ProjNET Inquiries with Government Responses. *NOTE* The Government's responses are not incorporated into the solicitation/contract. Refer to Amendment No.: 01 issued August 9, 2017 for material changes to the solicitation (and contract) terms and conditions.

View the file

Other files for this federal contract opportunity

Other files attached to Hamilton City Phase 2A Construction Project, newest first.
File Type Posted
A07.02-Atch_02_Specifications_9Aug17.pdf PDF
A07.01-Atch_03_Davis_Bacon_Wage_Determination_4Aug17.pdf PDF
A07.02-Atch_04_Plan_Sheet_G-111_9Aug17.pdf PDF
A07.02-17R0040_AMD_01.pdf PDF
A07.05-Site_Visit_Sign_In_Roster.pdf PDF
A07.01-Atch_01_Plans_1of2.pdf PDF
A07.01-Atch_01_Plans_2of2.pdf PDF
A07.01-Atch 02 Specifications 8May2017.pdf PDF
A07.01-Solicitation.pdf PDF
A07.01-Atch_03_Davis_Bacon_Wage_Determination_7Jul17.pdf PDF
A07.01-Atch_01_Plans_8May2017.7z 7Z file
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Technical Evaluators Report Closed Inquiries

Project: Hamilton City, CA - FY16 Phase 2A Hamilton City Flood Damage Reduction and Ecosystem Restoration Project (P2# 448794) Review: Hamilton City FY16 Phase 2A (Key Access) (2 -28 Jun 2017) (00001) (sorted by CommentID ) Displaying 33 inquiries.

Id Discipline Sheet Detail Spec 7076574 General G-111 Earthwork 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Do you have quantities for Borrow Area Sites A-E, and GCID Intake Facility?

Then the contractor will know how much dirt will have to be obtained from the Floodplain Borrow Areas.

On: Jul 24 2017.

Requires Amendment.

Forward request by email.

2-1 Government Response. Estimated volume of in place material at Borrow Areas A - E and at the GCID Intake Facility Borrow Area total approximately 190,000 cubic yards. This volume does not take into account required topsoil stripping of the borrow areas. Amendment forthcoming. On: Aug 01 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7076610 Construction Phasing G-001 01 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Is the Earthwork expected to start in the Spring of 2018?

What is the completion date?

On: Jul 24 2017. Forward request by email.

2-1 Government Response. Performance of the contract shall begin after issuance of the Notice to Proceed and be completed within the time frame identified in Block 11 of the Standard Form 1442 and as reiterated at clause 52.211-10. See Section 01 32 01 for specifications regarding "Project Schedule." On: Aug 01 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7087949 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

RFP section 5.3 Factor 1: Past Performance (Page 22 of 75) states "recency is defined as completed projects within the last 5 years." Will the Government accept substantially complete projects, meaning projects currently at 90% or more completion within the last 5 years?

Page 1 of 12ProjNet: Logged In User

8/10/2017https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminClosedR...

On: Jul 31 2017.

2-1 Government Response. Section 00 21 16 - Instructions to Proposers, paragraph 5.3.1.a will be revised to define recency as "completed projects within the last 10 years." Amendment forthcoming. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7087950 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

RFP section 5.3 Factor 1: Past Performance (Page 22 of 75) states "recency is defined as completed projects within the last 5 years." Due the unique and specific scope of work, will the government consider projects completed within the last 9 years so long as the scopes are relevant to this project?

On: Jul 31 2017.

1-1 Government Response. See response to Inquiry ID 7087949. On: Aug 03 2017

Current Request Status: Request Closed Information for this report is procurement sensitive.

7089472 Contracting 31 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• CLIN 0002, Clearing and Grubbing.

Please clarify what areas will be included in the measurement for payment. For example, will all areas within the construction limits be paid for regardless of what type, if any, of vegetation exists? Or will only ground disturbance areas be paid for? Will areas that only have grasses or are bare of vegetation be excluded from measurement? If measurement for payment will be only for areas that have brush or trees will the area for payment include only the area under the drip line of the trees or some additional area beyond the drip line?

On: Aug 01 2017. Forward request by email.

1-1 Government Response. Section 01 22 00 - 5, para. 1.3.1.1 states "Payment will be made for CLIN 0002 and 1002... which price will include costs associated with providing all labor, equipment, tools, supplies and incidentals necessary to complete the Clearing, Grubbing... as specified in Section 31 11 00 Clearing and Grubbing." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089476 Contracting 31 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• CLIN 0002, Clearing and Grubbing Will the area of the GCID borrow areas be paid for under the CLIN for clearing and grubbing?

On: Aug 01 2017. Forward request by email.

1-0

Page 2 of 12ProjNet: Logged In User

1-1 Government Response. Reference the Government's reply for Inquiry ID: 7089472 regarding Clearing and Grubbing. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089523 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• CLIN 0004, Topsoil Stripping Will the topsoil stripping within the GCID borrow areas be paid for under the CLIN for topsoil stripping?

1-1 Government Response. Yes, the cost of borrow area topsoil stripping is included in CLIN 0004 Topsoil

Stripping. See specification citations below.

Section 01 22 00, paragraph payment for Topsoil Stripping will be for "costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to complete the TOPSOIL STRIPPING as specified in section 31 00 00 EARTHWORK."

section 31 00 00 EARTWORK, para. 3.1.2, "Topsoil must be stripped from all areas to be excavated (including borrow sites)..." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089526 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• CLIN 0013, Embankment Fill We suggest that this CLIN include the work for the embankment only and that a CLIN be added for GCID borrow excavation and a CLIN be added for waterside borrow excavation.

1-1 Government Response. Thank you for your suggestion. Based on Section 01 22 00 - 8, para. 1.3.10.1, payment will be made for CLIN 0013 and 1013... which price will include costs associated with providing all labor, equipment, tools, supplies and incidentals necessary to construct the new embankment fill including filling the levee embankment and ramps as specified in Section 31 00 0... and as shown on drawings." This measurement and payment sufficiently describes all effort associated with the new embankment fill and therefore no new CLIN is anticipated. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089530 Contracting 01 22 00 .1.4.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 22 00.1.4.1 As written, the language of measurement for Construction Standby, is confusing. Please clarify.

Page 3 of 12ProjNet: Logged In User

1-1 Government Response. Please specify what is confusing. On: Aug 03 2017

Information for this report is procurement sensitive.

7089534 Contracting 01 22 00 .1.5 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 22 00 -1.5 OPTION 3

As written the scope of work is very unclear. Are we to include the cost of developing a new staging area, installing additional fencing, relocating the Contracting Officer's Office (and we assume the contractor's facilities), moving onsite equipment to a new area and then moving everything back to its original area on the project? And, relative to Option 3, what is the meaning of the last sentence in paragraph 1.5.1.1 that reads "Payment also includes full compensation for all cost associated with mobilization (60 percent) and demobilization (40 percent)"? Are we to duplicate our bid price for CLIN 0001 in addition to the costs for other work specified in CLIN 3001 for each of the 5 occurrences?

1-1 Government Response. Please reference Section 00 70 00, DFARS 252.236-7004 on page 68 of 75 which addresses Payment for Mobilization and Demobilization. The risk for discovery of cultural resources is higher in the Sacramento Valley including Hamilton City. In the event of a cultural resource discovery, the Government may exercise this option to require the contractor to move from one portion of the project site to another at the contractor's proposed price. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089538 Contracting 01 35 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 35 26 – 1.5.1.1 SITE SAFETY AND HEALTH OFFICER (SSHO)

Most small business contractors cannot justify the cost to employee a full time person that is qualified to serve as a SSHO on this project. And if they do, and that person resigns the position or is dismissed, the contractor most certainly would have to replace that person with an independent contractor or a person hired through an employment service company. Will USACE accept a SSHO that is not on the contractor's payroll?

1-1 Government Response. Section 01 35 26 - 10, para. 1.5.1.1 states "the contractor must employ a minimum of one competent person at each project site to function as the SSHO..." The intent is that the SSHO must be an employee of the prime contractor. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089541 Contracting 01 45 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 45 00 – 13.4.2 CQC SYSTEM MANAGER

The majority of small business contractors do not have enough engineering or supervisoral persons on their payroll that they can afford to dedicate one of those persons as a CQC manager and still retain the capability to manage their projects. And if they do, and that person resigns the position or is dismissed, the contractor most certainly would have to replace that person with an independent contractor or a person hired through an employment service company. Will USACE accept a CQC system manager that is not on the contractor's payroll?

Page 4 of 12ProjNet: Logged In User

1-1 Government Response. Section 01 45 00 - 6, para. 3.4.2 requires the contractor to "identify as CQC

System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the contractor..." The intent is that the CQC System Manager be employed by the prime contractor. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089545 Contracting 01 50 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 50 00 – 2.2.4 COUNTY ENCROACHMENT PERMIT

Has USACE obtained an encroachment permit from Glenn County? If not, the bidders for this contract cannot include the cost of any unforeseen conditions the County may place on the successful contractor.

Also, given that GCID borrow areas C, D, E, and F are adjacent to State Highway 45 has USACE contacted Caltrans to determine what conditions it may place on the Contractor?

1-1 Government Response. USACE has not obtained an encroachment permit. Section 01 50 00, para. 2.2.4 requires the contractor to "obtain and adhere to an encroachment permit." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089547 Contracting 01 57 20 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 57 20 – 1.11 AIR RESOURCES

There appears to be a conflict between paragraph 1.11.4 that states that the NOx emission threshold is 85 pounds per day and paragraph 1.11.5 that states the NOx threshold is 25 pounds per day. Please clarify.

On: Aug 01 2017.

Forward request by email.

2-1 Government Response. The correct threshold is given in paragraph 1.11.5, 25 lbs. per day. The error in paragraph 1.11.4 will be corrected in a forthcoming amendment. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089548 Contracting 01 57 20 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 01 57 20 – 1.14.3.1 WESTERN YELLOW BILLED CUCKOO

Are there any areas designated as potential habitat for the yellow-billed cuckoo?

8/10/2017www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicAdminClosedR...

1-1 Government Response. In general, Hamilton City is a potential site for western yellow billed cuckoo habitat. However, there are no known habitats within the footprint of this project. That being said, if a habitat is discovered during the prosecution of this contract, the measures identified in Section 01 57 20 - 19, para. 1.14.3.1 will be implemented. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089551 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• Note 11 on plan sheet CD301 states that borrow areas A, B, and C contain little or no usable borrow. Is the bidder to assume that sampling and testing of these areas will not be required and that no borrow material from those sites will be used?

2-1 Government Response. The intent of note 11 is to make the Contractor aware that no all areas designated as borrow areas contain usable fill, but may be used for stockpiling of topsoil/fill.

Section 31 00 00 - 6, para. 2.2.1 requires the Contractor to submit a "Borrow Site Soil Sampling Work Plan" within 7 days after the notice to proceed and at least 30 days prior to the sampling activities at any borrow site..." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089552 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 - 2.2.1 EMBANKMENT FILL MATERIAL

The second sentence of the third paragraph of this section stages that "The contractor must perform additional pre-construction sampling and testing of the borrow sites to further define their suitability for use on this project."

However, the specification does not state how many samples are to be taken. We request that the frequency of sampling in the borrow areas be defined. Because the number of samples and tests may not be quantifiable at this time we suggest that a CLIN be added to pay for each sample taken and tested.

1-1 Government Response. Section 31 00 00 - 11, para. 2.2.1 states, "The Government has performed limited testing... The contractor must perform additional testing... to further define their suitability for use on this project." This intent is to require the contractor to take the tests necessary to determine suitability.

Documentation of the borrow site sampling and testing will be captured in the "Borrow Site Soil Sampling Work Plan to be submitted within 7 days after the Notice to Proceed." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089554 Contracting 31 00 00

Page 6 of 12ProjNet: Logged In User

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 - 2.2.1 EMBANKMENT FILL MATERIAL

When will the decision be made as to when the borrow material is usable or not? The specification for embankment material (first paragraph of this specification) is very restrictive. The contractor will bear a lot of risk if the quality of the borrow material is inconsistent and the material is not approved until placed in embankment and tested.

If the contractor encounters pockets of unusable material that were not identified by the specified sampling program he and the Government will not know that until after the material is placed in the embankment and the QC tests are complete. That could entail removal of previously placed embankment and open up the subject of how to dispose of the unusable material.

We request that the specification be changed to allow for the embankment material to be accepted based on the results of the testing performed in the borrow areas.

2-1 Government Response. Reference the reply to Inquiry ID: 7089552. On: Aug 03 2017

Information for this report is procurement sensitive.

7089555 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 – 2.2.1 EMBANKMENT FILL MATERIAL

We request that the specification define the minimum size, or quantity, of contiguous borrow area the contractor would have to excavate. Obviously it would not be productive if the contractor was made to chase small pockets of usable material. Also, the excavation of pockets of material would result in a lot of additional work to re-grade the areas to drain properly.

1-1 Government Response. Please refer to the Government's reply to Inquiry ID: 7089552 On: Aug 03 2017

Information for this report is procurement sensitive.

7089557 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 – 2.2.1 EMBANKMENT FILL MATERIAL

Where will unusable material encountered in the Observation Trench, or other excavations, be disposed of?

1-1 Government Response. Section 31 00 00 para. 3.7 states, "Unsatisfactory materials removed from excavations must be stockpiled for disposal."

