This announcement is for a firm-fixed-price design-build/design-bid-build single award task order contract for roof replacement and seismic upgrades of Building 225 at Hill Air Force Base in Utah. The contractor will provide all labor and materials to repair and replace the entire 600,000 square foot roof in approximately six phases through task orders over a five-year period with two one-year options. The project scope includes removal of existing roofing, repair of structural components, replacement of appurtenances, asbestos abatement, and associated seismic upgrades. The contracting agency is the U.S. Army Corps of Engineers Sacramento District. The NAICS code is 236220 for commercial and institutional building construction with a small business size standard of $36.5 million, and the PSC is Y1BZ for a magnitude between $25-100 million. A pre-proposal site visit will be scheduled.

Repair Roof Aircraft Production Facility Building 225 - W91238-18-R-0071

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This requirement is for a Single Aw ard Task Order Contract (SATOC) to provide all labor and materials necessary to repair by replacement the entire roof of Building 225 at Hill Air Force Base, Utah. This w ork w ill be accomplished in approximately six phases. Each phase w ill be completed as an individual task order against the SATOC. This SATOC has the f lexibility to support Design-Build (DB) and Design-Bid-Build (DBB) requirements. As allow ed by DFARS 217.204(e)(i), the ordering period for this SATOC is f ive years w ith tw o one-year option periods.

The project scope includes the removal of existing roofing materials and repair of any damaged structural roofing components. The Contractor shall replace any other roofing appurtenances, such as heat tape, rain gutters, etc., removed or damaged during the roof replacement cycle. The Contractor shall abate asbestos, or any other hazardous materials encountered, in full compliance w ith all law s and regulations.

The value of this SATOC is Not-to-Exceed $48,000,000.00.

In accordance w ith FAR 36.204 (g), the estimate value of the seed project is betw een $5,000,000.00 and $10,000,000.00.

KENLEY LOTT 916-557-5326

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

14-Sep-2018

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________1826 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________15 Oct 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour) Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9123818R0071 93

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 01 10 - Table of Contents

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 01 Bldg 225 Summary of

Work

2 03-AUG-2018

Attachment 02 Davis Bacon Wage Determinations

12 09-FEB-2018

Attachment 03 DRAFT B225 RFP Specifications

554 25-JUL-2018

Attachment 04 DRAFT B225 RFP Drawings

77 25-JUN-2018

Attachment 05 B225 ASCE 41 Tier 2 Seismic Evaluation

531 23-JUL-2018

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job DB/DBB B225 Roof Replacement

FFP

Provide all labor, management, supervision, tools, materials, equipment and transportation for DESIGN (when applicable) and CONSTRUCTION of repairs, replacement and seismic upgrades to Bldg 225 Area C - Lower Sawtooth Roof, Area F - Southeast Barrel Roof, Area A - Northwest Barrel Roof, Area B - Northeast Barrel Roof, Area H - East Annex Roof, Area D - Upper Sawtooth Roof, Area E - Southwest Barrel Roof, and associated site improvements at Hill AFB, UT in strict accordance with all RFP documents, drawings and specifications. Task Orders under this CLIN may be Design-Build or Design-Bid-Build. Ordering Period: April 2019 – March 2024 FOB: Destination

SIGNAL CODE: A

NET AMT

1001 1 Job OPTION DB/DBB B225 Roof Replacement

FFP

Provide all labor, management, supervision, tools, materials, equipment and transportation for DESIGN (when applicable) and CONSTRUCTION of repairs, replacement and seismic upgrades to Bldg 225 Area C - Lower Sawtooth Roof, Area F - Southeast Barrel Roof, Area A - Northwest Barrel Roof, Area B - Northeast Barrel Roof, Area H - East Annex Roof, Area D - Upper Sawtooth Roof, Area E - Southwest Barrel Roof, and associated site improvements at Hill AFB, UT in strict accordance with all RFP documents, drawings and specifications. Task Orders under this CLIN may be Design-Build or Design-Bid-Build. Ordering Period: April 2024 – March 2025

2001 1 Job OPTION DB/DBB B225 Roof Replacement

FFP

Provide all labor, management, supervision, tools, materials, equipment and transportation for DESIGN (when applicable) and CONSTRUCTION of repairs, replacement and seismic upgrades to Bldg 225 Area C - Lower Sawtooth Roof, Area F - Southeast Barrel Roof, Area A - Northwest Barrel Roof, Area B - Northeast Barrel Roof, Area H - East Annex Roof, Area D - Upper Sawtooth Roof, Area E - Southwest Barrel Roof, and associated site improvements at Hill AFB, UT in strict accordance with all RFP documents, drawings and specifications. Task Orders under this CLIN may be Design-Build or Design-Bid-Build. Ordering Period: April 2025 - March 2026

