DDESS GA-AL FACILITIES 1 2 3 4

FACILITY NAME: Dexter ES Faith MS Loyd ES McBride ES INSTALLATION: Fort Bennning Fort Bennning Fort Bennning Fort Bennning

ADDRESS:

99 Yeager Avenue Fort Benning, GA 31905

1375 Ingersoll Street Fort Benning, GA 31905

5701 Santa Fe Rd Fort Benning, GA 31905

700 Custer Rd. Fort Benning, GA 31905

FACILITY USE: Grades K-5 Grades 6 - 8 Grades PK - 5 Grades PK - 5

PERMANENT GROSS SQUARE FOOTAGE: 43,289 98,047 49,268 42,067

STUDENT POPULATION: 248 568 469 452

KITCHEN?

Yes, but not functional, cold storage only

Yes Yes, but not Functional Cold Storage only

Yes, but not Functional Cold Storage only

CAFETERIA? Yes Yes Yes Yes MULTIPURPOSE ROOM/AUDITORIUM? Yes Yes Yes Yes GYMNASIUM? Yes Yes No No

MAJOR MECHANICL SYSTEMS: 100 TN York Chiller

120 TN York Chillers (2ea) used in conjunction with three boilers McQuay RTU (4ea) Trane ERUs 3ea

60 Ton Trane Chiller, 60 Ton Carrier Chiller, Cooling Tower

60 Ton Trane Chiller with Cooling Tower

PRIMARY TYPE OF CONSTRUCTION:

Concrete and brick, Low slope roof covered by Standing Seam steel roof

Concrete and brick, Low slope roof covered by Standing Seam steel roof

Concrete and brick, Low slope roof covered by Standing Seam steel roof

Concrete and brick, Low slope roof covered by Standing Seam steel roof

YEAR OF CONSTRUCTION: 1968 1987 1958 1965

Section C-3 (Mech) Yes Yes Yes Yes Section C-4 (DDC) Yes Yes Yes Yes Section C-5 (Plumbing) No No No No Section C-6 (Electrical) No No No No Section C-7 (Kitchen Equipment) Yes Yes Yes Yes Section C-8 (Roof Systems & Site) No No No No Section C-9 (Building Systems) No No No No Section C-10 (Fire Alarm & Suppression) Yes Yes Yes Yes Section C-11 (Playgrounds) Yes Yes Yes Yes

MAINTENANCE SECTIONS

NOTE: The scope of the contract shall include all requisite preventative maintenance and demand maintenance and repair services, as defined more fully in this Performance Work Statement (PWS) up to the limit of liability ($20,000) for the “Maintenance Sections” indicated above with a “yes.” In addition, the scope of the contract shall include the ability to order on demand maintenance or repair services for requirements above the limit of liability for any “Maintenance Section” indicated above with a “yes.” Also, the contract shall include the ability to order on demand maintenance or repair services for requirements for any amount for those “Maintenance Sections” indicated above by a “no” or to add Sections in their entirety, or portions thereof, for requisite preventive maintenance. Those on demand requirements or “Maintenance Sections” not included in the initial solicitation shall be added by way of bilateral task order or modification.

DDESS GA-AL FACILITIES 5 6 7 8

FACILITY NAME: Stowers ES White ES Wilson ES DSO INSTALLATION: Fort Bennning Fort Bennning Fort Bennning Fort Bennning

ADDRESS:

7791 Stowers Dr. Fort Benning, GA 31905

300 First Division Rd. Fort Benning, GA 31905

112 Lavoie Ave. Fort Benning, GA 31905

Bldg 2670 &441 Custer Rd.

Fort Benning, GA 31905

FACILITY USE: Grades PK - 5 Grades K - 5 Grades PK - 5 Administrative

PERMANENT GROSS SQUARE FOOTAGE: 74,934 44,061 46,780 32,930

STUDENT POPULATION: 339 228 375 NA

KITCHEN? Yes Yes, but not Functional Cold Storage only

Yes, but not Functional Cold Storage only

Cold Storage Only

CAFETERIA? Yes Yes Yes No MULTIPURPOSE ROOM/AUDITORIUM? Yes Yes Yes No GYMNASIUM? Yes Yes Yes No

MAJOR MECHANICL SYSTEMS:

Cooling Tower with 46 Water Source Heat Pumps

60 Ton Trane Chiller 25 Ton Carriers Chillers (4ea) 25 Ton Trane Chiller

100 Ton York Chiller 60 Ton York Chiller

PRIMARY TYPE OF CONSTRUCTION:

Concrete and brick TPO cover Low Slope Roof

Concrete and brick TPO covered Low Slope Roof

Concrete and brick, Low slope roof covered by standing seam steel roof

Concrete and brick Asphalt shingled roof

YEAR OF CONSTRUCTION: 1993/2003 1961/1994 1965/1958 1956/1960/1965/1987

Section C-3 (Mech) Yes Yes Yes Yes Section C-4 (DDC) Yes Yes Yes Yes Section C-5 (Plumbing) No No No No Section C-6 (Electrical) No No No No Section C-7 (Kitchen Equipment) Yes Yes Yes Yes Section C-8 (Roof Systems & Site) No No No No Section C-9 (Building Systems) No No No No Section C-10 (Fire Alarm & Suppression) Yes Yes Yes Yes Section C-11 (Playgrounds) Yes Yes Yes Yes

MAINTENANCE SECTIONS

NOTE: The scope of the contract shall include all requisite preventative maintenance and demand maintenance and repair services, as defined more fully in this Performance Work Statement (PWS) up to the limit of liability ($20,000) for the “Maintenance Sections” indicated above with a “yes.” In addition, the scope of the contract shall include the ability to order on demand maintenance or repair services for requirements above the limit of liability for any “Maintenance Section” indicated above with a “yes.” Also, the contract shall include the ability to order on demand maintenance or repair services for requirements for any amount for those “Maintenance Sections” indicated above by a “no” or to add Sections in their entirety, or portions thereof, for requisite preventive maintenance. Those on demand requirements or “Maintenance Sections” not included in the initial solicitation shall be added by way

DDESS GA-AL FACILITIES 9 10 11 12 13

FACILITY NAME: Bus Barn Maintenance Rucker PS Rucker ES Maxwell ES INSTALLATION: Fort Bennning Fort Bennning Fort Rucker Fort Rucker Maxwell AFB

ADDRESS:

Bldg 4029 Hefferson Rd. Fort Rucker, AL 36362

1049 Baltzell Ave. Fort Benning, GA 31905

Bldg 22210 Artillery Rd. Fort Rucker, AL 36362

Bldg 21037 Red Cloud Rd. Fort Rucker, AL 36362

800 Magnolia Blvd.

Maxwell AFB, AL 36112

FACILITY USE: Bus parking and maint Maintenance Grades PK - 1 Grades 2-6 Grades PK - 8

PERMANENT GROSS SQUARE FOOTAGE: 5,825 2,198 68,926 107,652 108,477

STUDENT POPULATION: NA NA 344 369 341

KITCHEN? No No Yes Yes Yes

CAFETERIA? No No Yes Yes Yes MULTIPURPOSE ROOM/AUDITORIUM? No No No Yes Yes GYMNASIUM? No No Yes Yes Yes

MAJOR MECHANICL SYSTEMS: 3.5 Ton Rheem Split System Yes Trane RTU (13 ea)

40 Ton Trane Chiller 50 Ton Trane Chiller 60 Ton Trane Chiller (2ea) 70 Ton Trane Chiller 90 Ton Chiller Trane RTUs (3ea) Carriers RTUs (4ea)

100 Ton Trane Chiller 100 Ton York Chiller 60 Ton Trane Chiller 60 ton York Chiller 50 ton York Chiller (2 ea)

PRIMARY TYPE OF CONSTRUCTION:

Metal Building Standing Seam steel roof

Concrete and brick asphalt shingled roof

Concrete and brick TPO covered Low Slope Roof

Concrete and brick TPO covered Low Slope Roof

Concrete and brick, part standing seam steel roof, and part aphalt shingled roof

YEAR OF CONSTRUCTION: 1999 1966 1972 1965/1984 1963/1987/1998

Section C-3 (Mech) Yes Yes Yes Yes Yes Section C-4 (DDC) Yes Yes Yes Yes Yes Section C-5 (Plumbing) No No No No No Section C-6 (Electrical) No No No No No Section C-7 (Kitchen Equipment) Yes Yes Yes Yes Yes Section C-8 (Roof Systems & Site) No No No No No Section C-9 (Building Systems) No No No No No Section C-10 (Fire Alarm & Suppression) Yes Yes Yes Yes Yes Section C-11 (Playgrounds) Yes Yes Yes Yes Yes

MAINTENANCE SECTIONS

NOTE: The scope of the contract shall include all requisite preventative maintenance and demand maintenance and repair services, as defined more fully in this Performance Work Statement (PWS) up to the limit of liability ($20,000) for the “Maintenance Sections” indicated above with a “yes.” In addition, the scope of the contract shall include the ability to order on demand maintenance or repair services for requirements above the limit of liability for any “Maintenance Section” indicated above with a “yes.” Also, the contract shall include the ability to order on demand maintenance or repair services for requirements for any amount for those “Maintenance Sections” indicated above by a “no” or to add Sections in their entirety, or portions thereof, for requisite preventive maintenance. Those on demand requirements or “Maintenance Sections” not included in the initial solicitation shall be added by way

GA-AL