W91238-18-R-0059 DDHU Lot 3 Improvements Attachment 2
SUPPLEMENTAL CONTRACT REQUIREMENTS
1. Performance Period: Refer to contract section 00700, FAR 52.211-10. The performance period for the work stated above shall be 365 calendar days.
2. Liquidated Damages: Refer to contract section 00700, FAR 52.211-12, Liquidated Damages-Construction. Liquidated damages for this work are $2,291.00 for each day of delay.
3. Authorities: “Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.”
4. Wage Determination: General Decision No. UT180062, or its most current modification at the time of award is hereby applicable to work performed under this task order. The most current decision or its modification can be found at https://wdol.gov/wdol/scafiles/davisbacon/UT104.dvb?v=1
6. Time Extensions For Unusually Severe Weather: Refer to FAR 52.249.10, Default (Fixed- Priced Construction). All weather delay will need to be submitted and approved by the Contracting Officer Representative.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(22) (17) (13) (08) (05) (03) (01) (02) (03) (05) (12) (22) https://wdol.gov/wdol/scafiles/davisbacon/UT104.dvb?v=1
SUPPLEMENTAL CONTRACT REQUIREMENTS