W91236-16-R-0004_Attachment_J-10_Record_of_Major_Facility_Downtime.pdf

PDF 56 KB Posted

Attached to
AIWW Facilities Operations and Maintenance, Atlantic lntracoastal Waterway, Norfolk District, Virginia and North Carolina
Solicitation number
W91236-16-R-0004
Issued by

About this file

Attachment J-10 Record of Major Facility Downtime

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 February 2016

ATTACHMENT 10

RECORD OF MAJOR FACILITY DOWNTIME

DOWNTIME SUMMARY

NORTH LANDING BRIDGE

DATE

OPERATION

OUT/IN

DESCRIPTION OF BREAKDOWN

3/11/2012 1700 - 1800 Va. Beach wedge failure.

5/15/2012 0900 - 1700 Va. Beach span gear box failure.

5/31/2013 1000 - 1425 Va. Beach wedge failure.

7/3/2013 1234 - 1420 Chesapeake wedge failure.

DEEP CREEK BRIDGE

01/01/2012- 12/31/2014

None

DEEP CREEK LOCKS

1/2/2012 – 03/19/2012

Taking out river end gates. DSC closed for entire period.

1 February 2016

GREAT BRIDGE LOCKS

11/06/2013 11/22/13

12 HOURS PER

DAY

B GATE VALVE NORTH SIDE FAILURE. OPERATIONAL

AROUND TIDE SCHEDULE

2/18/2014 1000 - 1630 CHANGING OUT C GATES FOR REFURBISHMENT

11/04/2014 1130 - 1515 DIVING OPERATIONS ON B GATE VALVE

SOUTH MILLS LOCKS

1/4/2012 – 03/19/2012

Taking out river end gates for refurbishment. DSC closed for entire period.

SOUTH MILLS BRIDGE

01/01/2012- 12/31/2014

None