SF30 Amend 06.pdf
PDF 142 KB Posted
- Solicitation number
- W91238-12-R-0001
About this file
SF30 Amendment 06
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Design-Build (D-B) (2-Phase) of a Life Science Test Facility (LSTF) Bldg Addition, Dugw ay Proving Grounds, UT. This project is a D-B of a 41,200 SF permanent addition to the existing Life Sciences Test Facility (LSTF) building. Project w ill house test research, design, analysis and report w riting area for scientists, an area for calibration, maintenance and repair of sensitive laboratory instruments, an autoclave w ith supporting equipment, ten Bio-Safety Level 2 (BSL2), five BSL3 labs and one additional BSL3 Aerosol Chamber. The existing building w ill be renovated so that access to the new addition is through the existing LSTF. Subject to availability of funds.
This is a Full and Open (Unrestricted) Acquisition. Estimated Cost Range is betw een $ 25,000,000 and $ 50,000,000.
Purpose of this amendment is to extend the offer due date from 29 May 2012 to 30 May 2012 by 1:00 pm (Pacific Time)provide revisions to Section 00 22 20 for Key Personnel and revisions to the Pricing Schedule and Pricing Notes.
1. CONTRACT ID CODE PAGE OF PAGES
1 32
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-May-2012
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91238-12-R-0001
X 9B. DATED (SEE ITEM 11)
05-Jan-2012
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-May-2012
CODE
USACE SACRAMENTO DISTRICT
ATTN: CONTRACTING DIVISION
1325 J STREET
SACRAMENTO CA 95814-2922
W91238 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W91238-12-R-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION - CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
REVISION 2 PRICING SCHEDULE
CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL, EQUIPMENT, ETC. NECESSARY
TO PERFORM ALL WORK IN STRICT ACCORDANCE WITH THE TERMS AND CONDITIONS
SET FORTH IN THE CONTRACT TO INCLUDE ALL ATTACHMENTS THERETO.
LINE ITEM UNIT OF TOTAL
NO. DESCRIPTION QUANTITY MEASURE PRICE
BASE (DESIGN)
0001 Life Science Test Facility Addition - Design
FFP
The Contractor shall furnish materials, labor, equipment, facilities and transportation necessary to design the Life Science Test Facility Addition within the 5-foot building line and in strict accordance with this contract and its attachments.
1 Lump Sum $________________
0002 Sitework, Utilities & Sewage Lagoon - Design
FFP
The Contractor shall furnish materials, labor, equipment, facilities and transportation necessary to design the sitework, utilities and sewage lagoon outside the 5-foot building line in strict accordance with this contract and its attachments.
0003 Comprehensive Interior Design - Design
The Contractor shall furnish materials, labor, equipment, facilities and transportation necessary to prepare a Comprehensive Interior Design (CID) package in strict accordance with this contract and its attachments.
1 Lump Sum $_______________
BASE (CONSTRUCTION)
0004 Life Science Test Facility Addition - Construction
FFP
The Contractor shall furnish materials, labor, equipment, facilities and transportation necessary to construct the Life Science Test Facility Addition within the 5-foot building line and in strict accordance with this contract and its attachments.
0005 Sitework, Utilities & Sewage Lagoon - Construction
The Contractor shall furnish materials, labor, equipment, facilities and transportation necessary to construct the sitework, utilities and sewage lagoon outside the 5-foot building line in strict accordance with this contract and its attachments.
Sub-Total BASE Price (CLINS 0001 THRU 0005) $________________
OPTION ITEMS
1001 Energy Consumption Savings of 50%
Provide all material, labor, and equipment to design, construct and install the Life Science Test Facility Addition to the energy consumption savings of 50% below the consumption of a baseline building compared to ASHRAE Standard 90.1. Per Engineering and Construction Bulletin (ECB) No.2014-14, dated 28 June 2010, Item 3.
1002 Grey Water Recovery
Provide all material, labor, equipment to design, construct and install a grey water recycling system that will be used to capture grey water from lavatories, showers and floor drains, and reuse the gray water for dual flush toilets and urinals. The system shall comply with 2009 Uniform Plumbing Code (UPC) and in strict accordance with this contract and its attachments.
1003 Hot Water Solar Heating System
Provide all material, labor, equipment to design, construct and install passive solar hot water heating system that will supply 30% of the peak domestic hot water demand and is connected to the domestic hot water system to aid in heating the water as per FEMP requirements and in strict accordance with this contract and its attachments.
1004 Uninterruptible Power Supply (UPS)
OPA Funded
Provide all material, labor, equipment to procure and install deliver a UPS for critical systems (HVAC controls, laboratory computers, access control/intrusion detection, life safety systems, etc.) in strict accordance with this contract and its attachments. Note: UPS design and installation costs will be included in the base bid and will be MILCON funded.
