Attachment 4 - Supplemental Condition Requirements

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARCF Natomas Reach I Contract 1 1793

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 05

SUPPLEMENTARY CONDITION REQUIREMENTS FOR REACH I - CONTRACT 1

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS

1.3.1 SCR-1 Location of Work

1.3.2 SCR-2 Scope of Work

1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of

Completion

1.3.4 SCR-4 Site Conditions

1.3.5 SCR-5 Lands and Right-of-Way

1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public

Agencies

1.3.7 SCR-7 Contractor's Tools and Equipment

1.3.8 SCR-8 Locking Gates

1.3.9 SCR-9 Water Source for Construction Operations

1.3.10 SCR-10 Cleaning Up

1.3.11 SCR-11 Protection of Existing Improvements

1.3.12 SCR-12 Record Drawings

1.3.13 SCR-13 Flood Emergency

1.3.14 SCR-14 Permits and Approvals

1.3.15 SCR-15 Dust Control

1.3.16 SCR-16 Fire Control

1.3.17 SCR-17 Air Pollution Control

1.3.18 SCR-18 Noise Control

1.3.19 SCR-19 Allowable Work Hours

1.3.20 SCR-20 Cultural Resources

1.3.21 SCR-21 Protection of Existing Trees

1.3.22 SCR-22 Biological Resources

1.3.23 SCR-23 Raptor and Migratory Birds

1.3.24 SCR-24 Wetlands and Sensitive Habitats

1.3.25 SCR-25 U.S. Fish and Wildlife Service

1.3.26 SCR-26 Speed Limit

1.3.27 SCR-27 Reclamation District 1000 (RD1000) Coordination

1.3.28 SCR-28 Provision Regarding Maintaining Minimum Flood

Protection During Construction

1.3.29 SCR-29 Coordination with the Contracting Officer and Utilities

Relocation

1.3.30 SCR-30 Haul Routes

1.3.31 SCR-31 Resource Coordination

1.3.32 SCR-32 Flood Contingency Plan

1.3.33 SCR-33 Utility Provider Response Plan

1.3.34 SCR-34 Stop Work Authority

1.3.35 SCR-35 Floodway Construction Schedule

1.3.36 SCR-36 High Visibility Fencing, Habitat Preservation and

Buffers

00 73 05 - 1

6 June 2018

1.3.37 SCR-37 General Safety Requirements

1.3.38 SCR-38 Storm Water Pollution Prevention Plan

1.3.39 SCR-39 Storm Water Data Report

1.3.40 SCR-40 Grading (Encroachment) Permit

1.3.41 SCR-41 Cobbles

1.3.42 SCR-42 Staging Area

1.3.43 SCR-43 Recreation/Community Mitigation - Reach I - Contract 1

1.3.44 SCR-44 City Streets - Reach I - Contract 1

1.3.45 SCR-45 Storage Area - Reach I - Contract 1

1.3.46 SCR-46 Project Signage

1.3.47 SCR-47 Traffic Control Plan

1.3.48 SCR-48 Reach I Disposal Sites

1.3.49 SCR-49 Stages and Sequence of Work

1.3.50 SCR-50 Construction Standby and Onsite Remobilization

1.3.51 SCR-51 City of Sacramento Encroachment Permit

1.3.52 Site Access and Fiber Optic Sensor Instillation Assist

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

00 73 05 - 2

SECTION 00 73 05

SUPPLEMENTARY CONDITION REQUIREMENTS FOR REACH I - CONTRACT 1

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D2488 (2017e1) Standard Practice for Description adn Identification of Soils (Visual-Manual Procedures)

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation. The following shall be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals; G

Permits and Approvals; G

Construction emission/dust control plan; G

Slurry Spill Prevention Plan; G

Flood Contingency Plan; G

Utility Provider Response Plan; G

Grading (Encroachment) Permit; G

Traffic Control Plan; G

Storm Water Data Report; G

Haul Route Permit; G

Storm Water Pollution Prevention Plan; G

1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS

1.3.1 SCR-1 Location of Work

The Natomas Basin is approximately 53,000 acres (82 square miles) and is situated north of downtown Sacramento. Reach I, which is situated mostly on

00 73 05 - 3

Garden Highway along the American River, is approximately 2.19 miles in length (STA 0+00 to STA 115+00). The Reach I Contract 1 project is from STA 0+00 to STA 115+00.

1.3.2 SCR-2 Scope of Work

The existing Garden Highway levee, along Reach I - Contract 1, is between 9 and 24 feet tall. Crown elevations vary between approximately 39 and 43 feet, including the pavement section. Landside toe elevations range from approximately 19 to 36 feet. The levee crown width varies from about 25 to 120 feet, with a typical width of 60 feet. The landside and waterside slopes range between approximately 1.1H: 1V to 3.6H: 1V (horizontal:

vertical).

A slag cement-cement-bentonite (SCCB) seepage cutoff wall will be installed with an approximate bottom elevation of -5.0 feet. The 30-inch wide SCCB cutoff wall will start by overlapping by approximately 50ft an existing cement-bentonite (CB) seepage cutoff wall which ends at approximately STA 3+01 near Gateway Oaks Drive and it will end at approximately STA 113+00.