Section 01 00 00 para. 1.21 requires the contractor to "locate a reliable commercial disposal site, and secure a disposal site as needed for the project." On: Aug 03 2017

Page 7 of 12ProjNet: Logged In User

Information for this report is procurement sensitive.

7089559 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 – 3.4 OVER-EXCAVATION OF EXISTING DITCHES AND GRAVEL ROADS

How will this excavation be paid for?

1-1 Government Response. Payment for over-excavation is captured by Section 01 22 00, para. 1.3.10.1, "Payment will be made for CLIN 0013 and 1013 "EMBANKMENT FILL" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to construct the new EMBANKMENT FILL, including filling the Levee Embankment and Ramps, as specified in section 31 00 00 EARTHWORK and as shown on the Drawings." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089563 Contracting 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 – 3.3 EXCAVATION OF OBSERVATION TRENCH

If the Government's geotechnical engineer requires that the observation trench be deepened will the additional excavation be paid for as by a contract modification? Just paying for the additional excavation under the CLIN for Observation Trench Excavation would not be justifiable because the type of equipment and the productivity would most likely be much different than the planned work. In lieu of paying for the additional excavation by modification you could add a CLIN for "Over-excavation of Observation Trench".

1-1 Government Response. Thank you for the recommendation. However, an additional CLIN as suggested by this inquiry will not be added. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089599 Cost Engineering 31 00 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 00 00 – 3.6 GROUND SURFACE PREPARATION

Assuming through no fault of the contractor, if the Government's geotechnical engineer determines that the prepared subgrade is not appropriate for supporting the new fill, will the work required to correct the condition, and then re-compact and re-test the subgrade, be paid for as a change given that there is no pay item for such work?

1-1 Government Response. The Government will administer the contract based on the contract's terms and conditions. Should a situation arise as described in your inquiry, the Government will consider the facts presented at the time, and make a determination in accordance with the contract's terms and conditions.

On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089604 Contracting 31 11 00

Page 8 of 12ProjNet: Logged In User

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

• 31 11 00 – 1.4 IRRIGATION SYSTEMS and -3.6 IRRIGATION SYSTEMS REMOVAL In the specifications and on Plan Sheets C-101 through C-113 reference is made to existing irrigation systems that have to be removed in their entirety. Given that there is no possible way for a bidder to estimate the size, length, and depth of the existing irrigation systems we request that the Government more clearly define this work and how it is to be paid for.

A typical detail for the work is needed to define the excavation and backfill limits depending on the size of the pipe encountered. We also believe that the Government should add a CLIN to quantify the excavation and backfill quantities so that the contractor can be fairly compensated for the actual work completed.

1-1 Government Response. Paragraph 1.4 of Section 31 11 00 defines the expected extents of the irrigation systems. The removal extents will be modified as part of a forthcoming amendment. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7091140 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

As of today, August 2, 2017, we have not received answers to any RFIs. In accordance with FAR, Offerors shall be provided adequate time to review the RFI responses and finalize an approach based on the answers. In order to minimize risk to the Government, we respectfully request that the government postpone the proposal due date 14-calendar days from the day all RFIs are answered. This will provide time for Government answers, as well as allowing Offerors time to review and adjust proposals based on changes resulting from RFI answers.

On: Aug 02 2017. Forward request by email.

1-1 Government Response. Section 00 20 00 - Instructions for Procurement, Inquiries, paragraph 'C' (page 7 of 75) states the bidder inquiry system will be unavailable for new inquiries 10 days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7093531 Contracting Section 31 11 00 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will the contractor be allowed to mix chipped material from clearing and grubbing with the salvaged topsoil?

On: Aug 03 2017. Forward request by email.

1-1 Government Response. No, mixing chipped material from clearing and grubbing with salvaged topsoil will not be permitted. Section 31 11 00, para. 3.7 states that "all timber on the project site noted for clearing and grubbing must become the property of the contractor, and must be removed from the project site and disposed of." On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7093847 Contracting 01 22 00 .1.4.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please reference ProjNet ID #7089530. In the response the Government asked the bidder to specify what is confusing.

Page 9 of 12ProjNet: Logged In User

One thing that is confusing is the definition of a "Day". If the contractor's crew is actively working and the Contracting Officer stops that crew during the work shift for 4 hours until the CO orders the work to resume is that a day or a partial day or not day at all under this CLIN?

Another possibility is that a "day" for the purposes of this CLIN is intended to be for a 24 hour period in which the CO has ordered that no work is to be performed at all.

Please clarify.

On: Aug 03 2017. Forward request by email.

1-1 Government Response. The Government's intent is not to exercise this option and order the contractor to resume work on the same calendar day. The risk for discovery of cultural resources is higher in the Sacramento Valley including Hamilton City. In the event of a cultural resource discovery, the Government may exercise this option to require the contractor to standby at the contractor's proposed daily price (not to exceed 30 calendar days) while the Government completes the necessary consultation with the State Historic Preservation Office. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7095094 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The time frame stated only allows offerors 6 working days to review and adjust to RFI answers, request subcontractor bids, receive competitive quotes, wrap-up the cost estimate, and prepare and ship the package, due on August 15, 2017, in light of this, we would respectively request a 14-day extension for this proposal to allow a more realistic and reasonable time frame for preparation and shipping of the proposal.

On: Aug 04 2017. Forward request by email.

1-1 Government Response. Please refer to the response for Inquiry ID 7091140. For most solicitations we issue, the FAR requires that solicitations be issued for a minimum of 30 days. Mission requirements as well as the scope, size and complexity of the project factor into the determination as to whether or not a solicitation should be issued for greater than 30 days. We consider these aspects well in advance of issuing the solicitation as the FAR requires that every acquisition have an acquisition plan. Considering those aspects of this project, we have determined 30 days to be reasonable. Historically, we close ProjNET for submission of new inquiries 10 days prior to proposal due date. Generally speaking, we have found great success with these timeframes. While we are sensitive to the pressures offerors are under to submit timely proposals, in this case, we have determined that it is not in the Government's best interest to extend the proposal due date at this time. On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7095101 Contracting General Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Page 10 of 12ProjNet: Logged In User

Will the Government accept a VERY RELEVANT project of essentially the same type of magnitude of effort and complexities this solicitation requires, that is 90% complete?

On: Aug 04 2017. Forward request by email.

1-1 Government Response. Please refer to Section 00 21 16, para. 5.3.1.a as revised via Amendment 01 dated 8/9/2017. Recency is defined as "completed projects within the last 10 years." On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7096468 Civil CD301 Note 7 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Reference Note number 7 on Sheet CD301 which states that "Borrow material from the GCID Intake Facility Borrow Area and Borrow Areas A thru E must be prioritized for use to the maximum extent possible." We interpret this statement that these borrow areas (assuming that the required testing demonstrates that these materials are satisfactory) are to be depleted in their entirety before utilizing the Floodplain Borrow Area. Please verify whether this interpretation is correct. If not correct, please clarify the intent of this note.

On: Aug 05 2017. Forward request by email.

1-1 Government Response. Maximum extent possible means that all satisfactory material determined to be available in the GCID Intake Facility Borrow Area and Borrow Areas A thru E via required borrow area testing must be used prior to use of any floodplain borrow material. On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7096469 Civil G-111, CD303 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Reference Sheets G-111 and CD303 which show the Floodplain Borrow Areas. Does the Government have an estimate of the volume of borrow available at the Floodplain Borrow Areas? If not, can the Government provide topographic data for the Floodplain Borrow Areas in order for the contractors to assess how much borrow material is available?

1-1 Government Response. Reference Sheet G-111 as revised via Amendment No.: 01 dated 8/9/2017, estimated bulk volume of material available in the floodplain borrow areas is approximately 100,000 cubic yards. On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7096471 Civil C-502 Over-Excavation Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Reference Sheet C-502, Existing Ditch And Gravel Road Over-Excavation Detail. Please clarify how the over-excavation volumes are measured and paid and in which CLIN this over-excavation will be paid.

Page 11 of 12ProjNet: Logged In User

1-1 Government Response. Per previous response to similar inquiry, "Payment for over-excavation is captured by Section 01 22 00, para. 1.3.10.1, "Payment will be made for CLIN 0013 and 1013 "EMBANKMENT FILL" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to construct the new EMBANKMENT FILL, including filling the Levee Embankment and Ramps, as specified in section 31 00 00 EARTHWORK and as shown on the Drawings."

On: Aug 03 2017 " On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7096473 Civil 32 92 33-1.6.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Reference Specification 32 92 33, Grass Seeding and Erosion Control, paragraph 1.6.1, Grass Seeding Times, which includes the statement "Where it is not possible or practical to seed and establish an acceptable stand of grass by 1 October, provide temporary erosion and sediment control measures to all bare and disturbed soil so that the soil is adequately protected while the grass is maturing." Is the application of straw mulch over hydroseeded areas an acceptable form of temporary erosion and sediment control in lieu of erosion control blankets and straw wattles?

1-1 Government Response. Please refer to paragraph 2.1.1.6 Straw Mulch of section 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL, specifically reference CASQA CABMPHE Straw Mulch, EC-6 On: Aug 10 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete