OCT2026_NCSRM_IndusrtyDaySlides_PH1A SATOC FINAL.pdf
PDF 9 MB Posted
- Solicitation number
- W9123627Z13MA
About this file
This is an Industry Day presentation for the Norfolk Coastal Storm Risk Management (CSRM) Phase 1A Floodwall and Pump Stations project, held on October 29, 2026, by the U.S. Army Corps of Engineers Norfolk District.
The $6.2 billion overall Norfolk CSRM program includes storm-surge barriers, approximately 8 miles of floodwalls, nearly 1 mile of levees, nature-based features, 11 tide gates, and 10 pump stations. Phase 1A, spanning from Berkeley Bridge to Campostella, consists of 6 floodwall segments and 2 pump stations. A Single Award Task Order Contract (SATOC) valued at $200-$300 million with 4-6 task orders ($15M-$60M each) will be used for floodwall construction, with the base contract to be administered by USACE and awarded through negotiated procedures using best-value trade-off evaluation. The Phase 1A Water Street segment is being procured separately as a stand-alone $50-75M contract. The Harbor Park Pump Station ($40-60M) will be a design-build contract awarded by the City of Norfolk in January 2027, while Newton's Creek Pump Station ($100-150M) will be design-bid-build and advertised April 2028 with award targeted for October 2028. SATOC acquisition lead time is 12-24 months, with a 5-year base ordering period. A Project Labor Agreement (PLA) is mandated per Executive Order 14063 for contracts exceeding $35 million. All authorized funding is currently available. Proposals must be submitted through SAM.gov and the PIEE Solicitation module. Evaluation criteria include past performance, management approach, technical approach, small business participation plan, and seed project pricing. Small business subcontracting goals are under market research review. Sources Sought posting is anticipated for 2nd Quarter FY27 with a 2-week response deadline. Environmental permits required include VADEQ water protection certification, USACE regulatory clearance, VMRC review for future phases, Chesapeake Bay Preservation Act clearance, land disturbance permits, Coast Guard approval for navigable waters crossing, and SHPO cultural resources survey.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Industry Day Focus: Phase 1A FLOODWALL SATOC 29 October 2026
Norfolk District
NORFOLK COASTAL STORM
RISK MANAGEMENT
AGENDA
Opening Remarks MAJ Warner, Norfolk District Deputy Commander
Program Overview Chrissie Figueroa, Program Manager
City of Norfolk and USACE Partnership Kyle Spencer, City of Norfolk, Chief Resilience Officer
Phase 1A Floodwall and Pump Stations Phase 1A Floodwalls overview and status
Phase 1A SATOC Phase 1A Pump stations
Jenny Britt, Project Manager
Phase 1A Engineering Technical requirements by sub-phase
Stephen Reed, CSRM Design Team Lead, Engineering Division
Contracting Overview and Requirements Acquisition Planning and Strategy
Project Labor Agreement Pre-Solicitation Process and Procedures
Small Business Summary of Upcoming Contracts and Task Orders
Candace Lotomau, Contracting Officer, Chief of Contracting
Environmental Considerations and Constraints Chrissie Figueroa, Program Manager
Question and Answer Questions from Industry
Feedback, thoughts?
All
Closing Remarks
NORFOLK CSRM
PROJECT OVERVIEW
Chrissie Figueroa Program Manager
USACE
$6.2 Billion Project Storm-surge barriers Nearly 8 miles of floodwalls Nearly 1 mile of levees Nature Based Features Mitigation 11 tide gates 10 pump stations Home elevations Basement fills Commercial floodproofing
OVERALL PROGRAM OVERVIEW
BACKGROUND: FUTURE WITHOUT PROJECT (FWOP)
Without Project
1.4% AEP
Note: Assumes USACE Intermediate RSLR increase of 1.45 ft. from 2016
AEP = Annual Exceedance Probability NACCS = North Atlantic Coast Comprehensive Study RSLR = Relative Sea Level Rise
With Project 2075
1.4% AEP
Note: Assumes USACE Intermediate RSLR increase of 1.45 ft. from 2016
AEP = Annual Exceedance Probability NACCS = North Atlantic Coast Comprehensive Study RSLR = Relative Sea Level Rise
BACKGROUND: FUTURE WITH PROJECT (FWP)
DESIGN STATUS STRATEGY BY PHASE
Phase 1A Berkley Bridge to
Campostella 1A Water Street
Contract May 2027 In-House Design
SATOC
for remaining floodwall FY28 In-House Design, Non-Federal Sponsor Design, and AE
Design
Phase 1A Pump
Stations Harbor Park:
City of Norfolk Award DB
Construction Contract 2026
Newton's Creek:
AE Design-Bid- Build
Phase 1B Town Point
Park/ Waterside
AE Design-Bid- Build
Phase 1C/D Ghent to Town
Point Park/ Downtown
AE Design-Bid- Build
Phase 2 Pretty Lake
Surge Barrier
AE Design-Bid- Build
Phase 3 Lafayette
Outer Surge Barrier
AE Design-Bid- Build
Phase 4 Broad Creek Surge Barrier
AE Design-Bid- Build
OVERALL PROJECT SCHEDULE
FUTURE PHASE CONSTRUCTION COST ESTIMATE AWARD YEARS
Phase 5 – Non-Structural $500M – $600M FY27
Phase 1A – Newton's Creek Pump Station $100M – $150M FY29
Phase 1B – Town Point Park/Waterside $500M – $600M FY29-FY31
Phase 1C/D - West Ghent through Freemason $1B – $1.5B FY33-FY35
Phase 3 – Lafayette Surge Barrier $1B – $1.5B FY33-FY39
Phase 2 – Pretty Lake Surge Barrier $400M – $500M FY36
Phase 4 – Broad Creek Surge Barrier $500M – $600M FY37
Last Industry Day, February 2025
Feedback from Industry informed same scope contract benefits; Pump Stations are stand-alone and floodwall are separate scopes.
Smaller scope TOs/contracts are more acceptable.
Long lead times for significant utility relocations.
Phasing the floodwall construction allows for construction to start sooner.
Project Labor Agreement Considerations
Other Real Estate requirements
WHAT WE LEARNED SINCE LAST INDUSTRY DAY
PARTNERSHIP
Kyle Spencer Chief Resilience Officer
City of Norfolk
CITY OF NORFOLK PARTNERSHIP PROJECTS
NORFOLK CSRM PHASE 1A
OVERVIEW AND STATUS
Jenny Britt Project Manager
Overview:
6 Floodwall Segments Design-Bid-Build (DBB) Water Street standalone construction contract Harbor Park Floodwall: City design; SATOC with a seed project
PHASE 1A FLOODWALLS
PHASE 1A - FLOODWALL SATOC
USACE will administer the contract.
Acquisition will begin prior to utility relocations.
4-6 task orders planned.
SATOC Cost: $200-$300M Task Orders: $15M-$60M Award Seed Project – Harbor Park: June 2028
PHASE 1A PUMP STATIONS
Project Element Advertisement Scheduled
Award Cost Est
Harbor Park Pump Station (Design Build) City Contract
September 2026 January 2027 $40M-$50M
Newton’s Creek Pump Station and Tide Gate
(Design-Bid-Build) April 2028 October 2028 $100-$150M
Harbor Park Pump
Station
Newton’s Creek Pump
Station
Clay Ave. Bridge (Designed and
Constructed by City of Norfolk)
NORFOLK CSRM PHASE 1A
ENGINEERING ELEMENTS
Stephen Reed CSRM Design Team Lead
Engineering Division
PHASE 1A - WATER STREET
DRAFT
NOT FOR CONSTRUCTION
DRAFT
NOT FOR CONSTRUCTION
PHASE 1A - HARBOR PARK PUMP STATION
PHASE 1A - FERRY DOCK
DRAFT
NOT FOR CONSTRUCTION
PHASE 1A - HARBOR PARK
PHASE 1A - HARBOR PARK
PHASE 1A - RAILROAD
PHASE 1A – NEWTONS CREEK PUMP STATION
PHASE 1A – SUBSTATION
DRAFT
NOT FOR CONSTRUCTION
PHASE 1A – SOUTH BRAMBLETON
PHASE 1A - SATOC
CONTRACT REQUIREMENTS
Candace Lotomau Contracting Officer
District Contracting Chief
A SATOC was selected to ensure consistency throughout the Phase 1A Floodwall.
Starting construction soonest on the segments that ready for construction.
ACQUISITION PLANNING AND STRATEGY
Scope Phase 1A Floodwall SATOC
Contract Capacity $200-$300M
Contract Awards 4 to 6 TO’s
Task Orders $15M-$60M
SB Subcontracting Goal MR is ongoing.
Ordering Period 5yr base
Special Consideration(s) PLA
Acquisition Lead Time 12-24 mos
In accordance with EO 14063, Use of Project Labor Agreement for Federal Construction Projects, dated 22 January 2024, mandates PLAs for large construction projects within the United States, with an estimated contract cost of $35M or more.
What is a PLA?
- A pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f).
- Establishes terms and conditions of employment for a specific construction project, including:
• Provisions that bind all contractors and subcontractors to the agreement;
• No-strike, no-lockout clauses included; and
• Grievance/arbitration procedures.
- USACE will neither negotiate nor become signatory to a PLA.
- The Solicitation will require all prospective offerors to submit a fully negotiated PLA with its price proposal offer (RFO 52.222-33).
- The PLA would be incorporated into the contract at time of award.
PROJECT LABOR AGREEMENT
The Solicitation will contain RFO 52.222-33 and the following language will be included:
Synopsis: Offerors shall submit an offer subject to Project Labor Agreement (PLA) requirements in accordance with RFO 22.502-2, General requirements for project labor agreements. Any PLA reached pursuant to the PLA requirements in the solicitation does not change the terms of the contract or provide for any price adjustment by the Government.
Solicitation: Supplementary Conditions Section 00 73 00: “Offerors shall submit a copy of a Project Labor Agreement (PLA) with its offer as set forth in [insert section] of this solicitation. Any PLA reached pursuant to the PLA requirements in this solicitation does not change the terms of the contract or provide for any price adjustment by the Government.
See RFO provision 52.222-33, Notice of Requirement for Project Labor Agreement, and RFO clause 52.222-34, Project Labor Agreement, for definitions and requirements pertaining to the use of a PLA on this contract.”
Submitted PLAs shall be reviewed for compliance with all statutes, regulations, Executive Orders, and agency/contract requirements as part of the responsibility determination, in accordance with RFO Subpart 9.1. Identified areas of non-compliance will be addressed with the offeror and corrected during discussions, if discussions are opened.
Please respond to Sources Sought questions regarding PLA. If more than 1 offeror, PLA will be required.
Award will only be made to an offeror with a compliant PLA
PROJECT LABOR AGREEMENT CONTINUED…
ACQUISITION PROCEDURES
Submissions:
Pre-solicitation and solicitation publicized through…
Proposals must be submitted through the PIEE Solicitation module for consideration.
*Alternate forms of submission approved on case-by-case basis upon approval of KO.
Potential Evaluation Criteria:*
Factor 1 – Past Performance Factor 2 – Management Approach Factor 3 – Technical Approach Factor 4 – Small Business Participation Plan Factor 5 – Seed Project Price or Price Schedule
*Subject to change
SMALL BUSINESS
Size Standards http://www.sba.gov/size
SystemAward Management
(SAM)
http://www.sam.gov
Small BusinessAdministration http://www.sba.gov
KEY RESOURCES
MARKET RESEARCH:
SOURCES SOUGHT POST: 2nd QTR FY27
-Respond Not Later Than: 2 weeks from posted date
-PLEASE respond regardless of your socioeconomic category!
-ALL information you provide is considered when making any set-aside decisions, subcontracting goals, etc.
Deputy for Small Business Programs:
Stormie Wicks Stormie.B.Wicks@USACE.Army.Mil http://www.sba.gov/size http://www.sam.gov/ http://www.sba.gov/ mailto:Stormie.B.Wicks@USACE.Army.Mil
Project Element Scheduled Award Date
Cost Estimate Additional Notes
Phase 4 – AE TO Contract 2026 $3-7M 35% Design of Broad Creek Surge Barrier
Phase 1A East – AE TO Contract 2026 $3-7M 100% Design Campostella, Brambleton, and
Railroad portions of Phase 1A Phase 1A Harbor Park
Pump Station Construction 2027 $40-60M Design-Build contract by City of Norfolk
NCSRM Reviews – AE Contract 2027 $2-4M Complete Reviews for design on all phases of
NCSRM
Phase 1A Water Street -
Construction 2027 $50-75M Stand-alone Contract
Phase 1A Floodwall - SATOC Construction 2027/2028 $15-60M/task order SATOC w/Seed Project
Task Order #1 - PH 1A Harbor Park
SUMMARY OF SCHEDULED CONTRACTS AND TASK
ORDERS (NEXT 2 YEARS)
*Estimated based on timeline for utility relocations and real estate certification
ENVIRONMENTAL CONSIDERATIONS AND
CONSTRAINTS
Chrissie Figueroa Program Manager
37ENVIRONMENTAL & CULTURAL RESOURCES PERMITS
NEEDED FOR PHASE 1A
- Virginia Department of Environmental Quality (VADEQ) Water Protection Permit/Section 401 Water Quality Certification
– For impacts to waters of the US, including wetlands
- USACE Regulatory – Regulatory Guidance Letter (RGL) 88-05 – USACE does not issue permits to itself for Civil Works Projects. USACE would need to be applicant/co-applicant
- VADEQ General Construction Permit/SWPP – Contractor requirement issued by City of Norfolk since DEQ has delegated their authority to the localities
- Virginia Marine Resources Commission (VMRC) –The Attorney General’s office has confirmed that no permit is required for the flood control project and related measures. However, Baylor Grounds in future phases must be reviewed by VMRC
- Local Wetlands Board Permit – Permit is not required. Exempt from City of Norfolk
- Chesapeake Bay Preservation Act (CBPA) – Will need clearance and is issued by City and currently working with the city
- Land Disturbance Permit from City of Norfolk – Contractor obtains before start of construction
- Coast Guard – Permit or waiver, for bridge over navigable waters at Newtons Creek
- State Historic Preservation Officers (SHPO) - Submittal of Phase 1 Survey
QUESTIONS AND ANSWERS SESSION
1. Please confirm whether USACE intends to award the SATOC to a single prime contractor who would then receive all anticipated Phase 1A task orders (currently identified as approximately 4 to 6 task orders), or whether individual construction segments and task orders may be separately competed and awarded to other contractors outside of the SATOC.
Answer: Single Prime Contractor. There is a separate action being solicited for PH1A Water Street which is procured as a stand-alone contract.
2. Please provide the anticipated procurement and construction schedule for the Phase 1A Floodwall SATOC, including the anticipated dates for issuance of the Phase One solicitation, Phase One submissions and shortlisting, Phase Two solicitation, proposal due date, SATOC award, issuance of the first task order, and anticipated construction
NTP.
Answer: There will be one Phase for the SATOC. See overall schedule provided with next question.
QUESTIONS RECEIVED FROM INDUSTRY
3. Additionally, please provide the anticipated sequencing and approximate timing of the remaining 4 to 6 task orders over the five-year ordering period, to the extent currently known.
Answer:
QUESTIONS RECEIVED FROM INDUSTRY CONTINUED…
4. What portion of the approximately $250 million shared SATOC capacity is currently authorized and funded, and is funding available for the anticipated first task order?
Answer: All is authorized and funded.
5. What type of procurement and source-selection method does USACE anticipate using for the base SATOC award? Specifically, will the procurement use sealed bidding or negotiated procedures, and will award be based on low bid, lowest-price technically acceptable, or a best-value? Are qualifications comparatively valuable, or are they only a pass/fail before price?
Answer: Negotiated procedures using Best-Value Trade Off.
6. Please provide the status of utility relocations within the SATOC limits of Phase 1A.
Which relocations are expected to be completed by utility owners or the City before each task order, and which utility relocations or installations are expected remain within the scope?
Answer: Utility conflicts will be relocated or removed before construction.
Stormwater rerouting to Ph1 pump stations are in scope. Also, any extension of services to the project area is in scope, and in some cases there are utility penetrations during or after construction.
7. What is the anticipated scope, magnitude, and construction duration of the first task order, and what are the current target dates for release of the base solicitation, proposal due date, SATOC award, and first task-order notice to proceed?
Answer: Information forthcoming in sources sought.
Q & A SESSION
CLOSING REMARKS
Michael Darrow, PE, PMP Deputy District Engineer for Programs and Project Management Michael.R.Darrow@usace.army.mil
(757) 201-7112
Brandon Harris, PE Chief, Engineering Division Brandon.K.Harris@usace.army.mil
(757) 603-7014
Sarah Taylor, PE Deputy Chief, Engineering Division Sarah.m.taylor@usace.army.mil
(757) 284-1524
Christopher Adams Chief, Construction Division Christopher.G.Adams@usace.army.mil
(434) 484-2887
Stephen Reed, PE CSRM Design Team Lead, Engineering Division Stephen.W.Reed@usace.army.mil
(757) 201-7740
CONTACT INFORMATION
Candace Lotomau District Contracting Chief Candace.c.lotomau@usace.army.mil
(757) 201-7131
Stormie Wicks, MBA Deputy for Small Business Programs Stormie.B.Wicks@usace.army.mil
(757) 201-7077
Jennifer Britt (Jenny), PMP Project Manager Jennifer.m.britt@usace.army.mil
(757) 201-7455
Christyn Figueroa, PE, PMP Coastal Storm Risk Program Manager Christyn.D.Wiederhold@usace.army.mil
(904) 616-6593
Raven Sasser, MBA Senior Contract Specialist Raven.D.Sasser@usace.army.mil
(757) 201-7136 mailto:Michael.R.Darrow@usace.army.mil mailto:Brandon.K.Harris@usace.army.mil mailto:Sarah.m.taylor@usace.army.mil mailto:Christopher.G.Adams@usace.army.mil mailto:Stephen.W.Reed@usace.army.mil mailto:Candace.c.lotomau@usace.army.mil mailto:Stormie.B.Wicks@usace.army.mil mailto:Jennifer.m.britt@usace.army.mil mailto:Christyn.D.Wiederhold@usace.army.mil mailto:Raven.D.Sasser@usace.army.mil
| NORFOLK COASTAL STORM RISK Management |
| Agenda |
| NORFOLK CSRM�PROJECT OVERVIEW |
| Overall Program Overview |
| Background: future without project (FWOP) |
| Background: Future With project (FWP) |
| Slide Number 7 |
| Design Status Strategy by phase |
| Overall Project Schedule |
| What We Learned since last industry day |
| NORFOLK CSRM�Partnership |
| Slide Number 12 |
| CITY OF NORFOLK PARTNERSHIP PROJECTS |
| NORFOLK CSRM Phase 1a�overview and status |
| Phase 1A FLOODWALLS |
| Phase 1A - Floodwall Satoc |
| Phase 1A pump stations |
| NORFOLK CSRM PHASE 1A�ENGINEERING ELEMENTS |
| Engineering elements |
| PHASE 1A - WATER STREET |
| PHASE 1A - HARBOR PARK PUMP STATION |
| PHASE 1A - FERRY DOCK |
| PHASE 1A - HARBOR PARK |
| PHASE 1A - HARBOR PARK |
| PHASE 1A - RAILROAD |
| PHASE 1A – NEWTONS CREEK PUMP STATION |
| PHASE 1A – SUBSTATION |
| PHASE 1A – south brambleton |
| NORFOLK CSRM�PHASE 1A - SATOC�CONTRACT REQUIREMENTS |
| Acquisition planning and strategy |
| Project labor agreement |
| Project labor agreement continued… |
| Acquisition procedures |
| Small business |
| Summary of scheduled contracts and Task orders (next 2 years) |
| Environmental Considerations and constraints |
| Environmental & Cultural Resources Permits Needed for Phase 1A |
| Questions and answers session |
| Questions received from industry |
| Questions received from industry continued… |
| Questions received from industry continued… |
| Questions received from industry continued… |
| q & a session |
| Closing Remarks |
| CONTACT INFORMATION |