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 01-APR-2019 TO

31-MAR-2024

N/A UTAH AREA OFFICE

7227 6TH STREET (COE) BUILDING 366

HILL AFB UT 84056-5214

L2M0270

1001 POP 01-APR-2024 TO

31-MAR-2025

N/A (SAME AS PREVIOUS LOCATION)

2001 POP 01-APR-2025 TO

31-MAR-2026

N/A (SAME AS PREVIOUS LOCATION)

Section 00 20 00 - Instructions for Procurement

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2016 52.204-16 Commercial and Government Entity Code Reporting JUL 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) -

Alternate I

OCT 1997

52.215-16 Facilities Capital Cost of Money JUN 2003 52.215-20 Requirements for Certified Cost or Pricing Data or

Information Other Than Certified Cost or Pricing Data

OCT 2010

52.217-3 Evaluation Exclusive Of Options APR 1984 52.222-5 Construction Wage Rate Requirements--Secondary Site of the

Work

MAY 2014

52.232-13 Notice Of Progress Payments APR 1984 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.215-7008 Only One Offer OCT 2013

CLAUSES INCORPORATED BY FULL TEXT

52.215-20 REQUIREMENTS FOR COST OR PRICING DATA OR INFORMATION OTHER THAN COST

OR PRICING DATA (OCT 2010)—ALTERNATE II (OCT 1997)

(a) Exceptions from cost or pricing data. (1) In lieu of submitting cost or pricing data, offerors may submit a written request for exception by submitting the information described in the following subparagraphs. The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.

(i) Identification of the law or regulation establishing the price offered. If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.

(ii) Commercial item exception. For a commercial item exception, the offeror shall submit, at a minimum, information on prices at which the same item or similar items have previously been sold in the commercial market that is adequate for evaluating the reasonableness of the price for this acquisition. Such information may include--

(A) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities;

(B) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market;

(C) For items included on an active Federal Supply Service Multiple Award Schedule contract, proof that an exception has been granted for the schedule item.

(2) The offeror grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this provision, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation , access does not extend to cost or profit information or other data relevant solely to the offeror's determination of the prices to be offered in the catalog or marketplace.

(b) Requirements for cost or pricing data. If the offeror is not granted an exception from the requirement to submit cost or pricing data, the following applies:

(1) The offeror shall prepare and submit cost or pricing data and supporting attachments in accordance with Table 15-2 of FAR 15.408.

(2) As soon as practicable after agreement on price, but before contract award (except for unpriced actions such as letter contracts), the offeror shall submit a Certificate of Current Cost or Pricing Data, as prescribed by FAR 15.406- 2.

(c) When the proposal is submitted, also submit one copy each to: (1) the Administrative Contracting Officer, and

(2) the Contract Auditor.

(End of provision)

52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR INFORMATION OTHER

THAN CERTIFIED COST OR PRICING DATA (OCT 2010)—ALTERNATE IV (OCT 2010)

(a) Submission of certified cost or pricing data is not required.

(b) Provide data described below:

Data descriptions will be included in task orders and/or modification proposal requests.

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price Indefinite-Delivery Indefinite-Quantity Single Award Task Order Contract resulting from this solicitation.

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, Sacramento District ATTN: Construction Contracting Officer, Room 878 1325 J Street Sacramento, CA 95814

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- (To be determined upon issuance of Phase Two solicitation

(c) Participants will meet at-- Building 366 (Utah Resident Office), Hill AFB, UT

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Department of Defense Supplement (48 CFR Chapter Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 21 16 - Instructions to Proposers

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

1. SUBMITTAL INFORMATION FOR OFFERORS:

The following documents must be returned with your proposal.

(a) The completed Standard Form 1442 with continuation pages, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address. DO NOT COMPLETE

SECTION 00 10 00 FOR THE PHASE ONE PROPOSAL. OFFERORS SHALL

COMPLETE SECTION 00 10 00 AND SUBMIT ALONG WITH THEIR PHASE TWO

PROPOSALS

(b) Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment. Note: If the SF 1442 and/or the pricing schedule was changed by amendment, be sure to use the amended pages when submitting your proposal.

(c) Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).

(d) Any other documents required by the solicitation

(e) Your Bid Guarantee (e.g., Standard Form 24, “Bid Bond”) will be requested in Phase Two

(f) The completed CLIN Schedule will be requested in Phase Two with your proposed contract line item prices inserted in the appropriate spaces. Prices must be proposed for all contract line items and priced sub-line items. Unit prices are to be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off extended prices to the nearest dollar.

Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

2. INQUIRIES:

Prospective offerors should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

(a) For information related to amendments, and the dates set for receipt of proposals, please check http://www.fbo.gov

(b) Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

http://www.fbo.gov/ https://www.projnet.org/projnet

(c) To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the QUICK ADD link. Select agency as USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click continue. Fill in all required information and click Add User.

(d) From this page you may view all bidder inquiries or add an inquiry.

(e) Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

(f) The Solicitation Number is : W91238-18-R-0071 The Bidder Inquiry Key is: QM8RR5-N78WYW

(g) The Bidder Inquiry System will be unavailable after 21 September 2018 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

(h) Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

(i) The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago).

The telephone number for the Call Center is 800-428-HELP.

(j) Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

(k) The point of contact for this solicitation is:

Contract Specialist: Kenley Lott Telephone: (916) 557-5326 E-MAIL Kenley.Lott@usace.army.mil

(l) All technical questions on the specifications or drawings must be submitted in writing to:

(m) Oral explanations or instructions are not binding. Changes to the solicitation can only be made by an amendment to the solicitation.

3. DIRECTIONS FOR SUBMITTING OFFERS:

Envelopes/packages containing offers must be sealed, marked and addressed as follows:

MARK ENVELOPES/PACKAGES:

Solicitation No. W91238-18-R-0071 mailto:Kenley.Lott@usace.army.mil

ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division (Kenley Lott) 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTION PERTAINING TO HAND-CARRIED OFFERS:

Hand-carried offers must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, offerors may no longer hand-carry their offers directly to Contracting Division. Offers may NOT be turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no public parking in the Building.

The contract specialist will be in the Building Lobby 20 minutes prior to the closing time to accept hand-carried offers.

Offerors who desire to hand-deliver their offers at an earlier time must coordinate with the contract specialist in advance in order to arrange to be met in the Building Lobby by Contracting Division personnel.

Please ensure that all courier and delivery personnel are aware of these procedures.

4. CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

NOTE: Preaward Survey will be requested in Phase Two.

5. AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

(a) The internet URL for Corps of Engineers publications is http://www.publications.usace.army.mil/

(b) Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications. Information about the CCB can be obtained from http://www.wbdg.org/ccb/ccb.php

6. PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15.

http://www.publications.usace.army.mil/ http://www.wbdg.org/ccb/ccb.php

7. INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

FOR PHASE TWO PROPOSALS ONLY: Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate. Failure to provide required documentation described herein may cause the offeror to be deemed "unacceptable".

8. ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

9. SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION:

It is a requirement that any and all contractors that intend to do business with the government must be registered in the System for Award Management (SAM) database. No contract may be awarded by the government to any contractor who is not registered in SAM. If your company is not registered in SAM, you must register in order to be eligible for any government award.

The following link provides access to the SAM website:

https://www.sam.gov/portal/public/SAM/

If you have difficulties with or questions regarding the SAM registration, the following link has been set up by the Defense Logistics Agency (DLA) to assist contractors registering for CAGE codes for enrollment and navigation within SAM:

https://www.logisticsinformationservice.dla.mil/CAGETier3/ https://www.sam.gov/portal/public/SAM/ https://www.logisticsinformationservice.dla.mil/CAGETier3/

Section 00 22 00 - Supplementary Instructions

EVALUATION CRITERIA

Section 00 22 00 - Supplementary Instructions

INSTRUCTIONS TO OFFERORS

INSTRUCTIONS TO OFFERORS AND EVALUATION CRITERIA

1. OVERVIEW

This solicitation is for the Design-Build/Design-Bid-Build SATOC for the Building 225 Roof Replacement project at Hill AFB, UT. This solicitation utilizes a two-phase source selection process requiring two separate proposal submittals. The Phase One proposal consists of only non-price technical factors. The Government shall select approximately 3-5 of the most highly qualified offerors from Phase One who will be given the opportunity to submit a Phase-Two proposal that consists of price and technical factors. In accordance with FAR 15.306 the Government does not intend to conduct discussions during either phase of this solicitation, but reserves the right to do so if discussions appear to be in its best interest.

