herein will mitigate for those impacts of the upgrade and retrofit in agreement with local resource agencies and the Coastal Commission Act.
The Military Ocean Terminal Concord (MOTCO) Pier II Upgrade Mitigation and Enhancement Planting and Establishment service contract is required because of impacts to the native emergent plants as a result of the Pier 2 MOTCO Repair/Upgrade Pier 2 Construction Contract. The construction contract resulted in the repair the existing, non-functional Pier 2 at MOTCO through implementation of the Pier 2 MOTCO Repair/Upgrade Pier 2 Construction Contract. Prior work consisted of the demolition of parts of Pier 2 except the East Trestle, the reconstruction of structural elements and utilities, the upgrade of shore-side roads and electrical infrastructure. The project will replace the existing Pier 2 with a new platform and will replace three existing trestles with a single new trestle, reducing the existing footprint of Pier II by 30,942 square feet addition to demolition, modernization and repair of the existing Pier 2 structure, habitat restoration and shoreline protection will be implemented in the marsh and uplands between White Road and Pier 2. Construction and demolition elements are shown on Exhibit B, Habitat Restoration Plan Figure 4A-4F.
1.2 Objectives: The objectives of this Performance Work Statement (PWS) is to develop, enhance, establish and re-establish inter-tidal wetlands and upland and buffer vegetation at the Pier II site and to eradicate highly invasive weed species. Habitat development is based on installing and establishing 1.32 acres of tidal brackish water and enhancing the habitat quality at the tidal brackish habitat and the upland areas within the project site by removing most of the invasive plant species and seeding the upland areas. Plant self-sufficiency is achieved when the plants roots are well developed so that water fowl predation and wave action will not negatively impact vegetative cover, roots have reached ground water and are able to live and thrive without artificial watering or maintenance.
1.3 Scope: Services require the Contractor to design, plan, coordinate, organize, manage, and perform the activities described herein. Tasks include plant material salvage and cultivation, seed collection and propagation, seedling and salvage plant installation, soil preparation, and grass seeding. Maintenance and establishment tasks includes:
Regular coordination with MOTCO DPW Environmental person(s), compliance with all installation guidance and restrictions, MEC clearance, watering, weeding, identified noxious section control, mowing, spraying, storm water sampling, testing, monitoring, and reporting, replacing dead plants and restoration and cleanup just prior to completion of the contract. The Contractor shall accomplish healthy plant growth and maturity.
1.4 Period of Performance: The period of performance shall be for one (1) Base Year of 12 months and two (2) 12-month option years. The Period of Performance reads as follows:
P a g e | 3
• Base Year
• Option Year I
• Option Year II
1.5 Place of Performance: The work to be performed under this contract will be performed at the project site known as the Pier II Restoration East and West sites. This site is located on MOTCO Installation in Clyde California, Contra Costa County.
1.6 Special Qualifications: The Contractor is responsible for ensuring the herbicide spray employees possess and maintain current pesticide spraying certification during the execution of this contract. The Contractor is responsible for ensuring all employees meet criteria for entry on the installation.
1.7 Contractor Quality Control (CQC):
The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.
2.0 CONTRACTOR QUALITY CONTROL (CQC):
The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract.
2.1 Work Phases: Contractor Quality Control is the means by which the Contractor ensures that the work activities, to include that of subcontractors and suppliers, complies with the requirements of the Contract. Conduct at least three phases of control for each definable feature of work as follows:
2.1.1 Preparatory Phase: Perform this phase prior to beginning work on each definable feature of work, after all required plans/documents/materials are accepted, proper base coordination is accomplished, and after copies are at the work site. This phase includes:
• Review of the Contract requirements and drawings.
• Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the Contract.
• MEC Clearance planning and coordination with MOTCO.
• Review of the appropriate activity hazard analysis to assure safety requirements are met.
• POC contact cut sheet developed of Contractor key personal and MOTCO key personal involved with the project.
2.1.2 Workmanship Phase: This phase is accomplished during the performance of each work activity.
Perform daily checks to assure completion of the particular feature of work. Accomplish the following:
• Verify adequacy of controls to ensure full Contract compliance. Verify required control inspection and testing.
• Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
• Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
2.1.3 Acceptance Phase: Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work.
• Pre-final Inspection: The Government will perform the Pre-final inspection to verify that the facility is complete and ready to be turned over to the Government. A Government Pre-final
P a g e | 4
Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items.
• Final Inspection: The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified as being unacceptable, along with all remaining work performed under the Contract, will be complete and acceptable by the date scheduled for the final acceptance inspection.
2.2 Documentation and Monthly Coordination: Maintain current records providing factual evidence that required quality control activities have been performed. Monthly update conference calls to update USACE and MOTCO of current progress, issues, and concerns.
2.3 Notification: Of Noncompliance: The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice.
Such notice, is deemed sufficient for the purpose of notification when delivered to the Contractor at the work site. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
3.0 DEFINITIONS AND ACRONYMS
3.1. Definitions: Available upon request.
3.2. Acronyms: Available upon request.
4.0. GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
4.1. Services: The Government will not provide the Contractor any services.
4.2 Facilities: The Government will not provide the Contractor any facilities. . However, the government will provide an area designated for the Contractor’s use. The Contractor may establish facilities to include, but not limited to covered storage, etc. on or in the designated area. Provide all utilities to this area. The Government will not be responsible for any damage to or loss of equipment and supplies stored on the Government’s premises.
Maintain fire extinguishers and other safety equipment responsibly.
4.3 Utilities: The Contractor must provide their own utilities and will not be authorized to tap into MOTCO infrastructure. The Government will not provide utilities. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities. Cleaning vehicles and equipment will not be permitted onsite. Electricity and phone service will NOT be furnished by the Government for the Contractor’s work area.
4.4 Equipment: The Government will not provide any equipment.
4.5 Materials: The Government will not provide any materials.
4.6 Data: The Government may provide computer data in the form of AutoCAD files, Microsoft Word Files, Microsoft Excel Files for creation of certain contractor submittals that follow specified formats, templates or development of as-built and as-installed drawings.
5.0. CONTRACTOR FURNISHED ITEMS AND SERVICES:
P a g e | 5
The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 4.0 of this PWS. Grading to remove perennial pepperweed and restore the wetland marsh plain will be conducted concurrent with the structure removal noted above. Existing wetlands and uplands in the areas shown on Figures 4A-H will be excavated with the use of low-ground pressure equipment, with up to six feet of soil and vegetative matter excavated and removed from the site.
6.0. PERFORMANCE OBJECTIVES:
6.1. Basic Services. The Contractor shall provide services for the development of native vegetation habitats. These services include salvaging, harvesting, propagating and installing plants; water fowl deterrent; wave erosion control barriers; designing and installing an irrigation system; eradicating noxious weeds and invasive species; creating and erecting plant and site protection features; and maintaining the plants and features until the plants have reached self-sufficiency.
6.2 Services and Scope: The work described herein applies to all restoration and enhancement sites within this PWS, except as noted. Provide the following services and items, including but not limited to:
6.2.1 Post-Award Meeting: The Contractor agrees to attend any post-award meeting convened by the Contracting Officer in accordance with Federal Acquisition Regulation Subpart 42.5 – Post Award Orientation. The meeting may be attended via teleconference. The Contractor shall coordinate a Post- Award meeting with the USACE-SPK (Sacramento District) Contracting Office (CT) Point of Contact (POC), Donald Sumner, Donald.Sumner@usace.army.mil, via email 10 days after award of this PWS, and ensure that all contractor parties, including those having authority to sign on behalf of the Contractor, as well as, all other required parties that will be coordinating the work efforts on a daily basis, are present at the meeting. This meeting may be conducted by telephone conference or in person. If the Contractor attends the meeting in person, travel costs shall be at the Contractor's own expense. The Contractor shall take meeting minutes during this meeting and submit to the Contracting POC, no later than seven (5) business days after the meeting. The meeting shall occur as soon after task order award as possible.
6.2.2. Preparing and Submitting Plans: Prepare and submit all plans pertinent to the work required herein.
Refer to Attachment G-Submittal Register. At a minimum, provide the following:
6.2.2.1 Performance Work Plan: addressing the design approach. Describe all tasks as listed in the Performance Objectives and how each will be performed. Identify who will undertake the tasks, where the work will be done, what will be done, and task duration.
6.2.2.2 Project Schedule: Keep the project schedule up to date and submit every month with the Contractor’s invoice.
6.2.2.3 Accident Prevention Plan (APP): to be prepared in accordance with Appendix A of EM
385-1-1, US ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS
MANUAL. See paragraph 15. SAFETY REQUIREMENTS. Prepare the written site-specific Accident Prevention Plan (APP) in accordance with the format and requirements of USACE EM 385-1-1 (2014). Cover all paragraph and subparagraph elements in Appendix A of USACE EM 385-1-1 "Minimum Basic Outline for Preparation of Accident Prevention Plan". Append the Activity Hazard Analyses (AHAs) to the APP. Use the APP for the project because it will present site specific hazards and provide site specific controls. Where a paragraph or subparagraph element is not applicable to the work to be performed indicate "Not Applicable" next to the heading. Address job-specific tasks and any unusual or unique aspects of the project or activity for which it is written. Interface the APP with the Contractor's overall safety and health program (SHP). Include and make site-specific in the applicable APP element any portions of the Contractor's overall safety and health program referenced in the APP. The Government considers the Prime Contractor to be the "controlling authority" for all worksite safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety mailto:Donald.Sumner@usace.army.mil
P a g e | 6 provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. Sign the APP in accordance with the requirements of EM 385-1-1, Appendix A.
• Activity Hazard Analysis (AHA) Appendix to the APP. Develop an Activity Hazard
Analysis (AHA) for every operation involving site activities presenting hazards. Format the AHA(s) in accordance with Figure 1-2 of EM 385-1-1. Submit subsequent AHAs as amendments to the APP. Identify the analysis and evaluate hazards and outline the proposed methods and techniques for the safe completion of each phase of work. At a minimum, in the AHA define the activity being performed, sequence of work, specific safety and health hazards anticipated, control measures (to include personal protective equipment) to eliminate or reduce each hazard to acceptable levels, equipment to be used, inspection requirements, training requirements for all involved, and the competent person in charge of that phase of work.
• Submittals: Submit to the COR and the Government Safety Officer, operations using chemicals containing 2,4-D, Sulfometuron, or any other chemicals which have TLVs, PEL standards, or other regulated standards based on known health hazards, a Health Hazard Control Program. Address the requirements in EM 385-1-1 Section 06.A and be completed by a qualified Industrial Hygienist, or equivalent competent person in Industrial Hygiene operations in the Health Hazard Control Program. A sampling technician working under the CIH may perform any sampling required to do the work
• References. Comply with the most current version of the following referenced documents, at a minimum:
EM 385-1-1, USACE Safety & Health Requirements Manual, 30 November 14 Edition.
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManua ls/EM_385-1-1.pdfTitle 29 Code of Federal Regulations (CFR) 1910, Occupational Safety and Health Standards.
NIOSH/OSHA/USCG/EPA, Occupational Safety and Health Guidance Manual for Hazardous Waste Activities (October 1985).
American Conference of Governmental Industrial Hygienists (ACGIH®), TLVs® and BELs®, Threshold Limit Values for Chemical Substances and Physical Agents & Biological Exposure Indices (2016).
Title 8 California Code of Regulations (CCR) Chapter 4 Subchapter 4, Construction Safety Orders.
8 CCR Chapter 4 Subchapter 7, General Industry Safety Orders.
8 CCR Sections 3203 & 1509, Injury and Illness Prevention Program.
OSHA ancillary safety and health regulations governing certain aspects for this contract include:
Respiratory Protection (29 CFR 1910.134/8 CCR Section 5144) Occupational Noise Exposure (29 CFR 1910.95/8 CCR Sections 5095-5100) Hazard Communication (29 CFR 1910.1200/29 CFR 1926.59/8 CCR Section 5194) The Control of Hazardous Energy (Lockout/Tagout) (29 CFR 1910.147) Proposition 65 (22 CCR Section 12000) Chemicals Know to the State to Cause Cancer or Reproductive Toxicity
6.2.2.4 Injury and Illness Prevention Program (IIPP): Submit a corporate Injury and Illness Prevention Program (IIPP) for projects within the State of California. Address all elements of Title 8 California Code of Regulations (CCR) Section 3203 and Section 1509. Develop the IIPP under the direct supervision of a qualified SHM.
6.2.2.5 Environmental Protection Plan (EPP): to include:
P a g e | 7
• A Temporary Work Facility Plan: showing locations of temporary excavation for roads, ingress/egress, material storage, structures, sanitary facilities, fence locations, signs, etc.
Show proposed activity in each portion of the site and measures for marking the limits of use areas and areas to be preserved. Indicate measures to minimize the amount of mud transported onto paved public roads.
• A Spill Control Plan: including procedures, instructions, and reports to be used in the event of an unforeseen spill.
6.2.2.6 Quality Control Plan (QCP): List the projects key design team members along with their functional discipline and state the risks inherent to the project. Include an inspection plan covering all services required by this contact; on-site records of all inspections; and methods for identifying and preventing deficiencies in the quality of service performed. Develop and maintain a complete QCP to assure the requirements of this Contract are provided as specified. The Contracting Officer will review the QCP and list any needed clarifications, and return to Contractor for response, if necessary. Include the following in the QCP during performance of Contract, at a minimum:
• An inspection plan covering all services required by this contact. Specify in the inspection plan the areas to be inspected on either a scheduled or unscheduled basis, how often inspections will be accomplished and documented, and specify the title of the individual(s) who will perform the inspections.
• Provide on-site records of all inspections conducted noting necessary corrective action taken. The Government reserves the right to request copies of any and/or each inspection.
• Incorporation of either active or established internal policy and procedures for updating equipment and procedures that may affect performance of Contract.
• On-site records identifying the character, physical capabilities, certifications and ongoing training of each employee performing services under this Contract.
• On-site records of any complaints or problems, with procedures taken to allow for corrections and/or elimination before effects caused interruption of performance of Contract.
