BID_OPENING_BID_ABSTRACT_01302019.pdf

PDF 244 KB Posted

Attached to
Maintenance Dredging, James River, IDIQ
Solicitation number
W91236-19-B-0002
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W91236-19-B-0002 JAMES RIVER Maintenance Dredging SATOC IDIQ Bid Opening: 29 January 2019 2:00 PM EST

GOVERNMENT ESTIMATE

BASE TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 0001 Mobilization/Demobilization BASE 1.00 Job $757,119.00 $757,119.00 CLIN 0002 Mob/Demob Add'd Pipeline BASE 1.00 Job $195,503.00 $195,503.00 CLIN 0003 Dredge Lower & Middle BASE 750,000.00 CY $4.26 $3,195,000.00 CLIN 0004 Dredge Upper James River BASE 250,000.00 CY $8.70 $2,175,000.00 CLIN 0005 Dredge Upper to Hopewell BASE 30,000.00 CY $8.86 $265,800.00 CLIN 0006 Dredge Upper Rch Hrb to Rch DW BASE 100,000.00 CY $6.32 $632,000.00 CLIN 0007 Transportation of Plant BASE 150.00 Mi $1,121.42 $168,213.00 CLIN 0008 Install & Remove Add'l Pipeline BASE 12,000.00 LF $3.85 $46,200.00 CLIN 0009 Dredge Upper Pipeline Exc. 7500 LF BASE 25,000.00 CY $9.81 $245,250.00 CLIN 0010 Dredge Lower Pipeline Exc. 10000 LF BASE 150,000.00 CY $6.10 $915,000.00 CLIN 0011 Sitework BASE 1.00 Job $115,665.00 $115,665.00 CLIN 0012 Standby Time BASE 1.00 DY $36,000.00 $36,000.00

TOTAL (BASE YEAR) $8,746,750.00

OPTION YEAR 1 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 1001 Mobilization/Demobilization Op Yr 1 1.00 Job $781,717.00 $781,717.00 CLIN 1002 Mob/Demob Add'd Pipeline Op Yr 1 1.00 Job $201,855.00 $201,855.00 CLIN 1003 Dredge Lower & Middle Op Yr 1 750,000.00 CY $4.40 $3,300,000.00 CLIN 1004 Dredge Upper James River Op Yr 1 250,000.00 CY $8.98 $2,245,000.00 CLIN 1005 Dredge Upper to Hopewell Op Yr 1 30,000.00 CY $9.15 $274,500.00 CLIN 1006 Dredge Upper Rch Hrb to Rch DW Op Yr 1 100,000.00 CY $6.53 $653,000.00 CLIN 1007 Transportation of Plant Op Yr 1 150.00 Mi $1,158.00 $173,700.00 CLIN 1008 Install & Remove Add'l Pipeline Op Yr 1 12,000.00 LF $3.98 $47,760.00 CLIN 1009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 1 25,000.00 CY $10.13 $253,250.00 CLIN 1010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 1 150,000.00 CY $6.30 $945,000.00 CLIN 1011 Sitework Op Yr 1 1.00 Job $119,423.00 $119,423.00 CLIN 1012 Standby Time Op Yr 1 1.00 DY $37,170.00 $37,170.00

TOTAL (OPTION YEAR 1) $9,032,375.00

OPTION YEAR 2 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 2001 Mobilization/Demobilization Op Yr 2 1.00 Job $805,464.00 $805,464.00 CLIN 2002 Mob/Demob Add'd Pipeline Op Yr 2 1.00 Job $207,987.00 $207,987.00 CLIN 2003 Dredge Lower & Middle Op Yr 2 750,000.00 CY $4.53 $3,397,500.00 CLIN 2004 Dredge Upper James River Op Yr 2 250,000.00 CY $9.25 $2,312,500.00 CLIN 2005 Dredge Upper to Hopewell Op Yr 2 30,000.00 CY $9.43 $282,900.00 CLIN 2006 Dredge Upper Rch Hrb to Rch DW Op Yr 2 100,000.00 CY $6.73 $673,000.00 CLIN 2007 Transportation of Plant Op Yr 2 150.00 Mi $1,193.00 $178,950.00 CLIN 2008 Install & Remove Add'l Pipeline Op Yr 2 12,000.00 LF $4.10 $49,200.00 CLIN 2009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 2 25,000.00 CY $10.44 $261,000.00 CLIN 2010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 2 150,000.00 CY $6.49 $973,500.00 CLIN 2011 Sitework Op Yr 2 1.00 Job $123,051.00 $123,051.00 CLIN 2012 Standby Time Op Yr 2 1.00 DY $38,299.00 $38,299.00

TOTAL (OPTION YEAR 2) $9,303,351.00

BASE YEAR (CLINS 0001-0012)

OPTION YEAR 1 (CLINS 1001-1012)

OPTION YEAR 2 (CLINS 2001-2012)

Total Evaluated Price (Base + ALL Options)

Prepared By: Stormie Wicks, Contract Specialist

Approved By: Eartha D. Garrett, Contracting Officer

27,082,476.00

8,746,750.00 9,032,375.00 9,303,351.00

W91236-19-B-0002 JAMES RIVER Maintenance Dredging SATOC IDIQ

COTTRELL CONTRACTING CORP. BID BOND: Y/N Y Acknowledged Amends.: Y/N Y BASE TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 0001 Mobilization/Demobilization BASE 1.00 Job $400,000.00 $400,000.00 CLIN 0002 Mob/Demob Add'd Pipeline BASE 1.00 Job $10,000.00 $10,000.00 CLIN 0003 Dredge Lower & Middle BASE 750,000.00 CY $4.15 $3,112,500.00 CLIN 0004 Dredge Upper James River BASE 250,000.00 CY $7.00 $1,750,000.00 CLIN 0005 Dredge Upper to Hopewell BASE 30,000.00 CY $7.00 $210,000.00 CLIN 0006 Dredge Upper Rch Hrb to Rch DW BASE 100,000.00 CY $5.00 $500,000.00 CLIN 0007 Transportation of Plant BASE 150.00 Mi $950.00 $142,500.00 CLIN 0008 Install & Remove Add'l Pipeline BASE 12,000.00 LF $2.00 $24,000.00 CLIN 0009 Dredge Upper Pipeline Exc. 7500 LF BASE 25,000.00 CY $8.00 $200,000.00 CLIN 0010 Dredge Lower Pipeline Exc. 10000 LF BASE 150,000.00 CY $4.75 $712,500.00 CLIN 0011 Sitework BASE 1.00 Job $48,000.00 $48,000.00 CLIN 0012 Standby Time BASE 1.00 DY $32,000.00 $32,000.00

TOTAL (BASE YEAR) $7,141,500.00

OPTION YEAR 1 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 1001 Mobilization/Demobilization Op Yr 1 1.00 Job $415,000.00 $415,000.00 CLIN 1002 Mob/Demob Add'd Pipeline Op Yr 1 1.00 Job $10,000.00 $10,000.00 CLIN 1003 Dredge Lower & Middle Op Yr 1 750,000.00 CY $4.20 $3,150,000.00 CLIN 1004 Dredge Upper James River Op Yr 1 250,000.00 CY $7.10 $1,775,000.00 CLIN 1005 Dredge Upper to Hopewell Op Yr 1 30,000.00 CY $7.10 $213,000.00 CLIN 1006 Dredge Upper Rch Hrb to Rch DW Op Yr 1 100,000.00 CY $5.50 $550,000.00 CLIN 1007 Transportation of Plant Op Yr 1 150.00 Mi $1,000.00 $150,000.00 CLIN 1008 Install & Remove Add'l Pipeline Op Yr 1 12,000.00 LF $2.00 $24,000.00 CLIN 1009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 1 25,000.00 CY $7.50 $187,500.00 CLIN 1010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 1 150,000.00 CY $5.00 $750,000.00 CLIN 1011 Sitework Op Yr 1 1.00 Job $55,000.00 $55,000.00 CLIN 1012 Standby Time Op Yr 1 1.00 DY $30,000.00 $30,000.00

TOTAL (OPTION YEAR 1) $7,309,500.00

OPTION YEAR 2 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 2001 Mobilization/Demobilization Op Yr 2 1.00 Job $450,000.00 $450,000.00 CLIN 2002 Mob/Demob Add'd Pipeline Op Yr 2 1.00 Job $10,000.00 $10,000.00 CLIN 2003 Dredge Lower & Middle Op Yr 2 750,000.00 CY $4.25 $3,187,500.00 CLIN 2004 Dredge Upper James River Op Yr 2 250,000.00 CY $7.15 $1,787,500.00 CLIN 2005 Dredge Upper to Hopewell Op Yr 2 30,000.00 CY $7.50 $225,000.00 CLIN 2006 Dredge Upper Rch Hrb to Rch DW Op Yr 2 100,000.00 CY $5.00 $500,000.00 CLIN 2007 Transportation of Plant Op Yr 2 150.00 Mi $1,000.00 $150,000.00 CLIN 2008 Install & Remove Add'l Pipeline Op Yr 2 12,000.00 LF $2.00 $24,000.00 CLIN 2009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 2 25,000.00 CY $8.00 $200,000.00 CLIN 2010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 2 150,000.00 CY $5.00 $750,000.00 CLIN 2011 Sitework Op Yr 2 1.00 Job $50,000.00 $50,000.00 CLIN 2012 Standby Time Op Yr 2 1.00 DY $30,000.00 $30,000.00

TOTAL (OPTION YEAR 2) $7,364,000.00

BASE YEAR (CLINS 0001-0012)

OPTION YEAR 1 (CLINS 1001-1012)

OPTION YEAR 2 (CLINS 2001-2012)

Total Evaluated Price (Base + ALL Options) Aparent

Low Bidder

7,141,500.00 7,309,500.00 7,364,000.00

21,815,000.00

SOUTHWIND CONTRUCTION CORP. BID BOND: Y/N Y Acknowledged Amends.: Y/N Y BASE TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 0001 Mobilization/Demobilization BASE 1.00 Job $2,405,622.02 $2,405,622.02 CLIN 0002 Mob/Demob Add'd Pipeline BASE 1.00 Job $91,709.17 $91,709.17 CLIN 0003 Dredge Lower & Middle BASE 750,000.00 CY $6.53 $4,897,500.00 CLIN 0004 Dredge Upper James River BASE 250,000.00 CY $8.07 $2,017,500.00 CLIN 0005 Dredge Upper to Hopewell BASE 30,000.00 CY $8.08 $242,400.00 CLIN 0006 Dredge Upper Rch Hrb to Rch DW BASE 100,000.00 CY $8.08 $808,000.00 CLIN 0007 Transportation of Plant BASE 150.00 Mi $1,081.57 $162,235.50 CLIN 0008 Install & Remove Add'l Pipeline BASE 12,000.00 LF $5.35 $64,200.00 CLIN 0009 Dredge Upper Pipeline Exc. 7500 LF BASE 25,000.00 CY $16.03 $400,750.00 CLIN 0010 Dredge Lower Pipeline Exc. 10000 LF BASE 150,000.00 CY $11.20 $1,680,000.00 CLIN 0011 Sitework BASE 1.00 Job $76,736.23 $76,736.23 CLIN 0012 Standby Time BASE 1.00 DY $45,254.60 $45,254.60

TOTAL (BASE YEAR) $12,891,907.52

OPTION YEAR 1 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 1001 Mobilization/Demobilization Op Yr 1 1.00 Job $1,158,882.35 $1,158,882.35 CLIN 1002 Mob/Demob Add'd Pipeline Op Yr 1 1.00 Job $93,549.00 $93,549.00 CLIN 1003 Dredge Lower & Middle Op Yr 1 750,000.00 CY $6.73 $5,047,500.00 CLIN 1004 Dredge Upper James River Op Yr 1 250,000.00 CY $8.33 $2,082,500.00 CLIN 1005 Dredge Upper to Hopewell Op Yr 1 30,000.00 CY $8.33 $249,900.00 CLIN 1006 Dredge Upper Rch Hrb to Rch DW Op Yr 1 100,000.00 CY $8.33 $833,000.00 CLIN 1007 Transportation of Plant Op Yr 1 150.00 Mi $1,120.55 $168,082.50 CLIN 1008 Install & Remove Add'l Pipeline Op Yr 1 12,000.00 LF $5.46 $65,520.00 CLIN 1009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 1 25,000.00 CY $16.58 $414,500.00 CLIN 1010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 1 150,000.00 CY $11.57 $1,735,500.00 CLIN 1011 Sitework Op Yr 1 1.00 Job $78,563.84 $78,563.84 CLIN 1012 Standby Time Op Yr 1 1.00 DY $46,246.54 $46,246.54

TOTAL (OPTION YEAR 1) $11,973,744.23

OPTION YEAR 2 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 2001 Mobilization/Demobilization Op Yr 2 1.00 Job $1,185,944.92 $1,185,944.92 CLIN 2002 Mob/Demob Add'd Pipeline Op Yr 2 1.00 Job $95,390.71 $95,390.71 CLIN 2003 Dredge Lower & Middle Op Yr 2 750,000.00 CY $6.92 $5,190,000.00 CLIN 2004 Dredge Upper James River Op Yr 2 250,000.00 CY $8.60 $2,150,000.00 CLIN 2005 Dredge Upper to Hopewell Op Yr 2 30,000.00 CY $8.60 $258,000.00 CLIN 2006 Dredge Upper Rch Hrb to Rch DW Op Yr 2 100,000.00 CY $8.60 $860,000.00 CLIN 2007 Transportation of Plant Op Yr 2 150.00 Mi $1,142.95 $171,442.50 CLIN 2008 Install & Remove Add'l Pipeline Op Yr 2 12,000.00 LF $5.58 $66,960.00 CLIN 2009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 2 25,000.00 CY $17.14 $428,500.00 CLIN 2010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 2 150,000.00 CY $11.95 $1,792,500.00 CLIN 2011 Sitework Op Yr 2 1.00 Job $80,404.06 $80,404.06 CLIN 2012 Standby Time Op Yr 2 1.00 DY $47,242.61 $47,242.61

TOTAL (OPTION YEAR 2) $12,326,384.80

BASE YEAR (CLINS 0001-0012)

OPTION YEAR 1 (CLINS 1001-1012)

OPTION YEAR 2 (CLINS 2001-2012)

Total Evaluated Price (Base + ALL Options)

12,891,907.52 11,973,744.23 12,326,384.80

37,192,036.55

TRUE EXCELLENCE GROUP LLC BID BOND: Y/N N Acknowledged Amends.: Y/N Y BASE TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 0001 Mobilization/Demobilization BASE 1.00 Job $1,000,000.00 $1,000,000.00 CLIN 0002 Mob/Demob Add'd Pipeline BASE 1.00 Job $750,000.00 $750,000.00 CLIN 0003 Dredge Lower & Middle BASE 750,000.00 CY $8.00 $6,000,000.00 CLIN 0004 Dredge Upper James River BASE 250,000.00 CY $8.10 $2,025,000.00 CLIN 0005 Dredge Upper to Hopewell BASE 30,000.00 CY $8.10 $243,000.00 CLIN 0006 Dredge Upper Rch Hrb to Rch DW BASE 100,000.00 CY $8.10 $810,000.00 CLIN 0007 Transportation of Plant BASE 150.00 Mi $1,500.00 $225,000.00 CLIN 0008 Install & Remove Add'l Pipeline BASE 12,000.00 LF $25.00 $300,000.00 CLIN 0009 Dredge Upper Pipeline Exc. 7500 LF BASE 25,000.00 CY $8.20 $205,000.00 CLIN 0010 Dredge Lower Pipeline Exc. 10000 LF BASE 150,000.00 CY $8.20 $1,230,000.00 CLIN 0011 Sitework BASE 1.00 Job $150,000.00 $150,000.00 CLIN 0012 Standby Time BASE 1.00 DY $1,743.12 $1,743.12

TOTAL (BASE YEAR) $12,939,743.12

OPTION YEAR 1 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 1001 Mobilization/Demobilization Op Yr 1 1.00 Job $1,000,000.00 $1,000,000.00 CLIN 1002 Mob/Demob Add'd Pipeline Op Yr 1 1.00 Job $750,000.00 $750,000.00 CLIN 1003 Dredge Lower & Middle Op Yr 1 750,000.00 CY $8.00 $6,000,000.00 CLIN 1004 Dredge Upper James River Op Yr 1 250,000.00 CY $8.10 $2,025,000.00 CLIN 1005 Dredge Upper to Hopewell Op Yr 1 30,000.00 CY $8.10 $243,000.00 CLIN 1006 Dredge Upper Rch Hrb to Rch DW Op Yr 1 100,000.00 CY $8.10 $810,000.00 CLIN 1007 Transportation of Plant Op Yr 1 150.00 Mi $1,500.00 $225,000.00 CLIN 1008 Install & Remove Add'l Pipeline Op Yr 1 12,000.00 LF $25.00 $300,000.00 CLIN 1009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 1 25,000.00 CY $8.20 $205,000.00 CLIN 1010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 1 150,000.00 CY $8.20 $1,230,000.00 CLIN 1011 Sitework Op Yr 1 1.00 Job $150,000.00 $150,000.00 CLIN 1012 Standby Time Op Yr 1 1.00 DY $1,743.12 $1,743.12

TOTAL (OPTION YEAR 1) $12,939,743.12

OPTION YEAR 2 TITLE Est QTY UNIT UNIT PRICE Est AMOUNT CLIN 2001 Mobilization/Demobilization Op Yr 2 1.00 Job $1,000,000.00 $1,000,000.00 CLIN 2002 Mob/Demob Add'd Pipeline Op Yr 2 1.00 Job $750,000.00 $750,000.00 CLIN 2003 Dredge Lower & Middle Op Yr 2 750,000.00 CY $8.00 $6,000,000.00 CLIN 2004 Dredge Upper James River Op Yr 2 250,000.00 CY $8.10 $2,025,000.00 CLIN 2005 Dredge Upper to Hopewell Op Yr 2 30,000.00 CY $8.10 $243,000.00 CLIN 2006 Dredge Upper Rch Hrb to Rch DW Op Yr 2 100,000.00 CY $8.10 $810,000.00 CLIN 2007 Transportation of Plant Op Yr 2 150.00 Mi $1,500.00 $225,000.00 CLIN 2008 Install & Remove Add'l Pipeline Op Yr 2 12,000.00 LF $25.00 $300,000.00 CLIN 2009 Dredge Upper Pipeline Exc. 7500 LF Op Yr 2 25,000.00 CY $8.20 $205,000.00 CLIN 2010 Dredge Lower Pipeline Exc. 10000 LF Op Yr 2 150,000.00 CY $8.20 $1,230,000.00 CLIN 2011 Sitework Op Yr 2 1.00 Job $150,000.00 $150,000.00 CLIN 2012 Standby Time Op Yr 2 1.00 DY $1,743.12 $1,743.12

TOTAL (OPTION YEAR 2) $12,939,743.12

BASE YEAR (CLINS 0001-0012)

OPTION YEAR 1 (CLINS 1001-1012)

OPTION YEAR 2 (CLINS 2001-2012)

Total Evaluated Price (Base + ALL Options)

12,939,743.12 12,939,743.12 12,939,743.12

38,819,229.36

Bid submitted by True Excellence did not conform to the requirements of the Solicitation, and is hereby found Non-Responsive IAW

FAR 14.301

GOV EST
KTR1
KTR2
KTR 3
2019-01-30T15:12:35-0500
WICKS.STORMIE.B.1115654078
2019-01-30T15:19:56-0500
GARRETT.EARTHA.D.1045443074

File details come from the government source that posted it.