1005 Large Sized Steam Sterilizers (Autoclaves) BSL3 Room AC1
OPA Funded
Provide all material, labor, equipment to procure and install deliver (2) two each large sized steam sterilizers in Room AC1 in strict accordance with this contract and its attachments.
Primus Pit Mounted Steam Sterilizer Model PSS8-L-MSDD or equal. Note: Steam sterilizers design and installation costs will be included in the base bid and will be MILCON funded.
1006 Medium Sized Steam Sterilizers (Autoclaves) BSL2 Room AC2
OPA Funded
Provide all material, labor, equipment to procure and install deliver(2) two each medium sized steam sterilizers in Room AC2 in strict accordance with this contract and its attachments.
Primus Steam Sterilizer Model PSS8-F-MSSD or equal. Note: Steam Sterilizers and design and installation costs will be included in the base bid and will be MILCON funded.
Sub-Total OPTION Price (CLINS 1001 and 1006) $________________
TOTAL BASE and OPTION Price (CLINS 0001 thru 1006) $________________
The following have been added by full text:
REVISION 2 PRICING NOTES
1. Prices must be submitted on all individual CLINS of this Pricing Schedule. Failure to do so may cause the proposal to be determined "unacceptable".
2. If a modification to a price is submitted which provides for a lump sum adjustment to the total price, the application of the lump sum adjustment to each item in the Pricing Schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every item in the Pricing Schedule.
3. The offeror shall distribute his indirect costs (overhead, profit, bond, etc.) over all the items in the Pricing Schedule. The Government will review all submitted Pricing Schedules for any unbalancing of the items. Any submitted Pricing Schedule determined to be unbalanced may cause the proposal to be determined "unacceptable".
4. Arithmetic Discrepancies - For the purpose of initial evaluation of offers, the following will be utilized in resolving arithmetic discrepancies found on the face of the Pricing Schedule as submitted by the offeror:
(a) Obviously misplaced decimal points will be corrected;
(b) Apparent errors in addition of lump-sum and extended prices will be corrected.
5. The successful offeror grants the options listed in the pricing schedule to the Government. Option CLINs 1001, 1002, and 1003 may be exercised any time up to 60 12 days after receipt of Notice to Proceed. Option CLINs 1004, 1005, and 1006 may be exercised any time up to 540 days after receipt of Notice to Proceed.
Exercise of the option occurs upon mailing of written notice to the Contractor. Exercise will be made by the Contracting Officer. The price for exercise of the option includes all work and effort associated with the scope of that item. No additional time for contract completion will be allowed when an option is exercised. The given contract completion time was formulated to include time necessary to perform all option work.
6. The target ceiling for contract award for design and construction is $28,192,000.00 (MILCON) based on the funds made available for this project. The Government cannot guarantee that additional funds can be made available for award. Offerors are under no obligation to approach this ceiling.
7. This requirement is included or provided for in the financial plan for fiscal year 2012. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available. The accounting classification will be 212 2050. This statement is not a commitment of funds.
The subject project is considered a high priority in that there is a high probability that the requirement will not be cancelled.
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been added by full text:
SECTION 00 22 20
PROPOSAL PHASE II INSTRUCTIONS AND EVALUATION
1 PHASE-TWO PRICE VOLUME.
1.1 NUMBER OF SETS OF THE PRICE PROPOSAL.
Submit the original (no copies) of the price proposal volume.
1.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE PRICE PROPOSAL.
Use only 8-1/2” x 11” pages. There are no page limits for the price proposal; however, limit responses to required information. Excess information will not be evaluated. Organize your price proposal as indicated below. If a tab is not applicable to your proposal, omit that tab but do not renumber the subsequent tabs.
PHASE TWO PRICE PROPOSAL VOLUME
TAB CONTENTS OF THE PRICE PROPOSAL
1 Proposal Cover Sheet
2 SF 1442; Acknowledgement of Amendments; Joint Venture Agreement
3 Pricing Schedule
4 Work Breakdown Structure
5 Representations, Certifications, and Other Statements of Offerors
6 Bid Guarantee
7 Pre-Award Survey Information
8 Subcontracting Plan
1.3 DETAILED SUBMISSION REQUIREMENTS FOR THE PHASE TWO PRICE PROPOSAL.
Tab 1 of the Price Proposal: Proposal Cover Sheet.
The proposal cover sheet is required by FAR 52.215-1 (c)(2). This provision, titled “Instructions to Offerors – Competitive Acquisition” is provided in full text in Section 00 21 00. The format and content for the proposal cover sheet follows:
PROPOSAL COVER SHEET
1. Solicitation Number:
2. The name, address, DUNS Number, and telephone and facsimile numbers of the offeror.
3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item.
4. Names, titles, E-MAIL address, and telephone and facsimile numbers of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation:
5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(End of Proposal Cover Sheet)
Tab 2 of the Price Proposal: SF 1442; Acknowledgement of Amendments; Joint Venture Agreement.
The Standard Form (SF) 1442 must be completed by the offeror and duly executed with an original signature by the official(s) identified in the proposal cover sheet as authorized to bind the offeror in accordance with FAR 4.102, which includes specific instructions pertaining to individuals, partnerships, corporations, Joint Venture participants, and agents. Include the offeror’s DUNS number in block 14 of the SF 1442, along with the offeror’s address. All amendments must be acknowledged in accordance with the instructions on the Standard Form 30, Amendment. If the offeror is a Joint Venture (JV), include a copy of the JV agreement and indicate its status. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the original SF 1442.)
Tab 3 of the Price Proposal: Pricing Schedule.
Submit the completed Pricing Schedule (Section 00 10 00) with the offeror’s proposed contract prices inserted in the appropriate spaces. Prices must be proposed for all contract line items. Unit prices must be extended to the actual “dollar and cents” amounts (e.g., to two decimal places). Do not round off the extended prices to the nearest dollar.
Check your pricing submission very carefully for mathematical and clerical errors prior to submission. Any qualification of pricing may render the proposal unacceptable and therefore not eligible for award. (Note: It is preferred, but not required, that you use a document protector in lieu of punching holes in the completed “original” pricing schedule.)
Tab 4 of the Price Proposal: Work Breakdown Structure.
Submit a Work Breakdown Structure of the offeror’s proposed contract prices using the format below, in accordance with Unified Facilities Criteria (UFC) 3-740-05.
01 SUBSTRUCTURE 11 ELECTRIC POWER AND LIGHTING
02 SUPERSTRUCTURE 12 ELECTRICAL SYSTEMS
03 EXTERIOR CLOSURE 13 EQUIPMENT
04 ROOFING 14 FURNISHINGS
05 INTERIOR CONSTRUCTION 15 SPECIAL CONSTRUCTION
06 INTERIOR FINISHES 16 SELECTIVE BUILDING DEMOLITION
07 CONVEYING SYSTEMS 17 SITE PREPARATION
08 PLUMBING 18 SITE IMPROVEMENTS
09 HVAC M2 19 SITE CIVIL/MECHANICAL UTILITIES
10 FIRE PROTECTION SYSTEMS 20 SITE ELECTRICAL UTILITIES
21 DESIGN EFFORT
Tab 5 of the Price Proposal: Representations, Certifications, and Other Statements of Offerors.
The offeror must have electronically completed the annual representations and certifications on the “Online Representations and Certifications Application” (ORCA) website in accordance with FAR 52.204-8 (provided in full text in Section 00 45 00). The offeror is responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete. Additionally, the offeror must also complete and return the “Representations, Certifications, and Other Statements of Offerors” included in Section 00 45 00 of the solicitation. If the offeror is a Joint Venture, all participants must separately complete both the ORCA Representations and Certifications and Section 00 45 00.
Tab 6 of the Price Proposal: Bid Guarantee.
All offerors must submit a bid guarantee, (e.g., Standard Form 24, Bid Bond) which complies with the requirements of FAR 28.101 Bid Guarantees, and any Defense and Army supplements thereto.
Tab 7 of the Price Proposal: Pre-Award Survey Information.
a. The contracting officer is required to make an affirmative pre-award determination of the prospective contractor’s responsibility in accordance with the mandatory requirements of Part 9 of the Federal Acquisition Regulation (FAR) and its supplements. The contracting officer must have sufficient information available to determine that a prospective contractor meets these minimum standards. Therefore, the offeror is requested to provide the pre-award survey information described below with its price proposal:
(1) The completed Construction Contractor Data Form with Supplemental Schedules A-C (see format which follows). If the offeror is a large multi-segmented business concerns, the data provided on the supplemental schedules may be limited to information that directly pertains to the specific segment of the business concern (i.e., the division, group, unit, etc.) proposed to perform work under the prospective contract with its own work force. If the offer is being submitted by a Joint Venture, submit a separate form for each Joint Venture participant. The offeror may submit pre-award survey information in another format, provided that the information furnished is substantially the same as that which would be furnished on the Construction Contractor Data Form and its supplemental schedules.
(2) Current financial statements. If the financial statement is more than 60 days old, submit a certificate stating that the firm's financial condition is substantially the same, or, if not the same, state the changes that have taken place. If a Joint Venture, provide this information for each participant in the Joint Venture.
(3) Banking information. Provide letters from banks or other financial institutions with which the contractor conducts business. The letters should contain information about your firm's accounts, loans, lines of credit, etc. The Government is interested in financial stability, timely payments, the length and nature of the relationship between the firm and the financial institution, and the firm's financial ability to perform the contract. The letters should also provide the name and telephone number of the bank representative the Government may contact. If a Joint Venture, provide this information for each Joint Venture participant.
b. The Government will treat the pre-award survey information submitted by the offeror as proprietary.
(Tab 7 of the Price Proposal: Pre-Award Survey Information)
CONSTRUCTION CONTRACTOR DATA DATE:
Firm Name and Telephone Number Main Office Address (Street, City, and State)
Branch Offices Services Rendered Construction Design Consultant
Organization Individual Joint Venture Partnership Corporation
Date Organized Date Incorporated:
State:
Names of Officers and Other Key Personnel
I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below) Partners:
Officers:
Other Key:
Remainder: Subtotal Permanent:
Maximum Personnel at Any Time:
Date:
Total:
II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF
(DATE): Present Value ($)
Current Assets:
Acquisition Cost ($) Current Liabilities:
Net Worth:
IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION
WORK IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE (LIST
MOST RECENT FIRST)
V—LARGEST JOB EVER
CONTRACTED
(If Other Than in Past Six Years)
$ LARGEST JOB IN PAST 6 YRS Contract Amount:
Date:
Description:
Owner:
$ Contract Amount:
Date:
Description:
Owner:
Avg. Annual Income
VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES
NAME AND POSITION/TITLE OF PERSON SIGNING
SIGNATURE
See attachment for explanations or detailed description of item(s) reported above.
CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS
List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.
CONTRACT
NUMBER
AMOUNT
DESCRIPTION/
LOCATION
ORGANIZATION/
CONTACT PERSON/
PHONE NUMBER
PERCENT
COMPLETE
CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS
List below the principal construction projects your firm has completed within the past six years, including all DoD contracts with a total value exceeding $ 22,000,000.00.
NUMBER
AMOUNT
DESCRIPTION/
LOCATION
ORGANIZATION/
CONTACT PERSON/
PHONE NUMBER
PERCENT
SUBLET
CONSTRUCTION CONTRACTOR DATA – SCHEDULE C –
CONSTRUCTION AND/OR TECHNICAL EQUIPMENT
List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.
QUANTITY
DESCRIPTION
CONDITION
YEARS OF
SERVICE
PRESENT
STATUS
Tab 8 of the Price Proposal: Subcontracting Plan.
a. All offerors submitting offers with a total value (including all options) exceeding $1,500,000 that are not small businesses are required to submit a subcontracting plan. The plan must be prepared in accordance with Public Law 95-507 and the following instructions and format, which conform to FAR 52.219-9(d)(1) through (d)(11) and include the required statutory elements as described in FAR 19.704 and the additional requirements of DFARS
219.704 and AFARS 5119.704. Evaluation of the subcontracting plan by the Government will be as prescribed in FAR 19.705 (and its supplements).
b. Do not just address the following issues in short; follow the guidance of FAR 52.219-9 in its entirety. The plan should address all records as described in FAR 52.219-9(d)(11)(i) through (vi).
c. In accordance with FAR 19.704 if the contract contains options, the cumulative value of the basic contract and all options is considered in determining whether a subcontracting plan is necessary. Once it has been decided if a plan is necessary, the subcontracting plan shall contain separate parts, one for the basic contract and one for each option.
d. In other words, it is necessary to address planned subcontracting dollars and percentages of the total to be awarded to small business concerns, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business concerns, small disadvantaged business, and with women-owned small business concerns separately for the basic contract period and each option period or option item.
e. If the subcontracting plan's proposed subcontracting goals do not meet the Corps of Engineers' subcontracting goals, the subcontracting plan must be submitted with a full explanation of the reasons for the lesser goals established by the plan. A small disadvantaged business goal of less than five percent must be approved one level above the contracting officer (DFARS 219.705-4).
2 PHASE TWO TECHNICAL PROPOSAL VOLUME.
2.1 NUMBER OF SETS OF THE TECHNICAL PROPOSAL.
The Phase Two Technical Proposal is to be submitted in one hard “original” and seven (7) copies. In addition, submit one complete copy of the technical proposal (minus any past performance evaluation information) on Compact Disk (CD) using a searchable “pdf” file format which will become part of the contract. Also include on the CD an electronic file (e.g., “.prx”) for the Network Analysis System (NAS) schedule (P3 preferred) required to be submitted under Tab 4 of the Technical Proposal.
2.2 FORMAT, CONTENTS, AND LIST OF TABS FOR THE TECHNICAL PROPOSAL.
Use 8-1/2” x 11” pages for the narrative portions of the proposal. There is not a page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below. The tabs directly correlate to the technical evaluation factors. Although the Government may use information contained anywhere within the technical proposal in its evaluation of any technical evaluation criteria, the Government is not obligated to search for or to consider information that is not located in the specified location.
Number the pages. Do not include information pertaining to your proposed pricing for this project in the technical proposal except as specified in the submittals under Tab 7, Socio-Economic Considerations. Limit your submittals to the information specified; excess information will not be evaluated.
PHASE TWO TECHNICAL PROPOSAL
TAB CONTENTS
4. FACTOR 4 – TECHNICAL SOLUTION
Technical Narrative
NAS Schedule Construction Approach Conceptual Design Leadership in Energy and Environmental Design Approach Offeror’s Statement of Compliance with 10 U.S.C. 2858
5. FACTOR 5 – KEY PERSONNEL
Key Personnel Resumes and Example Projects Demonstrating Qualification and Experience
6. FACTOR 6 – MANAGEMENT APPROACH
Project Organization Chart Management Plan Approach to Project Quality Control
7. FACTOR 7 – SOCIO-ECONOMIC CONSIDERATIONS
Proposed Small Business Participation
2.3 DETAILED SUBMISSION REQUIREMENTS AND EVALUATION CRITERIA FOR THE PHASE
TWO TECHNICAL PROPOSAL.
a. The Offeror is required to propose a specific project team including key subcontractors and key personnel for evaluation in response to this Request for Proposals. For purposes of this procurement, the terms “key subcontractors” and “key personnel” are used to refer only to the prospective subcontractors and proposed personnel whose qualifications, experience, and past performance will be evaluated by the Government as part of the source selection process. For reasons of efficiency, not all of the subcontractors and personnel critical to successful post-award contract performance have been included in this group. In order to streamline the proposal submission and evaluation process, please limit your submission to the information specifically requested. Information pertaining to other subcontractors or other personnel not designated as “key” by the Government will be considered excess and will not be evaluated.
b. For the purposes of this procurement, a key subcontractor is defined as any subcontractor performing “key” major work elements for which capability information is required to be submitted for evaluation as part of the Offeror’s technical proposal. The Government has designated the following major work elements as “key”:
--Design Firm --Containment Laboratory Construction Effort --Any Subcontractor performing work greater than $1,000,000.00
c. For the purposes of this procurement, a key person is defined as any person proposed for a key position whose resume is submitted for evaluation as part of the Offeror’s technical proposal. The Government has designated the following positions as “key”:
--Project Manager --Design-Build Project Manager --On-Site Project Superintendent --Design Coordination Manager --Contractor Quality Control (CQC) System Manager --Site Safety and Health Officer
d. The Offeror’s attention is directed to the clause in Section 00 73 00 titled “Key Personnel and Subcontractors”.
In accordance with this clause, any post-award changes to the key personnel and/or key subcontractors in the accepted proposal will require contracting officer approval.
e. Preface – Key Personnel Introduction.
Provide a summary list of the key personnel proposed for this project. For each named individual, identify their proposed position, their prospective employer, their proposed work location under the prospective contract, and their proposed duties, responsibilities and authorities. The submission is limited to two pages.
Tab 4 of the Technical Proposal: Factor 4 – Technical Solution.
1. Technical Narrative.
a. The plan/approach must be in sufficient detail to clearly demonstrate (1) the offeror’s understanding of the principal components of work described in the project specifications and drawings and (2) the offeror’s understanding of the site and other conditions that could impact schedule. The narrative should contain sufficient information to allow the Government to perform a basic analysis of the proposed approach.
b. Describe in general terms how the offeror will approach the design of the Life Science Test Facility Addition. If more than one Architect-Engineer design firm will be involved in the project, clearly distinguish the roles of each.
Also address any design effort that will be performed “in-house” by the prime contractor. Describe the roles and planned interaction between the Independent Technical Reviewers and various contractor and government personnel.
c. Describe in general terms how the offeror will approach the construction of the Life Science Test Facility Addition. The Government is interested in information such as: 1) site prep, 2) demolition, 3) utilities, 4) construction work discipline sequencings, 5) site work, and 6) clean-up. Identify any betterments included in the offer, i.e., those items, materials, equipment or processes that exceed the minimum requirements in the contract specifications, and discuss how these betterments increase value to the Government. Provide catalog cuts or other documentation necessary to clearly indicate the quality of the proposed betterments. The offeror shall make a statement that their design complies with the most current regulations, standards, codes, and Design Requirements.
d. Describes any significant problems or major difficulties anticipated in performing or accomplishing the work, challenges associated with this project, and offeror’s plan for avoiding problems and mitigating difficulties which could adversely impact project schedule. If no problems and difficulties are anticipated, state so and why.
e. Formatting and Other Restrictions: The submission is limited to six 8-1/2” x 11” pages total. Catalog cuts or other documentation necessary to clearly indicate the quality of proposed betterments can be provided separately from the six 8-12” x 11” page total.
f. Evaluation Criteria:
(1). The Government will evaluate the soundness and workability of the offeror’s approach and method to design and construct a containment laboratory with emphasis on mechanical and electrical systems. As part of its evaluation, the Government will consider whether the Offeror’s approach appears reasonable, realistic, achievable, and reflects logical sequencing and progression of activities.
(2). The greater the narrative demonstrate knowledge and understanding based on the specifications, drawings, site, and other conditions; the higher the evaluation rating.
(3). Offerors proposing betterments will receive higher evaluation ratings IF the proposed betterments are considered by the Government to be desirable and to add significant value to the project. The betterment will be evaluated to determine if the creative ideas of the offeror enhance the overall design and function of the project compared to the minimum criteria established in Section 01 10 10. Failure to provide any betterment(s) will not be considered a proposal weakness or deficiency.
(4). Offerors will receive a rating of no lower than “Marginal”, as long as the offeror has made a reasonable attempt to respond to the proposal submission requirements. Notwithstanding the above, an offeror who fails to provide the requested information for evaluation will receive an “Unacceptable” rating.
2. NAS Project Schedule.
a. Provide a hard copy of the NAS Project Schedule or GANTT chart (not a Pert Chart), broken down to the “Feature of Work” level, that graphically illustrates the proposed integration, scheduling, and phasing of the major features on the critical and near-critical path for this project, including final close-out. Also include an electronic file (e.g., “prx” of the NAS Schedule (Primavera P3 preferred)) on the CD containing the technical proposal.
b. The schedule is to include activities on the near critical and critical paths, including the following:
-NTP
-Charrette Meetings -Design Reviews:
Government, Contractor, Designer, -Independent Technical Reviews -Design review conferences -Construction activities broken down to the “Feature of Work” level -Adverse weather per section 01 00 00 -Pre Commissioning System Testing -Final Commissioning System Testing -Mechanical System Testing -Electrical System Testing -Test and Balancing -Landscaping -Contractor Punch-out Inspection items -Pre-final Inspection -Correction of pre-final inspection items -Final Inspection -Correction of Final Inspection items.
-Project Complete
c. Clearly indicate the following time frames:
(1) The durations of the principle components of work with anticipated start and finish dates. For the purpose of this pre-award design and construction sequence plan only, assume a Notice to Proceed (NTP) date of 25 May 2012.
Also include consideration of any option items on the chart that are on the critical or near-critical path. Assume for the purposes of this submission that the Government will exercise any options in the timeframe specified in the solicitation (see Pricing Schedule Notes).
(2) The total number of calendar days allocated to design (“hammock activities”)
(3) The total number of calendar days allocated to construction (“hammock activities)
(4) The total number of calendar days from NTP to Project Complete (“hammock activities)
d. The milestone schedule can not exceed the contract performance period specified on the SF 1442 and must also be in compliance with any contractually required interim completion dates specified in the solicitation for separate parts or stages of the work. (Should the offeror discover during proposal preparation that the project cannot be completed within the required contract performance period, please notify the Contracting Officer immediately.)
e. The Government’s requirement is that all design and construction on this project be completed within the number of days after Notice to Proceed as stated on the SF 1442, inclusive of all review periods and Government phasing requirements specified. The offeror may propose a completion period of lesser duration, subject to the following conditions
(1) If an offer is accepted which proposed a shorter performance period than that required by the Government, that proposed shortened performance period will be incorporated into and will become a binding part of the resultant contract. Additionally, any assessment of liquidated damages will be based on the shortened performance period accepted by the Government.
(2) A compliance statement completed by the offeror and duly executed with an original signature by an official authorized to bind the company must be included in the technical proposal under this tab. Failure to include this signed statement may render an offer which proposes a completion period of lesser duration ineligible for contract award.
f. As the NAS project schedule that is required to be included as part of the Technical Approach/Solution is a preliminary schedule for pre-award evaluation purposes only, the actual NAS project schedule submitted in the offeror’s Technical Proposal will not be incorporated into the contract. Therefore, the Government may at its discretion consider minor irregularities to be weaknesses in the proposal, rather than deficiencies. Nonetheless, the successful offeror will be required to submit a schedule after contract award that fully complies with all of the requirements of Section 01 32 01.00 10, whether or not all pre-award discrepancies were noted or corrected during negotiations.
g. Formatting and Other Restrictions.
(1). Include both a hard copy NAS Project Schedule in each copy of the technical proposal and an electronic file “.prx” of the NAS Project Schedule (Primavera P3 preferred) on the CD containing the technical proposal.
(2). There is not a page limitation for this submission; however, pages must not exceed 11” x 17” in size. Ensure the font size is legible so each activity and its duration can be read.
(3). Number line items on the NAS Project Schedule for easy reference.
h. Evaluation Criteria.
(1) The Government will evaluate the NAS Project Schedule to determine the extent to which it demonstrates (1) the Offeror’s understanding of the unique requirements and challenges of this project and (2) the Offeror’s ability to schedule and integrate the design and/or major work elements, construction and close-out activities critical to meeting the contract performance schedule specified in the solicitation. As part of its evaluation, the Government may consider whether the Offeror’s approach to the scheduling/phasing of these major activities appears reasonable, realistic, and achievable. The Government may also consider whether the Offeror’s approach to scheduling/phasing of major activities reflects logical sequencing and progression of activities; inclusion of all of the important features of the work; milestones along the critical path, incorporation of time for Government activities such as submittal review; and appropriate consideration of recognizable constraints, including material and equipment lead times and the impacts on construction activities of adverse weather typical for the construction site.
(2) Proposed schedule and approach that clearly reflect an understanding of the complexity of this project will be evaluated more favorably. Schedule and approach demonstrating professionalism and thoroughness will be evaluated more favorably. In addition, proposed schedules that reasonably demonstrate the ability to reduce the 900 day completion period from initial notice to proceed through completion of construction of all options will be evaluated more favorably. Preparation of the NAS schedule using Primavera (P3) and the Corps’ SDEF format in accordance with Appendix A to ER 1-1-11 will be considered an advantage.
(3) Offerors will receive a rating of no lower than “Marginal”, as long as the offeror has made a reasonable attempt to respond to the proposal submission requirements. Notwithstanding the above, an offeror who fails to provide the requested information for evaluation will receive an “Unacceptable” rating.
3. Construction Approach.
a. Provide your team’s solution for architect plan and construction needed to accomplish the project. Provide a basic description of the overall proposal for the Life Science Test Facility addition; site development including grading and drainage, utility connections and distribution, sewage lagoon, landscaping design, paving, etc.; architectural design incorporating the required construction; and the system and material proposed for the structural, mechanical, and electrical.
b. Discussion to include the prime contractor’s construction effort approach, specifically addressing work sequencing, work force utilization, subcontractor phasing and the proposed roles and interaction between the Design-Build Project Manager, On-Site Project Superintendent, Contractor Quality Control (CQC) System Manager, Site Safety and Health Officer and government personnel.
c. The narrative shall cover all features of the offeror’s unique construction solutions. The narrative should not be a recital of any Government provided specifications but should demonstrate how the offeror’s technical approach will result in additional quality and value to the Government. The elements covered must reinforce each other and be self-explanatory in presenting your technical approach. As appropriate, the narrative should cover, but not necessarily be limited to the following:
DEMOLITION – Describe elements to be demolished, sequence of work, safety methods, and disposal methods.
CIVIL – Include the rationale for the major features of the construction. Clearly delineate the elements of construction. Explain the inter-relationship of the new building(s) and landscaping with respect to parking, utilities, vehicular and pedestrian traffic, sewage lagoon and other features
ARCHITECTURAL - Describe the overall construction concept/approach and the relationship of the facility to the site. Describe interior and envelope building systems. Describe energy saving devices and long-term low-maintenance features. Also, describe how the proposed solution achieves compatibility with the surrounding buildings and/or natural environment and state any owner requirements. Describe force protection measures incorporated.
MECHANICAL – Provide a narrative description of the basic plumbing, and HVAC systems and tie-ins including manufacturer’s names and type/model of proposed equipment to be used. Describe any force protection measures incorporated into the mechanical construction.
ELECTRICAL – Describe the power distribution systems required for this project. The description should discuss major aspects of each system.
d. Formatting and Other Restrictions: The submission is limited to eight 8-1/2” x 11” pages total.
e. Evaluation Criteria: The construction approach specifically developed for this project will be evaluated for its soundness and workability in accordance with the elements identified in the above Para 3. Construction Approach.
Considerations will also include the proposed roles and interaction between the Design-Build Project Manager, On- Site Project Superintendent, Contractor Quality Control (CQC) System Manager, Site Safety and Health Officer and government personnel.
4. Conceptual Design.
a. The submittal requirement for this factor consists of both narrative and rendering drawings, as described below.
(1). The narrative shall cover all features of the offeror’s unique design solutions. The narrative should not be a recital of any Government provided specifications but should demonstrate how the offeror’s technical approach will result in additional quality and value to the Government. The elements covered must reinforce each other and be self-explanatory in presenting your technical approach. The narrative shall also include the proposed roles and interaction between the Architect-Engineer (A-E) firms), any proposed in-house designer, Independent Technical Reviewers, various contractor and government personnel. The offeror shall make a statement that their design complies with the most current regulations, standards, codes, and Design Requirements (Section 01 10 10). As appropriate, the narrative should cover, but not necessarily be limited to the following:
DEMOLITION – Describe elements to be demolished, sequence of work, safety methods, and disposal methods.
CIVIL – Include the rationale for the major features of the design. Provide a site-specific description of the vehicular and pedestrian traffic flow design, main entrance design and utility design, fire access design, site landscape design, and drainage plan. Describe how the analysis of geotechnical information has been used to develop an understanding of the proposed building foundation and pavement sections design. Emphasize any special features and force protection measures incorporated in the design.
ARCHITECTURAL – Describe the overall design concept/approach and the relationship of the facility to the site. Describe interior and envelope building systems. Also, describe how the design concept/approach proposed solution achieves compatibility with the surrounding buildings and/or natural environment and state any owner requirements. Describe force protection measures incorporated in the design.
MECHANICAL – Describe the design approach and the basis of design (summer/winter, indoor/outdoor design conditions for critical and non-critical systems). Provide a narrative design description of the basic plumbing, and HVAC systems. and tie-ins Describe any force protection measures incorporated into the mechanical design.
ELECTRICAL – Describe the power distribution systems design required for this project. The description should discuss major design aspects of each system.
(2). Drawings, if included, shall be in English measurements, 1/2 size (11” x 17”). The number of drawings is as deemed appropriate by the offeror to demonstrate an understanding of the complexity and extent of the project.
Suggested drawings are:
CIVIL
Civil Site/Grading Plan – Locate proposed improvements including: building footprint, parking, AC paving, curbs, walks, concrete slabs, access roadways and sewage lagoon. Plan shall also indicate drainage improvements, culverts, swales, and ditches.
Utility Plan – Locate utilities as necessary. Indicate required existing utility demolition and new utility entry points to building.
ARCHITECTURAL
Cover sheet with title, drawing index, schedule of gross and net area to assure that designs fall within the minimum area limitations in Section 01 10 10, and other information the offeror considers pertinent. Analysis shall cover: type of construction, height and area limitations, requirements for fire-rated walls, fire-rated doors, and means of egress and interior finish ratings.
Building plan(s) with sufficient detail to determine scope and function. Plans will show: walls, doors, windows, circulation, fixtures, casework & attached components, basic dimensions, room names and areas (square meters/square feet). Roof plan shall show roof configuration and different materials, drainage, skylights, and other significant information.
Exterior elevations.
Building section shall show major structural elements, walls, floors, ceilings, floor-to-floor distance(s), grade to roof peak, adjacent grade, and site element relationships.
Exterior perspective(s) shall show the building entrance, architectural features, walkways, finish materials, and planned site elements, including adjacent facilities. (One minimum perspective, in color, is required.)
ELECTRICAL
Lighting/Power/Communications Plans.
Show general exterior electrical and telecommunication points of connection, and include any related demolition required.
b. Formatting and Other Restrictions: The narrative submission is limited to eight 8-1/2” x 11” pages and the drawing submission is limited to ten size B (11” X 17”) drawings.
c. Evaluation Criteria: The design approach specifically developed for this project will be evaluated for its soundness and workability in accordance with the elements identified in the above Para 4. Conceptual Design.
Considerations will also include the proposed roles and interaction between the Architect-Engineer (A-E) firm(s), any proposed in-house designer, Independent Technical Reviewers, various contractor, and government personnel.
5. Leadership in Energy and Environmental Design Approach.
a. The purpose of the Leadership in Energy and Environmental Design (LEED) approach is to determine the offeror’s ability to incorporate, document, and obtain LEED certification. The narrative must therefore be in sufficient detail to clearly demonstrate (1) the offeror’s understanding of the principal components of work described in the project specifications and drawings and (2) the offeror’s understanding of the site and other conditions that could improve the overall LEED rating.
b. Describe in general terms the offeror’s approach to obtain possible LEED Green Building Rating System certification points in areas such as: 1) sustainable sites, 2) water efficiency, 3) energy and atmosphere, 4) materials and resources, 5) indoor environmental quality, and 6) innovation and design process.
c. Describe 1) proposed energy and environmental savings, 2) increased productivity, and 3) how performance will be verified.
d. Formatting and Other Restrictions: The submission is limited to four 8-1/2” x 11” pages.
e. Evaluation Criteria.
(1). The evaluation will include the extent to which it demonstrates the offeror’s understanding of the unique requirements and challenges of this project; 1) incorporating and documenting Leadership in Energy and Environmental Design (LEED) Green Building Rating System standards for environmentally sustainable construction, 2) proposing energy and environmental savings, 3) increasing productivity, and 4) verifying performance.
(2). The greater the proposed LEED certification points in the six major areas (sustainable sites, water efficiency, energy and atmosphere, materials and resources, indoor environmental quality, and innovation and design process), the more favorable the evaluation rating.
(3). The Leadership in Energy and Environmental Design (LEED) approach will be evaluated to the extent it demonstrates the unique requirements and challenges of this project and the documentation of possible LEED Green Building Rating System certification points.
6. Offeror’s Statement of Compliance with 10 U.S.C. 2858.
a. In accordance with 10 U.S.C. 2858, funds appropriated for military construction (including Base Realignment And Closure (BRAC)-funded and Family Housing-funded MILCON) may not be expended for additional costs involved in expediting a construction project without Secretarial level approval. Therefore, if the offeror proposes a completion period of lesser duration than the performance period on the SF 1442, a compliance statement completed by the offeror and duly executed with an original signature by an official authorized to bind the company must be included in the technical proposal.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .