Attachment 1 - List of Drawings
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B01.01-Abstract_of_Bids.pdf | ||
| A07.01-18B0007_AMD_01.docx | DOCX document | |
| A07.01-Atch_03_Technical_Specifications_29June18.pdf | ||
| A07.01-18B0007_AMD_01.docx | DOCX document | |
| A07.01-Atch_04_Supplemental_Condition_Requirements_29June18.pdf | ||
| A07.01-Atch_06_DB_Wage_Determination_CA09_29Jun18.pdf | ||
| A07.01-Atch_03_Technical_Specifications.pdf | ||
| A07.01-Atch_04_Supplementary_Condition_Requirements.pdf | ||
| A07.01-Atch_05_Reach_I_GDR.pdf | ||
| CLIN_0001_Exhibit_A_List_of_Pay_Items.pdf | ||
| A07.01-Atch_06_DB_Wage_Determination_CA09_1Jun18.pdf | ||
| A07.01-Atch_02_Plans.pdf | ||
| A07.01-RIC1_IFB_Solicitation.docx.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCF Natomas Reach I Contract 1 1793
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15
LIST OF DRAWINGS
01/07
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1 Amendment 0001
6 June 2018
SECTION 00 01 15
LIST OF DRAWINGS
01/07
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING REVISION TITLE
NO. NO.
G-001 N/A COVER SHEET
G-002 N/A SHEET INDEX
G-003 N/A GENERAL NOTES (1 OF 2)
G-004 N/A GENERAL NOTES (2 OF 2)
G-005 N/A GENERAL SYMBOLS
G-006 N/A GENERAL ABBREVIATIONS
G-101 N/A LOCATION MAP
G-102 N/A CONTROL LINE PLAN AND CURVE TABLE
G-103 N/A CONSTRUCTION LIMIT PLAN
G-104 N/A CONSTRUCTION LIMIT LINE TABLES
G-105 N/A REACH 19A BERM SITE CONTROL LINE PLAN AND
CONSTRUCTION LIMIT PLAN AND LINE TABLE
G-106 N/A HAUL ROUTES AND STAGING AREAS
G-107 N/A SURVEY CONTROL MAP
V-101 N/A AERIAL PHOTO AND TREE REMOVAL STA 0+00 (CONTROL LINE A)
TO STA 25+00(CONTROL LINE B)
V-102 N/A AERIAL PHOTO AND TREE REMOVAL STA 25+00
TO STA 42+00(CONTROL LINE B)
V-103 N/A AERIAL PHOTO AND TREE REMOVAL STA 42+00
(CONTROL LINE B) TO STA 51+50(CONTROL LINE A)
V-104 N/A AERIAL PHOTO AND TREE REMOVAL STA 51+50
TO STA 68+50 (CONTROL LINE A)
V-105 N/A AERIAL PHOTO AND TREE REMOVAL STA 68+50
TO STA 85+50 (CONTROL LINE A)
V-106 N/A AERIAL PHOTO AND TREE REMOVAL STA 85+50
TO STA 102+00 (CONTROL LINE A)
V-107 N/A AERIAL PHOTO AND TREE REMOVAL STA 102+00
TO STA 115+00 (CONTROL LINE A)
V-108 N/A TREE INVENTORY TABLE (1 OF 4)
V-109 N/A TREE INVENTORY TABLE (2 OF 4)
V-110 N/A TREE INVENTORY TABLE (3 OF 4)
V-111 N/A TREE INVENTORY TABLE (4 OF 4)
CD-101 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 0+00
(CONTROL LINE A) TO STA 25+00 (CONTROL LINE B)
CD-102 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 25+00
TO STA 42+00(CONTROL LINE B)
CD-103 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 42+00
(CONTROL LINE B) TO STA 51+50(CONTROL LINE A)
DOCUMENT 00 01 15 Page 2
DRAWING REVISION TITLE
NO. NO.
CD-104 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 51+50
TO STA 68+50(CONTROL LINE A)
CD-105 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 68+50
TO STA 85+50(CONTROL LINE A)
CD-106 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 85+50
TO STA 102+00(CONTROL LINE A)
CD-107 N/A EXISTING TOPOGRAPHY AND DEMOLITION STA 102+00
TO STA 115+00(CONTROL LINE A)
C-001 N/A KEY MAP
C-101 N/A PLAN AND PROFILE STA 0+00 (CONTROL LINE A) TO
STA 16+50 (CONTROL LINE B)
C-102 N/A PLAN AND PROFILE STA 16+50 TO STA 25+00
(CONTROL LINE B)
C-103 N/A PLAN AND PROFILE STA 25+00 TO STA 33+50
(CONTROL LINE B)
C-104 N/A PLAN AND PROFILE STA 33+50 TO STA 42+00
(CONTROL LINE B)
C-105 N/A PLAN AND PROFILE STA 42+00 (CONTROL LINE B) TO
STA 43+00 (CONTROL LINE A)
C-106 N/A PLAN AND PROFILE STA 43+00 TO STA 51+50
(CONTROL LINE A)
C-107 N/A PLAN AND PROFILE STA 51+50 TO 60+00
(CONTROL LINE A)
C-108 N/A PLAN AND PROFILE STA 60+00 TO 68+50
(CONTROL LINE A)
C-109 N/A PLAN AND PROFILE STA 68+50 TO 77+00
(CONTROL LINE A)
C-110 N/A PLAN AND PROFILE STA 77+00 TO 85+50
(CONTROL LINE A)
C-111 N/A PLAN AND PROFILE STA 85+50 TO 93+50
(CONTROL LINE A)
C-112 N/A PLAN AND PROFILE STA 93+50 TO 102+00
(CONTROL LINE A)
C-113 N/A PLAN AND PROFILE STA 102+00 TO 110+00
(CONTROL LINE A)
C-114 N/A PLAN AND PROFILE STA 110+00 TO 115+00
(CONTROL LINE A)
C-201 N/A BLANKET DRAIN PLAN VIEW
C-202 N/A REACH 19A BERM AND STOCKPILE SITE PLAN
C-203 N/A HEWITT STOCKPILE SITE PLAN
C-204 N/A AMERICAN RIVER PARKWAY BIKE PATH CONNECTOR
C-301 N/A TYPICAL SECTIONS AND DETAILS (1 OF 6)
C-302 N/A TYPICAL SECTIONS AND DETAILS (2 OF 6)
C-303 N/A TYPICAL SECTIONS AND DETAILS (3 OF 6)
C-304 N/A TYPICAL SECTIONS AND DETAILS (4 OF 6)
C-305 N/A TYPICAL SECTIONS AND DETAILS (5 OF 6)
C-306 N/A TYPICAL SECTIONS AND DETAILS (6 OF 6)
C-307 N/A TYPICAL SECTIONS AND DETAILS - CUTOFF WALL CONSTRUCTION
SEQUENCING (1 OF 3)
C-308 N/A TYPICAL SECTIONS AND DETAILS - CUTOFF WALL CONSTRUCTION
SEQUENCING (2 OF 3)
C-309 N/A TYPICAL SECTIONS AND DETAILS - CUTOFF WALL CONSTRUCTION
SEQUENCING (3 OF 3)
C-310 N/A BLANKET DRAIN DETAILS
C-311 N/A MISCELLANEOUS DETAILS - (1 OF 2)
C-312 N/A MISCELLANEOUS DETAILS - (2 OF 2)
DOCUMENT 00 01 15 Page 3
NO. NO.
C-313 N/A REACH 19A SEEPAGE BERM TYPICAL SECTIONS AND DETAILS
C-501 N/A LEVEE CROSS SECTIONS STA 2+00 (CONTROL LINE A)
STA 10+00 TO STA 20+00 (CONTROL LINE B)
C-502 N/A LEVEE CROSS SECTIONS STA 21+00 TO STA 32+00
(CONTROL LINE B)
C-503 N/A LEVEE CROSS SECTIONS STA 33+00 TO STA 44+00
(CONTROL LINE B)
C-504 N/A LEVEE CROSS SECTIONS STA 45+00 TO STA 47+00
(CONTROL LINE B) AND STA 40+00 TO STA 48+00
(CONTROL LINE A)
C-505 N/A LEVEE CROSS SECTIONS STA 49+00 TO STA 60+00
(CONTROL LINE A)
C-506 N/A LEVEE CROSS SECTIONS STA 61+00 TO STA 72+00
(CONTROL LINE A)
C-507 N/A LEVEE CROSS SECTIONS STA 73+00 TO STA 84+00
(CONTROL LINE A)
C-508 N/A LEVEE CROSS SECTIONS STA 85+00 TO STA 96+00
(CONTROL LINE A)
C-509 N/A LEVEE CROSS SECTIONS STA 97+00 TO STA 108+00
(CONTROL LINE A)
C-510 N/A LEVEE CROSS SECTIONS STA 109+00 TO STA 115+00
(CONTROL LINE A)
C-511 N/A BERM CROSS SECTIONS STA 858+00 TO STA 863+00
C-512 N/A BERM CROSS SECTIONS STA 864+00 TO STA 868+00
B-001 N/A BORING LOG LEGEND AND NOTES
B-002 N/A BORING LOCATIONS (1 OF 2)
B-003 N/A BORING LOCATIONS (2 OF 2)
B-101 N/A CUTOFF WALL PROFILE AND BORING LOG OF EXPLORATION
STA 10+00 TO STA 36+00 (CONTROL LINE B)
B-102 N/A CUTOFF WALL PROFILE AND BORING LOG OF EXPLORATION
STA 36+00 TO STA 47+28.89 (CONTROL LINE B)
B-103 N/A CUTOFF WALL PROFILE AND BORING LOG OF EXPLORATION
STA 39+50 TO STA 67+00 (CONTROL LINE A)
B-104 N/A CUTOFF WALL PROFILE AND BORING LOG OF EXPLORATION
STA 67+00 TO STA 95+00 (CONTROL LINE A)
B-105 N/A CUTOFF WALL PROFILE AND BORING LOG OF EXPLORATION
STA 95+00 TO STA 115+81.12 (CONTROL LINE A) AND
STA 0+00 TO 5+00 (NEMDC BASELINE)
CU-101 N/A UTILITY PLAN STA 0+00 (CONTROL LINE A)TO STA 25+00
(CONTROL LINE B)
CU-102 N/A UTILITY PLAN STA 25+00 TO STA 42+00 (CONTROL LINE B)
CU-103 N/A UTILITY PLAN STA 42+00 (CONTROL LINE B) TO STA 51+50
(CONTROL LINE A)
CU-104 N/A UTILITY PLAN STA 51+50 TO STA 68+50 (CONTROL LINE A)
CU-105 N/A UTILITY PLAN STA 68+50 TO STA 85+50 (CONTROL LINE A)
CU-106 N/A UTILITY PLAN STA 85+50 TO STA 102+00 (CONTROL LINE A)
CU-107 N/A UTILITY PLAN STA 102+00 TO STA 115+00 (CONTROL LINE A)
CU-108 N/A 4-INCH SANITARY SEWER FORCE MAIN RELOCATION PLAN AND
PROFILE STA 10+00 TO STA 17+00
CU-109 N/A WATER MAIN RELOCATION PLAN AND PROFILE (SHEET 1 OF 3)
STA 298+00 TO 305+50
CU-110 N/A WATER MAIN RELOCATION PLAN AND PROFILE (SHEET 2 OF 3)
STA 305+50 TO STA 313+00
CU-111 N/A WATER MAIN RELOCATION PLAN AND PROFILE (SHEET 3 OF 3)
STA 400+00 TO STA 400+88.6
CU-112 N/A SUMP 58 DISCHARGE LINES RELOCATION PLAN AND PROFILE
DOCUMENT 00 01 15 Page 4
NO. NO.