Suitable soil from the excavation of the cutoff wall will be used to construct the Reach 19A seepage berm. If additional suitable soil remains after construction of the Reach 19A seepage berm, the soil will be placed at the Hewitt stockpile location.

A blanket drain will be installed from STA 16+72 to STA 24+02 consisting of a geotextile lined 24-inch thick layer of ASTM C33 sand beneath soil type 2 fill. From STA 19+42 to STA 21+59 the blanket drain's finished grade will be lined with a concrete slope and have a rock and sand mixture at the toe of the blanket drain. From STA 16+72 to STA 19+42 and from STA 21+59 to STA 24+02 the blanket drain will be covered with soil type 2 and have a permeable concrete toe.

Utility encroachments including water, sewer, electrical, and storm water sump station discharge lines will be relocated per the plans.

Access to the construction site will involve temporary partial and full shutdown of Garden Highway.

1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of Completion

The time of completion for this contract, which shall include all segments of work to be completed in their entirety and in accordance with the project plans and these specifications, shall be as outlined below and incorporated into the Contractor's schedule.

00 73 05 - 4

TIME CONSTRAINTS FOR REACH I - CONTRACT 1

Description of Work

Date of Completion

A. Contracting Officer and Resident Engineer's Office Facility

Installed and ready for occupancy not later than five (5) calendar days prior to start of construction or not later than fifteen (15) calendar days after Notice to Proceed, whichever occurs first

B. Traffic Control Plan Traffic Control Plan shall be approved and traffic control measures installed prior to the start of construction activities

C. Copies of Permits Contractor to provide to Contracting Officer within 10 days of receipt

D. Slurry Spill Prevention Plan

Submit to Contracting Officer 30 days prior to commencement of construction activities

E. Flood Contingency Plan including Flood Evacuation Plan for the waterside staging area

Submit to Contracting Officer 30 days prior to commencement of construction activities

F. Complete blanket drain and waterline relocations

31 October 2018

G. Complete cutoff wall and Garden Highway improvements (4" SSFM and Sump 58, Roadway and Bike Path improvements)

31 October 2019

H. Complete erosion control seeding of all areas

30 November 2019

I. Complete demobilization and site clean up of all areas

30 November 2019

J. Record Drawings Submit to Contracting Officer within 10 days after Government approval of working drawings

Cutoff wall and ground disturbance work along Garden Highway shall not begin before 15 April 2019. All construction activities along Garden Highway and the bike path, including the bike path access road near the I-5 bridge, from the west end of the project through the Natomas Park Drive intersection (STA 2+51 to STA 39+50 Control Line A) shall be completed and open for access (vehicular, bicycle, and pedestrian) prior to commencement of any construction activities that limit access (vehicular, bicycle, or pedestrian) between STA 39+50 and STA 113+00.

Garden Highway closure shall not exceed 6 months. Contractor shall provide monthly progress updates to the Contracting Officer for review.

00 73 05 - 5

1.3.4 SCR-4 Site Conditions

The Contractor shall satisfy himself or herself concerning the nature and location of the work; the general and local conditions, particularly those affecting transportation, disposal, handling and storage facilities;

availability of labor, water, power, communications, roads, climatic conditions and seasons; physical conditions at the job sites and Project areas as a whole; job-site topography and ground conditions; permits, equipment, and facilities needed preliminary to, and during, work prosecution; and all other matters which can in any way affect the work, including cost thereof. Failure of the Contractor to become acquainted with all available information regarding any applicable conditions will not relieve the Contractor from the responsibility for properly estimating either the difficulties or the costs of successfully performing the work.

1.3.5 SCR-5 Lands and Right-of-Way

The right-of-way for the construction work, as shown on the Plans, will be provided by the Government. The Contractor is responsible for obtaining land rights and easements for areas to be used for the Contractor's own convenience outside the right of way shown and footprint limits on the Plans and shall absorb complete liability for the use, and/or associated activities related to the use of such land. The Contractor is responsible for all work and costs associated with obtaining land rights and easements.

If the contractor receives land rights and easements outside of the construction limits, these rights shall be received in writing and shall be forwarded to the Government for their records. Contractor shall also receive release of liability of the Government for any damage to these addition areas in writing.

Compliance with environmental and cultural laws shall be followed by the contractor if using lands other than those identified by the Corps.

1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public Agencies

The Contractor shall allow the following Agencies and Jurisdictional public agencies unrestricted access to the project site at all times:

United States Army Corps of Engineers

California Department of Water Resources

Reclamation District 1000

Sacramento Area Flood Control Agency

County of Sacramento

City of Sacramento

Sacramento Area Sewer District

Central Valley Flood Protection Board

California State Department of Fish and Wildlife

United States Fish and Wild Life Service

00 73 05 - 6

National Marine Fishery Service

All Visitors shall comply with the safety requirement in the EM 385-1-1 and contractor safety plans. All Visitors shall coordinate with the onsite Government representative prior to visiting the job site.

1.3.7 SCR-7 Contractor's Tools and Equipment

The Contractor shall furnish all equipment, materials, tools, supplies, and manufactured articles required for the completion of the work in accordance with the Contract. The Contractor shall take the necessary precautions to secure tools and equipment from theft while on-site. The Government assumes no responsibility for lost, vandalized, or stolen equipment belonging to the Contractor, its subcontractors, or its employees.

1.3.8 SCR-8 Locking Gates

The Contractor shall take care to protect and operate any existing gates that control access to the Project right-of-way, in conformance with the Government, RD1000, and the City and County of Sacramento requirements.

These requirements include preventing passage through the gates of unauthorized persons and equipment during periods of Contractor use of the gates and locking the gates during non-construction periods, if so directed by the Contracting Officer.

1.3.9 SCR-9 Water Source for Construction Operations

Contractor is responsible for securing, and obtaining all water needed for the project for both potable uses and for construction purposes.

Contractor shall only use water from City of Sacramento system. Water shall not be pumped from the American River or Steelhead Creek.

Construction water should be reused onsite to the extent practical and disposed of in a manner consistent with the quality of the water after use. Excess water shall not be disposed of into any wetland, stream, river, or storm drainage without all applicable local and regulatory permitting.

Contractor shall be responsible for disposal of all construction water.

1.3.10 SCR-10 Cleaning Up

The Contractor shall dispose of all trash items in closed containers, which shall be removed at least once per day. Vegetative wastes shall be chipped and delivered to waste energy facilities, mulched, composted, or used for firewood and removed at least once per week.

1.3.11 SCR-11 Protection of Existing Improvements

Except as specified herein or as shown on the Plans, existing structures and utility lines shall not be disturbed, damaged, or undermined by the Contractor, except where in the opinion of the Contracting Officer it is essential to relocate such improvements. If relocation of any facility is required, the Contractor shall relocate the improvements to be at least equal in condition to the original. The Contractor shall take all necessary precautions to prevent any damage to existing facilities. Should damage or injury occur as a result of the Contractor's operations, the Contractor shall repair or replace such damaged facilities to the Contracting Officer's satisfaction at the Contractor's expense.

00 73 05 - 7

The Contractor shall repair any damage to public and private streets resulting from the Contractor's operations, as directed by the Contracting Officer. Repair shall be made per industry standards and conform to local jurisdictional requirements. Repairs shall be made at no additional cost to the Government.

1.3.12 SCR-12 Record Drawings

The Contractor shall maintain a neat and accurate marked set of working record drawings in accordance with Specifications. The record drawings shall be subject to the inspection of the Contracting Officer at all times and shall be kept current weekly with all work instructions, change orders, and construction adjustments shown thereon and initiated by inspection.

The Contracting Officer reserves the right to withhold progress payments, or portions thereof, if record drawings are not maintained as stated above.

1.3.13 SCR-13 Flood Emergency

In the event of a flood emergency requiring action by the jurisdictional flood control agencies prior to completion of the work, the Contracting Officer shall have the right to suspend the work in accordance with the General Specifications. Such suspension includes the right of the Contracting Officer to take over the Project to conduct flood protection activities. The flood emergency plan will be commenced when the H Street Gauge is reads 26 feet NGVD29 and is predicted to rise.

1.3.14 SCR-14 Permits and Approvals

The Contracting Officer has obtained various permits, agreements, and rights for performance of the work. These permits may be described more fully in other SCRs and these specifications. The Contractor will be required to obtain additional permits or be a signatory on the Contracting Officer obtained permits as noted throughout the specifications. The Contractor shall be responsible for complying with all conditions of the permits and agreements. Any delays to the Project resulting from the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time for such delays.

The Contractor is responsible for obtaining all environmental permits or use permits (including CALTRANS Encroachment Permit) required for easements to land being used for the Contractor's own convenience and for work within the State Right of Way. Any delays to the Project resulting from the lack of these additional permits or the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time or additional compensation for such delays. Copies of all permits obtained by the Contractor shall be given to the Contracting Officer within 10 days of receipt of permit. The contractor is responsible for paying all permit fees.

1.3.15 SCR-15 Dust Control

The Contractor shall comply with the provisions of Section 01 57 20 ENVIRONMENTAL PROTECTION of the Specifications. The Contractor shall prepare and submit a construction emission/dust control plan to the Contracting Officer and Sacramento Metropolitan Air Quality Management District (SMAQMD) and shall receive approval of the plan before groundbreaking. During the performance of the work, the Contractor shall

00 73 05 - 8 assume all responsibility for dust control and shall furnish all labor, equipment, and means required, and shall carry out proper and efficient measures wherever and as often as necessary to prevent the construction operations from producing dust in amounts harmful to persons, damaging to property, or causing a nuisance to persons living nearby or occupying buildings in the vicinity of the work, or as directed by the Contracting Officer. Dust control will be strictly enforced with particular emphasis on work areas adjacent to residential and agricultural properties. The curtailment of the construction activities as a result of inadequate dust control measures will not be considered an unavoidable delay. The Contractor shall suspend all grading operations when fugitive dust levels exceed levels specified by SMAQMD regulations or deemed unacceptable by the Contracting Officer. The Contractor is responsible for paying any fees assessed by SMAQMD.

1.3.16 SCR-16 Fire Control

No burning shall be allowed for any activities associated with this project.

Delivering removed vegetative material to compost or waste-to-energy facilities is encouraged. Land filling of material shall be minimized.

Smoking shall not be permitted in areas near flammable materials such as dry grass or in restricted areas as identified by the Contracting Officer.

Cigarette butts shall be placed in appropriate receptacles.

1.3.17 SCR-17 Air Pollution Control

The Contractor shall comply with the air pollution control protocols specified in Section 01 57 20 ENVIRONMENTAL PROTECTION of the Specifications. To the extent available, the Contractor shall use existing power sources for the Contractor provided trailers rather than temporary power generators. If existing power sources are unavailable, clean fuel, low-emission on-site stationary generator equipment shall be used.

Low-sulfur fuel shall be used for stationary construction equipment. The Contractor shall be responsible for arranging appropriate consultation with the Air Resources Board and the SMAQMD, to determine registration and permitting requirements before operating portable engines or portable engine-driven equipment at the project site.

1.3.18 SCR-18 Noise Control

The Contractor shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION of the Specifications to avoid and minimize noise impacts from the construction activities.

Before construction activity begins within 500 feet of one or more residences, the Contractor shall provide written notification to the potentially affected residents, identifying the type, duration, and frequency of activities. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if demolition noise levels are overly intrusive.

Before haul truck trips are initiated on roads within 600 feet of one or more residences, the Contractor shall provide written notification at least one day before to the potentially affected residents, identifying the hours and frequency of haul truck trips. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if haul truck noise levels are overly intrusive or

00 73 05 - 9 outside exempt daytime hours.

1.3.19 SCR-19 Allowable Work Hours

The Contractor shall limit construction activities to between the following hours on the following days for Reach I - Contract 1:

Construction shall be performed Monday through Saturday 7 AM to 6 PM and Sunday 9 AM to 6 PM.

Heavy machinery activity off of the levee is restricted to the staging area for one hour prior to 7:00 AM and for one hour after sunset (as posted in the newspaper or online) or 10:00 PM whichever occurs sooner. No other construction work will be allowed outside the above mentioned hours. Any extended work hours must be reflected in the Contractor's initially approved schedule for the Project.

1.3.20 SCR-20 Cultural Resources

The Contractor shall comply with protocols in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the Specifications.

Contractor shall conduct Construction Personnel Training for all on-site employees. If cultural resources are discovered during construction activities, Contractor shall cease work within 100 feet of the vicinity of the find and immediately contact the archaeologist, through the Contracting Officer, and cooperate with all pertinent mitigation procedures.

Construction personnel shall participate in a cultural awareness program, which will be provided by the USACE Archeologist at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.

1.3.21 SCR-21 Protection of Existing Trees

All trees of any kind inside the work limits and designated in the drawings as protect in place are to be protected. Contractor shall place protective barrier fencing where possible at the drip line around trees designated as protect in place in the drawings. All trees outside the work limits, of any kind, are not to be disturbed. Contractor shall place protective barrier fencing around trees adjacent to construction areas as directed by the Contracting Officer. If damaged by the Contractor, damaged trees and landscaping shall be replaced by Contractor or otherwise mitigated as directed by Contracting Officer at the Contractor's expense.

1.3.22 SCR-22 Biological Resources

The Contractor shall comply with the Section 01 57 20, ENVIRONMENTAL PROTECTION, of the Specifications to avoid and minimize effect upon endangered or sensitive species in the Project area. The Contractor shall schedule activities to comply with the provisions and provide required notice for surveys to be conducted by the Government's Environmental Representative. Construction personnel shall participate in an environmental awareness program, which will be provided by the USACE Biologist at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.

00 73 05 - 10

1.3.23 SCR-23 Raptor and Migratory Birds

The Contractor shall comply with the provisions of the Construction Contractor Protocols for Avoiding and Minimizing Impacts to Raptors, Special Status, and Other Nesting Birds, which are included in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the Specifications. If a nesting bird is found injured on the Project site, the Contracting Officer shall be notified immediately so the animal can be relocated to a either a wildlife care facility or a raptor recovery facility.

1.3.24 SCR-24 Wetlands and Sensitive Habitats

The Contractor shall not impact Wetlands and Sensitive Habitats.

1.3.25 SCR-25 U.S. Fish and Wildlife Service

A Biological Opinion has been issued by the U.S. Fish and Wildlife Service.

The Contract documents contain all of the terms and conditions from the Biological Opinion, and the Contractor is responsible for implementing all requirements and obligations stated in the Contract documents.

1.3.26 SCR-26 Speed Limit

The speed limit in all Project work areas and along levees shall be 15 m.p.h., except on county roads, city streets and highways. The Contracting Officer may also require that speed limits on project site be reduced further to ensure vibration limits, dust protocols or other criteria are not violated. The Contractor shall post, at a minimum, two speed limit signs at each end of the work zone.

1.3.27 SCR-27 Reclamation District 1000 (RD1000) Coordination

RD1000 is responsible for inspection and maintaining the existing levees and drainage facilities throughout the project area. The Contractor shall coordinate their work with RD1000 through the Contracting Officer, allowing RD1000 access to its facilities at all times.

The Contractor shall conduct the work so that RD1000 personnel and equipment are not prevented from access to and passage along the existing levees at all times for normal and emergency purposes.

1.3.28 SCR-28 Provision Regarding Maintaining Minimum Flood Protection During Construction

Contractor shall have all levee improvements planned for a construction season completed by the deadlines outlined in Time of Completion requirements as described in paragraph 1.3.3, SCR-3, herein. Contractor shall not disturb the existing levee system beyond the limits of construction. Disturbance includes but is not limited to roadways, ramps, pipes and/or utilities crossings, or excavations within the limits of construction. Stockpiling suitable construction materials is acceptable provided written approval is first obtain from the Contracting Officer.

1.3.29 SCR-29 Coordination with the Contracting Officer and Utilities Relocation

Contractor shall coordinate and cooperate with the Contracting Officer and all utility providers on relocation of any overhead and underground electrical, sewer, water and storm utilities within the limits of

00 73 05 - 11 construction that may hinder the performance of Contractor's construction activities. Contractor shall assist in coordination and work with the Contracting Officer such that the utilities are relocated in time not to delay and to allow for completion of improvements in accordance with the Time of Completion schedule. Unless the relocation is called for on the drawings, the cost of any relocations is the responsibility of the Contractor.

1.3.30 SCR-30 Haul Routes

All haul and access routes shall be existing public roads and maintenance roads, except for restrictions noted on the drawings. Stockpiling of construction materials, including portable equipment, vehicles, and supplies, shall be restricted to designated construction staging areas and work sites. Movement of heavy equipment to and from the Project site shall be restricted to load limit approved roadways. The Contractor's construction access points shall be limited to those shown on the Plans, defined in the Specifications, or as directed in the field by the Contracting Officer. Paved areas at these controlled access points shall be swept each day, or more frequently, as required by the Contracting Officer to control dust and clean up material tracked or spilled on said paved areas or roadways. The Contractor shall conform to all governing codes, laws, and ordinances.

Contractor shall obtain a Haul Route Permit. This permit shall consist of a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be the responsibility of the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.

1.3.31 SCR-31 Resource Coordination

All contact and coordination with the resource agencies shall occur through the Contracting Officer in coordination with the Government's environmental representative.

1.3.32 SCR-32 Flood Contingency Plan

In the event the water surface elevation of the adjacent river is forecasted by the State-Federal Flood Forecast Center to increase significantly for any reason, the Contracting Officer reserves the right to require the Contractor to stop excavation and to begin continuous operations to complete all partially completed section (s) of the levee embankment cutoff wall and drainage blanket. At least 15 days prior to any Levee Excavation, the Contractor shall submit a contingency plan outlining the contingency operations in the event that river elevations above the flood stage are forecasted. The contingency plan shall include the proposed measure to protect the landside areas which have a reduced level of protection due to construction activities. The plan shall include river stage monitoring, river stage at which the plan will be activated, material and equipment to be used in performance of the contingency plan, and

00 73 05 - 12 location, type and quantity of the stockpiled emergency material. The plan shall also include the length of levee, where stockpiled material will be stored, and the method for monitoring river elevations. The Contractor shall keep any levee degrade material on the project site for the duration of the construction period, protected from inclement weather, for use as emergency backfill as necessary. The Flood Contingency Plan shall be submitted to the Contracting Officer for review.

1.3.33 SCR-33 Utility Provider Response Plan

Contractor shall prepare and submit a Utility Response Plan to the Contracting Officer, Sacramento Area Sewer District (SASD), Sacramento Municipal Utility District (SMUD), Comcast, and the City of Sacramento.

Plan shall detail how utility locations are verified, provide protocol for coordination with Utility Providers, detail process on conducting required worker training for all on-site employees with respect to accidental utility damage, and provide utility provider emergency contact information. Contractor is responsible for coordinating any temporary utility services needs during construction, and shall assume all temporary utility services cost.

1.3.34 SCR-34 Stop Work Authority

The Contracting Officer, Administrative Contracting Officer, and Contracting Officer's Representative shall have the authority to immediately stop any activity that is not in compliance with the permits, and/or order any reasonable measure to avoid the unauthorized take of an individual of the Covered Species (e.g., giant garter snake, Swainson's hawk, valley elderberry longhorn beetle, Federally- and State-listed fish).

1.3.35 SCR-35 Floodway Construction Schedule

Contractor shall not perform any work within the existing floodway including all staging area activities, (i.e., waterside or within the American River Parkway) per the date restrictions in Time of Completion requirement herein and shall not begin any construction until evaluation of upstream conditions indicate that inundation of these areas is unlikely to occur.

1.3.36 SCR-36 High Visibility Fencing, Habitat Preservation and Buffers

Contractor shall provide high visibility fencing that shall be placed to prevent encroachment of construction personnel and equipment into areas outside of or adjacent to the project footprint that contain sensitive habitats, including at least 20 feet from the dripline of elderberry shrubs and up to 200 feet from the edge of aquatic features that are suitable giant garter snake habitat. K-Rails, if used, shall be used in areas noted on the drawings. The fencing shall be inspected by the Contractor before the start of each work day and shall be maintained until completion of the Project. The Contractor shall not remove the fencing until construction of the Project is completed. No insecticides, herbicides, or other chemicals that might harm the valley elderberry longhorn beetle or its host plant shall be used within 100 feet of the elderberry shrubs.

1.3.37 SCR-37 General Safety Requirements

The Contractor shall conform to all applicable occupational safety and health standards, rules, regulations, and orders established by the State of California or Federal Government. The Contractor shall, upon request, 00 73 05 - 13 submit to the Contracting Officer a copy of their Injury Illness Prevention Program (IIPP) (including Site Safety Plan and Code of Safe Work Practices) for review. The Contractor is required to fulfill the requirements of these programs during the prosecution of the Work, and comply with conditions set forth in the Specifications. The Contractor shall comply with all regulations set forth in Consolidated EM 385-1-1.

1.3.38 SCR-38 Storm Water Pollution Prevention Plan

Coverage under the State Water Resources Control Board (SWRCB) General Permit to Discharge Water Associated with Construction Activity shall be obtained by the Contractor for this Project prior to initiation of any construction activities. The Notice of Intent (NOI) shall comply with the Terms of the General Permit to Discharge Storm Water Associated with Construction Activity (WQ Order No. 99-08-DWQ) and/or (WQ Order No.

2009-0009-DWQ); contingent upon SWRCB direction at the time of filing. The Contractor shall develop and submit to the Contracting Officer a Storm Water Pollution Prevention Plan (SWPPP) and BMP's as part of SWPPP or as separate item to be implemented and maintained throughout construction per Contract requirements for the work in accordance with the state's guidelines and the Specification 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL that address the all pertinent SWPPP regulations. The Contractor shall implement the SWPPP prior to the start of soil-disturbing activity, and be responsible for all monitoring and maintenance until permanent erosion control has been established, as determined by the Contracting Officer. The SWPPP shall include Best Management Practices to prevent sediment, runoff from dust control, and oil and other chemicals used in construction from entering areas of wildlife habitat. The Contractor shall use fiber netting and other environmentally sound materials and methods as defined in Specification 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL.

The Contractor is responsible for paying all SWPPP fees.

1.3.39 SCR-39 Storm Water Data Report

Contractor shall develop and submit for approval a Storm Water Data Report (SWDR) per the California Department of Transportation's CalTrans Storm Water Quality Handbook - Project Planning and Design for all construction activities within CalTrans Right of Way.

1.3.40 SCR-40 Grading (Encroachment) Permit

Contractor shall obtain a Grading (Encroachment) Permit from City of Sacramento prior to initializing work. Copy of work permit shall be submitted to the Contracting Officer prior to disturbing ground.

1.3.41 SCR-41 Cobbles

Contractor should be aware that cobbles, as defined by ASTM D2488, may exist within the cutoff wall profile. No additional allowances will be allowed for working within and around cobbles.

1.3.42 SCR-42 Staging Area

Staging areas available to the Contractor for the project have been identified in the Drawings and permits have been obtained for them by the Government. If additional areas are available for use, they will be the responsibility of the Contractor to obtain.

Below is a list of expected activities that will occur inside of the

00 73 05 - 14

American River parkway staging area inside Discovery Park.

A. General Activities

1. The contractor will place temporary facilities (trailers) as well as daily parking for USACE construction manager, contractor staff and project visitors;

2. The temporary storage of miscellaneous items such as project fencing and salvaged guard rails may occur within the staging area.

B. Utility Relocation

1. Overhead utility relocation work performed by others will include the use of utility line trucks and require the temporary storage of conductor wire and utility poles;

2. Electrical transformer storage will not be allowed within the American River parkway;

3. Underground utility relocation work will require the temporary storage of earthwork spoils and the removed utility lines which include abandoned steel sanitary sewer force main (which currently serves Discovery Park), and PVC, steel and reinforced concrete pipe from abandoned water and storm drain pipes;

4. The City of Sacramento asbestos-cement water pipe removal will be performed by others and storage of the removed asbestos-cement pipe will not be allowed within the American River parkway.

C. Tree Removal Equipment and Materials

1. Equipment for removal of tress along the crown and landside slope and toe of the Garden Highway levee may be temporarily stored within the American River parkway;

2. Debris from downed trees may be temporarily stored within the American River parkway.

D. Earthwork Material and Equipment

1. The contractor may store road paving equipment within the American River parkway as well as aggregate base material for roadway placement;

2. The contractor will temporarily place earthwork spoils that include topsoil and levee embankment material from slope flatting activities.

E. Slag-Cement-Bentonite Slurry Wall

1. The contractor will not be allowed to locate, even if temporarily, the batch (mixing) plant and materials for the slurry wall within the staging area in the American River parkway;

2. The contractor will not place spoils from the cutoff wall excavation within the limits of the American River parkway staging area;

3. The mixing or preparation of controlled low strength material, or its raw materials, will not be allowed within the American River parkway.

F. Road Work Material and Equipment

1. The storage of asphalt-concrete paving removed for levee improvements will not be allowed within the American River parkway;

2. The contractor may store road paving equipment within the parkway as well as aggregate base material for roadway placement. Suitable impervious liner or tarping materials shall be placed under paving equipment to catch and allow removal of oils.

00 73 05 - 15

1.3.43 SCR-43 Recreation/Community Mitigation - Reach I - Contract 1

A minimum of two weeks prior to start of work Contractor shall provide written notification to various agencies (e.g. City of Sacramento DPW Representative) specified by the Contracting Officer as well as outreach to the immediate project neighbors advising of the work, duration, the days of the week work is to take place, and the hours to be worked for each day.

USACE and Contractor to provide, via posted signage, a USACE project manager name, contact number and e-mail address as well as a Contractor project manager name, contact number and e-mail address, for residents in the vicinity of the Premises should any concern from the immediate project neighbors arise with regard to noise, traffic, or other such disturbance which directly results from USACE's and/or Contractor's work. The purpose of USACE and Contractor posting their respective contact information is to avoid Construction Inspection and Survey staff having to field telephone calls and other inquiries related to USACE's and Contractor's work.

In addition, signage shall be posted at the entrances to bike paths affected, Gateway Oaks, Natomas Park Drive, Discovery Park and Garden Highway and other key access points one month prior to commencement of construction and shall remain in place during the duration of the project.

Signage shall provide information on the reduced or closed access to the bike path and shall direct parkway visitors to alternate access points. The signs shall include a general description of the type of repairs being constructed; the approximate dates of commencement and completion;

information on alternative access points to the bike paths; and the contact name and number of the Contractor's Project Manager. Signs shall be at least 3' x 4' in size and printed on sturdy cardboard stock or plywood.

Signage text shall be subject to the review and approval of the City's Representative prior to its installation.

1.3.44 SCR-44 City Streets - Reach I - Contract 1

The Contractor shall ensure that its construction equipment and hauling operations do not damage City streets. Prior to start of construction, Contractor shall photograph all city streets within the construction area and along all haul routes before construction operations begin.

Photographs shall be submitted to the Contracting Officer and the City Department of Public Works Representative, Jon Liffring, Supervising Construction Inspector, (the "DPW Representative"), (916) 808-7124, and will be used to compare before and after project conditions at the project's end. Any damage to the City streets caused by Contractor's operations must be repaired at Contractor's cost and to City's satisfaction. Contractor may request as-builts from the City of Sacramento for streets and appurtenances.

The Contractor shall notify and submit truck routes for review to the Contracting Officer and the DPW Government Representative prior to starting work. Furthermore, the Contractor shall provide the City Representative with a location for a wash out area to wash and clean Contractor's trucks, equipment and tires before they exit the construction area.

1.3.45 SCR-45 Storage Area - Reach I - Contract 1

Contractor shall erect chain link fencing a minimum of eight (8) feet tall around the perimeter of its storage area. The fencing shall post signage no smaller than 3' x 3' in size providing the Contractor's company name as well as a name and telephone number for Contractor who may be contacted by the public in general in the event that any issues arise out of the use of

00 73 05 - 16 the Premises. All material remnants need to be removed from the storage site. Otherwise, a protective barrier shall be placed between the ground surface and stockpiled materials. Upon conclusion of the work, or prior to the time period that the use of the staging area shall cease, whichever occurs first, Contractor shall return the site to a condition equal to or better than the condition it was in at the time the of the Contractor's entry into the site.

1.3.46 SCR-46 Project Signage

The Contractor shall provide all signage for the project. Sign wording, sizes and other parameters shall be coordinated with the Contracting Officer and/or his/her representative.

1.3.47 SCR-47 Traffic Control Plan

In lieu of the traffic plan provided as a part of these contract documents, the contractor may opt to submit an alternative Traffic Control Plan to USACE (SPK) and City of Sacramento for review and approval prior to commencing construction activities. At a minimum, the alternative Traffic Control Plan shall achieve the following objectives:

(1) Two-way bike lanes are to be provided during construction. A two-way bike lane is to be provided by closing off the Garden Highway south east-bound land and will be kept open between Gateway Oaks Drive and Natomas Park Drive during construction phasing. If the bike paths are adjacent to vehicle traveled lanes, then a temporary concrete barrier shall separate the two types of traffic.

(2) The northern entrance to Discovery Park at Natomas Park Drive and Garden Highway shall not be impacted by construction during their three main events. These events have not been scheduled, however they are generally scheduled for early May (Bassmaster Tournament), the second week of September (the California Brewers Festival) and the Third week of October (the Aftershock Music Festival). During construction the Discovery Park entrance will remain open except when the construction of the cutoff wall is crossing Natomas Park Drive. Temporary road reconstruction measures and plating shall be done to reopen the Natomas Park Drive entrance to Discovery Park for vehicle and bike access as soon as possible but no longer than 4 days after the closure of the intersection for cutoff wall construction.

(3) Where feasible, one westbound and one eastbound lane shall be provided on Garden Highway between Gateway Oaks Drive and Natomas Park Drive during construction. In the event only one lane can be kept open (e.g.

when actively trenching on Garden Highway and swing radius of trenching equipment is a concern) a two way, one lane access will be provided on Garden Highway with traffic controls in place.

(4) The contractor shall implement traffic control measures to ensure vehicles exiting I-5 onto Garden Highway do not back up onto I-5.

Full roadway closure between Truxel Rd. and Northgate Blvd. shall not occur until absolutely necessary for progress of the construction of the cutoff wall to continue to end of project.

1.3.48 SCR-48 Reach I Disposal Sites

The Contractor shall dispose of soil from cutoff wall excavation at the Reach 19A Seepage Berm, and if additional spoils are produced, the Hewitt

00 73 05 - 17

Ag Field and Site 19A, identified in the contract documents. If not enough soil is excavated from constructing the cutoff wall to construct the Reach 19A Seepage Berm to the neat lines shown on the plans, the Contractor shall coordinate with the Contracting Officer to determine the final configuration of the seepage berm.

1.3.49 SCR-49 Stages and Sequence of Work

The following describes the construction stages and sequence of work:

STAGE STATION DESCRIPTION

1 25+00 to 32+00 (Control Line B) Blanket Drain Construction including portion of 12" and 24" water main under blanket drain

2 19+00 to 32+00 (Control Line A) 12" and 24" Water Main Construction outside of Blanket Drain

3 13+00 to 27+00 (Control Line B) Cutoff Wall Construction

4 10+41 to 13+00 (Control Line B) Cutoff Wall Construction

5 30+10 to 41+50 (Control Line B) Cutoff Wall Construction

6 41+50 (Control Line B) to 39+00 (Control Line A)

Cutoff Wall Construction

7 37+50 (Control Line A) 4" SSFM Construction

8 39+00 to 50+50 (Control Line A) Cutoff Wall Construction

9 50+50 to 113+00(Control Line A) Cutoff Wall Construction

10 70+00 Sump 58 Discharge lines Construction

1.3.50 SCR-50 Construction Standby and Onsite Remobilization

In the event that Cultural Resources are discovered during construction the Contracting Officer may instruct the Contractor to stop work in accordance with these specifications. The Contracting Officer may also in the event of cultural resource discovery require the Contractor to restrict construction in a specific area of the project and relocate equipment and resume work at a distance of up to 300 feet from the restricted area. The restricted area will be determined by the Contracting Officer in consultation with the Government archeologist.

1.3.51 SCR-51 City of Sacramento Encroachment Permit

The Contractor shall obtain an Encroachment Permit for the City of Sacramento for work conducted per these Specifications and the Plans. The Encroachment Permit application is attached as an appendix to Section 00 73 05.

00 73 05 - 18

1.3.52 Site Access and Fiber Optic Sensor Instillation Assist

The Contractor shall allow access to representatives of the University of California, Berkley in order to install permanent fiber optic sensors in a portion of the cutoff wall between STA 13+50 to STA 27+00 and STA 30+10 to STA 38+50 of Control Line B. The fiber optic sensors will be installed in no more than two elements as defined in Specification Section 31 56 13 Slag Cement-Cement-Bentonite Cutoff Wall - Open Trench. The data collected using the fiber optic sensors will not be used to determine cutoff wall acceptance nor will the installation relieve the contractor of any of the requirements of the contract specifications and drawings. The Contractor must allow the installation of the fiber optic sensors after completion of full depth excavation of the cutoff wall element but prior to the initial set of the cutoff wall element. Following installation of the fiber optic sensors, the Contractor shall allow access to representatives of the University of California, Berkley to collect data near the installation location of the fiber optic sensors. Access afforded by the Contractor to representatives of the University of California, Berkeley at no cost to the Government. The Contractor may be requested to assist in lowering the fiber optic sensors into the cutoff wall element using either the long stick excavator or other available excavation equipment at the project site. The estimated time required will be two hours per element. The cost of this item is appurtenant to the Construction of the Project. No additional payment shall be made for allowing access to the site or assisting in the installation of the fiber optic sensor.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

00 73 05 - 19

Engineering Services Division

Development Engineering 300 Richards Blvd., 3rd Floor

Sacramento, CA 95811

Phone: 916-808-8300 Fax: 916-808-1984

CONSTRUCTION ENCROACHMENT PERMIT APPLICATION

AND PROCESSING INSTRUCTIONS

Submission to the City

***Work may begin only AFTER the City has issued the "CONSTRUCTION ENCROACHMENT PERMIT"***

INCOMPLETE APPLICATIONS PACKAGES W ILL NOT BE

ACCEPTED AND WILL BE RETURNED T O THE APPLICANT

1 of 12 2-15

Completed "Construction Encroachment Permit Application" Form 8 1/2" x 11" (or larger size) site plan – 4 copies Traffic Control Plan (also include pedestrian path of travel) – 4 copies List of active building permits for this location Proof of liability insurance on "Accord" Form AND "ADDITIONAL INSURED ENDORSEMENT" page Permit deposit/fee - $300 MINIMUM FEE Trench Cut Fee (if applicable)

Preparation of Application and Submittal Requirements

1. Completed "Construction Encroachment Permit Application" Form a). Type or neatly print all information in blanks on the "CONSTRUCTION ENCROACHMENT PERMIT APPLICATION" (See attached form on page 2).

2. Site plan (Submit 4 copies) a). Prepare a site plan that is neat, readable, fully dimensioned…