6.2.2.7 Noxious Weed Control Plan: A Weed Eradication plan shall be provided by a Weed Control Specialist who has at least 5 years’ experience working on similar projects. Plan will specify herbicides to be used. Indicate types of equipment to be used for each mowing and for each herbicide application. Include application rates for each herbicide used, all additives including dyes, personal and their certification for application. Complete and submit required permits and plans to county noxious weed boards. Submit the weed control plan with the performance work plan for approval by the Contracting Officer. The weed control plan does not substitute or replace any environmental submittals or safety submittals related to herbicide use that are required. The weed control plan must be updated regularly, refer to section 6.2.24., Preparing Activity Records.
Pepperweed (Lepidium latifolium): The Contractor shall eradicate Lepidium latifolium from a minimum of 95% of the project site using mechanical, mowing, and herbicide controls and follow guidance in the attached HRP. Contractor shall control the uses of the above methods for all noxious and invasive weeds indicated in the HRP to gain 95% control of invasives throughout the site.
• Spraying activities shall occur monthly at a minimum in accordance with all local, state and federal guidelines.
P a g e | 8
• Sprayed vegetation shall be marked by Contractor. Recommend using a die in the herbicide mix to indicate areas of application. Contractor to include invasive control and tracking plan prior to ground disturbance and any herbicide application.
Develop and implement noxious weed control plan for all noted weeds in the HRP and in restoration & enhancement areas to achieve 95% controls of noted species.
6.2.2.8 Storm Water Pollution Prevention Plan (SWPPP): Provide a SWPPP for compliance with the State Water Resources Control Board (SWRCB) Order Number 2010-0014-DWQ Construction General Stormwater Discharge Permit. See Attachment D, Temporary Storm Water Pollution Control for more complete SWPPP and permit coverage requirements.
6.2.2.8.1 Construct Storm Water Retention Basin: Construct two (2) retention basins using local fill material only to support White Road existing drainage outfalls. Basin shall be placed downstream of culvert outflow. Basin crest shall not be within 3 inches of outfalls lowest elevation. Construct basin berm from local native soil, compacted to 95%, with designated basin outfall area, notched, with large rock riprap with geotextile fabric under the riprap. Each basin shall be capable of holding a minimum of 900 cubic feet of water. Side slopes shall be no steeper than 3 to 1 and shall be vegetated. Utilize existing drainage patterns. Include energy dissipaters to prevent scouring from culvert.
6.2.3. Monitoring for Cultural Resources: Notify the Contracting Officer two weeks prior to flagging site so he/she can notify the Governments Archeologist of upcoming activities. There are no known cultural resources within the site boundary but that does not exclude their potential presence. Direct and setup the fencing locations around discovered known cultural resources. If two or more artifacts are found within close proximity to each other, contact the Corps’ Archeologist to determine whether or not a cultural site exists at that location, prepare a daily monitoring log that includes a summary of each day’s activities that includes a description and photographs of new finds, if any, and coordination efforts. At end of field work submit to the Corps a field summary report of monitoring activities and daily logs. Archeological, historic, and architectural work will be carried out by, or under the direction supervision of a person or persons meeting qualifications set forth in the Secretary of the Interior’s Professional Qualification Standards (36 CFR Part 61). Submit 10 copies of the field summary report and monitoring logs. Refer to Attachment F, Submittal Register.
6.2.4. Setting-up Site: Coordinate all site activities with MOTCO Ordnance Officer (XO). The recently excavated portion of the site, active restoration area, will be cleared to depth, 2 feet maximum, by prior Pier II construction activities in all disturbed areas. Enhancement areas will not have been cleared to depth. The site will be cleared to depth, 2 feet maximum, by prior Pier II construction activities in all disturbed areas.
Once XO clears site, or if needed with their presence, the Contractor shall identify, mark and establish site boundary lines and infrastructure locations, test soils locations, provide work signs, construct safety fencing, staging areas, wetlands, and cultural sites. Verify site conditions prior to ground disturbance.
Contractor is responsible to provide their own XO support for restoration activities. Thoroughly clean all adjacent public pavements of impacts upon completion of work. Refer to Attachment F, Submittal Register.
6.2.4.1 Verify Site Conditions: Before performing any work, verify site conditions. Provide photographs of all existing access roads for Contracting Officer review prior to commencing work.
These will serve to verify pre-work conditions. Identify existing features and underground obstructions and utilities, including notifying Underground Service Alert (U.S.A.) at 1-800-642- 2444 for all locations in this Contract. Read materials found on OSHA website http://www.dir.cago.
6.2.4.2 Boundary and Infrastructure Layout: Identify and stake property boundary lines. Mark on the ground, showing the extents of where all infrastructures will be located. Include access and http://www.dir.cago/
P a g e | 9 maintenance roads, electrical hookups and routing, signage, staging area location, sensitive resources/habitat (e.g. elderberry habitat) temporary construction limits and locations to all other tasks included in project. Prior to starting work at all sites, obtain approval from the Government.
Keep all vehicle traffic to staging area and maintenance roads. Do not drive off of designated project site.
Under this PWS, the Contractor will perform munitions response actions for military munitions (MM) and munitions debris (MD). The project site contains is areas both cleared and not cleared to depth and any ground penetrating activities require appropriate XO support. Activities may involve munitions and explosives of concern (MEC), which includes UXO, DMM, and MC if found in high enough concentrations to cause an explosive threat, non-explosive concentrations of MC and incidental contaminants related to MM.
It is the Contractor's responsibility to comply with all applicable federal, state and local laws and regulations and to fulfill the performance objectives of this PWS in a manner that is consistent with any applicable orders or permits, all existing and future cleanup agreements or guidance for the Installation, and relevant DoD and Army policy, for the duration of the contract.
MEC-Related Guidance
MEC-related guidance includes, but may not be limited to, the following:
• MEC includes UXO, as defined in 10 U.S.C. 101(e)(5); DMM, as defined in 10 U.S.C.
2710(e)(2); or Munitions Constituents (MC), as defined in 10 U.S.C. 2710(e)(3), present in high enough concentrations to pose an explosive hazard.
• MEC distinguishes specific categories of military munitions that may pose unique explosives safety risks. Because MEC being actively managed may be determined to be hazardous waste, 29 Code of Federal Regulations (CFR), Hazardous Waste Operations and Emergency Response, Section 1910.120, may apply.
• Per the guidelines set forth in DoDI 4140.62 and DDESB Technical Paper 18, UXO qualified personnel will be responsible for determining the explosive safety status of any material recovered that may pose an explosive hazard (i.e., material potentially presenting an explosive hazard (MPPEH)).
• Should MEC be encountered during this response, UXO-qualified personnel will evaluate the explosive hazard and remove it, including by open detonation in place. This response will be conducted per the CERCLA and the NCP, applicable state and federal regulation, and applicable DoD, U.S. Army policies and procedures.
6.2.4.3 Maintenance Roads: Are not be required as part of this PWS. Contractor to utilize existing infrastructure, namely White Road.
6.2.4.4 Soil Testing: The Restoration Native Plant Specialist shall collect and have a qualified soils laboratory analyze four composite samples from the excavated portions of the marsh plain and four composite samples from intact areas of the marsh plain. Standard pre-planting analysis of chemical suitability, available nutrients, texture and organic matter content shall be conducted, with comparisons between samples collected from the excavated and intact portions of the marsh.
The soils laboratory shall provide recommendations on amendments if the results indicate that soils in the excavated areas of the marsh exhibit soils deficiencies that would impair plant establishment. If soil amendment is determined to be warranted, it shall be implemented by the Landscape Contractor prior to planting.
6.2.4.5 Staging Area Setup: Include an onsite staging area that contains all appropriate temporary facilities needed to construct and maintain the project, include as necessary, securable storage bins, temporary fencing (encompassing the entire staging area, shade structures, drinking water
P a g e | 10 and sanitation stations. The Contractor is responsible for the security of all stored material and facilities.
6.2.4.6 Protect Existing Native Vegetation: Do not disturb existing native vegetation, unless required herein.
6.2.4.7 Provide Work Signs: Provide work signs at the western portion facing White Road by the monument and the eastern portion of the restoration and enhancement project site. Include project identification signs identifying the project name and that it is a Pier II Restoration & Enhancement Project. Include the cooperating agency names, Contractor name, Contractor contact information, State wage rates, EEO and project health information, and safety requirements. Present signs on 4 feet by 8 feet face, made of exterior plywood or better material, supported by two 4 inch by 4 inch diameter posts, professional grade.
Include the names of the following agencies:
• U.S. Army Corps of Engineers
• MOTCO
• State of California – The Resources Agency
• U.S. Department of the Interior, Fish and Wildlife Service
6.2.5. Providing SWPPP and BMPs: Work under this Contract is anticipated to disturb greater than one acre of land. Obtain coverage under the California State Water Resources Control Board Construction Activities Storm Water General Permit Order No. 2009-0009-DWQ as amended by 2010-0014-DWQ and 2012-0006-DWQ (CGP). The Contractor is the Legally Responsible Person (LRP) for storm water permits.
6.2.5.1 Preliminary Risk Calculations: indicate the following:
• Pier II East and West Restoration & Enhancement Site – Risk Level 1
• Risk Level 1 sites follow Attachment D, 01 57 23.01 Temporary Storm Water Pollution
Control, Risk Level 1
• The site’s risk is influenced by the Contractor’s anticipated dates of disturbance and site stabilization window. The stabilization timeframes may be influenced by seeding schedule requirements in Attachment E, Section 32 92 33 Grass Seeding and Erosion Control. Re-calculate risk level’s based on the Contractor’s anticipated start dates of work and anticipated date of stabilization.
Do not commence work until a WDID number is received from the State Water Board.
Collect pre-project photographs of the site at all transect monitoring location indicated in the HRP at a minimum in compliance with base Anti-Terrorism and Force Protection standards.
Include, the following minimum BMPs during installation and establishment (regardless of risk level or permit status) and that it is required to be returned to a condition demonstrating no future erosion potential. Minimum BMPs include but are not limited to perimeter protection, stabilized project entrance/exit, stockpile management, project site sediment perimeter controls, waste management, good housekeeping, stockpile management, preservation of existing vegetation, stabilized project entrance/exits, tracking control and wind erosion (dust) control.
Prevent dust from leaving the project site by providing dust control during dust generating project activities (including but not limited to work traffic on unpaved roadways and grading).
Follow their manufacturer’s instructions and conform to BMP fact sheets outlined in the California Storm Water Quality Association (CASQA) BMP Handbook.
P a g e | 11
6.2.5.2 Notice of Termination: As construction finishes follow the Notice of Termination (NOT) guidelines outlined in the attachments and terminate coverage. The site must not pose any additional sediment discharge risk than it did prior to the commencement of construction.
6.2.5.3 Temporary Storm Water Permit Related Submittals: Below are the required submittals in relation to temporary storm water pollution control. Separate sets of submittals are required for each site. Digital submittals are preferred over paper copies.
• Storm Water Pollution Prevention Plan (SWPPP) - Government Approval Required
• Permit Registration Documents (PRDs) - Government Approval Required
• BMP Product Data
• SWPPP Amendments
• Sampling Results
• Numeric Action Level (NAL) Exceedance Reports
• Rain Event Action Plans (REAPS)
• Inspection Reports (Weekly, prior to forecast rain, daily during rain events, and once following rain)
• Annual Report
• Post Construction Storm Water Management Plan
• Final SWPPP
• NOT Application – Government Approval Required
• See Attachment D1 Temporary Storm Water Protection Control Risk Level 1. See
Attachment F – Submittal Register.
6.2.6 Weed Eradication Plan A Weed Eradication Plan shall be developed by a professional with at least 5 years’ experience keying native and exotic weeds to address the removal of highly evasive exotic plants from the project site area to comply with guidance in the attached HRP. The results of the initial survey along transits shown in the HRP,l are used to provide a site specific plan based on the quantities of exotic invasive species present at the site. The plan shall prioritize on eradication of the highly invasive exotic weed species that are actively growing onsite. The following plant species shall be targeted: Pepperweed (Lepidium latifolia), Iceplant (Carpobrotus edulus), Common Reed (Phragmites australis), Giant Reed (Arundo donex), Himalayan blackberry (Rubus armeniacus), Saltcedar (Tamarix ramosissima), Pampas grass (Cortaderia jubata), Starthistle (Centaurea solstitialis), Italian thistle (Carduus pycnocephalus), Fennel (Foeniculum vulgare), Artichoke thistle (Cynara cardunculus), Poison hemlock (Conium maculatum), and other species out-competing the Native plants at the project site.
The plan, at a minimum, shall utilize a combination of mechanical and herbicide controls to reduce or stop seed production and kill and/or remove noxious and invasive weeds within the project site to 95% controls.
6.2.6.1 Initial Weed Survey/ Native Emergent Survey: The Native Plant Specialist shall take a plant vegetation survey of exotic species and the native species growing within the project site no more than 45 days after contract award and prior to ground disturbance, weeding or herbicide application has been performed. The Surveyor shall use a hand held GIS unit with a horizontal accuracy within industry standards for surveys. For each measured area, the Contractor shall identify the plant species noted for each measurement. The survey shall include the following species: Pepperweed (Lepidium latifolia), Exotic Common Reed (Phragmites australis), and Iceplant (Carpobrotus edelus), Himalayan Blackberry (Rubus armenius), Fennel (Foeniculum vulgare), Giant Reed (Arundo donax), Salt Cedar (Tamarix ramosissima), Star Thistle (Centaurea solstitialis), and exotic species found onsite that are define in the ‘high’ category in the California Invasive Plant Council (Cal-IPC) or plant species not named here that appear to dominate the native species at the project site.
The Cal-IPS website: http://www.cal-ipc.org
The Contractor shall measure the total area of all invasives and exotic weeds indicated in the HRP and create a table showing date sampled, transect identifier, area (in square feet), area as percent of total site, and trends of target plants. The Contractor shall label all of the polygons (GIS instrument) for each of the
P a g e | 12 plant species. The Contractor shall have the polygons identified per each species and have the polygons (shape files) inserted into a Computer Aided Drafting (CAD) program, with an outline of the project site.
An AutoCad version 14 file .dwg AND .kmz format. The polygons generated by the GIS shall include aerial imagery and be submitted to the COR yearly.
Native Water Emergent Plant Survey: Survey shall include the zone that is set aside for Habitat Restoration Salvage (Fig 4E). Within this zone, the Contractor shall identify the water emergent species present within the 1.32 are zone, and record the number of salvaged plant massing’s showing species, original amount transplanted and current survival rates.
6.2.7. Layout: Evenly spaced grid planting of salvaged plant material in area shown in Exhibit B, Figure 4E.
6.2.8. Seeding Grass: Do not disk or disturb the soil in preparation for grass seeding, however, mow all herbaceous growth close to soil prior to seeding. Apply grass seed to the entire upland and buffer area of the project sites. Perform grass seeding using the no-till drill seeding method. To meet SWPPP compliance, reseed as necessary to meet 70% SWPPP vegetative coverage compliance by the end of the first year after seeding. Native grass establishment must comply with the performance standards indicated in Attachment E Section 32 92 33 Grass Seeding and Erosion Control requirements. For grass seed mixtures, see Attachment C Plant Schedule and Exhibit B for seeding locations.
6.2.9. Providing Water: Design, provide, deliver, store, operate and maintain all water components, including water source, electrical power, equipment, and materials. Provide and deliver water to all plants as needed. See Attachment C for Planting Schedules.
6.2.10. Laying out Plant Locations: Prior to planting and/or placing salvage plantings, layout and flag plant locations on the ground for grid planting layout for salvage and intertidal. Evenly space plant locations along within grid. Coordinate and adjust plant locations as per the Contracting Officer and obtain his/her approval prior to installing any plants. See Attachment C, Plant Schedule in conjuncture with Exhibit B, HRP.
6.2.11. Planting Pits: Excavate a plant pit capable of supporting each size of salvaged and/or containerized plant where the flag locations have been placed. Dig each planting pit to the depth of the plant’s root ball and twice as wide. All locations must be pre-flagged and cleared by XO prior to any ground disturbance.
6.2.12. Salvage/Store Water Emergent Plants: Provide and install all container and salvaged plants, at the locations flagged, for the species and at the amounts as indicated within this Contract. Keep woody plants 15 feet from site perimeter and any designated interior maintenance roads. For all woody plants, provide browse guard (1/2 gallon milk carton or similar), gopher cage, stake, geotextile fabric mulch, slow-release commercial grade free-flowing fertilizer appropriate for the plant and soil characteristics with proximity to water. Provide fertilizer product data to Contracting Officer for review prior to work. Place a stake inside the browse guard to keep the guard upright and so that birds can use it to climb out. Water basin are not required, however manipulate soil around plant so that all the water from the emitter is contained and soaks into the soil before it flows away from the root zone of the plant. Water-in all plants within 12 hours of installation. Refer to Attachment F, Submittal Register for plant installation submittal requirements.
See Attachment C, Plant Schedule for plant container sizes, quantities, and densities.
6.2.13. Watering: Hand water in plants after installation. No watering of restoration area or upland/buffer area of site shall occur during establishment period.
6.2.14. Weeding: Within one month of the first herbicide spraying, remove blackberry brambles, Giant Reed, Star Thistle, Salt Cedar, Ice plant, etc. as identified in HRP.
P a g e | 13
Weeding is to occur and generally timed following the latest rains that generate growth. For each Establishment Period year (EP) provide the following:
• Base Year Weeding: 6 times throughout year as needed.
• EP1 Weeding: 4 times throughout the year as needed.
• EP2 Weeding: 3 times throughout the year as needed
6.2.15. Mechanical Vegetation Controls: Cut back weeds, native grasses, and dead plant material. Keep a fire suppressor water system, such as a trailered water tank with a motor-generated water hose, onsite and near the work area wherever mowing and other hazardous activities are being performed. Provide the following:
• Base Contract Mechanical Controls: 6 times, timed and spaced to capture growth throughout the season. Mechanically control target noxious and invasive weeds to promote target species growth.
• EP1 Mechanical Controls: 6 times, timed and spaced to capture growth throughout the season.
Mechanically control target noxious and invasive weeds to promote target species growth.
• EP2 Mechanical Controls: 6 times, timed and spaced to capture growth throughout the season.
Mechanically control target noxious and invasive weeds to promote target species growth.
6.2.16. Herbicide Application: The herbicide application program shall be developed to remove highly invasive species from the project site. All application of herbicide must follow the approved Weed Control Plan. Prevent herbicide overspray and wind drift into non-target and planted areas. Additionally, when spraying herbicide, apply enough to cover plant yet minimize herbicide coming in contact with the soil. Do not spray when wind will carry spray to non-target areas. Do not spray when warm weather can volatilize herbicide and cause damage to non-target areas. Utilize low pressure drift resistant spray nozzles, anti-drift agents, spray shields and any other means necessary to ensure non-target areas are not damaged by overspray and wind drift. To accomplish this, the efforts required herein are to reduce and eliminate the non-native exotic grass and broadleaf herbaceous vegetation and accompanying seed banks while enhancing native species establishment. Select the appropriate herbicide designed to kill all non-native grasses and undesirable exotic growth, including all vegetative growth that occurs onsite, on the maintenance road, and within the staging area and site edges. Prevent annual grasses from setting viable seed, keep broadleaf weeds under 6” in height. When the staging area is removed and no longer in use, seed its entire area and establish native grass prior to leaving. All spraying must be performed by a certified applicator for the type of herbicide used. Place proper notifications at adjacent public roads/trails two days prior to spraying operations. Weed eradication for species indicated in the HRP is required by the contractor to 95% of the total site area.
• All herbicides shall be applied in accordance with local, state, and federal regulations and regulations set by the California Department of Pesticide Regulation and the MOTCO IPMP according to labeled instruction. Care shall be taken to avoid contact with any native vegetation, and foliar applications shall only be employed on calm days when winds are below 5 miles/hour.
If winds above 5MPH, written approval much be given by COR.
• Herbicide treatments shall be conducted under the supervision of a State of California- licensed Pest Control Advisor. Herbicide applications shall be made by a Licensed Pesticide Applicator.
• Herbicide treatments shall be selectively applied to target species to the maximum extent possible.
• Herbicide treatments in the tidal marsh shall be timed to coincide with the ebb tide, and to the extent feasible, shall be conducted during tidal cycles that maximize the area that will not be inundated within 24 hours of herbicide application.
Provide herbicide product and equipment data to COR for review prior to work. Refer to Attachment F, Submittal Register. Spray applications are defined as follows:
6.2.16.1 Spraying: “Noxious / Invasive Herbicide Spraying” is defined as the initial and ongoing site spraying prior to ground disturbance and throughout establishment period. Application of herbicide is designed to kill and reduce the existing non-native, invasive, and exotic competition
P a g e | 14 to preserve and foster growth native and indigenous species. Areas that have abundant amounts of desirable existing natives that are to remain. The goal is to retain the existing natives and remove noxious and invasives to 95% noxious and invasive free. Follow guidance in the HRP, attached.
• “Spot Spraying” is defined herein as spraying and killing targeted undesirable broadleaf vegetation or non-native exotic as defined in the HRP. Prior to spot spraying, coordinate the goals with the Contracting Officer. Spray all targeted undesirable vegetation with a non-selective herbicide designed to completely kill the targeted existing vegetation or a selective herbicide to target specific weed and non-native grass species.
The application quantities for spraying are as follows:
• IP Grass Treatment Spraying: : 6 times; time spraying to capture weed growth over entire site
• EP1 Spraying: timed and spaced to capture growth.
o Rows: 4 times o Middles: 2 times o Pre-seeding spraying: 1 time o Spot Spraying: 8 times
• EP2 Spraying: timed and spaced to capture growth.
o Rows: 3 times o Spot Spraying: 9 time
6.2.17. Surveying Plants: Contractor must provide quarterly survival reports from transects indicated in the HRP along with annual survivorship reports to the CO. Include discussion for success and shortfalls, BMPs implemented, species richness, natural recruitment, and other pertinent site and restoration information critical to projects success. Present the results in each of the subsequent annual reports. See Attachment F, Submittal Register and section 6.2.20 for details.
6.2.18. Replacing Dead Plants & Missing Plants (from tidal and/or waterfowl): At the end of the first and second year establishment periods replace all dead plants, including using new browse guards, fertilizer, and mulch of like material, size and type as was originally installed. Coordinate species with the Contracting Officer prior to ordering plant material. Since some species are not always readily available at a local nursery, anticipate in advance those species that may need to be replaced and pre-grow the plants so they are at the required container size and ready when needed. Due to unavailability or poor species performance, adjustments to replacement species may be desirable and accepted, provided coordination has been performed with the Contracting Officer in advance and a written approval of species substitutions has been issued.
6.2.19. Preparing Activity Records: Prepare activity records, which include monthly records of work performed during each month of the contract, as-built drawings of all installation work, and a weed control plan for each year of the contract.
• Prepare monthly activity records, one for each month of the Contract. Submit the monthly activity record with each invoice, addressing specific tasks billed. Include activities of all installation and maintenance work that is performed throughout each preceding month of the contract. Submit record along with each monthly invoice, within 7 working days following the end of each month.
Each monthly record must not be longer than one page on 8-1/2”x11” format.