2. BASIS OF CONTRACT AWARD

2.1 ELIGIBILITY FOR CONTRACT AWARD

In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the Contracting Officer makes an affirmative determination of responsibility. To be determined responsible, a prospective contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.

2.2 SOURCE SELECTION USING THE “BEST VALUE” TRADE-OFF PROCESS

The Government, during Phase Two, will select the offer that represents the best value to the Government by using the tradeoff process described in FAR Part 15. This process permits tradeoffs between price and technical (“non-price”) factors and allows the Government to accept other than the lowest priced offer. The award decision will be based on a comparative analysis and an integrated assessment of proposals against all source selection criteria in the solicitation.

2.3 THE TECHNICAL EVALUATION FACTORS

The Government will evaluate each offeror’s technical proposal based on how well the proposal addresses each of the evaluation factors, listed below, and on how well the offeror has performed on related projects through the evaluation of the past performance information provided from references or obtained from other sources. Each of the evaluation factors will be evaluated by the Government and an adjectival rating and risk rating will be determined by consensus of the Government evaluation board for all technical factors other than past performance. The Past

Performance factor will be evaluated by the Government to determine a Performance Confidence Assessment rating.

The evaluation factors correlate directly to the main organizational tabs identified in the proposal submission instructions.

Phase One Proposal

(1) Factor 1: Experience and Capability

(2) Factor 2: Technical Approach

(3) Factor 3: Past Performance

Phase Two Proposal - To be included with the amendment initiating phase two.

(4) Factor 4: Technical Approach

(5) Factor 5: Performance Capability

The Source Selection Authority will consider only the Phase One proposals during Phase One, however both the Phase One and the Phase Two proposals and all the relative strengths and weaknesses will be used in determining the best value to the Government in Phase Two.

2.4 RELATIVE IMPORTANCE OF TECHNICAL EVALUATION FACTORS AND OF

PRICE TO THE TECHNICAL EVALUATION FACTORS

All non-priced evaluation factors, when combined, are significantly more important than cost or price. The Government is concerned with striking the most advantageous balance between technical merit (“quality”) and cost to the Government (i.e., the price). If competing technical proposals are determined to be essentially equal, price could become the controlling factor.

The Technical Evaluation Factors are listed below in descending order of importance:

Phase One Factor 1 – Experience and Capability is the most heavily weighted factor.

Factor 2 – Technical Approach is weighted less than Factor 1.

Factor 3 – Past Performance is weighted less than Factor 2.

Phase Two Factor 4 – Technical Approach Factor 5 – Performacne Capability Phase Two criteria details will be supplied once we are that point in the acquisition. *Note:

Phase One criteria will also be used in the ultimate award decision.

3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

INSTRUCTIONS TO OFFERORS FOR PHASE ONE PROPOSALS ARE PROVIDED IN

PHASE ONE. THE INSTRUCTIONS TO OFFERORS FOR PHASE TWO WILL BE

PROVIDED AFTER PHASE ONE DURING PHASE TWO.

3.1 GENERAL INSTRUCTIONS – PHASE ONE

3.1.1 The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements may be seen as indicative of the type of problems that could be expected during contract performance. Lack of conformance may therefore result in a higher risk assessment, in addition to any other impacts on the evaluation. Material omission(s) may cause the technical proposal to be rejected as unacceptable. However, in accordance with FAR 52.215- 1, the Government may waive informalities and minor irregularities in proposals. For example, a failure by a proposed key subcontractor to submit a properly executed letter of commitment may be considered as increasing risk, but will not be considered a proposal deficiency.

3.1.2 Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may receive a lower rating. The Government is under no obligation to search for information that is not in the specified location.

3.1.3 Proposals which are generic, vague, or lacking in detail may receive a lower rating.

Responses that are essentially blanket offers of compliance are not adequate substitutes for the detailed and complete technical information necessary to establish that an offeror can meet US Government needs. The proposal submission instructions are written to give prospective contractors, where feasible, an indication of the level of detail desired by the Government. The offeror’s failure to include information that the Government has indicated should be included may result in the proposal receiving a lower rating and/or being found deficient if inadequate detail is provided.

