H.01.04 SPOE Fort Lee RTA Specifications 07.28.2021.pdf
PDF 5 MB Posted
- Attached to
- Ship Loading and Unloading Mock-up, Fort Lee, VA Federal contract opportunity
- Solicitation number
- W9123621B2040
About this file
This solicitation calls for proposals to construct a ship loading and unloading mock-up at Fort Lee, Virginia. Key requirements include building a replica cargo ship with two ramps to accommodate roll-on/roll-off vehicles, as well as supporting facilities like electrical service, emergency lighting, ventilation fans, an underground water storage system, and site improvements. Proposals are due by the date specified in the solicitation, which will then be evaluated for award. The selected contractor must follow all security protocols at Fort Lee and coordinate utility connections through the Contracting Officer. The work must be completed by the schedule defined in the final contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B.01.02_OF 1419 - Abstract of Offers Seaport Embarkation.pdf | ||
| 21B2040 Amend 5.pdf | ||
| H.01.01_W91236170001 - SPOE Fort Lee - M-001 2021.09.07.pdf | ||
| H.01.01_W91236170001 - SPOE Fort Lee - FA101 2021.09.07.pdf | ||
| Site Visit Sign-in Ship Loading and Unloading Mock-up.pdf | ||
| W9123621B2040 Amendment 004.pdf | ||
| H.01.04 Spec Section 31 31 16.pdf | ||
| H.01.04 Spec Section 01 45 00.00 10.pdf | ||
| W9123621B2040 Amend 3.pdf | ||
| 21B2040 Amendment 2.pdf | ||
| A.07.24 Amendment 0001 to Solicitation W9123621B2040.pdf | ||
| H.01.01 SPOE Fort Lee RTA Submittal Drawings 07.28.2021.pdf | ||
| W91236-21-B-2040 Solicitation.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US ARMY CORPS OF ENGINEERS
NORFOLK DISTRICT
BCOES Submittal Specifications Date: July 28, 2021 Contract: W91236-17-D-0001 Task Order:
W912620F0025
Design of Seaport of Embarkation Training
Facility (SPOE) Fort Lee, Virginia
277 Bendix Road, Suite 300 Virginia Beach, VA 23452
(757) 466-1732 (Main)
(757) 466-1493 (Fax)
SPOE Training Facility Contract No. W91236-17-D-0001 Fort Lee, Virginia
SEALS PAGE Page 1
SEALS PAGE
DESIGN PROFESSIONALS OF RECORD
Architect:
Kelly J. Olt, RA Lic. No. 11279
Civil/Site Engineer:
John G. Drake, PE Lic. No. 060060
Structural Engineer:
Matthew W. Wilde, PE Lic. No. 057870
SEALS PAGE Page 2
Fire Protection/Life Safety Engineer:
Martin H. Ford, PE Lic. No. 0408072
Mechanical Engineer:
Edward G. Bennett, PE Lic. No. 054463
Electrical/Telecommunications Engineer:
Keith J. Neubert, PE Lic. No. 048062
SEALS PAGE Page 3
Civil/Stormwater Engineer:
Amity B. Dewey, PE Lic. No. 055840
END OF DOCUMENT
SEALS PAGE Page 4
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00.00 50 2/2013 SUMMARY OF WORK FOR NORFOLK DISTRICT
PROJECTS
01 30 00 11/20 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 02/15 PROJECT SCHEDULE
01 33 00 08/18 SUBMITTAL PROCEDURES
01 33 29 02/17 SUSTAINABILITY REPORTING
01 35 26 11/20 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 11/16 QUALITY CONTROL
01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19 PROJECT IDENTIFICATION
01 74 19 02/19 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
01 86 12.07 40 02/18 RELIABILITY CENTERED ACCEPTANCE FOR
MECHANICAL SYSTEMS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 02/19 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 12 00 08/18 STRUCTURAL STEEL
05 30 00 05/15 STEEL DECKS
05 40 00 05/15 COLD-FORMED METAL FRAMING
05 52 00 02/18 METAL RAILINGS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 42 63 05/11 FABRICATED WALL PANEL ASSEMBLIES
07 53 23 05/12 ETHYLENE-PROPYLENE-DIENE-MONOMER
ROOFING
07 60 00 05/17 FLASHING AND SHEET METAL
07 92 00 08/16 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 33 23 08/20 OVERHEAD COILING DOORS
08 71 00 02/16 DOOR HARDWARE
DI VI SI ON 09 - FI NI SHES
09 90 00 05/11 PAINTS AND COATINGS
PROJECT TABLE OF CONTENTS Page 1
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 03 00.00 20 08/10 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 34 23.00 40 02/17 HVAC POWER VENTILATORS
DI VI SI ON 26 - ELECTRI CAL
26 05 19.10 10 05/16 INSULATED WIRE AND CABLE
26 20 00 08/19 INTERIOR DISTRIBUTION SYSTEM
26 51 00 05/20 INTERIOR LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 00 00 08/08 EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 32 19.16 02/21 GEOTEXTILE SOIL STABILIZATION
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 11 23 08/17 AGGREGATE BASE COURSES
32 15 00 05/17 AGGREGATE SURFACING
DI VI SI ON 33 - UTI LI TI ES
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 11 23 11/09 NATURAL GAS AND LIQUID PETROLEUM PIPING
33 40 00 02/10 STORM DRAINAGE UTILITIES
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DI VI SI ON 34 - TRANSPORTATI ON
34 73 13 11/19 TIEDOWNS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION 01 11 00.00 50
SUMMARY OF WORK FOR NORFOLK DISTRICT PROJECTS
2/2013
PART 1 GENERAL
1.1 DEFINITIONS
a. Facility: The facility is:
Seaport of Embarkation Training Facility (SPOE) Fort Lee, Virginia
CO: Contracting Officer or his authorized representative.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
Construct a new Seaport of Embarkation (SPOE) training facility with a replica of a cargo ship with two ramps to accommodate roll-on/roll-off capabilities of vehicles. Supporting facilities include electrical services for LED lighting in the interior, emergency and egress lighting, and ventilation exhaust fans located at the opposite end of the loading ramps; underground water storage system; new gravel hardstand; and site improvements.
1.2.2 Location
The work shall be located at Fort Lee where shown on the drawings.
1.3 PERSONNEL RESTRICTIONS
Personnel are limited to the immediate site areas and shall not enter buildings or facilities not involved in the work. All employees of the Contractor will be subject to all rules and regulations of the Facility which pertain to personnel. The Contractor shall erect fences and signs as specified and be responsible for the restrictions of all personnel. The Contractor's plans for restricting personnel access to the project site shall be submitted for approval as a part of the Safety Plan (Accident Prevention Plan). Facility access shall be restricted. Contractor shall comply with current security requirements. All vehicles shall be registered with the military police.
1.3.1 Security Requirements at Fort Lee
No employee or representative of the Contractor will be admitted to the work site unless he furnishes satisfactory proof that he is a citizen of the United States or has proper identification to work in the United States.
a. Personnel Information - All authorized non-military personnel utilizing the base are required to have in their possession at all times a Base Visitor Pass or Base Identification. This pass is issued by the Fort Lee Visitors Control Center located at 500 Lee Avenue, Building 5228.
Proof of identity is required to obtain a visitor pass or Base Identification. The Visitors Contol Center is open Monday through Friday
SECTION 01 11 00.00 50 Page 1 except Federal holidays from 8:00 a.m. to 4:00 p.m. A minimum of 5 working days prior to start of work, the Contractor shall furnish to the Fort Lee, Security Department, via the Contracting Officer, the following information for Contractor and subcontractor personnel required to enter the Station:
(1) Contract Number
(2) Beginning Date (Month, Day, Year)
(3) Ending Date (Month, Day, Year)
(4) Name of the company (The Prime Contractor and Sub Contractor)
(5) Full Name of the employee (First, Middle and Last)
(6) Address of Current (Employee's) Residence (Bldg#, Street, City, State, Zip or City and Country)
(7) Social Security Number (SS#)
(8) US Citizen (Yes / No)
(9) Gender (Male/Female)
(10) Race (American Indian or Alaska Native, Asian, Black or African American, Native Hawaiian or Other Pacific Islander, and White)
(11) Date of Birth (Month, Day, Year)
(12) Place of Birth (City, State, Country)
b. The Fort Lee Security Department will run a criminal history check on Contractor employees as a condition of employment. Official proof of identity or naturalization papers may be required, which will be returned once entered into the security computer system. Based on the results of the criminal history check, the Security Officer will or will not grant entry to the Station. If entry is denied, the Contractor will be immediately notified. Fort Lee Security may require updating or rechecking criminal history based on the duration of the contract. NOTE: Fort Lee Security has been denying entry to persons whose police record checks are positive. Failure to obtain entry approval will not affect the contract price or time of completion.
c. Proof of Identity -Official identification can consist of copies of birth certificates, valid federal identification, valid state identification, or valid naturalization papers. Examples of official identification are valid state issued driver's license, military ID card, military dependent ID card, green card, etc. Expired identification is not valid.
d. Base Entry Passes - Contractor base entry passes will be valid for each entry aboard Fort Lee from 6:00 a.m. to 6:00 p.m., Monday through Friday except for Federal holidays, unless prior arrangements have been made with the Contracting Officer, and Fort Lee Security has been notified. The passes are the property of the base and are to be returned to Visitor's Control Center upon completion of the contract or termination of employment. Replacement passes must be requested in writing and be accomplished by written authorization from the Contracting Officer.
SECTION 01 11 00.00 50 Page 2
Compliance with this requirement is mandatory and certification thereof to the Contracting Officer is required prior to submitting final invoices.
Failure to return badges will hold up Contractor's final payment.
e. Contractor Responsibility for Employees - The Contractor is responsible for employees under his employment. Ensure that employees are familiar with and obey station traffic, safety, and security regulations.
f. Unofficial photography, cameras, or photographs are prohibited on Fort Lee property. When official photographs are required, submit a written approval request containing specific justification and details to the Contracting Officer 5 days prior.
g. Firearms, Weapons, Alcoholic Beverages, Illegal Drugs, and Contraband are prohibited on Fort Lee property. Violators may be prosecuted. State issued/authorized concealed weapons permits are not valid on Federal (Fort Lee) property.
h. Motor Vehicle Operation - Ingress and egress of personnel will be subject to the Fort Lee security regulations.
(1) All personnel must be made aware of the base speed limits:
25 mph (unless otherwise posted)
Speed limits are enforced and violators will be ticketed. Fort Lee traffic violations are processed through the federal court system.
(2) Seat belts are MANDATORY.
(3) Parking is in designated areas only, between two white lines. No parking is permitted in fire lanes, on seeded areas, in reserved parking slots, or assigned handicapped parking. Any equipment or vehicle that does not fit within a standard parking space must contact the Contracting Officer to determine a designated area for parking such equipment or vehicle.
Contractor employees shall park vehicles (Commercial or Private) in areas designated by the Contracting Officer. This area may or may not necessarily be within reasonable walking distance of the construction site. The contractor shall provide transportation between the parking area and the construction site. Contractor employee parking shall not interfere with existing and established parking requirements of the Base.
(4) Traffic accidents should be reported immediately by calling 911 or 804-734-7400 for non-emergencies.
(5) All personnel entering the installation are subject to random vehicle inspections/searches at any time while on the base. The purpose of these inspections is to detect the theft of Government and private property, firearms, weapons, alcoholic beverages, illegal drugs, or contraband.
(6) Information required for Vehicle Passes- Driver's are required to bring the vehicle, contract number, vehicle registration, copy of vehicle insurance policy, valid state inspection documentation, and valid driver's license to the Visitor Control Center. Vehicles without passes will not be allowed entry to base.
SECTION 01 11 00.00 50 Page 3
i. Commercially Owned Vehicles - All commercial Vehicles are to clearly display the authorized company name or logo on both sides of the vehicle.
ii. Privately Owned Vehicles - No Privately Owned Vehicles will be allowed within secure/controlled industrial areas located on Fort Lee.
iii. Rental Vehicles - The driver is to show all paper work from the rental company showing that the driver is authorized to operate the subject vehicle. Rental vehicles will not be allowed in secure/controlled industrial areas located on Fort Lee unless the rental vehicle clearly displays the authorized operating company name or logo on both sides of the vehicle.
i. Access to Restricted Areas - Base entry passes allow access to designated areas on the installation only. Entries into secure/controlled industrial areas are prohibited unless the contract requires it.
j. Current Information - Contractors will be responsible for keeping the vehicle and employee lists current, and for securing and returning identification cards belonging to terminated employees to the Fort Lee Security Department.
k. Providing Information to Subcontractors - Prime Contractors shall be responsible for ensuring that subcontractors receive security information. Failure to comply with the specified requirements will result in prime contractors and subcontractors being denied access to the construction site.
l. Fort Lee is not responsible for job site security. Removal of material from job-site and base are subject to security checks.
Contractor is to notify Fort Lee security of any special measures (watchmen, alarm, etc), security concerns, security problems, or unusual activities within the job site.
1.4 TRANSPORTATION FACILITIES
The Facility is served by an all weather surfaced road network. Road(s) within the Facility proposed to be used by the Contractor shall be subject to prior approval of the Facility authorities and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition. All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.
1.4.1 Use of Roads
Hard-surfaced roads from major and primary municipal roads serve the Facility. The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights. Facility speed limits and traffic controls shall be observed.
SECTION 01 11 00.00 50 Page 4
Any lane closure or activity that impacts traffic or travel requires notification and approval at least two weeks in advance. Any request for closure shall include complete details of alternate route to include electronically submitted drawings. If approved, proper routing, signage, and traffic control will be provided at contractor's expense.
Notification will be submitted through the Contracting Officer.
1.4.2 Road Restrictions
The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. Other roads may be used only with the approval of the CO.
1.4.3 Cleated Vehicles
Cleated vehicles shall not be moved over surfaced roads except at the immediate site of the area where they are to be used.
1.5 SPECIAL CONTRACTOR REQUIREMENTS
1.5.1 COORDINATION IN WORK AREAS
1.5.1.1 Utilities
Utilities on Fort Lee, including electric, water, sewer, telephone, and cable are operated by privatized utility companies. Coordinate connection and disconnection of utilities through the Contracting Officer.
1.5.1.2 Unoccupied Work Area
The area where the Contractor is scheduled to perform the work will not be occupied during the work, however, the Contractors work activities may affect other area(s) that are occupied. All work shall be in accordance with the Contractor's work plan.
1.5.1.3 Maintenance of Utilities
Any utility outage requires 2 week notification and approval through the Contracting Officer. Any active utilities, including but not limited to electricity, gas, water, sewer, heating, air conditioning, or any like service, that will require interruption or replacement in any occupied area affected as a result of the Contractors scheduled work activities, shall be temporarily provided by the Contractor at his own expense until the affected service is fully and permanently restored. All temporary method(s) of service replacement the Contractor proposes for use on this contract shall be approved by the CO prior to commencing the work.
1.5.1.4 Hours of Work
The normal work hours for construction shall be from 8:00 a.m. to 4:30 p.m. Monday through Friday of each week. Any request to change these hours shall be made in writing to the Contracting Officer at least two calendar days prior to the desired day on which the change is to go into effect. The changed hours shall not go into effect until written permission has been received from the Contracting Officer.
SECTION 01 11 00.00 50 Page 5
1.5.1.5 Existing Utility Location
Existing utilities must be located before doing any digging work on the Facility. The Contractor shall be responsible to contact the USAG Fort Lee Public Utilities Specialist/Contract Officer's Representative through the office of the COR, obtain all necessary utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of his work. It shall be the responsibility of the Contractor to contact the USAG Fort Lee Public Utilities Specialist/Contract Officer's Representative through the office of the COR for locating commercial utilities 48 hours prior to digging operations. The contractor shall be responsible for maintaining marked utilities. The contractor shall be responsible for maintaining utility markings.
1.5.1.6 Digging Permits
Contractor is responsible for obtaining all digging permits, including associated locating and marking services, in accordance with installation and local requirements, at no additional cost to the Government.
"Clearance Permits for Digging', must be obtained before doing any work on Facility. The Contractor shall be responsible to obtain all necessary digging permits and pay costs associated with the permit,which may be necessary to accomplish his work.
1.5.1.7 Personnel Escort
An authorized Contractor representative must escort all personnel attempting to obtain a badge to Security. The representative shall sign documentation that the employee meets Security criteria and is suitable for a badge to be issued.
1.6 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.6.1 Schedule
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
SECTION 01 11 00.00 50 Page 6
BASED ON (5) DAY WORK WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Fort Lee 10 9 9 6 8 7 8 7 6 5 7 9
1.6.2 Records
Upon acknowledgement of the Notice to Proceed and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
1.6.3 Impacted Days
The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.8 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Notify the Contracting Officer at least 15 days prior to starting excavation work.
SECTION 01 11 00.00 50 Page 7
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the storage area located on site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
1.9 PHYSICAL DATA
The physical conditions indicated on the drawings and in the specifications are the result of site visits, surveys, and borings. See civil drawings.
1.10 SITE CONTAMINATION
This site is a former industrial site which is perceived to be a clean location.
1.10.1 Contamination Removal
In the event that contamination is encountered, the Contracting Officer shall be advised immediately. The contamination shall be removed as directed and replaced with satisfactory material. Payment therefore will be made in conformance with the CHANGES clause of the CONTRACT CLAUSES.
1.10.2 Compliance Requirements
The Contractor shall comply with applicable Federal, state and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with any hazardous material, substance or waste.
1.10.3 Requirements
The requirements of this clause and any act or failure to act by the Government shall not relieve the Contractor of any responsibility or liability for the safety of Government, Contractor or subcontractor personnel or property.
1.11 INTERRUPTIONS OF UTILITIES
1.11.1 Approval
Utility services shall be interrupted by the Contractor to relocate, make connections, or interrupt for any purpose, without written approval of the
CO.
1.11.2 Request
Request for permission to shut down services shall be submitted in writing to the CO not less than 10 calendar days prior to date of proposed interruption. The request shall give the following information:
a. Nature of Utility (Gas, L.P. or H.P., Water, Electrical, Communications, Fire Alarm Systems, Security Systems)
SECTION 01 11 00.00 50 Page 8
b. Size of line and location of shutoff.
c. Buildings and services affected.
d. Hours and date of shutoff.
e. Estimated length of time service will be interrupted.
1.11.3 Service Interruptions
Services shall not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.
1.11.4 Timely Disconnections
Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or non-work days of the Using Agency without any additional cost to the Government.
1.11.5 Utilities Operation
Operation of valves on water mains will be by Government personnel. Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Facility Fire Department shall be notified by the Contractor in writing 72 hours prior to the proposed interruption. The Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay and shall restore service without delay in event of emergency.
1.11.6 Gas
Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas line have been shut off.
1.12 HISTORICAL AND ARCHAEOLOGICAL FINDS
Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by
SECTION 01 11 00.00 50 Page 9 reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the applicable clauses of the contract.
1.13 SUBCONTRACTS AND WORK COORDINATION
Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:
a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.
b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.
c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.
d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.
1.14 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT
The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.
1.15 PURCHASE ORDERS
To ensure proper expediting of orders the Contractor and his subcontractors shall furnish to the Contracting Officer, one copy of each purchase order covering supplies or services required for performance of the work. Each purchase order shall clearly indicate the date of placement, the date delivery is required in order to avoid delay in the scheduled progress of the work, and the date delivery is promised by the supplier or producer. Copies of purchase orders shall be forwarded on the date issued.
1.16 PROFIT
1.16.1 Weighted Guidelines
Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value
Degree of Risk 20 Relative difficulty of work 15
SECTION 01 11 00.00 50 Page 10
Factor Rate Weight Value Size of Job 15 Period of performance 15 Contractor's investment 05 Assistance by Government 05 Subcontracting 25
1.16.2 Value
Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
1.16.2.1 Degree of Risk
Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
1.16.2.2 Period of Performance
The period of performance shall be 30 days from the issuance of notice to proceed.
1.17 BLASTING
Blasting will not be permitted.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00.00 50 Page 11
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
SECTION 01 30 00 Page 1
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State of Virginia Law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION CONFERENCE
Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting Conference . The meeting conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
SECTION 01 30 00 Page 2 daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.
1.8.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction Post-Award Kickoff meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G RO
Preliminary Project Schedule; G RO
Initial Project Schedule; G RO
Periodic Schedule Update; G RO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
SECTION 01 32 01.00 10 Page 1
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
SECTION 01 32 01.00 10 Page 2
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Long procurement activities
d. Submission and approval of O & M manuals.
SECTION 01 32 01.00 10 Page 3
e. Submission and approval of as-built drawings.
f. Submission and approval of DD1354 data and installed equipment lists.
g. Submission and approval of testing and air balance (TAB).
h. Submission of TAB specialist design review report.
i. Submission and approval of fire protection specialist.
j. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
k. Air and water balancing.
l. Building commissioning - Functional Performance Testing.
m. Controls testing plan submission.
n. Controls testing.
o. Performance Verification testing.
p. Other systems testing, if required.
q. Contractor's pre-final inspection.
r. Correction of punch list from Contractor's pre-final inspection.
s. Government's pre-final inspection.
t. Correction of punch list from Government's pre-final inspection.
u. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
SECTION 01 32 01.00 10 Page 4
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a
SECTION 01 32 01.00 10 Page 5 building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to permits, construction submittal, procurement, fabrication, weather…