Maintenance Dredging of Waterway on the Coast of Virginia Bradford Bay Accomack County Virginia
Solicitation number
W9123620B0009
Issued by

About this file

This document is an amendment to a solicitation for maintenance dredging services. The solicitation is for dredging approximately 118,000 cubic yards of material from Bradford Bay Channel and Finney Creek in Accomack County, Virginia and placing it in an overboard placement site within Bradford Bay. A hydraulic cutterhead dredge will be used to complete the work. The required response date was extended from January 14, 2020 to January 21, 2020. Bidders must perform before- and after-dredging surveys of the overboard placement area. Permits from the Virginia Marine Resources Commission and the Virginia Department of Environmental Quality as well as a letter from the Accomack County Department of Environmental Programs are included as attachments. The work must be completed within 135 days of receiving a notice to proceed with the option to add additional time if optional items are exercised or quantities exceed estimates. Invoices should be sent to the U.S. Army Corps of Engineers Norfolk District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

W91236-20-B-0009 for Bradford Bay Maintenance Dredging is hereby amended as follow s:

Please see continuation page for full Amendment breakout.

Contracting POC: Allen Scott Brainerd (757) 201-7668 allen.s.brainerd@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Dec-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123620B0009

X 9B. DATED (SEE ITEM 11)

09-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Dec-2019

CODE

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123620B0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 1

W91236-20-B-0009 Bradford Bay Maintenance Dredging is hereby Amended as follows:

1 .Bidder Inquiry on ProjNet closeout date is hereby changed from 7 January 2020 to 14 January 2020

2. Bid Opening date changed from 14 January to 21 January 2020

3. Bidder Inquiries and Corresponding Government Responses are hereby incorporated:

Bidder Inquiry number 8307676

a. Section 01 57 20 paragraph 3.1.1 states “The Contractor shall adhere to and perform all requirements stated in the Virginia Department of Environmental Quality and Virginia Marine Resource Commission permits”. Please have these permits sent out once acquired, to the Contractors so that they may be reviewed prior to the bid date.

Government Response to Bidder Inquiry number 8307676: Referenced permits will be included through an amendment to the solicitation.

Bidder Inquiry number 8307747

b. Are there any core borings available for this project? If so, can those please be sent out to the Contractors?

Government Response to Bidder Inquiry number 8307747: There have been no core borings or other tests done within the contract dredging area. It is expected that the material to be dredged is shoaled material from relatively recent sediment transport and deposit, mostly silts and fines.

Bidder Inquiry number 8307776

c. Is it to be assumed that the majority of material to be removed will be silt?

Government Response to Inquiry number 8307776: Please refer to government response to bidder inquiry number 8307747. It is expected that the material to be dredged is mostly silts and fines.

Bidder Inquiry number 8307791

d. It is understood that the Contractor is responsible for performing an after dredge survey of the overboard placement area. Who will be responsible for performing the pre-dredge survey of the overboard placement area?

Government Response to Inquiry number 8307791: An amendment will be issued to specify that a Before Placement and After Placement survey of the overboard placement area will be performed by the Contractor.

Bidder Inquiry number 8307805

e. The preferred route for the discharge pipeline is shown on the contract drawings. If the Contractor is to use the provided pipeline route, will there be any areas that need to remain floating? If so, can you please detail on the plan drawings which areas need to remain floating.

Government Response to Inquiry number 8307805: The pipeline may be floated in all areas other than where the pipeline is to cross the navigation channel. Refer to provisions in specification section 35 20 23 and EM 385-1- 1.

Bidder Inquiry number 8307812

f. Section 01 57 20 paragraph 3.3.1.1 "Any pipeline across the bounds of the public or private leased oyster and shellfish grounds shall be floating" In areas that the pipeline is required to be floating, will the Contractor be allowed to use anchors for their pipeline in order to keep it in place?

Government Response to Inquiry number 8307812: The contractor shall comply with all the provisions within EM 385-1-1 and the specifications regarding the use of submerged and floating pipelines.

Bidder Inquiry number 8308292

g. Please detail on the plan drawings where the designated staging area will be for the contractors use. (fueling, crew changes, etc.). It is critical that this staging area be provided to the Contractor prior to bid date as the lack thereof could render this project unbidable due to its location.

Government Response to Inquiry number 8308292: No staging area will be designated by the Government. It will be the Contractor’s responsibility to coordinate and secure a staging area (local marina or facility), if needed.

Bidder Inquiry number 8312868

h. For clarity, will the Contractors pipeline need to remain floating from the Lower Bradford Bay Channel approximately Sta. 38+54 to 112+00?

Government Response to Inquiry number 8312868: The pipeline does not need to remain floating, but needs to be safely secured to not impede navigation. Refer to section 35 20 23 and EM 385-1-1.

