About this file

Amendment 0004

View the file

Other files

File Type Posted
Amd_0007_-_Specifications.pdf PDF
Amd_0007_-_Drawings.pdf PDF
W91238-15-R-0028-0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0004_-_Drawings.pdf PDF
Amendment_0004_-_Specifications.pdf PDF
Amd_0003_Specifications.pdf PDF
Amd_0003_Pricing_Schedule(Phase_I).pdf PDF
Amd_0003__Drawings_.pdf PDF
W91238-15-R-0028-0003.pdf PDF
Site_Visit_Sign-In_Sheet.pdf PDF
Site_Visit_Notes.pdf PDF
W91238-15-R-0028_Amd_0001.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W62N6M51215827

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project: Hamilton City Project, CA The purpose of this modification is to:

1) Extend the Proposal due date.

2) Make corrections and revisisons to this Solicitation in response to Bidder Inquiry Questions.

3) Revised Specification Sections:

-00 22 10 Supplementary Instructions -01 00 00 General Requirements -02 82 10 Fencing -31 00 00 Earthw ork -32 92 33 Grass Seeding and Erosion Control

4) Revised Draw ing Sheets - G-004, CD-106, CD-108 and G-413

1. CONTRACT ID CODE PAGE OF PAGES

J 1 25

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Jun-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-15-R-0028

X 9B. DATED (SEE ITEM 11)

12-May-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 6 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Jun-2015

CODE

US ARMY CORPS OF ENGINEERS, SACRAMENTO

CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91238-15-R-0028

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION - CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Amd 0003 Pricing

Schedule

2 11-JUN-2015

Attachment 2 Specifications 436 01-MAY-2015 Attachment 3 YellowBilled Cuckoo 1 01-MAY-2015 Attachment 4 Drawings 75 01-MAY-2015 Attachment 5 Borings 23 01-MAY-2015 Attachment 6 Wage Determination CA9 45 01-MAY-2015 Attachment 7 Amd 0003 Specifications 76 11-JUN-2015 Attachment 8 Amd 0003 Drawings 23 11-JUN-2015 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Amd 0003 Pricing

Schedule

2 11-JUN-2015

Attachment 10 Amd 0004 - Drawings 4 19-JUN-2015 Attachment 2 Specifications 436 01-MAY-2015 Attachment 3 YellowBilled Cuckoo 1 01-MAY-2015 Attachment 4 Drawings 75 01-MAY-2015 Attachment 5 Borings 23 01-MAY-2015 Attachment 6 Wage Determination CA9 45 01-MAY-2015 Attachment 7 Amd 0003 Specifications 76 11-JUN-2015 Attachment 8 Amd 0003 Drawings 23 11-JUN-2015 Attachment 9 Amd 0004 -

Specifications

78 19-JUN-2015

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 26-Jun-2015 01:00 PM to 29-Jun-2015 01:00 PM.

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

The following have been modified:

SECTION 00 22 10

SECTION 00 22 10

PROCUREMENT ACQUISITION

BASIS OF AWARD,

GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS,

EVALUATIONS, AND BASIS OF AWARD

1. OVERVIEW.

1.1. This is a “Single Phase Lowest Priced Technically Acceptable Request for Proposals” solicitation for Hamilton City Flood Damage Reduction and Ecosystem Restoration Project, Glenn County, California. The Contracting Officer will award a firm fixed-price contract to the responsive and responsible Proposer whom the Source Selection Authority determined had the lowest priced technically acceptable proposal, conforms to the solicitation, is fair and reasonable, and proposes the lowest overall price.

1.2. Overview of the Source Selection Process. The Lowest Price Technically Acceptable (LPTA) source selection process is appropriate when best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price. Proposals are evaluated for technically acceptability but not ranked using the non-cost/price factors.

1.3 Offeror’s are advised that the Government intends to make awards on the basis of initial technical acceptable proposals without conducting discussions with offeror’s, but reserves the right to conduct discussions if determined by the Source Selection Authority to be necessary [see FAR Part 14.501(a)]. Therefore, the initial proposal should contain the offeror’s best terms from a technical and price standpoint.