3.1.4 Any prescribed page and formatting limitations will be strictly adhered to and enforced by the Government. The Government will not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit three pages in response to an item with a two page limitation, the information on the first two pages would be evaluated but the information on the third page would not be evaluated. If an offeror were to submit a fold-out sheet (e.g. 11”x17”) in response to a one-page limitation where fold-out sheets were not authorized, only the information that could reasonably have been submitted on one 8-1/2 x 11 inch sheet would be evaluated. If an offeror were to submit three 8- 1/2 x 11 inch pages in response to a one not-to-exceed 11 x 17 inch page limitation, only the information that could reasonably have been submitted on one 11 x 17 inch sheet would be evaluated. If an offeror submitted alternates that were not requested (e.g. key subcontractor), the information will not be evaluated.

3.1.5 The degree of risk to the Government inherent in the offeror’s technical proposal will be a consideration under every evaluation factor.

3.1.6 A “deficiency” is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. “Weakness” means a flaw in a proposal that increases the risk of unsuccessful contract performance. A “significant weakness” is a proposal flaw that appreciably increases the risk of unsuccessful contract performance.

3.1.7 The Government cannot accept an offer with a deficiency in its technical proposal. The term “acceptable” is therefore used in this context to describe a technical proposal that does not contain a deficiency and thus could be accepted by the Government, notwithstanding any weaknesses or significant weaknesses in the proposal. Additionally, multiple significant weaknesses in a proposal may be considered a deficiency.

3.1.8 The Government cannot make award based on a deficient offer. Therefore, a rating of “Unacceptable” under any factor will render the offer ineligible for award, unless the Government elects to enter into discussions with that offeror and all deficiencies are remedied in a revised proposal.

3.1.9 Failure of a proposed key subcontractor to furnish authorization for the Government to discuss its past performance with the offeror will not be considered a proposal deficiency.

However, the Government will not be able to disclose to the offeror any details pertaining to their performance problems that may impact their overall rating.

3.1.10 The Government will utilize a Combined Technical/Risk Rating for some technical factors or subfactors other than past performance. Other technical factors or subfactors other than past performance will receive a rating of either “Acceptable” or “Unacceptable”. The specific Phase One factors and/or subfactors which will receive Combined Technical/Risk Ratings versus “Acceptable” or “Unacceptable” ratings are identified below.

Factors/Subfactors Description Rating Method Rating Definitions

Factor 1 Experience and Capability

Combined Technical/Risk Rating

DoD Source Selection Procedures Table

Subfactor 1 Prime Contractor / Key Subcontractor(s) Example Projects Demonstrating Experience and Capability

Combined Technical/Risk Rating

DoD Source Selection Procedures Table

Subfactor 2 Bonding Capability Acceptable/Unacceptable Rating

DoD Source Selection Procedures Table C-1

Factor 2 Technical Approach, Multiple Task Order Capability

Combined Technical/Risk Rating

DoD Source Selection Procedures Table

Factor 3 Past Performance, Prime Contractor / Key Subcontractor(s) Example Projects Demonstrating Past Performance

Past Performance Relevancy Rating and Past Performance Confidence Assessment Rating

DoD Source Selection Procedures Tables 4 and 5

As indicated above and in accordance with Tables 3 and C-1 of the DoD Source Selection Procedures, the evaluation team will assign either Combined Technical/Risk Ratings or an “Acceptable” or “Unacceptable” rating to each of the technical factors and subfactors other than the Past Performance factor. For any factors that contain subfactors, the Government will take into consideration the ratings for each subfactor to determine an overall Combined Technical/Risk Rating at the factor level. The Combined Technical/Risk Ratings, Acceptable/Unacceptable Ratings and their descriptions are in the tables below. Any rating of “Unacceptable” will result in the offer being unawardable unless remedied through discussions.

DoD Source Selection Procedures Table 3

DoD Source Selection Procedures Table C-1

Acceptable/Unacceptable Ratings

ADJECTIVAL

RATING DESCRIPTION

Acceptable Proposal meets the requirements of the solicitation.

Combined Technical/Risk Rating

COLOR

RATING RATING DESCRIPTION

Blue Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Red Unacceptable

Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

Unacceptable Proposal does not meet the requirements of the solicitation.

3.1.11 Past Performance Evaluation. The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. The past performance evaluation considers each offeror's demonstrated recent and relevant record of performance in supplying products and services that meet the contract’s requirements. One performance confidence assessment rating is assigned for each offeror after evaluating the offeror's recent past performance, focusing on performance that is relevant to the contract requirements. The past performance evaluation will focus on three elements: the recency, relevance and quality of the offeror’s past performance information.

3.1.12 In accordance with Table 4 of the DoD Source Selection Procedures, the Government will assign an adjectival rating commensurate with the level of relevancy of the offerors’ past performance submission. The adjectival past performance relevancy ratings and their descriptions are in the table below.

DoD Source Selection Procedures Table 4

Past Performance Relevancy Rating

RATING DESCRIPTION

Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

3.1.13 In accordance with Table 5 of the DoD Source Selection Procedures, the Government will assign a pest performance confidence rating commensurate with the Government’s level of confidence in the offeror’s ability successfully complete the contract requirements based on the offeror’s past performance submission and other past performance information obtained by the Government. The past performance confidence ratings and their descriptions are in the table below.

DoD Source Selection Procedures Table 5

Past Performance Confidence Assessment Ratings

RATING DESCRIPTION

Substantial Confidence

Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence

Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Neutral Confidence

No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

3.2 GENERAL PROPOSAL PREPARATION. PHASE-ONE

The proposal shall be submitted as summarized below and as required by the specifications.

3.2.1 Marking of Proposal Volumes:

Mark each volume as “Technical Volume”. In addition, mark the outside front cover of each volume with the project title and location, solicitation number, name and address of the offeror, and volume copy number. (Markings which identify the offeror are not required on either the back cover or on the spine/binding.)

3.2.2 Tabbing of Proposal Volumes:

Offers are to be formatted and tabbed in accordance with the instructions that follow for each proposal volume.

3.2.3 Table of Contents:

Include a table of contents for each proposal volume.

4 PHASE-ONE PROPOSAL

4.0 REQUIRED CONTENTS OF PHASE ONE PROPOSALS

4.1 NUMBER OF SETS OF THE PHASE ONE TECHNICAL PROPOSAL

Proposals must be submitted by land mail or air courier to the address below. Hard copy submissions shall include four (4) copies of the Technical Proposal (One original and three copies) and one (1) original hard copy Price Proposal and be accompanied by a compact disk of both proposals in CD format. The hard copy and CD proposals must be received by the date and time listed in block 13 (A) of the SF1442. Any questions regarding this solicitation shall be sent via the instructions in Section 00 21 16 of this solicitation. Questions arising after the close of ProjNet shall be directed to Kenley Lott, Contract Specialist, email:

Kenley.Lott@usace.army.mil. Phone inquiries will not receive a response.

4.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE PHASE ONE TECHNICAL

PROPOSAL

Use 8-1/2” x 11” pages for the narrative portions of the proposal. The overall technical proposal has no page limit; however limits may be imposed at the tab level. Number the pages by Tab so that the first page under each tab is numbered “Page 1” and following pages are numbered consecutively. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location. Do not include any information pertaining to proposed pricing for this project in the technical proposal; price proposals shall be submitted only during Phase Two of the source selection process. Limit your submittals to the information specified; excess information will not be evaluated. Organize your technical proposal as indicated below.

4.3 ORGANIZATION OF PHASE-ONE TECHNICAL PROPOSAL

TAB Contents to be included under each tab

TAB 1. – PREFACE

• Prime Contractor / Key Subcontractor Introduction

• The completed Standard Form 1442 with continuation pages, without a price, duly executed with an original signature by an official authorized to bind the company. Ensure that the firm’s DUNS or DUNS+4 Number is entered in the block with its name and address.

• Your acknowledgement of any and all Amendments to the solicitation in accordance with the instructions on the Standard Form 30 Amendment.

• Joint Venture Agreement (if applicable)

• Your completed Representations, Certifications, and Other Statements of Bidders/Offerors (Section 00 45 00).

TAB 2. FACTOR 1 – EXPERIENCE AND CAPABILITY

• Subfactor 1 - Prime Contractor / Key Subcontractor(s) Example Projects Demonstrating Experience and Capability

• Subfactor 2 - Bonding Capability

TAB 3. FACTOR 2 – TECHNICAL APPROACH

• Multiple Task Order Capability

TAB 4. FACTOR 3 – PAST PERFORMANCE

• Prime Contractor / Key Subcontractor(s) Example Projects Demonstrating Past Performance

4.4 DETAILED SUBMISSION REQUIREMENTS AND EVALUATION CRITERIA FOR

THE PHASE-ONE TECHNICAL PROPOSAL

4.4.1 Tab 1 of the Technical Proposal: Preface

4.4.1.1 Prime Contractor/Key Subcontractor Introduction

4.4.1.1.1 The Offeror is required to propose a specific project team including key subcontractors for evaluation in response to this Request for Proposals. For purposes of this procurement, the terms “key subcontractors” are used to refer only to the prospective subcontractors whose qualifications, experience, and past performance will be evaluated by the Government as part of the source selection process. For reasons of efficiency, not all of the subcontractors critical to successful post-award contract performance have been included in this group. In order to streamline the proposal submission and evaluation process, please limit your submission to the information specifically requested. Information pertaining to other subcontractors not designated as “key” by the Government will be considered excess and may not be evaluated.

4.4.1.1.2 For the purposes of this procurement, a key subcontractor is defined as any subcontractor performing “key” major work elements for which capability information is required to be submitted for evaluation as part of the Offeror’s Phase-One technical proposal.

The Government has designated the following major work elements as “key”:

- Architect-Engineer Design

- Registered Roofing Consultant (RRC)

4.4.1.1.3 Any changes to key subcontractors in your Phase 2 proposal from your Phase 1 proposal will not be allowed.

4.4.1.1.4 Any subcontractors and outside associates or consultants required by the Contractor in connection with the services covered by the contract will be limited to individuals or firms that were specifically identified and agreed to during negotiations. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these subcontractors, associates, or consultants.

4.4.1.1.5 Provide a brief introduction narrative. Identify and provide the name, DUNS number, address, point of contact e-mail address, and a brief description of the role and authority of each firm that will be involved in performance of this contract at the prime contractor and key subcontractor level. If the proposed prime contractor is a Joint Venture, describe the relationship, role, and authority (to include management authority) of each firm. (Note: If a proposed firm has branch offices, provide information for each individual branch office that will perform work under the contract with its own workforce.) List the major work elements to be self-performed by the offeror’s in-house work force, the major work elements to be performed by each key subcontractor, and any other major work to be subcontracted to other contractors. The submission is limited to two (2) 8-1/2”x11” pages for narrative. In addition to the narrative, the offeror shall submit commitment letters from each of the key subcontractors stating that they will be dedicated to providing their applicable services to the prime contractor for each task order placed against this SATOC.

4.4.1.1.6 The Government will not evaluate the Preface - Prime Contractor/Key Subcontractor Introduction. The purpose of this narrative is to provide a brief introduction for information purposes; however, if applicable, the government reserves the right to consider it throughout the evaluation of the other factors.

4.4.2. Tab 2 of the Technical Proposal: Factor 1 – Experience and Capability:

4.4.2.1 Prime Contractor / Key Subcontractor Example Projects Demonstrating Experience and Capability.

4.4.2.1.1 The offeror shall, submit “example projects” (either commercial, institutional or Government) that demonstrate the prime’s and key subcontractor’s experience working on projects of similar scope, complexity, and magnitude to that of the Summary of Work, draft specifications, and draft drawings attached to this solicitation and capability to successfully perform under the resulting contract.

4.4.2.1.2 The offeror must provide a narrative to explain how the experience and capabilities shown by the example projects are relevant to the draft specifications and drawings attached to this solicitation and show the contractor’s and key subcontractor’s understanding of the risks, work requirements, and approach necessary to successfully complete the resulting contract.

4.4.2.1.3 In doing so, the offeror shall submit at least three (3) but not more than six (6) example projects of similar scope, complexity, and magnitude as the the Summary of Work, draft specifications, and draft drawings attached to this solicitation that individually or collectively demonstrate the following characteristics of the prime contractor and key subcontractors. The narrative shall include the following information:

(1) The offeror’s experience and capabilities as a prime contractor to successfully perform the resulting contract. Explain how the experience and capabilities shown by the example projects are relevant to this project and show the contractor possesses an understanding of the risks and requirements and approach necessary to successfully act as the prime contractor for the resulting contract.

(2) The offeror’s design-build management capability. Explain how the experience and capabilities shown by the example projects are relevant to the Summary of Work, draft specifications, and draft drawings attached to this solicitation and show the contractor’s and/or key subcontractor’s possess an understanding of the risks, and requirements and approach necessary to successfully manage the design-build requirements of the resulting contract.

(3) The experience and capabilities of the lead designer to design the Building 225 Roof Replacement.