Attachment 4 Supplementary Condition

View the file

Other files

File Type Posted
1826-35_41_17-AM02.pdf PDF
W91238-13-R-0041-0002.pdf PDF
1-04-0614-AM02.pdf PDF
W91238-13-R-0041 _Amendment_0001.pdf PDF
13-R-0041_Site_Visit_Sign_in_Sheet_07OCT13.jpg JPG image
Attachment_2._SPECS_1826.pdf PDF
Attachment_1._PLANS.pdf PDF
Attachment_3._Wage_Determination_26SEP13.docx DOCX document
W91238-13-R-0041_R7L7.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARCF WRDA 96 - Phase 2 Remaining Sites - Sites R7 and L7 1826

00 73 05 - 1

SECTION 00 73 05

SUPPLEMENTARY CONDITION REQUIREMENTS FOR SITES R7 AND L7

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010;

Changes 4-6 2011; Change 7 2012) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation. The following shall be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals; G

Permits and Approvals; G

Construction emission/dust control plan; G

Permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage; G

Slurry Spill Prevention Plan; G

Flood Contingency Plan; G

Utility Provider Response Plan; G

Storm Water Pollution Prevention Plan; G

Grading Permit; G

1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS

1.3.1 SCR-1 Location of Work

The Project is located in Sacramento County, California, along portions of the American River levee that protects the City of Sacramento.

1.3.2 SCR-2 Scope of Work

The existing right bank (east) levee of the American River at Site R7 is approximately 11 feet in height (as measured from the landside toe) with a crown width of approximately 10 to 15 feet in the levee section. There is an

00 73 05 - 2 asphalt road on the levee crown on both sides of the H Street Bridge. There are unpaved dirt ramps on both sides of the bridge connecting the levee crown to an asphalt pedestrian path on the waterside of the levee, and an asphalt ramp down to a path on the landside that runs parallel to Fair Oaks Boulevard. The length of the "window" is approximately 151 feet. The waterside and landside slopes are approximately 4:1 and 3:1 (H:V), respectively. H Street becomes Fair Oaks Boulevard at the right bank of the river.

Site L7 is directly across the river from Site R7. The existing left bank (west) levee of the American River at Site L7 is approximately 12 feet in height (as measured from the landside toe) with a crown width of approximately 18 to 20 feet in the levee section. There is an asphalt road on the levee crown on both sides of the H Street Bridge. There are unpaved dirt ramps on both sides of the bridge connecting the levee crown to an asphalt pedestrian path on the waterside of the levee, and an asphalt ramp down to a path on the landside that runs parallel to H Street. The length of the "window" is approximately 325 feet. The waterside and landside slopes are both approximately 2.5:1 (H:V).

There is a 12" steel water pipe suspended from the bottom of the H Street Bridge at both sites. There are also overhead electric lines and power poles at both sites. At Site L7, there is an underground 72" steel storm drain pipe that connects to a vault on the waterside slope of the levee, just south of the H Street Bridge. This active storm drain pipe will be encased in controlled low strength material (CLSM) where the pipe crosses the proposed levee improvements.

1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of Completion

The following constraints will apply and must be incorporated into the Contractor's schedule. Site R7 is available from 15 April through 31 December 2014, but Site L7 is only available from 1 August 2014 through 31 December 2014. The time the Contractor can have the pipes crossing the H- Street Bridge is between 1 August and 1 November 2014 (access through the L7 church property will only be available between 1 August and 31 December 2014, and the jet grouting work needs to be completed by 1 November 2014.

At Site R7, the elderberry shrubs need to be fenced 20-feet in diameter for the entire construction period. The remaining portion of the Staging Area is usable starting 15 April 2014.

TIME OF COMPLETION FOR SITE R7

Contracting Officer and Resident Engineer's Office Facility

Installed and ready for occupancy not later than five (5) calendar days prior to start of excavation or not later than fifteen (15) calendar days after Notice to Proceed, whichever occurs first

Complete pre-production cutoff wall 30 work days (5 calendar weeks)

00 73 05 - 3

Complete waterside blanket 24 work days (4 calendar weeks)

Complete cutoff wall 60 work days (10 calendar weeks)

Complete installation of riprap 6 work days (1 calendar week)

Complete paving of bike paths 6 work days (1 calendar week)

Complete permanent erosion control and site cleanup for all disturbed areas

12 work days (2 calendar weeks)

Copies of Permits Contractor to forward to Contracting Officer within 10 days of receipt

Slurry Spill Prevention Plan Submit to Contracting Officer 30 days prior to commencement of construction activities

TIME OF COMPLETION FOR SITE L7

Contracting Officer and Resident Engineer's Office Facility

Installed and ready for occupancy not later than five (5) calendar days prior to start of excavation or not later than fifteen (15) calendar days after Notice to Proceed, whichever occurs first

Complete waterside blanket 24 work days (4 calendar weeks)

Complete cutoff wall 60 work days (10 calendar weeks)

Complete installation of riprap 6 work days (1 calendar week)

Complete paving of bike paths 6 work days (1 calendar week)

Complete permanent erosion control and site cleanup for all disturbed areas

12 work days (2 calendar weeks)

Copies of Permits Contractor to forward to Contracting Officer within 10 days of receipt

Slurry Spill Prevention Plan Submit to Contracting Officer 30 days prior to commencement of construction activities

00 73 05 - 4

1.3.4 SCR-4 Site Conditions

The Contractor shall satisfy himself or herself concerning the nature and location of the work; the general and local conditions, particularly those affecting transportation, disposal, handling and storage facilities;

availability of labor, water, power, communications, roads, climatic conditions and seasons; physical conditions at the job sites and Project areas as a whole; job-site topography and ground conditions; permits, equipment, and facilities needed preliminary to, and during, work prosecution; and all other matters which can in any way affect the work, including cost thereof. Failure of the Contractor to become acquainted with all available information regarding any applicable conditions will not relieve the Contractor from the responsibility for properly estimating either the difficulties or the costs of successfully performing the work.

The EA/IS shall be made available upon request by contacting the Contracting Officer.

1.3.5 SCR-5 Lands and Right-of-Way

The right-of-way for the construction work, as shown on the Plans, will be provided by the U.S. Army Corps of Engineers (USACE).

1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public Agencies

American River Flood Control District (ARFCD) is responsible for inspecting and maintaining the existing levee. The Contractor shall conduct the work so that ARFCD personnel and equipment are not prevented from access to the existing levee at all times for normal and emergency purposes. The Central Valley Flood Protection Board, Sacramento Area Flood Control Agency (SAFCA), the U.S. Fish and Wildlife Service, the Army Corps of Engineers, the National Marine Fisheries Service (NMFS), the State Department of Fish and Game, City of Sacramento, and the County of Sacramento have jurisdictional authority over the work as defined in the respective sections, associated permits and/or agreements. The Contractor shall allow these agencies and other jurisdictional public agencies, unrestricted access to the Project site.

1.3.7 SCR-7 Contractor's Tools and Equipment

The Contractor shall furnish all equipment, materials, tools, supplies, and manufactured articles required for the completion of the work in accordance with the Contract. The Contractor shall take the necessary precautions to secure tools and equipment from theft while on-site. The Government assumes no responsibility for lost, vandalized, or stolen equipment belonging to the Contractor, its subcontractors, or its employees.

1.3.8 SCR-8 Locking Gates

The Contractor shall take care to protect and operate any existing gates that control access to the Project right-of-way, in conformance with the Government, ARFCD, and City of Sacramento requirements. These requirements include preventing passage through the gates of unauthorized persons and equipment during periods of Contractor use of the gates and locking the gates during non-construction periods, if so directed by the Contracting

00 73 05 - 5

1.3.9 SCR-9 Water Source for Construction Operations

Contractor is responsible for identifying, securing, and obtaining all water needed for the project for both potable uses and for construction purposes.

Water shall not be pumped from the American River. Construction water should be reused onsite to the extent practical and disposed of in a manner consistent with the quality of the water after use. Excess water shall not be disposed of into any wetland, stream, river, or storm drainage without permitting.

Contractor shall be responsible for disposal of all construction water.

1.3.10 SCR-10 Cleaning Up

The Contractor shall dispose of all trash items in closed containers, which shall be removed at least once per day. Vegetative wastes shall be chipped or delivered to waste energy facilities, mulched, composted, or used for firewood.

1.3.11 SCR-11 Protection of Existing Improvements

Except as specified herein or as shown on the Plans, existing structures and utility lines shall not be disturbed, damaged, or undermined by the Contractor, except where in the opinion of the Contracting Officer it is essential to relocate such improvements. If relocation of any facility is required, the Contractor shall relocate the improvements to be at least equal in condition to the original. The Contractor shall take all necessary precautions to prevent any damage to existing facilities. Should damage or injury occur as a result of the Contractor's operations, the Contractor shall repair or replace such damaged facilities to the Contracting Officer's satisfaction at the Contractor's expense.

The Contractor shall repair any damage to public and private streets resulting from the Contractor's operations, as directed by the Contracting Officer. Repair shall be made per industry standards and conform to local jurisdictional requirements. Repairs shall be made at no additional cost.

1.3.12 SCR-12 Record Drawings

The Contractor shall maintain a neat and accurate marked set of working record drawings in accordance with Specifications. The record drawings shall be subject to the inspection of the Contracting Officer at all times and shall be kept current weekly with all work instructions, change orders, and construction adjustments shown thereon and initiated by inspection. The Contracting Officer reserves the right to withhold progress payments, or portions thereof, if record drawings are not maintained as stated above.

1.3.13 SCR-13 Flood Emergency

In the event of a flood emergency requiring action by the jurisdictional flood control agencies prior to completion of the work, the Contracting Officer shall have the right to suspend the work in accordance with the General Specifications. Such suspension includes the right of the Contracting Officer to take over the Project to conduct flood protection activities.

00 73 05 - 6

1.3.14 SCR-14 Permits and Approvals

The Contracting Officer has obtained various permits, agreements, and rights for performance of the work. These permits may be described more fully in other SCRs and these specifications. The Contractor will be required to obtain additional permits or be a signatory on the Contracting Officer obtained permits as noted throughout the specifications. The Contractor shall be responsible for complying with all conditions of the permits and agreements. Any delays to the Project resulting from the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time for such delays.

The Contractor is responsible for obtaining all environmental permits or use permits required for easements to land being used for the Contractor's own convenience. Any delays to the Project resulting from the lack of these additional permits or the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time or additional compensation for such delays. Copies of all permits obtained by the Contractor shall be given to the Contracting Officer within 10 days of receipt of permit.

1.3.15 SCR-15 Dust Control

The Contractor shall comply with the provisions of Section 01 57 20 ENVIRONMENTAL PROTECTION of the General Specifications. The Contractor shall prepare and submit a construction emission/dust control plan to the Contracting Officer and Sacramento Area Air Quality Management District (SMAQMD) and shall receive approval of the plan before groundbreaking.

During the performance of the work, the Contractor shall assume all responsibility for dust control and shall furnish all labor, equipment, and means required, and shall carry out proper and efficient measures wherever and as often as necessary to prevent the construction operations from producing dust in amounts harmful to persons, damaging to property, or causing a nuisance to persons living nearby or occupying buildings in the vicinity of the work, or as directed by the Contracting Officer. Dust control will be strictly enforced with particular emphasis on work areas adjacent to residential and agricultural properties. The curtailment of the construction activities as a result of inadequate dust control measures will not be considered an unavoidable delay. The Contractor shall suspend all grading operations when fugitive dust levels exceed levels specified by SMAQMD regulations or deemed unacceptable by the Contracting Officer.

1.3.16 SCR-16 Fire Control

No burning shall be allowed for any activities associated with this project.

Delivering removed vegetative material to compost or waste-to-energy facilities is encouraged. Land filling of material shall be minimized.

Flammable construction/maintenance materials shall be stored away from Sump 91 and in a manner approved by the City of Sacramento Fire Marshall.

1.3.17 SCR-17 Air Pollution Control

The Contractor shall comply with the air pollution control protocols in the General Specifications. To the extent available, the Contractor shall use

00 73 05 - 7 existing power sources for the Contractor provided trailers rather than temporary power generators. If existing power sources are unavailable, clean fuel, low-emission on-site stationary generator equipment shall be used. Low-sulfur fuel shall be used for stationary construction equipment.

The Contractor shall be responsible for arranging appropriate consultation with the Air Resources Board and the SMAQMD, to determine registration and permitting requirements before operating portable engines or portable engine-driven equipment at the project site.

1.3.18 SCR-18 Noise Control

The Contractor shall comply with Section 01 57 20 ENVIRONMENTAL PROTECTION of the General Specifications to avoid and minimize noise impacts from the construction activities.

Before construction activity begins within 500 feet of one or more residences, the Contractor shall provide written notification to the potentially affected residents, identifying the type, duration, and frequency of activities. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if demolition noise levels are overly intrusive.

Before haul truck trips are initiated on roads within 600 feet of one or more residences, the Contractor shall provide written notification at least one day before to the potentially affected residents, identifying the hours and frequency of haul truck trips. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if haul truck noise levels are overly intrusive or outside exempt daytime hours.

1.3.19 SCR-19 Allowable Work Hours

For Site R7, no work shall be allowed on holidays without prior written approval from the DPW Representative. Written requests to work holidays should be provided to the DPW Representative a minimum of two weeks in advance. Work days shall be between the following hours on the following days:

Monday through Saturday: 7 AM - 6 PM (as posted in the newspaper or online), whichever is sooner Sunday: 9 AM - 6 PM (as posted in the newspaper or online), whichever is sooner

Passive (no operation of heavy machinery) activity off of the levee is restricted to the staging area for one hour after sunset (as posted in the newspaper or online) or 10:00 PM whichever occurs sooner. Only passive activity is allowed on Sundays. No other construction work will be allowed outside the above mentioned hours. Such extended work hours must be reflected in the Contractor's initial approved schedule for the Project.

For Site L7, no work shall be allowed on holidays without prior written approval from the DPW Representative. Written requests to work holidays should be provided to the DPW Representative a minimum of two weeks in advance. Work days shall be between the following hours on the following days:

00 73 05 - 8

Monday through Friday : 7 AM - 6 PM (as posted in the newspaper or online), whichever is sooner No access is allowed through the church parking lot after sunset on Friday; only access through the Sacramento State bike trail access will be available after sunset on Fridays Saturday 7 AM - 6 PM (as posted in the newspaper or online), whichever is sooner No access is allowed through the church parking lot; only access through the Sacramento State bike trail access will be available on Saturdays Sunday: 9 AM - 6 PM (as posted in the newspaper or online), whichever is sooner

Passive (no operation of heavy machinery) activity off of the levee is restricted to the staging area for one hour after sunset (as posted in the newspaper or online) or 10:00 PM whichever occurs sooner. Only passive activity is allowed on Sundays. No other construction work will be allowed outside the above mentioned hours. Such extended work hours must be reflected in the Contractor's initial approved schedule for the Project.

1.3.20 SCR-20 Archaeological, Paleontological, and Cultural Resources

The Contractor shall comply with protocols in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications.

Contractor shall conduct Construction Personnel Training for all on-site employees. If archeological, cultural, or paleontological resources are discovered during construction activities, Contractor shall cease work within 100 feet of the vicinity of the find and immediately contact the archaeologist, through the Contracting Officer, and cooperate with all pertinent mitigation procedures.

1.3.21 SCR-21 Protection of Existing Trees

All trees outside the work limits, of any kind, are to be protected.

Contractor shall place protective barrier fencing around sensitive trees adjacent to construction areas as directed by the Contracting Officer. If damaged by the Contractor, damaged trees and landscaping shall be replaced by Contractor or otherwise mitigated as directed by Contracting Officer at the Contractor's expense.

1.3.22 SCR-22 Biological Resources

The Contractor shall comply with the Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications to avoid and minimize effect upon endangered or sensitive species in the Project area. The Contractor shall schedule activities to comply with the provisions and provide required notice for surveys to be conducted by the Government's Environmental Representative. Construction personnel shall participate in an environmental awareness program, which will be provided by the Contracting

00 73 05 - 9

Officer at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.

1.3.23 SCR-23 Raptor and Migratory Birds

The Contractor shall comply with the provisions of the Construction Contractor Protocols for Avoiding and Minimizing Impacts to Raptors, Special Status, and Other Nesting Birds, which are included in Section 01 57 20, ENVIRONMENTAL PROTECTION, of the General Specifications. If a nesting bird is found injured on the Project site, the Contracting Officer shall be notified immediately so the animal can be relocated to either a wildlife care facility or a raptor recovery facility.

1.3.24 SCR-25 Wetlands and Sensitive Habitats

The Contractor shall not impact Wetlands and Sensitive Habitats.

1.3.25 SCR-27 U.S. Fish and Wildlife Service

A Biological Opinion has been issued by the U.S. Fish and Wildlife Service.

The Contractor shall comply with the terms and conditions and is responsible for implementing all requirements and obligations included in the opinion. A copy of the Biological Opinion is available upon request to the Contracting

1.3.26 SCR-28 Central Valley Flood Protection Board

The Government will obtain encroachment permits from the Central Valley Flood Protection Board for work on this project. A copy of the permit(s) will be made available, when obtained, and upon request to the Contracting Officer.

The Contractor will obtain a Use Permit from the State of California in the contractor's name for the Contractor's use of the property. Said Use Permit shall be obtained by the Contractor from, and shall be issued by, the Sacramento San Joaquin Drainage District operating by and through the Central Valley Flood Protection Board. The permit may be obtained by contacting the Chief of the Real Estate Branch, California Department of Water Resources, 1416 Ninth Street, Room 425, Sacramento, California, 95814, Telephone (916) 653-5815.

The Contractor shall comply with the conditions of this permit(s), except where the Technical Specifications specify criteria that are more stringent.

1.3.27 SCR-29 Speed Limit

The speed limit in all Project work areas and along levees shall be 15 m.p.h., except on county roads and on highways. The Contracting Officer may also require that speed limits on project site be reduced further to ensure vibration limits are not violated. The Contractor shall post at a minimum, two speed limit signs at each end of the haul route.

1.3.28 SCR-30 American River Flood Control District (ARFCD) Coordination

00 73 05 - 10

American River Flood Control District manages the existing levees throughout the project area. The Contractor shall coordinate their work with ARFCD through the Contracting Officer, allowing ARFCD access to its facilities at all times. The Contractor shall maintain access for the ARFCD through the Contracting Officer at all times.

1.3.29 SCR-31 Provision Regarding Maintaining Minimum Flood Protection During Construction

Contractor shall have all levee improvements planned for a construction season completed by the deadlines outlined in Time of Completion requirements as described in paragraph 1.3.3, SCR-3, herein. Contractor shall not disturb the existing levee system beyond the limits of construction. Disturbance includes but is not limited to roadways, ramps, pipes and/or utilities crossings, or excavations within the limits of construction. Stockpiling suitable construction materials is acceptable provided written approval is first obtain from the Contracting Officer.

1.3.30 SCR-32 Coordination with the Contracting Officer and Utilities Relocation

Contractor shall coordinate and cooperate with the Contracting Officer and all utility providers on relocation of any existing overhead and electrical utilities and gas within the limits of construction that may hinder the performance of Contractor's construction activities. Contractor shall assist in coordination and work with the Contracting Officer such that the utilities are relocated in time not to delay and to allow for completion of improvements in accordance with the Time of Completion schedule.

1.3.31 SCR-33 Haul Routes

All haul and access routes shall be existing public roads and maintenance roads, except for restrictions noted on the drawings. Stockpiling of construction materials, including portable equipment, vehicles, and supplies, shall be restricted to designated construction staging areas.

Movement of heavy equipment to and from the Project site shall be restricted to load limit approved roadways. The Contractor's construction access points shall be limited to those shown on the Plans, defined in the Specifications, or as directed in the field by the Contracting Officer.

Paved areas at these controlled access points shall be swept each day, or more frequently, as required by the Contracting Officer to control dust and clean up material tracked or spilled on said paved areas or roadways. The Contractor shall conform to all governing codes, laws, and ordinances.

Contractor shall obtain a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be incurred by the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.

00 73 05 - 11

1.3.32 SCR-34 Resource Coordination

All contact and coordination with the resource agencies shall occur through the Contracting Officer in coordination with the Government's environmental representative.

1.3.33 SCR-35 Flood Contingency Plan

In the event the water surface elevation of the adjacent river is forecasted by the State-Federal Flood Forecast Center to increase significantly for any reason, the Contracting Officer reserves the right to require the Contractor to stop excavation and to begin continuous operations to complete all partially completed section (s) of the levee embankment and the cutoff wall.

At least 15 days prior to any Levee Excavation, the Contractor shall submit a contingency plan outlining the contingency operations in the event that river elevations above the flood stage (as defined by the USACE) are forecasted. The contingency plan shall include the proposed measure to protect the landside areas which have a reduced level of protection due to construction activities. The plan shall include river stage monitoring, river stage at which the plan will be activated, material and equipment to be used in performance of the contingency plan, and location, type and quantity of the stockpiled emergency material. The plan shall also include the length of levee, where stockpiled material will be stored, and the method for monitoring river elevations. The Contractor shall keep any levee degrade material on the project site for the duration of the construction period, protected from inclement weather, for use as emergency backfill as necessary. The Flood Contingency Plan shall be submitted to the Contracting Officer for review.

1.3.34 SCR-36 Utility Provider Response Plan

Contractor shall prepare and submit a Utility Response Plan to the Contracting Officer, SRCSD, and the City of Sacramento. Plan shall detail how utility locations are verified, provide protocol for coordination with Utility Providers, detail process on conducting required worker training for all on-site employees with respect to accidental utility damage, and provide utility provider emergency contact information. Contractor is responsible for coordinating any temporary utility services needs during construction, and shall assume all temporary utility services cost.

1.3.35 SCR-37 Stop Work Authority

The Contracting Officer in cooperation with the Government's Environmental Representative shall have the authority to immediately stop any activity that is not in compliance with the permits, and/or order any reasonable measure to avoid the unauthorized take of an individual of the Covered Species (e.g., giant garter snake, Swainson's hawk, valley elderberry longhorn beetle, Federally- and State-listed fish).

1.3.36 SCR-38 Floodway Construction Schedule

Contractor shall not perform any work within the existing floodway (i.e., waterside) per the date restrictions in Time of Completion requirement herein and shall not begin any construction until evaluation of upstream conditions indicate that inundation of these areas is unlikely to occur.

00 73 05 - 12

1.3.37 SCR-39 High Visibility Fencing, Habitat Preservation and Buffers

Contractor shall provide high visibility fencing that shall be placed to prevent encroachment of construction personnel and equipment into areas outside of or adjacent to the project footprint that contain sensitive habitats, including at least 20 feet from the dripline of elderberry shrubs and up to 200 feet from the edge of aquatic features that are suitable giant garter snake habitat. K-Rails, if used, shall be used in areas noted on the drawings. The fencing shall be inspected by the Contractor before the start of each work day and shall be maintained until completion of the Project.

The Contractor shall not remove the fencing until construction of the Project is completed. No insecticides, herbicides, or other chemicals that might harm the longhorn beetle or its host plant shall be used within 100 feet of the elderberry shrubs.

1.3.38 SCR-40 General Safety Requirements

The Contractor shall conform to all applicable occupational safety and health standards, rules, regulations, and orders established by the State of California or Federal Government. The Contractor shall, upon request, submit to the Contracting Officer a copy of their Injury Illness Prevention Program (IIPP) (including Site Safety Plan and Code of Safe Work Practices) for review. The Contractor is required to fulfill the requirements of these programs during the prosecution of the Work, and comply with conditions set forth in the Specifications. The Contractor shall comply with all regulations set forth in EM 385-1-1.

1.3.39 SCR-41 Storm Water Pollution Prevention Plan

Coverage under the State Water Resources Control Board (SWRCB) General Permit to Discharge Water Associated with Construction Activity shall be obtained by the Contractor for this Project prior to initiation of any construction activities. The Notice of Intent (NOI) shall comply with the Terms of the General Permit to Discharge Storm Water Associated with Construction Activity (WQ Order No. 99-08-DWQ) and/or (WQ Order No. 2009- 0009-DWQ); contingent upon SWRCB direction at the time of filing. The Contractor shall develop and submit to the Contracting Officer a Storm Water Pollution Prevention Plan (SWPPP) for the work in accordance with the state's guidelines and the Specification 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL that address the all pertinent SWPPP regulations, including the new regulations that become effective as of July 1, 2010. The Contractor shall implement the SWPPP prior to the start of soil-disturbing activity, and be responsible for all monitoring and maintenance until permanent erosion control has been established, as determined by the Contracting Officer. The SWPPP shall include Best Management Practices to prevent sediment, runoff from dust control, and oil and other chemicals used in construction from entering areas of wildlife habitat. The Contractor shall use fiber netting and other environmentally sound materials and methods as defined in Specification 01 57 23 TEMPORARY STORM WATER POLLUTION

CONTROL.

1.3.40 SCR-42 Grading Permit

Contractor shall obtain a Grading Permit from City of Sacramento prior to initializing work. Copy of work permit shall be given to the Contracting Officer prior to disturbing ground.

00 73 05 - 13

1.3.41 SCR-43 Cobbles

Contractor should be aware that cobbles may exist within the cutoff wall profile. No additional allowances will be allowed for working around cobbles.

1.3.42 SCR-44 Local Jurisdictions Permitting Requirements

Contractor shall obtain a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be incurred by the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.

1.3.43 SCR-45 Staging Area

Staging areas needed by the Contractor for the project have been identified in the Drawings and permits have been obtained for them by the Government.

If additional areas are needed, they will be the responsibility of the Contractor to obtain.

1.3.44 SCR-46 Suspended Pipe Under Bridge

There is an existing 14 inch diameter pipe suspended under a portion of the H Street Bridge. No attempt has been made to evaluate the structural integrity of this pipe and its hangers. If the Contractor proposes to use this pipe for lines crossing the river, he will have to perform a structural analysis of the pipe and its hangers to ensure that this pipe and its hangers are structurally sound and capable of holding the weight of the lines crossing the river.

1.3.45 SCR-47 Project Signage

The Contractor shall provide all signage for the project. Sign wording, sizes and other parameters shall be coordinated with the Contracting Officer and/or his/her representative.

1.3.46 SCR-48 Segregate and Stockpile Topsoil

R7 USACE's CONTRACTOR shall segregate and stockpile the first 12 inches of topsoil from any excavation activity that occurs on the site. The material should be returned following construction activity.

1.3.47 SCR-49 Areas of Bare Soil Site in the Staging Area

At the end of levee construction activities, areas of bare soil site in the staging area shall be disked or tilled to a depth of 8 inches and hydroseeded with a native vegetation mix including California brome (Bromus carinatus), small fescue (Vulpina microstachys), and creeping wildrye (Leymus triticoides). After the area has been hydroseeded and sufficient

00 73 05 - 14 precipitation has provided soil moisture to a depth of 2 inches, plugs of semi-mature native grasses consisting of approximately 90% creeping wild rye (Leymus triticoides) and 5% each Santa Barbara sedge (Carex barbarae) and slender sedge (Carex praegracilis) would be planted every 9 square feet throughout the site. Monitoring revegetation shall continue for three years or until native vegetation reaches 20% cover with less than 5% invasive non-native vegetative cover. Irrigation lines, if used, would be removed prior to the termination of the restoration contract.

1.3.48 SCR-50 Sacramento Regional County Sanitation District (SRCSD) Conditions

R7 USACE CONTRACTOR acknowledges the existence of Sacramento Regional County Sanitation District (SRCSD) sewer pipelines in the Premises and adjacent to the Premises, identified in the "American River Common Features WRDA96 Project, Phase 2 Remaining Sites, Sites R7 and L7, H Street Bridge Crossing" Project Contract Plans.

Due to the lack of ground cover over the existing sewer force mains, SRCSD has concerns over the potential loading impacts to the facilities by construction equipment on the proposed access roads and staging area; direct staging (static loads) shall not be placed over SRCSD facilities. SRCSD is requiring that plating will be placed on or around these facilities in order to mitigate any potential loading concerns. Plating shall be designed to handle the anticipated construction loads with a minimum of 40,000 pounds, whichever is greater. The Contractor shall be required to provide SRCSD with the loading information for all applicable construction equipment to be staged within the SRCSD easement (or over SRCSD facilities) as well as the means and methods used to mitigate the projected loading.

1.3.49 SCR-51 Pipeline Crossing on H Street Bridge

Contractor shall use the R7 Staging Area Jet Grout and Jet Grout Waste Management System to conduct the L7 side jet grouting. Contractor shall provide all necessary equipment, labor and materials to construct a jet grout pipeline crossing over H Street bridge.

BMP's must be in place to ensure if a jet grout or jet grout waste line ruptures, no contaminants will enter the river. Construct BMP's in accordance with Plans, Stormwater Pollution Prevention Plan (developed by QSD) and as directed by the Contracting Officer.

Contractor shall obtain and pay all fees necessary to obtain an Encroachment Permit from the City of Sacramento. This will require listing the City of Sacramento as an additional insured on the Contractor's liability insurance.

The Contractor is also responsible for the $1,000 per day fines for a closure of the bridge sidewalk if incurred.

The minimum sidewalk width requirements for the pipeline crossing of 4 feet, to included 5'x5' turnarounds every 200 feet (meeting ADA requirements).

Refer to the detail on Sheet G-103.

1.3.50 SCR-52 Coordination with City of Sacramento - Guy West Bridge Project Manager

The City of Sacramento is planning to rehabilitate and paint the Guy West Bridge just upstream of H Street Bridge between June and September 2014.

00 73 05 - 15

The Contractor shall coordinate with the Project Manager, Mr. Zuhair Amawi (916-808-7620) with the City of Sacramento, to assure that pedestrians are able to cross one of these bridges and access the bike trails at all times.

Contractor shall coordinate with the Contracting Officer prior to contacting the Project Manager or the City of Sacramento.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Document --