Attachment No.: 02 Specifications, revision dated 8/9/2017. This volume supersedes all previous versions. See FAR 52.252-3, Alterations in Solicitation for specific changes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A07.06-ProjNET_Inquiries_w_GOV_reply.pdf | ||
| A07.02-17R0040_AMD_01.pdf | ||
| A07.01-Atch_03_Davis_Bacon_Wage_Determination_4Aug17.pdf | ||
| A07.02-Atch_04_Plan_Sheet_G-111_9Aug17.pdf | ||
| A07.05-Site_Visit_Sign_In_Roster.pdf | ||
| A07.01-Atch_01_Plans_1of2.pdf | ||
| A07.01-Atch_01_Plans_2of2.pdf | ||
| A07.01-Atch_01_Plans_8May2017.7z | 7Z file | |
| A07.01-Atch_03_Davis_Bacon_Wage_Determination_7Jul17.pdf | ||
| A07.01-Atch 02 Specifications 8May2017.pdf | ||
| A07.01-Solicitation.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION STATEMENT A
Approved for public release; distribution is unlimited
HAMILTON CITY FLOOD DAMAGE REDUCTION &
ECOSYSTEM RESTORATION PROJECT
PHASE 2A
GLEN COUNTY, CALIFORNIA
SPECIFICATION NO. 1589
DESIGN FILE NO. 50-04-6340
Hamilton City FDR and ER Phase 2A 1589
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 22 00 MEASUREMENT AND PAYMENT
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 62 35 RECYCLED / RECOVERED MATERIALS
01 71 10 MOBILIZATION AND DEMOBILIZATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND REMOVAL
02 82 10 FENCING
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00 AGGREGATE SURFACE COURSE
32 92 33 GRASS SEEDING AND EROSION CONTROL
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
10/10
PART 1 GENERAL
1.1 PAYMENT
1.2 REFERENCES
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
1.4 SUBMITTALS
1.5 GENERAL SAFETY REQUIREMENTS
1.5.1 General
1.5.2 The Prime Contractor's Superintendent
1.5.3 Violations
1.6 SECURITY
1.7 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.7.1 Monthly Anticipated Adverse Weather Delays
1.7.2 Operations During the Flood Season
1.8 EQUIPMENT DATA FORM
1.9 HOURS OF OPERATION
1.10 BID ITEM OVERRUN
1.11 WARRANTY OF CONSTRUCTION
1.12 NON CONTRACT WORK
1.13 DAMAGE TO ROADS
1.13.1 Documentation Regarding Potential Damage to Access Routes
1.13.1.1 Preconstruction Access Road Survey
1.13.1.2 Post-Construction Access Road Survey
1.14 SPECIAL SURVEY PROCEDURES
1.14.1 Survey Services
1.14.2 Survey Supervision and Scheduling
1.14.3 Personnel Plan
1.14.4 Special Survey Conditions - Preconstruction Survey Cross
Sections
1.14.5 Post Construction Surveys
1.15 SPECIAL CONSTRUCTION CONDITIONS
1.15.1 Points of Contact for River Discharge Data
1.15.2 River Gaging Stations
1.15.3 Groundwater
1.15.4 Project Security and Public Safety
1.15.5 Cooperation With Others
1.15.5.1 Agricultural Spraying
1.15.5.2 Other Government Contractors
1.16 MEETINGS
1.16.1 Preconstruction Meetings
1.16.2 Weekly Coordination Meetings
1.16.3 Contractor Quality Control Coordination Meeting
1.16.4 Preconstruction Safety Conference
1.17 WATER
1.18 UTILITIES
01 00 00 - 1 Amendment 0001
1.18.1 Pacific Gas and Electric (PG&E)
1.19 DESIGNATED BORROW SITES
1.20 COMMERCIAL BORROW SITE
1.21 COMMERCIAL DISPOSAL SITE
1.22 HAUL ROUTE PLAN
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIALS
PART 3 EXECUTION
3.1 AFTER AWARD DOCUMENTS
3.1.1 Hard Copies of Plans
ATTACHMENTS:
CESPK FORM 450
-- End of Section Table of Contents --
01 00 00 - 2
SECTION 01 00 00
GENERAL REQUIREMENTS
10/10
PART 1 GENERAL
1.1 PAYMENT
No separate payment will be made for the work covered under this section and all costs in connection therewith will be considered a subsidiary obligation.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EM 1110-1-1005 (2007) Control and Topographic Surveying
ER 415-1-15 (1989) Construction Time Extensions for Weather
U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT (CESPK)
CESPK FORM 450 (1992) Contractor Equipment Data Sheet
DM 4-805-10 (1991) Survey Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1926 Safety and Health Regulations for Construction
1.3 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx
01 00 00 - 3
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heros Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heros http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house _business_council_-_guide_to_hiring_veterans_0.pdf
1.4 SUBMITTALS
Government approval is required for all submittals with a "G" designation;
submittals not having a designation are for information only. The following must be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Preconstruction Quantity Survey Plan; G
Personnel Plan
Preconstruction Survey Cross Sections
Preconstruction Access/Haul Road Survey
Disposal Site Plan; G
Haul Route Plan; G
Borrow Source Plan; G
Hard Copies of Plans
Equipment List
SD-11 Closeout Submittals
Post-Construction Access/Haul Road Survey
Haul Road Repairs; G
1.5 GENERAL SAFETY REQUIREMENTS
1.5.1 General
For information regarding specific Safety Requirements see Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Refer to EM 385-1-1, Contract Clauses, and the Occupational Safety and Health Act (OSHA) Standards for Construction 29 CFR 1926; General Industry Standards 29 CFR 1910; and the National Fire Protection Association Codes are applicable to this
01 00 00 - 4 contract. In case of conflict the most stringent requirement of the standards is applicable.
1.5.2 The Prime Contractor's Superintendent
The Prime Contractor's superintendent must take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis (see below), tool box meetings, walk-through inspections, correction of violations, etc., and including that of the subcontractor's work.
1.5.3 Violations
If recurring violations and/or gross violation indicate that the safety performance is unsatisfactory, corrective action must be taken as directed, and at the discretion of the Contracting Officer the retention or some part thereof will be withheld from the progress payment until corrective action has been completed.
1.6 SECURITY
The project location may be particularly subject to vandalism. Materials left on-site are done so at the Contractors' risk, and if lost, at the Contractor's expense. Provide security for all the work. Particularly, construct and maintain the signs, including but not limited to, those necessary for Public Safety and Traffic Control, as specified in Section 6 of the General Provisions. Replace those signs damaged or destroyed due to vandalism at no additional expense to the Government.
1.7 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.7.1 Monthly Anticipated Adverse Weather Delays
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
01 00 00 - 5
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK
STATE CALIFORNIA INSTALLATION/NOAA MARYSVILLE STATION
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
7 6 5 4 1 0 0 0 1 2 5 7
Upon execution of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
Refer to ER 415-1-15.
Flow conditions in the Sacramento River will not be considered as adverse or unusually severe weather and no time extension to the contract will be granted to the Contractor for this circumstance.
1.7.2 Operations During the Flood Season
Construction activities are permitted during the flood season (November 1 to April 15), weather permitting.
1.8 EQUIPMENT DATA FORM
Furnish CESPK FORM 450 for all necessary equipment to perform work requiring adjustment of contract price and must submit these forms with the modification proposals. A sample form is at the end of this section.
1.9 HOURS OF OPERATION
Construction activities on weekdays Monday through Friday, including equipment warm-up, will be limited to daylight hours but not earlier than 7:00 A.M. and not later than 7:00 P.M. Construction activities on Saturdays, including equipment warm-up, will be limited to daylight hours, but not earlier than 8:00 A.M. and not later than 6:00 P.M. The Government must be given 48 hours notice prior to working on any Saturday.
Construction activities on Sunday are limited to daylight hours for scheduled maintenance only, but not earlier than 9:00 AM and not later than 6:00 PM. Construction activities are not permitted on Federal holidays. A list of Federal holidays for any given year can be found at:
https://www.opm.gov/policy-data-oversight/snow-dismissal-procedures/federal-holidays Submit requests for work hour variations a minimum 10 working days prior to the desired change to Contracting Officer and thier represtative for approval. Work hours are the discretion of the local jurisdiction therefore additional limits on hours operations may be imposed during this construction event. The Contractor will be notified a minimum of 10 working days prior to such changes.
1.10 BID ITEM OVERRUN
Throughout the contract (at a minimum, every five calendar days), monitor placement or installation of unit price items (if any) with respect to the original estimated quantities shown in the contract. If placement or
01 00 00 - 6 installation indicates a possible overrun with respect to the original estimated quantities shown in the contract, immediately provide written notification to the Contracting Officer with revised total estimated quantities.
1.11 WARRANTY OF CONSTRUCTION
(a) Performance Bond.
(1) It is understood that the Contractor's Performance Bond will remain effective throughout the life of all warranties and warranty extensions.
(2) In the event the Contractor or his designated representative fails to commence and diligently pursue any work required under the Warranty of Construction Section of the Technical Provisions within a reasonable time after receipt of written notification pursuant to the requirements thereof, the Contracting Officer has a right to demand that said work be performed under the Performance Bond by making written notice on the surety. If the surety fails or refuses to perform the obligation it assumed under the Performance Bond, the Contracting Officer must have the work performed by others, and after completion of the work, make demand for reimbursement of any or all expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
(3) Warranty repair work which arises to threaten the health or safety of personnel, the physical safety of property or equipment, or which impairs operations, habitability of living spaces, etc., will be handled by the Contractor on an immediate basis as directed verbally by the Contracting Officer or his authorized representative. Written verification will follow verbal instructions. Failure of the Contractor to respond as verbally directed will be cause for the Contracting Officer or his authorized representative to have the warranty repair work performed by others and to proceed against the Contractor as outlined in the paragraph b. above.
(b) Pre-Warranty Conference. Prior to contract completion and at a time designated by the Contracting Officer or his authorized representative, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of SECTION 00 73 00 SUPPLEMENTARY CONDITIONS, Paragraph, WARRANTY OF CONSTRUCTION, of this specification. Communication procedures for Contractor notification of warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer or his authorized representative for the execution of the construction warranty will be established/reviewed at this meeting.
In connection with these requirements and at the time of the Contractor's quality control completion inspection, the Contractor will furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue warranty work action on behalf of the Contractor. This single point of contact will be located within the local service area of the warranted construction, will be continuously available, and will be responsive to Government inquiry on warranty work action and status. This requirement does not
01 00 00 - 7 relieve the Contractor of any of his responsibilities in connection with Section 00 73 00 SUPPLEMENTARY CONDITIONS, Paragraph, WARRANTY OF
CONSTRUCTION.
(c) Equipment Warranty Identification Tags. Provide warranty identification tags on all equipment installed under this contract.
(d) Contractor's Response to Warranty Service Requirements. The following warranty service requirements are applicable to this contract.
Following notification by the Contracting Officer or the Contracting Officer's Representative, respond to a warranty service requirement identified by the Contracting Officer's Representative in accordance with the "Warranty Service Priority List" of this program. This list prioritizes warranty work into the categories:
First Priority 1A Perform on site inspection to evaluate situation, determine course of action, initiate work within 24 hours and work continuously to completion or relief.
Second Priority 1B Perform on site inspection to evaluate situation, determine course of action, initiate work within 48 hours and work continuously to completion of relief.
Third Priority All other work to be initiated within 5 work days and work continuously to completion or relief.
The "Warranty Service Priority List" must be compiled by the Contractor and approved by the Contracting Officer.
Should parts be required to complete the work and the parts are not immediately available provide the Contracting Officer's Representative with firm written proposals for emergency alternatives and temporary repairs for Government participation within 12 hours after arrival at the job site, and provide emergency relief until the required parts are available on site for the Contractor to perform permanent warranty repair. Include a firm date and time that the required parts must be available on site to complete the permanent warranty repair. The Contracting Officer's Representative will evaluate the proposed alternatives and negotiate the alternative considered to be in the best interest of the Government to reduce the impact of the emergency condition. Alternatives considered by the Contracting Officer's Representative will include the alternative for the Contractor to "Do Nothing" while waiting until the required parts are available to perform permanent warranty repair. Negotiating a proposal which will require Government participation and the expenditure of Government funds must constitute a separate procurement action by the using service.
1.12 NON CONTRACT WORK
Do not perform any work or erect any structure for third parties, landowners or otherwise, within the limits of the rights-of-way without prior approval of the Contracting Officer.
1.13 DAMAGE TO ROADS
Preserve and protect all existing private or project access or right-of-way roads. At the completion of work and prior to the Contractor leaving the project, he must restore to pre-project conditions all such roads and
01 00 00 - 8 provide documentation of Haul Road Repairs. Repairs must include replacement of base rock and/or surface treatment as required. Refer also to paragraph PROTECTION OF TRAFFIC in section 01 50 00 TEMPORARY
CONSTRUCTION FACILITIES AND CONTROLS.
1.13.1 Documentation Regarding Potential Damage to Access Routes
1.13.1.1 Preconstruction Access Road Survey
Complete and submit a Preconstruction Access/Haul Road Survey including digital video and digital photographs of all public, private, and project access or right-of-way roads. Submit two copies of the survey, the digital video, and the digital photographs before the start of construction operations. Video must be digital format.
1.13.1.2 Post-Construction Access Road Survey
After completion of construction of the project, submit a Post-Construction Access/Haul Road Survey including digital video and digital photographs of the same area where Preconstruction digital video and digital photographs were taken. Submit two copies of the survey, the digital video, and digital photographs.
1.14 SPECIAL SURVEY PROCEDURES
1.14.1 Survey Services
Perform all survey services in accordance with EM 1110-1-1005. This publication can be downloaded from: EM_1110-1-1005.pdf
1.14.2 Survey Supervision and Scheduling
Submit a Preconstruction Quantity Survey Plan of the proposed preconstruction quantity survey. All survey services must be performed by or under the direct supervision of a person licensed to practice surveying in the State of California. Prior to commencement of survey work, submit in writing the name and license number of the person who will perform the required surveys. Keep field notes in accordance with DM 4-805-10. The accuracy of the survey must be third order or better.
1.14.3 Personnel Plan
Plan stating the specific personnel names, license numbers, and specific tasks of those who will be performing the Preconstruction Survey Cross Sections, plus the procedures to be followed in conducting the Preconstruction Survey Cross Sections.
1.14.4 Special Survey Conditions - Preconstruction Survey Cross Sections
Survey cross sections along the entire length of the construction site, including all borrow areas planned to be used, and submit Preconstruction Survey Cross Sections before construction begins. Use these Preconstruction Survey Cross Sections to reflect existing ground before any construction activities begin and when measuring pay quantities for clearing and grubbing, topsoil stripping, excavation, riprap, and embankment fill, and grass seeding and erosion control. Use the Preconstruction Survey Cross Sections for measurement of work specified in SECTION 31 00 00 EARTHWORK. Survey cross sections perpendicular to the Construction Reference Line. Survey the cross sections within 2 feet of the locations
01 00 00 - 9 specified herein. Take the Preconstruction Survey Cross Sections at 50 foot intervals along the Construction Reference Lines shown on the drawings. Perform a profile survey of the top of the levee. Use this survey to show the elevations of the top of the levee shown on the plan and profile sheets.
Cross sections along the Construction Reference Line must extend from 25 feet landward of the landside levee toe, across the Construction Reference Line, and continue out to a point at least 25 feet waterward of the waterside toe of the levee.
Elevations must be taken at inflection points but at not more than 10 feet intervals. Horizontal and vertical accuracy must be to the nearest 0.1 foot. Horizontal locations must not deviate from the alignment of the cross section line by more than 1 foot. All cross sections must be plotted as viewed in the downstream direction. The survey data must be provided to the Contracting Officer on IBM-formatted CD ROM disks containing survey control and cross section points defined in the form of north and east coordinates and their elevations (i.e. X, Y and Z). Horizontal control must be referenced to the California Zone II, North American Datum (NAD) of 1983. Vertical control must be the National Geodetic Vertical Datum (NGVD) of 1929. Survey data must be provided in english units in either Microstation V8i 3D design file format (*.DGN), or AutoCAD 2013 or newer format (*.DWG). All data collected as part of the survey and all data used in the generation of digital terrain model surfaces (including, but not limited to point files and landxml files) for comparison to post construction surveys and generation of quantities must be included in the submittal.
Provide 2 CD/DVD of the electronic survey data files (including, but not limited to, CADD files, point data, etc.), and 2 sets of the cross section data, plotted as viewed in the downstream direction, with a 20 horizontal X 10 vertical grid, on a standard ANSI D size drawing sheet, at a scale of 1:10, horizontal and vertical. Preparing any needed layout drawings.
Black line prints from PDF files are acceptable.
If the results of the Preconstruction Survey Cross Sections show significant (15 percent or more) erosion than on the contract drawings, meet with the Contracting Officer to resolve the differences and use the Preconstruction Survey Cross Sections results to adjust designs as necessary.
1.14.5 Post Construction Surveys
Each post construction survey must be of the same scope as its corresponding preconstruction survey. Survey cross sections must be taken at the same interval and locations and must cover the same extents as the preconstruction survey cross sections. All data collected as part of each survey, used to generate quantities, and generated in the preparation of the submittal must be provided to the government.
1.15 SPECIAL CONSTRUCTION CONDITIONS
1.15.1 Points of Contact for River Discharge Data
The site is subjected to regulated discharges on the Sacramento River.
Contact the following individual with the U.S. Bureau of Reclamation to obtain flow forecasting information for planning construction activities.
The forecasts are updated monthly toward the middle of the month and
01 00 00 - 10 provide monthly average values. Daily flows are subject to variability in response to changing water demands.
Sacramento River Operations Mr. Paul Fugitani 916-979-2197
1.15.2 River Gaging Stations
Water surface elevation data is available for the stream gages operated by the Department of Water Resources. Obtain data from the California Department of Water Resources, California Data Exchange Center (CDEC) web site http://cdec.water.ca.gov. River forecasts available on the CDEC Website address is http://cdec.water.ca.gov/rivforecasts.html
The Government does not guarantee the reliability or accuracy of the hydrographs and will assume no responsibility for any deductions, conclusions, or interpretations that may be made from them. Undertake any such studies that are deemed necessary to assess the reliability and accuracy of the information presented in the hydrographs.
1.15.3 Groundwater
Groundwater at the site is expected to be near the same level as the Sacramento River water surface except when there is a rapid rise or decrease in the river, where the groundwater level will eventually follow by some unknown period of time.
1.15.4 Project Security and Public Safety
Require all visitors to abide by all construction site safety requirements. Notify the Contracting Officer 48 hours before the commencement of any physical activities on the site. Site security and the protection of equipment and materials is the responsibility of the Contractor for the duration of the contract.
1.15.5 Cooperation With Others
Provide a weekly update of planned construction activities and traffic operations for distribution by the Government to local agricultural stakeholders and landowners within and adjacent to the project site.
Annual harvest operations from late summer through the end of October are expected to produce significant agricultural equipment and truck traffic immediately adjacent to the project site including along designated haul/access routes. Stay within the designated haul/access routes as shown on the drawings. The designated haul/access routes are not project exclusive and the construction operation must not interfere with others.
Also see paragraph UTILITIES of this section for additional information on coordination with utility companies.
1.15.5.1 Agricultural Spraying
The agricultural land surrounding the project is subject to spraying of different chemicals by multiple application methods (i.e. land based or aerial spraying) throughout the year. Coordinate with the Agricultural Spray contact provided below for agricultural spray schedules, locations, and buffer zones of applied spray. Plan and adjust work activities
01 00 00 - 11 according to the spray schedules and recommended spray buffer zones.
Agricultural Spray Contact:
Cliff Kitayama 26 Kingsburry Ct Chico, CA 95926 cykit49@gmail.com Office:(530) 894-1360 Mobile:(530) 720-0035
1.15.5.2 Other Government Contractors
Other Government Contractors will be working in the vicinity of the project site and will require access to the land on the waterside of the setback levee. These other Contractors will be performing orchard removal and regular spraying for weed control purposes in the areas waterward of the Limits of Work shown in the Drawings. Coordinate with these other Government Contractors and gauranteee their access through the project site to their features of work.
1.16 MEETINGS
There may be other meetings required by this contract or unforeseen circumstances not indicated below.
1.16.1 Preconstruction Meetings
Arrange a preconstruction meeting as specified in Contract Clause 52.236-26 Preconstruction Conference.
1.16.2 Weekly Coordination Meetings
Schedule, prepare and distribute agenda and administer the weekly coordination meeting throughout of the project. The purpose of these meetings is to review the actual progress and planned activities for the upcoming two weeks. The weekly progress meeting will address the status of the SWPPP, Environmental concerns, RFI's and Submittals. The meeting is to be facilitated by the Contractor's CQCM, and attended by the superintendent, SSHO, USACE Engineering and construction field personnel, and any partners or sponsors who would like to attend. Meeting attendes will be coordinated with the Contracting Officer's Representative.
1.16.3 Contractor Quality Control Coordination Meeting
See section 01 45 00 QUALITY CONTROL regarding the obligation to set up the Quality Control Coordination Meeting.
1.16.4 Preconstruction Safety Conference
See SECTION 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS Paragraph titled Site Safety and Health Officer (SSHO) regarding the obligation to set up the Preconstruction Safety Conference and hold safety meetings.
1.17 WATER
Water and associated equipment required for dust control must be supplied by water trucks.
01 00 00 - 12
1.18 UTILITIES
Plan to accommodate the relocation, removal, or raising of known electrical utilities by Pacific Gas & Electric (PG&E) concurrently with setback levee construction. All PG&E relocations are expected to occur within the first half of the contract period of performance. Immediately notify the Contracting Officer in writing of any unidentified utilities encountered that may interfere with construction operations, within the construction limits. Identify the location of discovered utilities that were not shown on the plans and not visible as of the date of this contract. Notify the Contracting Officer at least 30 days in advance of the date on which work will be started which requires the removal or relocation of such unidentified utilities or private improvements. Care must be taken to preserve and protect any such improvements from injury or damage during construction operations. Construction operations which cause damages to personal property, utilities, public lands or interference of services must be fully reimbursed by the Contractor. Should such damage be found to have been caused without the Contractor's fault or negligence an equitable adjustment in the amount due under the contract will be made under the applicable CONTRACT CLAUSES.
1.18.1 Pacific Gas and Electric (PG&E)
Prior to commencing any work in the vicinity of the PG&E 10" natural gas transmission pipeline, provide to both the Government and PG&E an equipment list detailing data on all equipment planned to be operated in the vicinity of the pipeline. Depending on the equipment planned for use, more stringent coverage requirements than those given on the Drawings may be imposed by PG&E over their pipeline. Compliance with more stringent requirements, should they be necessary, is mandatory.
1.19 DESIGNATED BORROW SITES
Embankment fill and random fill, as defined in section 31 00 00 EARTHWORK, must be acquired from the designated Borrow Areas A, B, C, D, and E and the GCID Intake Facility Borrow Area shown on the drawings to the maximum extent possible. Once those borrow areas are depleted, fill material may be acquired from the designated Floodplain Borrow Areas, as shown on the Drawings.
1.20 COMMERCIAL BORROW SITE
In the case that the designated borrow sites defined in section 31 00 00 EARTHWORK and as shown on the Drawings do not provide adequate amounts of borrow for completion of the project, locate a reliable commercial borrow site, and secure Import Fill, as defined in section 31 00 00 EARTHWORK, as needed for the project. Comply with requirements defined in the plans, specifications, and contract documents in the selection and use of the commercial borrow site and materials. Comply with all applicable local, state, and federal regulations in the selection and use of the borrow site and activities associated with removal of borrow material.
Prior to beginning construction work submit a Borrow Source Plan to the Contracting Officer. Include the location of borrow site(s), as well as copies of borrow site current and valid NEPA/CEQA documentation, applicable Federal, State and Local permits. Provide certification to the Contracting Officer that the borrow material is free from contaminants and is suitable for use on the project. Prepare and submit the Borrow Source Plan at no additional cost to the Government.
01 00 00 - 13
1.21 COMMERCIAL DISPOSAL SITE
Locate a reliable commercial disposal site, and secure a disposal site as needed for the project. The disposal site must be in compliance with the requirements defined in the plans, specifications, and contract documents.
Disposal site and disposal activities must be in compliance with all applicable local, state, and federal regulations.
Prior to beginning construction work submit a Disposal Site Plan to the Contracting Officer. Include the location of disposal site(s), as well as copies of disposal site current and valid NEPA/CEQA documentation, applicable Federal, State and Local permits. Prepare and submit the Disposal Site Plan at no additional cost to the Government.
1.22 HAUL ROUTE PLAN
Submit a Haul Route Plan prior to beginning work. This plan must include offices, material storage areas and structures and the access routes to these areas. Indicate haul routes from the sites to major highways. Show all required traffic signs, special limits, warning devices, lighting and other such safety devices required by EM 385-1-1, OSHA, local cities and CALTRANS (on state roads), and any required permits for use of public roads from local and state agencies. Provide alternate routes in the plan for when interferences block designated haul routes. Revise and resubmit the plan if the haul routes being used are not as shown on the plan.
Require all visitors to abide by all construction site safety requirements. Notify the Corps Contracting Officer 48 hours before the commencement of any physical activities on the site. Work for sections such as Demolition, Grading, Tree Removal and other sections with excavations must be coordinated with this plan.
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIALS
The Government will provide an CD at the preconstruction conference that contains the following:
a. One set of electronic CADD drawing files in the specified software and format, revised to reflect all amendments,
b. A submittal register data file in comma separated value (CSV) format for import into the Resident Management System (RMS).
c. Informational copies of the contract specifications and drawings, the original solicitation drawings and specifications, plus all amendments in Portable Data Format (PDF).
PART 3 EXECUTION
3.1 AFTER AWARD DOCUMENTS
3.1.1 Hard Copies of Plans
Provide five (5) hard copy sets of the contract drawings and specifications from the PDF contract drawings and specifications. Provide these documents within 5 work days of receipt of the AWARD CD. Provide one (1) hard copy
01 00 00 - 14 prints of the drawings in ANSI D (22" x 34")format, five (5) hard copy prints of the drawings in 11"x17" format, and five (5) sets of the specifications in standard 8-1/2" x 11", double sided, 3-hole punched.
-- End of Section --
01 00 00 - 15
CONTRACTOR EQUIPMENT DATA SHEET
(Data to be furnished by Contractor for all equipment to be used on modifications as required under the Special Provisions of the Contract.)
DATE
CONTRACTOR CONTRACT NUMBER
1. EQUIPMENT DESCRIPTION
2. MODEL AND SERIES
3. YEAR PURCHASED
4. PURCHASE PRICE AT YEAR PURCHASED
5. LIST PRICE, YEAR OF MANUFACTURE
6. YEAR MANUFACTURED
7. EQUIPMENT HORSEPOWER
8. CARRIER HORSEPOWER
9. FUEL TYPE
10. SHIPPING WEIGHT
11. TIRE SIZE: FRONT - ______________________ DRIVE - _______________________ TRAILING - _______________________
REMARKS:
CESPK FORM 450 1 SEP 92 (Edition of Apr 84 will be used) FormFlow 2.2, ver 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
04/06
PART 1 GENERAL
1.1 SUBMITTALS
1.2 JOB PAYMENT ITEMS
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 Temporary Storm Water Pollution Control
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 Demolition And Removal
1.2.3.1 Unit of Measure
1.2.4 Haul Road Repairs
1.2.4.1 Unit of Measure
1.2.5 Irrigations Systems Removal
1.2.6 Unit of Measure
1.3 UNIT PRICE PAYMENT ITEMS
1.3.1 Clearing and Grubbing
1.3.1.1 Payment
1.3.1.2 Measurement
1.3.1.3 Unit of Measure
1.3.2 Topsoil Stripping
1.3.2.1 Payment
1.3.2.2 Measurement
1.3.2.3 Unit of Measure
1.3.3 Water Well Abandonment
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.4 Remove Pump
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.5 Remove Waterline
1.3.5.1 Payment
1.3.5.2 Measurement
1.3.5.3 Unit of Measure
1.3.6 Deer Fence
1.3.6.1 Payment
1.3.6.2 Measurement
1.3.6.3 Unit of Measure
1.3.7 Double Swing Gates
1.3.7.1 Payment
1.3.7.2 Measurement
1.3.7.3 Unit of Measure
1.3.8 Drainage Ditch Excavation
01 22 00 - 1
1.3.8.1 Payment
1.3.8.2 Measurement
1.3.8.3 Unit of Measure
1.3.9 Observation Trench Excavation
1.3.9.1 Payment
1.3.9.2 Measurement
1.3.9.3 Unit of Measure
1.3.10 Embankment Fill
1.3.10.1 Payment
1.3.10.2 Measurement
1.3.10.3 Unit of Measure
1.3.11 Grass Seeding and Erosion Control
1.3.11.1 Payment
1.3.11.2 Measurement
1.3.11.3 Unit of Measure
1.3.12 Aggregate Surface Course
1.3.12.1 Payment
1.3.12.2 Measurement
1.3.12.3 Unit of Measure
1.3.12.4 Way Bills and Delivery Tickets
1.3.13 Random Fill
1.3.13.1 Payment
1.3.13.2 Measurement
1.3.13.3 Unit of Measure
1.3.14 Import Fill
1.3.14.1 Payment
1.3.14.2 Measurement
1.3.14.3 Unit of Measure
1.4 OPTION 2
1.4.1 Construction Standby
1.4.1.1 Payment
1.4.1.2 Measurement
1.4.1.3 Unit of Measure
1.5 OPTION 3
1.5.1 Onsite Remobilization
1.5.1.1 Payment
1.5.1.2 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
01 22 00 - 2
SECTION 01 22 00
MEASUREMENT AND PAYMENT
04/06
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Way Bills and Delivery Tickets
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BID SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed must constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Mobilization and Demobilization
1.2.1.1 Payment
Payment will be made for Contract Line Item Number (CLIN) 0001 "MOBILIZATION AND DEMOBILIZATION" which price will include costs associated with mobilization and demobilization, as defined in Special Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION, including but not limited to: staging areas, drilling, general prep work, field offices and for all other work covered by these specifications. Price will also include any work for installation of temporary fences, Temporary Protective and Security Fencing, fence fabric, posts and fasteners, and the Contracting Officer's Office, as specified in section 01 71 10 MOBILIZATION AND DEMOBILIZATION, as shown on the Drawings, and as specified by the Contracting Officer.
Payment also includes full compensation for all costs associated with mobilization (60 percent) and demobilization (40 percent) with as-built drawings being a subsidiary cost of demobilizations at 0.5 percent of the original contract award amount.
1.2.1.2 Unit of Measure
Unit of measure: job.
01 22 00 - 3
1.2.2 Temporary Storm Water Pollution Control
1.2.2.1 Payment
Payment will be made for CLIN 0003 and 1003 "TEMPORARY STORM WATER POLLUTION CONTROL" which price will include all costs of furnishing, placing, establishing temporary storm water pollution control as specified in section 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL, and removing temporary BMP's.
1.2.2.2 Unit of Measure
Unit of measure: job.
1.2.3 Demolition And Removal
Measurement for payment will be made for CLIN 0005 and 1005 "DEMOLITION AND
REMOVAL"
which price will include all costs associated with the removal and proper disposal of gravel roads, corrugated metal pipes, and concrete pipes.
Include any cost incurred by the Contractor for demolition, removal, transportation and dumping including incurred fees under the CLIN 0005:
DEMOLITION AND REMOVAL. Removal of wells, waterlines, and pumps will be paid for under separate bid line items per unit titled "WATER WELL ABANDONMENT," "REMOVE PUMP," and "REMOVE WATERLINE." The bid line item must include all costs associated herein for each separate feature.
1.2.3.1 Unit of Measure
Unit of measure: job.
1.2.4 Haul Road Repairs
Measurement for payment will be made for CLIN 0016 and 1016 "HAUL ROAD
REPAIRS"
which price will include all costs associated with repair of damaged haul roads. The price must constitute full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for Haul Road Repairs. Include any cost incurred by the Contractor for demolition, removal, transportation and dumping including incurred fees under the CLIN 0016 HAUL ROAD REPAIRS.
1.2.4.1 Unit of Measure
Unit of measure: job.
1.2.5 Irrigations Systems Removal
Measurement for payment will be made for CLIN 0018 and 1019 "IRRIGATION SYSTEMS REMOVAL" which price will include all costs associated with removal of irrigation systems as required in section 31 11 00 CLEARING AND GRUBBING. The price must constitute full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for Irrigation Systems Removal. Include any cost incurred by the
01 22 00 - 4
Contractor for demolition, removal, transportation and dumping including incurred fees under the CLIN 0018 and 1019 IRRIGATION SYSTEMS REMOVAL.
1.2.6 Unit of Measure
Unit of measure: job.
1.3 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed must constitute full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.3.1 Clearing and Grubbing
1.3.1.1 Payment
Payment will be made for CLIN 0002 and 1002 "CLEARING AND GRUBBING" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to complete the Clearing, and Grubbing, and Irrigation Systems Removal as specified in section 31 11 00
CLEARING AND GRUBBING.
1.3.1.2 Measurement
Measure the CLEARING AND GRUBBING for payment by the total horizontal area, in acres, cleared and grubbed. The basis of measurement will be a survey of the area prior to clearing and grubbing and a second survey of the same area after the completion of the clearing and grubbing. Over clearing and grubbing performed for the convenience of the Contractor must not be measured for payment.
1.3.1.3 Unit of Measure
Unit of measure: acre.
1.3.2 Topsoil Stripping
1.3.2.1 Payment
Payment will be made for CLIN 0004 and 1004 "TOPSOIL STRIPPING" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to complete the TOPSOIL STRIPPING as specified in section 31 00 00 EARTHWORK. No separate payment will be made for temporary stockpiling and spreading/reuse of the stripped material.
1.3.2.2 Measurement
Measure the topsoil stripping for payment by use of the average end area method. The basis of measurement will be a survey of the area after clearing and grubbing and prior to topsoil stripping, and a second survey of the same area after the completion of the topsoil stripping.
Measurement must include the temporary stockpile and spreading/re-use of the stripped material. Over excavation and topsoil stripping performed for
01 22 00 - 5 the convenience of the Contractor must not be measured for payment.
1.3.2.3 Unit of Measure
Unit of measure: cubic yard.
1.3.3 Water Well Abandonment
1.3.3.1 Payment
Payment will be made for CLIN 0006 "WATER WELL ABANDONMENT" which price will include costs associated with abandonding water wells and standpipes, including full compensation for furnishing all labor, transportation, equipment and material necessary for constructing it as specified in section 31 00 00 EARTHWORK.
1.3.3.2 Measurement
Measurement for WATER WELL ABANDONMENT will be by each water well abandoned as required in these specifications and as shown on the Drawings.
1.3.3.3 Unit of Measure
Unit of measure: Each.
1.3.4 Remove Pump
1.3.4.1 Payment
Payment will be made for CLIN 0007 "REMOVE PUMP" which price will include costs associated with pump removal, including full compensation for furnishing all labor, transportation, equipment and material necessary for constructing it as specified.
1.3.4.2 Measurement
Measurement for REMOVE PUMP will be by each pump removed as required in these specifications and as shown on the Drawings.
1.3.4.3 Unit of Measure
Unit of measure: Each.
1.3.5 Remove Waterline
1.3.5.1 Payment
Payment will be made for CLIN 0008 "REMOVE WATERLINE" which price will include costs associated with waterline removal, including full compensation for furnishing all labor, transportation, equipment and material necessary for constructing it as specified.
1.3.5.2 Measurement
Measurement for REMOVE WATERLINE will be by the lineal feet of waterline removed. Measure the length of waterline removed for REMOVE WATERLINE along the center of the pipe.
01 22 00 - 6
1.3.5.3 Unit of Measure
Unit of measure: linear feet.
1.3.6 Deer Fence
1.3.6.1 Payment
Payment will be made for CLIN 0009 and 1009 "DEER FENCE" which price will include costs associated with furnishing, transporting, delivering, and placing Deer Fence, including full compensation for furnishing all labor, transportation, equipment and material necessary for constructing it as specified in section 02 82 10 FENCING and as shown on the Drawings.
1.3.6.2 Measurement
Measure the length of DEER FENCE installed along the centerlines of the posts from end to end of fence excluding lengths of double swing gates.
1.3.6.3 Unit of Measure
Unit of measure: linear feet.
1.3.7 Double Swing Gates
1.3.7.1 Payment
Payment will be made for CLIN 0010 and 1010 "DOUBLE SWING GATES" which price will include costs associated with double swing gates installation, including full compensation for furnishing all labor, transportation, equipment and material necessary for constructing it as shown in the Drawings.
1.3.7.2 Measurement
Measurement for DOUBLE SWING GATES will be by each double swing gate installed per the requirements in these specifications and as shown on the drawings.
1.3.7.3 Unit of Measure
Unit of measure: Each.
1.3.8 Drainage Ditch Excavation
1.3.8.1 Payment
Payment will be made for CLIN 0011 and 1011 "DRAINAGE DITCH EXCAVATION" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to excavate the DRAINAGE DITCH EXCAVATION as specified in section 31 00 00 EARTHWORK and as shown on the Drawings.
1.3.8.2 Measurement
Measure the Drainage Ditch Excavation for payment by use of the average end area method. The basis of measurement will be a survey of the area after clearing, grubbing, and stripping and prior to the excavation of the
01 22 00 - 7
Drainage Ditch, and a second survey of the same area after the excavation ofthe Drainage Ditch. Survey cross sections must be taken in sufficient numbers to account for geometric changes in the cross sections but not less than 100-foot increments measured along the ditch alignment. For areas where lines and grades are shown on the plans, measurement will be limited to those lines and grades.
1.3.8.3 Unit of Measure
Unit of measure: cubic yard.
1.3.9 Observation Trench Excavation
1.3.9.1 Payment
Payment will be made for CLIN 0012 and 1012 "OBSERVATION TRENCH EXCAVATION" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to excavate the OBSERVATION TRENCH EXCAVATION as specified in section 31 00 00 EARTHWORK and as shown on the Drawings.
1.3.9.2 Measurement
Measure the Observation Trench Excavation for payment by use of the average end area method. The basis of measurement will be a survey of the area after clearing, grubbing, and stripping and prior to the excavation of the Observation trench and a second survey of the same area after the excavation of the Observation trench. Survey cross sections must be taken in sufficient numbers to account for geometric changes in the cross sections but not less than 100-foot increments measured along the levee alignment. For areas where lines and grades are shown on the plans, measurement will be limited to those lines and grades.
1.3.9.3 Unit of Measure
Unit of measure: cubic yard.
1.3.10 Embankment Fill
1.3.10.1 Payment
Payment will be made for CLIN 0013 and 1013 "EMBANKMENT FILL" which price will include costs associated with providing all labor, equipment, tools, supplies, and incidentals necessary to construct the new EMBANKMENT FILL, including filling the Levee Embankment and Ramps, as specified in section 31 00 00 EARTHWORK and as shown on the Drawings. No separate payment will be made for construction/removal of temporary access ramps for the convenience of the Contractor or for the transport, temporary stockpile, or blending of soils used as embankment fill material.
1.3.10.2 Measurement
Measure the Embankment Fill for payment by use of the average end area method. The basis of measurement will be a survey of the area after clearing, grubbing, and stripping and after the excavation of the observation trench (where applicable) and prior to placement of the Levee Embankment and Ramps, and a second survey of the same area after the placement of the Levee Embankment and Ramps.