1-Atch_1_SOW_MOTCO_Repair_Pier_3-Phases_II-III.docx

DOCX document 35 KB Posted

Attached to
Military Ocean Terminal Concord (MOTCO) Pier 3 Pile Wrapping
Solicitation number
W91238-18-R-0038
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
W91238-18-R-0038-0004.pdf PDF
W91238-18-R-0038_Amendment_0003.pdf PDF
Revised_Specifications.pdf PDF
Motco_Pier_3_-_Revised_Staging_Area_Location.pdf PDF
W91238-18-R-0038-0002.pdf PDF
Pier_3_Site_Walk_7-19-18.pdf PDF
A07.05_-_Pre-proposal_Site_Visit_Sign-In_Sheet.pdf PDF
Attachment_3_-_Wage_Determinations.pdf PDF
Attachment_4_-_Pile_Wrapping_Matrix.pdf PDF
W91238-18-R-003801.pdf PDF
A07.01_-_I_NCIC_CONSENT_FORM_INSTRUCTIONS.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_3_of_7.pdf PDF
5-Atch_3_Wage_Determination_MOTCO_Repair_Pier_3-Phases_II-III.docx DOCX document
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_1_of_7_Redacted.pdf PDF
A07.05_-_NCIC_Consent_Form_-_W91238-18-R-0037.pdf PDF
A07.01_-_SUPPLEMENTAL_USACE_INSTRUCTIONS.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_4_of_7.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_7_of_7.pdf PDF
W91238-18-R-0038_RFP.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_5_of_7.pdf PDF
A07.01_-_I_MOTCO_FORM_190-3_INSTRUCTIONS.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_2_of_7.pdf PDF
2-Appendices_1-16_MOTCO_Repair_Pier_3-Phases_II-III_6_of_7.pdf PDF
4-Atch_2_Supplemental_Contract_Requirements_MOTCO_Repair_Pier_3-Phases_II-III.docx DOCX document
A07.05_-_MOTCO_Form_190-3.XLSX XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 – SOW April 18, 2018

STATEMENT OF WORK

Repair Pier 3 – Phases II-III Military Ocean Terminal, Concord, CA

1. SCOPE OF WORK

Contractor shall provide all labor, materials, tools and equipment necessary for construction of this project titled Repair Pier 3 Phases II-III, Military Ocean Terminal, Concord, CA. Work includes pile wrapping and deck repairs of Pier 3 as indicated in this Request for Proposal (RFP). See project specifications and drawings for more details.

2. SAFETY REQUIREMENTS

In addition to Section 01 35 26 of the specifications, all installation safety regulations shall be followed. Comply with the most current edition of USACE EM 385-1-1, and all applicable federal, state, and local laws, ordinances, criteria, rules and regulations including but not limited to 29 CFR 1910 and 29 CFR 1926.

3. AUTHORITIES STATEMENT

Only a warranted Contracting Officer acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.

4. PROJECT SCHEDULE

Overall project construction should be scheduled to take place during regular business hours (Mon-Fri, 0730-1600 except federal holidays).

Contractor shall hold Periodic Schedule Update Meetings and Weekly Progress Meetings in accordance with Specification 01 32 01 PROJECT SCHEDULE.

5. CONTRACTOR MANPOWER REPORTING

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for USACE. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil.

6. UNSCHEDULED INTERRUPTIONS

Work operations are subject to delay by unscheduled interruptions and contractor personnel may be required to immediately leave the designated work area or be denied access due to security operations. Mission requirements may necessitate suspension or cancellation of custodial operations for a period of 10 days or 45 days, dependent on which delay option in this contract is exercised. All incomplete work shall be rescheduled for completion at a later time and date mutually agreed upon by the ACO, COR, POC, QA personnel, and the Contractor. The Period of Performance will also be adjusted accordingly.

7. SECURITY

Contractor is responsible for maintaining the site and all other Contractor controlled areas in such a manner as to minimize the risk of injury or accident to site personnel or others who may be in the area. Contractor is also responsible for furnishing an identification badge/card to each individual working on the site.

See project specifications for more details regarding security requirements.

8. POST-AWARD POINTS OF CONTACT

The Administrative US Army COE POC & ACO will be designated at the time of award. They will be responsible for verifying that the Contractors’ performance and completion of work is in accordance with applicable requirements.

APPENDICES

Appendix 1 – Drawings Appendix 2 – Specifications Appendix 3 – USFWS Biological Opinion Appendix 4 – MOTCO Explosives Safety Submission (ESS) Appendix 5 – DDESB Approval of ESS Appendix 6 – MEC Support During HTRW Appendix 7 – Routine Inspection Report Appendix 8 – Special Inspection Report Appendix 9 – Minimum Separation Distances Appendix 10 – Naval Magazines As-Builts Appendix 11 – Special Structural Inspection Appendix 12 – Naval Weapons Station As-Builts Appendix 13 – Structural Repair Appendix 14 – DDESB Technical Paper Appendix 15 – EM 385-1-97 Appendix 16 – iWatch Appendix 17 – Environmental Impact Statement (EIS)