4. In Section 35 20 23 paragraph 1.4.4 Before Dredging Surveys, add the following paragraph after the existing paragraph:

“Perform a Before-Dredging-Survey of the overboard placement area prior to dredging. Survey shall be performed by an independent surveyor registered in Virginia and hired by the Contractor.”

5. In Section 01 57 20, include the attached permits and letters from the Virginia Marine Resources Commission, Department of Environmental Quality, and County of Accomack Department of Environmental Programs, outlined below.

VMRC Permit 2019-0900 VMRC Permit 2019-0900 Yellow Placard DEQ Permit 12-1255 Modification County of Accomack Department of Environmental Programs Letter

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 14-Jan-2020 02:00 PM to 21-Jan-2020 02:00 PM.

The Issued By organization has changed from

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510-1096

to

USA ENGINEER DISTRICT, NORFOLK

803 FRONT STREET

NORFOLK VA 23510

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

INSTRUCTIONS

1. PROJECT DESCRIPTION

Maintenance Dredging of Water on the Coast of Virginia (WCV) Bradford Bay, involves dredging approximately 118,000 cubic yards of material from Bradford Bay Channel and Finney Creek, and placement of the material within the 1000’ by 1000’ overboard placement site within Bradford Bay. A hydraulic cutter head dredge will be used to accomplish this work. Maximum pay depth (required + allowable), including optional work, will be -8 feet MLLW.

2. BIDDERS QUESTIONS AND COMMENTS:

All questions and/or comments shall be submitted via Projnet no later than 14 January 2020 at 02:00 PM Eastern Standard Time (EST).

The Government reserve the right not to respond after the deadline. Responses to questions and/or comments will be posted to www.Beta.SAM.gov.

The Bidder Inquiry System will be available the same day as the solicitation and unavailable for new inquires 7 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Therefore, all questions and/or comments should reach the above referenced Contracting Office via ProjNet no later than 14 January 2020.

Technical inquiries and questions relating to Invitation for Bid (IFB) procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue. From this page you may view all bidder inquiries or add inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team. The Solicitation Number is W91236-20-B-0009. The Bidder Inquiry Key is: AHHJYB-79ZM54 The Bidder Inquiry System will be unavailable for new inquires 7 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

3. BID EVALUATION AND AWARD

The Government will evaluate bids in response to this solicitation based upon the Total Evaluated Price without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government considering only price and the price-related factors specified elsewhere in the solicitation. The Government may reject any or all bids and accept other than the lowest bid; and/or waive informalities or minor irregularities in bids received.

4. AWARD TO RESPONSIBLE OFFEROR

To be determined responsible, a bidder must –

a) Have adequate financial resources to perform the contract, or the ability to obtain them;

b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;

c) Have a satisfactory performance record. A prospective contractor shall not be determined responsible or non-responsible solely on the basis of a lack of relevant performance history;

d) Have a satisfactory record of integrity and business ethics;

e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors);

f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and

g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations

In accordance with FAR Part 9.1, responsibility will be determined, prior to award, by the Contracting Officer through the performance of a pre-award survey or utilizing information from a previous pre-award survey and/or any performance data available. The apparent low bidder may be required to show that he has the necessary capital, experience, and owns or can procure the necessary plant or other resources to commence the work at the time prescribed in the specifications and thereafter to prosecute and complete the work safely and satisfactorily within the time specified. The below information will be requested of the apparent low offeror. This information is not required to be responsive to the invitation for bid.

h) Banking Information to include Branch/Location, Point of Contact and Telephone Number. Please insure the Bank is prepared to provide necessary information regarding average balances in your operating accounts, lines of credit and credit history.

i) Current commitments and expected dates of completion

j) Award to Responsible Offerors, Evidence of Authority to Sign Offers, Pre-Award Safety Conference, Incurring Costs, Agents, Unbalanced Bids, Unauthorized Instruction From Government or Other Personnel.

5. CONSTRUCTION TIME

* For the contract bid items, begin performance within 20 calendar days and complete all work within 135 calendar days of receipt of Notice to Proceed (NTP). It is the Government’s intent that the successful bidder will dredge to the optional depth, if so exercised by the Government, concurrent with dredging to the depth required in the base scope of work. Thus, optional items will be awarded with the base award. If optional items are exercised, additional performance time will be added to the contract based of one additional day per 1,000 cubic yards of dredged material added.

* Should the total quantity of material to be paid for and actually dredged under this contract exceed the estimated quantity from the Bidding Schedule, including optional work, additional time will be allowed at the rate of one day for each 1,000 cubic yards in excess of the estimated base contract quantity.

6. INVOICES SHALL BE SENT TO THE FOLLOWING:

U.S. ARMY CORPS OF ENGINEERS

ATTN: Daria Walker Contracting Division

803 FRONT STREET

NORFOLK, VA 23510-1096

EMAIL: cenao.ecaeinvoicing@usace.army.mil

(End of Summary of Changes) mailto:cenao.ecaeinvoicing@usace.army.mil