STA 1+00 TO STA 3+00
CU-113 N/A UTILITY DETAILS (1 OF 5)
CU-114 N/A UTILITY DETAILS (2 OF 5)
CU-115 N/A UTILITY DETAILS (3 OF 5)
CU-116 N/A UTILITY DETAILS (4 OF 5)
CU-117 N/A UTILITY DETAILS (5 OF 5)
CP-001 N/A TRAFFIC HANDLING PLAN GATEWAY OAKS DRIVE/
WEST EL CAMINO AVE INTERSECTION
CP-002 N/A TRAFFIC HANDLING PLAN BETWEEN GATEWAY OAKS DRIVE AND
NATOMAS PARK DRIVE (1 OF 2)
CP-003 N/A TRAFFIC HANDLING PLAN BETWEEN GATEWAY OAKS DRIVE AND
NATOMAS PARK DRIVE (2 OF 2)
CP-004 N/A TRAFFIC HANDLING PLAN GARDEN HIGHWAY/NATOMAS PARK DRIVE
INTERSECTION
CP-005 N/A TRAFFIC HANDLING PLAN WESTBOUND GARDEN HIGHWAY WATER
MAIN RELOCATION
CP-006 N/A TRAFFIC HANDLING PLAN GARDEN HIGHWAY BLANKET DRAIN
CP-007 N/A TRAFFIC HANDLING PLAN PRIVATE DRIVEWAY CLOSURE
CP-008 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY BETWEEN
GATEWAY OAKS PARK DRIVE AND 1-5 SOUTHBOUND RAMPS
CP-009 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY/NATOMAS PARK DRIVE
INTERSECTION
CP-010 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY BETWEEN NATOMAS
PARK DRIVE AND TRUXEL ROAD
CP-011 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY I-5 NORTHBOUND
RAMPS AND TRUXEL ROAD
CP-012 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY TRUXEL ROAD AND
NORTHGATE BLVD
CP-013 N/A TRAFFIC DETOUR PLAN GARDEN HIGHWAY/I-5 NORTHBOUND RAMPS
WATER MAIN RELOCATION
CP-014 N/A TRAFFIC DETOUR PLAN EASTBOUND GARDEN HIGHWAY WATER MAIN
RELOCATION
CP-015 N/A TRAFFIC DETOUR PLAN NATOMAS PARK DRIVE FORCE MAIN
RELOCATION
CP-101 N/A ROAD PLAN AND PROFILE STA 0+00 TO STA 8+00
(CONTROL LINE A)
CP-102 N/A ROAD PLAN AND PROFILE STA 32+00 TO STA 42+50
(CONTROL LINE A)
CP-103 N/A ROAD PLAN AND PROFILE STA 42+50 TO STA 52+50
(CONTROL LINE A)
CP-104 N/A ROAD PLAN AND PROFILE STA 52+50 TO STA 62+50
(CONTROL LINE A)
CP-105 N/A ROAD PLAN AND PROFILE STA 62+50 TO STA 72+50
(CONTROL LINE A)
CP-106 N/A ROAD PLAN AND PROFILE STA 72+50 TO STA 82+50
(CONTROL LINE A)
CP-107 N/A ROAD PLAN AND PROFILE STA 82+50 TO STA 92+50
(CONTROL LINE A)
CP-108 N/A ROAD PLAN AND PROFILE STA 92+50 TO STA 102+50
(CONTROL LINE A)
CP-109 N/A ROAD PLAN AND PROFILE STA 102+50 TO STA 114+00
(CONTROL LINE A)
CP-201 N/A SIGNING AND STRIPING PLAN STA 0+00 TO STA 17+00
(CONTROL LINE A)
CP-202 N/A SIGNING AND STRIPING PLAN STA 17+00 TO STA 34+00
(CONTROL LINE A)
DOCUMENT 00 01 15 Page 5
NO. NO.
CP-203 N/A SIGNING AND STRIPING PLAN STA 34+00 TO STA 51+50
(CONTROL LINE A)
CP-204 N/A SIGNING AND STRIPING PLAN STA 51+50 TO STA 68+50
(CONTROL LINE A)
CP-205 N/A SIGNING AND STRIPING PLAN STA 68+50 TO STA 85+50
(CONTROL LINE A)
CP-206 N/A SIGNING AND STRIPING PLAN STA 85+50 TO STA 102+00
(CONTROL LINE A)
CP-207 N/A SIGNING AND STRIPING PLAN STA 102+00 TO STA 116+13
(CONTROL LINE A)
CP-208 N/A SIGNING AND STRIPING PLAN GATEWAY OAKS DRIVE/WEST
EL CAMINO AVE INTERSECTION
CP-301 N/A ROAD TYPICAL SECTIONS (1 OF 2)
CP-302 N/A ROAD TYPICAL SECTIONS (1 OF 2)
CP-401 N/A ROAD TYPICAL DETAILS
CP-402 N/A CONSTRUCTION DETAIL AZUSA STREET ACCESS ROAD
S-101 N/A GENERAL STRUCTURAL NOTES
S-102 N/A TYPICAL CONCRETE REINFORCING DETAILS
S-103 N/A SUMP 58 VAULT STRUCTURAL DETAILS
S-104 N/A SUMP 58 VAULT STRUCTURAL DETAILS - ACCESS COVER DETAILS
S-105 N/A 24" WATER MAIN VAULT STRUCTURAL DETAILS
S-106 N/A 24" WATER MAIN VAULT STRUCTURAL DETAILS - ACCESS COVER
DETAILS
-- End of Document --
DOCUMENT 00 01 15 Page 6
| 00 01 15 - LIST OF DRAWINGS |
| 00 01 15 - LIST OF DRAWINGS |