2. BASIS OF AWARD.

The contract resulting from this solicitation will be awarded to the lowest priced offeror who submits a technically acceptable proposal. Technical acceptability is based upon the two non-priced (technical) factors: Experience and Capability and Past Performance.

2.1. ELIGIBILITY FOR CONTRACT AWARD

In accordance with the requirements of Part 9 of the Federal Acquisition Regulation (FAR), no contract shall be entered into unless the Contracting Officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the Contracting Officer makes an affirmative determination of responsibility. To be determined responsible, a prospective prime contractor must meet the general standards in FAR Part 9 and any special standards set forth in the solicitation.

2.2. THE TECHNICAL EVALUATION FACTORS:

a. The Government will evaluate the technical proposal that is deemed lowest price first and if the offeror is deemed technically acceptable, the Government will not evaluate any other proposals. If the lowest priced proposal is deemed “Not Technically Acceptable”, then the next lowest priced offeror will be evaluated. The technical evaluation is based on how well the proposal addresses each of the two evaluation factors, listed below and further described in the Technical Proposal Volume. Each of the evaluation factors will be evaluated by the Government and an adjectival rating of “Acceptable” or “Not Acceptable” determined by consensus of the Government evaluation board. There are no relative weights assigned to the factors.

b. The evaluation factors correlate directly to the main organizational tabs identified in the proposal submission instructions in the Technical Proposal Volume. However, any information contained in the technical proposal can nonetheless be considered by the Government in its evaluation under any factor.

These has identified the Technical Factors and they are:

FACTOR 1 – EXPERIENCE AND CAPABILITY

FACTOR 2 – PAST PERFORMANCE

2.3. GENERAL TECHNICAL EVALUATION CRITERIA

a. The evaluation shall be conducted in accordance with FAR Subpart 15.101-2 -- Lowest Price Technically Acceptable Source Selection Process. For this procurement, only one technical proposal may be submitted by each bidder. Bidders should submit a proposal that is complete without the need of additional explanation or information.

The Government shall make a final determination regarding a proposal's acceptability solely on the basis of the proposal as submitted. The Government may proceed without requesting further information from any offeror;

however, the Government may request additional information from bidders of proposals that have been found to be Unacceptable.

b. Technical Proposals will be rated at the factor level and will be evaluated in terms of Acceptable or Unacceptable. If any factor is found deficient, the proposal will be determined Unacceptable. The initial technical proposal may have limited Unacceptability and therefore eligible for discussions, if no award is made without discussion. However, an initial proposal that contains one or more unacceptable factor will be considered unacceptable and will be eliminated from further consideration.

c. If discussions are held with bidders whose proposals are considered Unacceptable and a request for proposal revisions are requested, the revised proposal will be re-evaluated in accordance with the criteria in the solicitation.

After completion of discussions and evaluation of any revised proposals, the proposal shall be determined as acceptable or unacceptable. If determined unacceptable, a notice of unacceptability will be forwarded to the bidder upon completion of the proposal evaluation and final determination of unacceptability.

d. The offeror’s conformance with the specified format and submission requirements will be considered during the technical evaluation. Failure to comply with the formatting and/or submission requirements may be seen as indicative of the type of problems that could be expected during contract performance. Lack of conformance will result in a Unacceptable rating, in addition to any other impacts on the evaluation. Material omission(s) may cause the technical proposal to be rejected as unacceptable.

e. Technical proposals which do not provide the specified information in the specified location in accordance with the submission instructions may be deemed Unacceptable. The Government is under no obligation to search for information that is not in the specified location.

f. Proposals which are generic, vague, or lacking in detail will be deemed Unacceptable. The proposal submission instructions are written to give prospective Prime Contractors, where feasible, an indication of the level of detail desired by the Government. The offeror’s failure to include information that the Government has indicated should be included will result in the proposal being “Unacceptable” if inadequate detail is provided.

g. Any prescribed page and formatting limitations will be strictly adhered to and enforced by the Government. The Government will not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit three pages in response to an item with a two page limitation, the information on the first two pages would be evaluated but the information on the third page would not be evaluated. If an bidder were to submit a fold-out sheet (e.g. 11”x17”) in response to a one-page limitation where fold-out sheets were not authorized, only the information that could reasonably have been submitted on one 8-1/2 x 11 inch sheet would be evaluated. If a offeror were to submit three 8-1/2 x 11 inch pages in response to a one not-to-exceed 11 x 17 inch page limitation, only the information that could reasonably have been submitted on one 11 x 17 inch sheet would be evaluated. If a offeror submitted alternates that were not requested the information will not be evaluated.

h. The degree of acceptability to the Government inherent in the offeror’s technical proposal will be a consideration under every evaluation factor except past performance.

i. The LPTA evaluation of each offeror’s proposal will determine if each technical factor is technically acceptable with a rating of acceptable or unacceptable. An “acceptable” rating will be assigned to a proposal that has satisfied all of the requirements of the technical evaluation factors set forth in the solicitation. An “unacceptable” rating will be assigned to a proposal that has not satisfied one or more requirements of the technical evaluation factors set forth in the solicitation. The technical proposal will be evaluated to ensure the contractor possesses the technical experience necessary to perform the work adequately described in the Statement of Work and attachments within the Period of Performance. The awardee will be the firm whose proposal is the lowest price of all of the technically acceptable proposals.

j. Failure of a proposed key person or sub-contractor to furnish authorization for the Government to discuss its past performance with the offeror will not be considered a proposal deficiency. However, the Government will not be able to disclose to the offeror any details pertaining to their performance problems.

k. Past Performance Evaluation. The past performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements The past performance evaluation considers first each offeror’s demonstrated recent and relevant record of performance that meet the contract’s requirements. Second a performance confidence assessment rating is assigned for each offeror after evaluating the bidder’s recent past performance, focusing on performance that is relevant to the contract requirements. Past Performance can include offerors past or current contracts (including Federal, State, Local Government and private industry of similar project requirements).

1. Past Performance Ratings

Acceptable:

Substantial, Satisfactory and Limited Confidence Rating will be considered as Acceptable. Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

Unacceptable:

A No Confidence Rating will be considered as Unacceptable. Failure to meet criteria defined in the Acceptable rating above.

Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a)(2)(iv)). Therefore, the offeror shall be determined in the context of “unknown” shall be considered “acceptable.”

2.4. EVALUATION OF THE PROPOSAL

a. When applicable, the Price Evaluation Preference for HUBZone Small Business Concerns will be applied. The Price Evaluation Adjustment for Small Disadvantaged Businesses will not apply to this procurement as it is currently suspended for Department of Defense.

b. Information required to be submitted in the Price volume in addition to the executed SF 1442 with acknowledgement of amendments and the completed pricing schedule will be used to determine the bidder’s eligibility for contract award in accordance with paragraph 2.1 above (for example, the bidder’s representations and certifications; the bid guarantee; the offeror’s pre-award survey information; and the offeror’s small business subcontracting plan). The Government may enter into exchanges with offerors about such information without it constituting discussions, subject to applicable FAR limitations; FAR 28.101-4, Noncompliance with bid guarantee requirements; and 52.219-9, ALT II, Small Business Subcontracting Plan.

3 GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS.

3.1 GENERAL INSTRUCTIONS.

3.1.1 Media, Page Size, Margins, Fonts, and Page Limitations.

Submit only the hard-copy paper documents and electronic files specifically authorized elsewhere in this section.

Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal. Except where another size is specifically authorized for a specific submission, use only 8 1/2” x 11” paper. Use at least 1 inch margins, which may include headers and footers. Do not justify the right margin. Ensure that all text and graphics are clearly legible. Do not use a font size smaller than 10, unusual font styles such as script, or condensed fonts. For submissions with page limitations, the pages will be counted as follows: One side of the paper is one page;

information on both the back and front of one sheet of paper will be counted as two pages. Where authorized, a foldout sheet will count as one page. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.

3.1.2 Proposal Binding.

The preferred method for assembling proposals is a method that enables the rapid insertion or deletion of pages such as three ring binders. Ensure recommended capacity is not exceeded and that pages turn freely. Do not use spring clamps, spiral binding systems, or heat binding systems.

3.1.3 Conditioning of Proposal or Bid.

Do not include exceptions to the terms and conditions of the solicitation in either the technical or bid price volumes.

Inclusion of any standard company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the proposal/bid is unacceptable and thus ineligible for award.

Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of the proposal/bid; see “Inquiries”, located in Section 00 21 16, for points of contact. Notwithstanding the above, the bidder must clearly describe in the proposal cover sheet submitted with the bid price volume any exceptions, within the proposal/bid, to the contractual and/or technical terms and conditions of the solicitation.

3.1.4 Restrictions on Bidder-Provided Information.

“Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can nonetheless be provided to the Government as part of the offeror’s technical proposal. Bidders that include in their proposals information that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must clearly mark the information in accordance with FAR 52.215-1, “Instructions to Offeror – Competitive Acquisition”, paragraph (e), “Restriction on disclosure and use of data”. Files shall not contain classified data.

4. PRICE PROPOSAL VOLUME.

4.1 NUMBER OF SETS OF THE PRICE PROPOSAL.

The Price Proposal is to be submitted in one hard “original” and _SIX_ copies. In addition, submit one complete copy of the Price proposal on Compact Disk (CD) using a searchable “pdf” file format.

Use the following cover sheet when submitting the Price Proposal Volume:

4.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE PRICE PROPOSAL.

Use 8-1/2” x 11” pages for the narrative portions of the proposal. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location.

Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal. Limit your submittals to the information specified; excess information will not be evaluated.

PRICE PROPOSAL VOLUME

TAB CONTENTS OF THE PRICE PROPOSAL

1 Proposal Cover Sheet

2 SF 1442; Acknowledgement of Amendments; Joint Venture Agreement

3 Pricing Schedule

4 Work Breakdown Structure

5 Representations, Certifications, and Other Statements of Offerors

6 Bid Guarantee

7 Pre-Award Survey Information

4.3 DETAILED SUBMISSION REQUIREMENTS FOR THE PRICE PROPOSAL.

Tab 1 of the Price Proposal: Proposal Cover Sheet.

The proposal cover sheet is required by FAR 52.215-1 (c)(2). This provision, titled “Instructions to Offerors – Competitive Acquisition” is provided in full text in Section 00 21 00. The format and content for the proposal cover sheet follows:

PROPOSAL COVER SHEET

1. Solicitation Number:

2. The name, address, DUNS Number, and telephone and facsimile numbers of the offeror.

3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.

4. Names, titles, EMAIL address, and telephone and facsimile numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation:

5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

(End of Proposal Cover Sheet)

Tab 2 of the Price Proposal: SF 1442; Acknowledgement of Amendments; Joint Venture Agreement.

The Standard Form (SF) 1442 must be completed by the offeror and duly executed with an original signature by the official(s) identified in the proposal cover sheet as authorized to bind the offeror in accordance with FAR 4.102, which includes specific instructions pertaining to individuals, partnerships, corporations, Joint Venture participants, and agents. Include the offeror’s DUNS number in block 14 of the SF 1442, along with the offeror’s address. All amendments must be acknowledged in accordance with the instructions on the Standard Form 30, Amendment. If the offeror is a Joint Venture (JV), include a copy of the JV agreement and indicate its status. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the original SF 1442.)

Tab 3 of the Price Proposal: Pricing Schedule.

Submit the completed Pricing Schedule (Section 00 10 00) with the offeror’s proposed contract prices inserted in the appropriate spaces. Prices must be proposed for all contract line items. Unit prices must be extended to the actual “dollar and cents” amounts (i.e., to two decimal places). Do not round off the extended prices to the nearest dollar.

Check your pricing submission very carefully for mathematical and clerical errors prior to submission. Any qualification of pricing may render the proposal unacceptable and therefore not eligible for award. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the completed “original” pricing schedule.)

Tab 4 of the Price Proposal: Work Breakdown Structure.

Submit a Work Breakdown Structure of the offeror’s proposed Base and Option contract prices using the format below, in accordance with Unified Facilities Criteria (UFC) 3-740-05

01 EARTHWORK

02 CONCRETE WORK

Tab 5 of the Price Proposal: Representations, Certifications, and Other Statements of Offerors.

The offeror must have electronically completed the annual representations and certifications in accordance with FAR 52.204-8 (provided in full text in Section 00 45 00). The offeror is responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Additionally, the offeror must also complete and return the “Representations and Certifications” in Section 00 45 00 of the solicitation. If the offeror is a Joint Venture, all participants must separately complete both annual representations and certifications and Section 00 45 00.

Tab 6 of the Price Proposal: Bid Guarantee.

All offerors must submit a bid guarantee, (e.g., Standard Form 24, Bid Bond) which complies with the requirements of FAR 28.101 Bid Guarantees, and any Defense and Army supplements thereto.

Tab 7 of the Price Proposal: Pre-Award Survey Information.

a. The contracting officer is required to make an affirmative pre-award determination of the prospective contractor’s responsibility in accordance with the mandatory requirements of Part 9 of the Federal Acquisition Regulation (FAR) and its supplements. The contracting officer must have sufficient information available to determine that a prospective contractor meets these minimum standards. Therefore, the offeror is requested to provide the pre-award survey information described below with its price proposal:

(1) The completed Construction Contractor Data Form with Supplemental Schedules A-C (see format which follows). If the offeror is a large multi-segmented business concerns, the data provided on the supplemental schedules may be limited to information that directly pertains to the specific segment of the business concern (i.e., the division, group, unit, etc.) proposed to perform work under the prospective contract with its own work force. If the offer is being submitted by a Joint Venture, submit a separate form for each Joint Venture participant. The offeror may submit pre-award survey information in another format, provided that the information furnished is substantially the same as that which would be furnished on the Construction Contractor Data Form and its supplemental schedules.

(2) Current financial statements. If the financial statement is more than 60 days old, submit a certificate stating that the firm's financial condition is substantially the same, or, if not the same, state the changes that have taken place. If a Joint Venture, provide this information for each participant in the Joint Venture.

(3) Banking information. Provide letters from banks or other financial institutions with which the contractor conducts business. The letters should contain information about your firm's accounts, loans, lines of credit, etc. The Government is interested in financial stability, timely payments, the length and nature of the relationship between the firm and the financial institution, and the firm's financial ability to perform the contract. The letters should also provide the name and telephone number of the bank representative the Government may contact. If a Joint Venture, provide this information for each Joint Venture participant.

b. The Government will treat the pre-award survey information submitted by the offeror as proprietary.

(Tab 7 of the Price Proposal: Pre-Award Survey Information)

CONSTRUCTION CONTRACTOR DATA DATE:

Firm Name and Telephone Number Main Office Address (Street, City, and State)

Branch Offices Services Rendered Construction Design Consultant

Organization Individual Joint Venture Partnership Corporation

Date Organized Date Incorporated:

State:

Names of Officers and Other Key Personnel

I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below) Partners:

Officers:

Other Key:

Remainder: Subtotal Permanent:

Maximum Personnel at Any Time:

Date:

Total:

II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF

(DATE): Present Value ($)

Current Assets:

Acquisition Cost ($) Current Liabilities:

Net Worth:

IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION WORK

IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE (LIST MOST

RECENT FIRST)

V—LARGEST JOB EVER

CONTRACTED

(If Other Than in Past Six Years)

$ LARGEST JOB IN PAST 6 YRS Contract Amount:

Date:

Description:

Owner:

$ Contract Amount:

Date:

Description:

Owner:

Avg. Annual Income

VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES

NAME AND POSITION/TITLE OF PERSON SIGNING

SIGNATURE

See attachment for explanations or detailed description of item(s) reported above.

CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS

List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.

CONTRACT

NUMBER

AMOUNT

DESCRIPTION/

LOCATION

ORGANIZATION/

CONTACT PERSON/

PHONE NUMBER

PERCENT

COMPLETE

CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS

List below the principal construction projects your firm has completed within the past six years, including all DoD contracts with a total value exceeding $9,800,000.00.

NUMBER

AMOUNT

DESCRIPTION/

LOCATION

ORGANIZATION/

CONTACT PERSON/

PHONE NUMBER

PERCENT

SUBLET

CONSTRUCTION CONTRACTOR DATA – SCHEDULE C –

CONSTRUCTION AND/OR TECHNICAL EQUIPMENT

List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.

QUANTITY

DESCRIPTION

CONDITION

YEARS OF

SERVICE

PRESENT

STATUS

5 TECHNICAL PROPOSAL VOLUME.

5.1 NUMBER OF SETS OF THE TECHNICAL PROPOSAL VOLUME.

The Technical Proposal is to be submitted in one hard “original” and Six (6) copies. In addition, submit one complete copy of the technical proposal on Compact Disk (CD) using a searchable and bookmarked “pdf” file format.

5.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE TECHNICAL VOLUME.

Use 8-1/2” x 11” pages for the narrative portions of the proposal. There is not a page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location.

Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal. Limit your submittals to the information specified; excess information will not be evaluated.

TECHNICAL PROPOSAL VOLUME

COVER SHEET

1. Name, Address, and DUNS Number of Prime Contractor

2. Telephone Number: ________________________________________________________________

3. Solicitation Number: _______________________________________________________________

4. Title of Project: ___________________________________________________________________

5. Name and Title of Person Authorized to Sign Bid: Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.

6. Names, titles, and telephone and email addresses of persons authorized to negotiate on the bidder’s behalf with the Government in connection with this solicitation:

7. The bidder agrees to perform the required work according to the proposed technical approach in strict accordance with the terms and conditions of this solicitation.

8 . Signature: ______________________________________________ Title

9. Bid Date: _____________________________________________

10. Amendments (Number & Date of Acknowledgement):

END OF COVER SHEET

TECHNICAL PROPOSAL

TAB CONTENTS

PREFACE

Prime Contractor/Key Subcontractor Introduction

1. FACTOR 1 – EXPERIENCE AND CAPABILITY

Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability

2. FACTOR 2 – PAST PERFORMANCE

Prime Contractor/Key Subcontractor Example Projects Past Performance Key Subcontractor Authorization Letters

5.3 DETAILED SUBMISSION REQUIREMENTS AND EVALUATION CRITERIA FOR THE

TECHNICAL PROPOSAL

5.3.1 Preface – Prime Contractor/Key Subcontractor Introduction

a. The Offeror is required to propose a specific project team including key subcontractors for evaluation in response to this Request for Proposals. For purposes of this procurement, the terms “key subcontractors” are used to refer only to the prospective subcontractors whose qualifications, experience, and past performance will be evaluated by the Government as part of the source selection process. For reasons of efficiency, not all of the subcontractors critical to successful post-award contract performance have been included in this group. In order to streamline the proposal submission and evaluation process, please limit your submission to the information specifically requested.

Information pertaining to other subcontractors not designated as “key” by the Government will be considered excess and will not be evaluated.

b. For the purposes of this procurement, a key subcontractor is defined as any subcontractor performing “key” major work elements for which capability information is required to be submitted for evaluation as part of the Offeror’s technical proposal. The Government has designated the following major work elements as “key”:

i.Earthwork construction effort ii.Quality Control testing of earthwork and concrete construction iii.Concrete outlet works construction effort

c. The Offeror’s attention is directed to the clause in Section 00 73 00 titled “Key Personnel and Subcontractors”. In accordance with this clause, any post-award changes to the key personnel and/or key subcontractors in the accepted proposal will require Contracting Officer approval.

d. Provide a brief introduction narrative. Identify and provide the name, DUNS number, address, point of contact email address, and a brief description of the role and authority of each firm that will be involved in performance of this contract at the prime contractor and key subcontractor level. If the proposed prime contractor is a Joint Venture (i.e., mentor protégé), describe the relationship, role, and authority (to include management authority) of each firm.

(Note: If a proposed firm has branch offices, provide information for each individual branch office that will perform work under the contract with its own workforce.) List the major work elements to be self-performed by the offeror’s in-house work force and by each key subcontractor. The submission is limited to two (2) 8-1/2”x11” pages for narrative.

e. The Government will not evaluate the Preface - Prime Contractor/Key Subcontractor Introduction. The purpose of this narrative is to provide a brief introduction for information purposes.

5.3.2 Tab 1 of the Technical Proposal: Factor 1- Prime Contract/Key Subcontractor Example Projects Experience and Capabilities

5.3.2.1. General

a. The information provided under this tab will be used to evaluate the experience and capability of the offeror and proposed key subcontractors. The resumes and example projects will provide the primary basis for acceptability for the Government’s evaluation of the offeror’s qualifications and experiences.

b. The Government is especially interested in relevant experience in levee construction and quality control testing.

The examples can either be commercial or institutional. The Key Elements are:

i. Levee construction;

ii. Quality control testing of levee and concrete construction;

iii. Concrete closure and outlet structure construction.

iv. Sequencing/Phasing

5.3.2.2. Prime Contractor/Key Subcontractor Example Projects Demonstrating Experience and Capability

a. The offeror is required to submit “example projects” for each of the four (4) below capability areas that demonstrate the prime’s and/or key subcontractor’s experience and capability to successfully complete the example project. Each offeror must submit example projects (Prime contractor and key subcontractor) with a minimum of two (2) example projects but no more than three (3) example projects demonstrating experience in the key elements listed below. Example projects are a requirement for the prime and key subcontractor.

Each offeror’s example projects shall include:

1. Two (2) example projects, but no more than three, demonstrating the offeror’s construction/project management experience and capability as a prime contractor on a similar project and scope;

2. Two (2) example projects, but no more than three, demonstrating the experience and capability of the firm (prime or subcontractor) that will be performing the majority of the levee construction effort;

3. Two (2) example projects, but no more than three, demonstrating the experience and capability of the firm (prime or subcontractor) that will be performing the majority of the concrete outlet works construction effort.

4. Two (2) example projects, but no more than three, demonstrating the experience and capability of the firm (prime or subcontractor) that will be performing the quality control testing for levee and concrete construction.

b. Do not submit construction projects that are not either complete or substantially complete. (For this purpose, “substantially complete” means that only punch list items remain for project acceptance or that the majority of the elements of the project have been turned over to the customer for beneficial occupancy.)

c. Only submit projects where construction began after 1 May 2005. Projects older than that will not be evaluated.

d. “Similar scope” is defined as a similar quantity (in cubic yards) of levee constructed and tested for construction quality control. Partial reconstruction of an existing levee after degrade and installation of a cutoff wall is considered to be levee construction.

e. Any prescribed page and formatting limitations shall be strictly adhered to and enforced by the Government. The Government may not evaluate any excess information resulting from the offeror’s failure to comply with the submission instructions. Examples: If an offeror were to submit four example projects in response to a requirement for three example projects, only the first three example projects will be evaluated and the information on the fourth project would not be evaluated.

f. Provide a Summary Matrix that indicates which submitted example project(s) demonstrates the experience(s) and capability(ies) of which firm (i.e. prime, subcontractor) will perform the capability area identified in paragraph 2.a above.

g. Formatting and Other Restrictions.

(1) Start the information for each example project on a new page. The submission is limited to Twenty (20) 8-1/2” x 11” pages for Factor 1.

(2) Use the “Project Information Form” which follows for submitting the example projects. Use of an alternate format could result in a lower rating if all of the specified information is not provided. (Note:

Do not submit a group of related jobs as one project unless all of the work was done under the same contract, or for indefinite delivery contracts, under one task order.)

PROJECT INFORMATION FORM

1. Example Project Number: Start with “1” for the first of all submitted projects and number consecutively.

2. Name of Contractor(s)/Key Subcontractor (s) that Project is Demonstrating Experience: Provide the name of the proposed firm(s) that this example project is demonstrating experience and capability.

3. Contract Number and Awarded Prime Contractor Name: Provide contract number assigned by the procuring Contracting Office and the name of the contractor that was awarded the contract.

4. Title and Location: Title and location of project or contract.

5. Month and Year Project Work Commenced and Month and Year Project was Completed.

6. Project Owner: Project owner or user, such as a government agency or installation, an institution, or corporation or private individual.

7. Point of Contact Name: Provide name of a person associated with the project owner or the organization that contracted for the construction, who is very familiar with the project and the firm’s (or firms’) performance.

8. Point of Contact Telephone Number: Include area code.

9. Description of the Project: Provide contract type, dollar amount, physical size, and brief description of prime contracted effort. If the firm (prime/key subcontractor) performed as a subcontractor, describe the work effort pertaining to the subcontracted effort, not the prime contract requirement. For each firm (prime/key subcontractor) that was involved on the example project, provide sufficient detail to establish the relevance to the current project to include (1) the performance period in month and year, (2) final dollar value, (3) physical size and (4) principal elements and special features of the work self-performed by that contractor’s employees.

10. Provide name of firm(s) (prime/key subcontractor) and branch offices, if appropriate, that were involved in the example project, their roles, and their respective contract numbers.

END OF FORM

(3) The Summary Matrix is limited to one page (NTE 11” x 17”) for Factor 1. For example:

Capability #1 #2 #3 #4 #5 #6 #7 #8 #9 Prime Contractor X X X Levee construction effort X X Structural construction effort X X

Levee and Concrete Quality Control testing

X X

h. Evaluation Criteria.

The Government will evaluate the example projects to determine if the offeror’s demonstrated recent and relevant experience and capability in each key area below:

1. The offeror’s construction/project management experience and capability as a prime contractor on a similar project and scope;

2. The offeror’s experience and capability of the firm (prime or subcontractor) that will be performing the majority of the earth moving construction effort;

3. The offeror’s experience and capability of the firm (prime or subcontractor) that will be performing the majority of the concrete construction effort.

4. The offeror’s experience and capability of the firm (prime or subcontractor) that will be performing the majority of the earthwork and/or concrete quality control testing.

g. Evaluation Criteria Definition:

Offer(s) will be deemed “Acceptable” if proposal clearly meets the minimum requirements of the Request For Proposal (RFP) evaluation factor one. If offeror provides any deviation(s) from the Request for Proposal (RFP), their proposal will be considered “Unacceptable”.

Rating Description Acceptable

Proposal clearly meets the minimum requirements of the solicitation.

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.

5.3.3 Tab 2 of the Technical Proposal: Factor 2 – Past Performance.

5.3.3.1. General.

a. The information provided under this tab will be used to evaluate the relevant past performance record of the offeror and proposed key subcontractors. Information other than that supplied by the offeror under this tab may be utilized by the Government in its evaluation of past performance.

b. The more similarities an example project has with the prospective contract, the greater the degree of relevancy.

The Source Selection Authority shall determine the relevance of similar past performance information.

5.3.3.2. Prime Contractor/Key Subcontractor Example Projects Past Performance.

a. Offerors are to provide past performance evaluation information on the example projects submitted under the Experience and Capability factor (e.g. Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Performance Assessment Reports (CPARS) (Construction Contractor Appraisal Support System (CCASS)), questionnaire, similar performance evaluation, or other performance evaluations completed previously).

b. The Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 Experience and Capability. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQ should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project (s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the

Government’s point of contact, Marsha Sells via email at Marsha.R.Sells@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Any other form from the State, Local Governments for past performance may be used if the offeror’s past performance evaluations are clearly understood and transferrable to the PPQ subject areas.

c. The Government is interested in the information provided under this tab to evaluate the past performance of the offeror and proposed key subcontractors with detailed relevant project experience stated in the RFP. The proposal must demonstrate that the Contractor has successfully completed minimum of two (2) no more than three (3) contracts of similar scope, magnitude and complexity demonstrating experience with levee and concrete construction and quality control testing. Contractor shall provide the government with any CCAS Evaluation with respect to each project or performance evaluation sheet from a government representative.

d. Offerors are to provide past performance evaluation information on the two (2) example projects, but no more than three, submitted under the Experience and Capability factor (e.g. Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Performance Assessment Reports (CPARS) (Construction Contractor Appraisal Support System (CCASS)), questionnaire, similar performance evaluation, or other performance evaluations completed previously). The Past Performance Questionnaire (PPQ) shall be included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 Experience and Capability.

e. Formatting and Other Restrictions

(1) Start the information for each example project on a new page. There is not a page limitation for this submission of Factor 2.

(2) Sample Past Performance Questionnaire:

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE.

PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND

ALL INFORMATION ON THIS FORM.

Form PPQ-0 (9/30/11)

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.

Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements.