About this file

Specs 1 of 2

View the file

Other files

File Type Posted
W14R0019-0004.pdf PDF
W14R0019-0003.pdf PDF
W14R0019-0003_CAD_Bathymetric_Survey_Data.DWG DWG drawing
W14R0019-0002.pdf PDF
W14R0019-0002_CAD_Files.zip ZIP file
W14R0019-0001.pdf PDF
W14R0019_Drawings.pdf PDF
W14R0019.pdf PDF
W14R0019_Specs_2_of_2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This page was intentionally left blank for double-sided printing.

Atlantic Wood Industries Superfund Site February 2014 Dredging and Dredged Material Handling Portsmouth, Virginia

REMEDIAL DESIGN – PHASE 2

DREDGING AND DREDGED MATERIAL HANDLING

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 41 00 BIDDING SCHEDULE

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 SPECIAL WORK CONDITIONS

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 31 19.00 50 PROJECT MEETINGS

01 32 01.00 50 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES

FOR CONTAMINATED SITES

01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)

01 45 04 CONTRACTOR QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 58 00 PROJECT IDENTIFICATION

01 76 00 PROTECTING INSTALLED CONSTRUCTION

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 32 00 ENVIRONMENTAL SAMPLING

02 61 13 HANDLING OF CONTAMINATED MATERIAL

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

31 05 19 MARKER GEOTEXTILE

31 09 13 GEOTECHNICAL INSTRUMENTATION

31 32 40 PREFABRICATED VERTICAL DRAINS

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

35 31 19 SUBAQUEOUS COVERS

DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT

44 40 00 WASTEWATER TREATMENT

APPENDICES

APPENDIX A SEDIMENT CHARACTERIZATION DATA

APPENDIX B POTENTIAL DEBRIS INFORMATION

APPENDIX C NAVY PIER DRAWINGS

Table of Contents Page 1

SECTION 00 41 00

BIDDING SCHEDULE

PART 1 GENERAL

1.1 BASIS OF BIDS

This Contract will be solicited with bid items and unit prices required for specifically selected work. A description of the bid items is contained in Section 01 22 00.00 10 MEASUREMENT AND PAYMENT. Also refer to Standard Form 1442, "Solicitation, Offer and Award” and Contract Clauses "FAR 52.212-11, Variation in Estimated Quantity" and "FAR 52.236-16, Quantity Surveys."

BASE BID ITEMS

Item Description Estimated Quantity Unit

Unit Price Amount

01 Mobilization 1 LS $ $

02 Construction of Effluent Treatment System

1 LS $ $

03 Effluent Treatment and Discharge

600 Day $ $

04 Containment Area No. 1 Preparation

1 LS $ $

05 PVD Installation 425,000 VLF $ $

06 Containment Area No. 1 Stormwater Management

600 Day $ $

07 Focused Debris Removal 15 Day $ $

08 Mechanical Dredging, Material Handling, Amendment and Placement (50,000 CY)

50,000 CY $ $

09 Mechanical Dredging Under Structures, Material Handling, Amendment and Placement

6,000 CY $ $

10 Debris Screening, Handling, and Transport to Containment Area No. 2 (0-100 tons)

100 Ton $ $

11 Debris Screening, Handling, and Transport to Containment Area No. 2 (100-500 tons)

400 Ton $ $

12 Confirmation Sampling Vibracoring

220 Each $ $

13 Confirmation Sample Analysis 260 Sample $ $

14 Additional Mechanical Dredging, Material Handling, Amendment and Placement after Confirmation Sampling

10,000 CY $ $

15 Removal of Effluent Treatment System

1 LS $ $

16 Demobilization 1 LS $ $

Total Base Bid Items $

Section 00 41 00 Page 1

OPTIONAL BID ITEMS

Estimated Quantity Unit

Unit Price Amount

A01 Temporary Shutdown 30 Day $ $

A02 Mechanical Dredging and Material Handling, Amendment and Placement(50,000 CY)

50,000 CY $ $

A03 Mechanical Dredging and Material Handling, Amendment and Placement(25,000 CY)

25,000 CY $ $

A04 Mechanical Dredging and Material Handling, Amendment and Placement(25,000 CY)

25,000 CY $ $

A05 Mechanical Dredging and Material Handling, Amendment and Placement(10,000 CY)

10,000 CY $ $

A06 Mechanical Dredging and Material Handling, Amendment and Placement(10,000 CY)

10,000 CY $ $

A07 Mechanical Dredging and Material Handling, Amendment and Placement(5,000 CY)

5,000 CY $ $

A08 Mechanical Dredging and Material Handling, Amendment and Placement(5,000 CY)

5,000 CY $ $

A09 Mechanical Dredging and Material Handling, Amendment and Placement(5,000 CY)

5,000 CY $ $

A10 Mechanical Dredging and Material Handling, Amendment and Placement(Zone 1)

13,000 CY $ $

A11 Mechanical Dredging and Material Handling, Amendment and Placement(Zone 2)

70,000 CY $ $

A12 Mechanical Dredging and Material Handling, Amendment and Placement(Zone 3)

20,000 CY $ $

A13 Mechanical Dredging and Material Handling, Amendment and Placement(Zone 4)

10,500 CY $ $

A14 Additional Mechanical Dredging, Material Handling, Amendment and Placement after Confirmation Sampling

30,000 CY $ $

A15 Sand Subaqueous Cover 75,000 SY $ $

A16 Stone Subaqueous Cover 12,000 SY $ $

A17 Move Surcharge Material from Containment Area No. 1 to Containment Area No. 2

110,000 CY $ $

A18 Move Surcharge Material within Containment Area No. 1

50,000 CY $ $

Section 00 41 00 Page 2

OPTIONAL BID ITEMS

Estimated Quantity Unit

Unit Price Amount

A19 Containment Area No. 1 Capping

45,000 SY $ $

Total Optional Bid Items $

Total Base Bid and Optional Bid Items $

-- End of Section --

Section 00 41 00 Page 3

SECTION 01 11 00

SUMMARY OF WORK

08/11

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

Work under this contract consists of activities to implement part of the Record of Decision for U.S. Environmental Protection Agency (EPA) Region 3 for the Atlantic Wood Industries (AWI) Superfund Site located in Portsmouth, Virginia.

The work specified by the Dredging and Dredged Material Handling Contract Documents is summarized as follows:

a. Perform required preconstruction surveys (bathymetric and topographic)

b. Identify all existing utilities in the field

c. Construct erosion and sediment controls and stormwater management facilities

d. Site preparation of land-side staging area and Containment Area No. 1 behind Offshore Sheet Pile Wall

e. Installation of PVDs, sand drainage layer, and sumps to consolidate in situ sediments in Containment Area No. 1

f. Dredging, transporting, and unloading contaminated sediments

g. Dewatering and amendment of contaminated sediments

h. Placement of amended sediments in containment areas

i. Collection, treatment, and discharge of effluent water from the dredging and dredged material handling and PVD discharge

j. Surcharge Containment Area No. 1 with amended sediment

k. Move surcharge from Containment Area No. 1 to Containment Area No. 2

l. Establish subgrade of Containment Area No. 1 and place low-permeability cover material.

Drawing GI-003 includes a general list of technical requirements for the project with references to individual drawings or specification sections where more detail is available.

1.1.2 Generalized Sequence of Construction

Definition of the detailed sequence of construction will be the responsibility of the Contractor as required in various work plan submissions listed in the Specifications. The following general sequence of construction outlines items that must be accomplished in a specific order by the Contractor:

Section 01 11 00 Page 1

a. Establish perimeter erosion, sediment and turbidity controls prior to initiating land disturbance and dredging operations.

b. Prepare decontamination facilities, dredged material amendment area(s) (in barge or on land) and wastewater treatment facilities.

c. The following items can be executed concurrently:

i. Install sand drainage layer, sumps, and pre-fabricated vertical drains (PVDs) in Containment Area No. 1.

ii. Install geotechnical instrumentation in accordance with the approved Fill Management Plan.

iii. Dredge the Northern Dredging Area, amend dredged material, and place amended material in the containment areas.

d. After completion of dredging in the Northern Dredging Area, dredge the

Southern Dredging Area, amend dredged material, and place amended material in the containment areas.

e. With written approval from Contracting Officer, move surcharged dredged material from Containment Area No. 1 to Containment Area No. 2.

f. Grade Containment Area No. 1 and place 12” of Low Permeability Gravel in accordance with final grades shown on site plan.

g. With written approval from Contracting Officer, remove temporary construction facilities, restore staging areas, remove decontamination facilities and erosion and sediment controls, and demobilize from the site.

h. Prepare and submit project closeout documents.

1.1.3 Location

The project site consists of approximately 48 acres of land on the industrialized waterfront area of the southern branch of the Elizabeth River in Portsmouth, Virginia, and approximately 35 acres of adjacent river bottom containing contaminated sediment.

The property is bounded by the Norfolk Naval Shipyard (also a National Priorities List site), the Southern Branch of the Elizabeth River, FIGG Bridge property, and several other small properties. Other adjacent property owners include the 3975 Elm Avenue Property Owner, PER, Wheelabrator and the Portsmouth Public School District (PPSD).

1.2 DEFINITIONS

Wherever in the Contract Documents these words or terms or pronouns antecedent to them are used, the intent and meaning shall be interpreted as follows:

a. Government—USACE, Norfolk District

b. Property Owner—either "Atlantic Metrocast, Inc."; "AWI"; "City of Portsmouth"; "FIGG Bridge"; "PER"; “U.S. Navy”; or "3975 Elm Avenue Property Owner"

Section 01 11 00 Page 2

c. Contracting Officer—authorized contractual representative of USACE, Norfolk District

d. Existing—that which was present at the site at the time of bid opening; to remain except where removal is indicated

e. New—to be furnished and installed by the Contractor as part of the Contract

f. Work Area—the grounds and appurtenances in the project site identified within the project Limit of Work

g. Proposed—to be furnished and installed by the Contractor as part of this Contract

h. Provide—it is understood to mean "provide complete in place"; that is, "furnished and installed"

i. Specified or shown—whenever in the Contract Drawings the words or expressions "Specified," "As Specified," "Shown," and "As Shown," or any one or more of said words or expressions are used in either the conjunctive or disjunctive form, such words or expressions shall be read and taken to mean "Specified in these Specifications and/or shown on the Contract Drawings"

j. Includes—it is understood to mean "includes, but is not limited to"

k. Where "equal to" or "approved equal" are used, the Contractor may substitute a product or material which in the judgment of the Contracting Officer, expressed in writing, is equal to that specified

l. Where "as directed," "as required," "as selected," "permitted,"

"acceptance," or similar words are used, it is understood that direction, requirement, selection, permission, or acceptance by the Contracting Officer and compliance with codes and regulations are intended unless stated otherwise.

1.3 REFERENCES

• CDM Federal Programs Corporation (CDM). 2006. Final Feasibility Study OU 2 Groundwater, Atlantic Wood Industries, Inc. Superfund Site, Portsmouth, Virginia

• CDM. 2006. Final Feasibility Study OU3 River Sediment, Atlantic Wood

Industries, Inc. Superfund Site, Portsmouth, Virginia

• CDM. 2007. Final Remedial Investigation Report for Operable Unit (OU) 2 Groundwater and OU3 River Sediment, AWI Superfund Site, Portsmouth, Virginia

• EA Engineering, Science, and Technology, Inc. (EA). 2009. Technical

Memorandum No. 5 - Determination of Area to be Dredged, Atlantic Wood Industries, Inc. Superfund Site, Portsmouth, Virginia. January.

Section 01 11 00 Page 3

• EPA. 2007. VAD990710410 Record of Decision (ROD), OUs 1, 2, and 3, AWI Superfund Site, Portsmouth, Virginia

1.3.1 CERCLA Documents

Information on the site conditions and history may be found in the 2007 ROD (http://www.epa.gov/reg3hwmd/npl/VAD990710410/rod/rod2007.htm) and the Final Remedial Investigation Report (CDM 2007) (http://loggerhead.epa.gov/arweb/public/search_results.jsp?siteid=VAD990710410)

1.3.2 Subsurface Investigations

Geotechnical investigations have been undertaken, and logs of those investigations are included in APPENDIX A – SEDIMENT CHARACTERIZATION DATA of these specifications.

1.3.3 Environmental Investigations

Previously, AWI operated a wood-treating facility at the site using both creosote and pentachlorophenol (PCP). The site was contaminated from the treatment operation, storage of treated wood, and disposal of wastes. In addition, the Navy leased part of the property from AWI and disposed of wastes on site, including used abrasive blast media and sludge from the production of acetylene.

Environmental investigations have been undertaken to characterize the material to be dredged and logs of those investigations are included in APPENDIX A – SEDIMENT CHARACTERIZATION DATA of these specifications.

1.3.4 Debris-Related Information

Investigations to characterize potential debris within the project footprint have been undertaken and are included in APPENDIX B – POTENTIAL DEBRIS INFORMATION of these specifications. The information included in APPENDIX B includes:

• Photographic Log of Existing Debris and Recent Debris Removal Efforts -includes a photograph of typical debris that was removed from the Wyckoff Inlet in Spring 2013 and photos of remaining timber pilings in Wyckoff Inlet to be removed.

• An Archaeological and Historical Records Review of the Atlantic Wood Industries Superfund Site, Portsmouth, Virginia (PCI 2009) — shows the historical location of two sunken barges in the project area. Both sunken barges have been removed to upland areas; some minimal residual debris may remain on the outside (east of) and inside (west of) the Offshore Sheet Pile Wall. The PCI report also provides historical information on the past structures in the project area that were demolished or collapsed and are now a source of potential debris. As indicated on the Drawings, much of this debris has been removed by recent remedial actions, including removing timber pilings from areas accessible by barge. Some timber pilings remain and can be seen above the water surface in shallow areas of the Wyckoff Inlet, behind the Offshore Sheet Pile Wall (OSPW).

Section 01 11 00 Page 4 http://www.epa.gov/reg3hwmd/npl/VAD990710410/rod/rod2007.htm

• Wyckoff Inlet Aerial Photograph (included in PCI 2009 report) — shows the location of previous pier and wharf structures in the project area. Some concrete piers have been removed from the site and some wooden and concrete piles have been removed; however, some piers and piles remain.

The Contractor should anticipate encountering some remnant pile fragments in areas below the mud line.

• PER Property (Formerly PPIC) Debris Investigation (EA 2009) — a probing survey was performed along the PER shoreline where a dilapidated concrete and stone wharf structure existed. Most of the concrete and stone has been removed along the shoreline, but some remnants may exist offshore.

The survey indicated where obstructions were encountered.

Additional debris-related information is provided on the Drawings.

More information about how debris shall be managed is included in Section

35 20 23, DREDGING.

1.4 ATLANTIC METROCAST, FIGG BRIDGE, 3975 ELM AVENUE PROPERTY OWNER, PER

PROPERTIES, AND NAVY ONGOING BUSINESS OPERATIONS

Section 11.2.5 of the ROD, (EPA 2007), requires coordination with Atlantic Metrocast and adjacent property owners to minimize disruptions to ongoing business operations. The Contracting Officer shall facilitate coordination of activities between the Contractor, construction activities of other contractors, and the Property Owners’ operations. Anticipated coordination activities include:

a. Atlantic Metrocast's (AWI) on-going precast concrete manufacturing and shipping operations.

b. Movement of any water-born vessels in the waters west of the Southern

Branch of the Elizabeth River navigable channel, adjacent to the U.S.

Navy's Southgate Annex. Coordination with the U.S. Navy will be required for navigation in those waters.

c. Ongoing construction activities associated with site development at the

PER property or the 3975 Elm Avenue property.

The Contractor shall coordinate and share usage of the existing South Bulkhead Tie-back Wall with AWI. Occasionally, AWI uses the wall for loading or unloading material or concrete products. The Contractor will receive 45 days of notice each time AWI needs to use the South Bulkhead area. During periods of use by AWI, the Contractor may lose use of this area. The Contractor may also use the Offshore Sheet Pile Wall, so long as adequate protection is provided as defined in the Contract Documents.

1.5 BOUNDARIES OF WORK

The Contracting Officer will provide land for the work specified, provisions for ingress and egress, parking areas, staging areas, and trailer areas. The Contractor shall not enter on or occupy with employees, tools, equipment, or material any ground of the area approved in the Construction Site Plan submittal (defined in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS) without the written consent of the Contracting Officer. The Contractor shall conduct his work so as not to impede unnecessarily any work being conducted by others on or adjacent to the site.

Section 01 11 00 Page 5

1.6 WORK HOURS

Normal hours for work shall be from 6 a.m. to 6 p.m., Monday through Friday.

Requests for additional work shall require written approval from the Contracting Officer 7 calendar days in advance of the proposed work period. Work hours for all project activities during dredging may be 24 hours per day, 7 days per week.

1.7 EXISTING WORK AREA

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. The Contractor shall perform work in such a manner as to prevent injury or damage to any portions of the existing work area which remain.

b. The Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.8 NOTIFICATIONS

The Contractor shall notify the Contracting Officer at least 15 days prior to starting dredging work. Notify U.S. Coast Guard and Miss Utility as specified in Section 01 14 00, SPECIAL WORK CONDITIONS.

1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the Contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

1.9.1 Schedule

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the baseline for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays for all weather dependent activities.

Section 01 11 00 Page 6

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON 5-DAY WORK

WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

9 9 9 6 7 6 8 7 6 5 6 9

1.9.2 Records

Upon acknowledgement of the Notice to Proceed and continuing throughout the Contract, the Contractor will record on the daily Contractor Quality Control Report (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

1.9.3 Impacted Days

The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays noted above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

Section 01 11 00 Page 7

SECTION 01 14 00

SPECIAL WORK CONDITIONS

11/11

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00, SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

• Notification to the U.S. Coast Guard.

1.2 CONTRACTOR NOTIFICATIONS

Notifications giving the dates and locations the Contractor intends to start work shall be prepared and sent to the agency as specified below. When the Contractor sends a Notification to a respective agency, a copy shall be furnished to the Contracting Officer at the same time.

1.2.1 Notification to the U.S. Coast Guard

The Contractor shall notify the Commander, Fifth Coast Guard District of his intended work operations and request that it be published in the Local Notice to Mariners. The Notification to the U.S. Coast Guard must be given in sufficient time so that it appears in the Notice to Mariners at least 21 calendar days prior to the commencement of in-water work.

1.2.2 Miss Utility Notification Requirements

The Contractor shall comply with all requirements of the Virginia Underground Utility Damage Prevention Act 56-265.14 (the Miss Utility law). The Contractor must call the Miss Utility Notification Center at 1-800-552-7001 before commencing any work. The Contractor shall provide to the Government, in writing, all Ticket numbers, Miss Utility system responses and other information upon completion of the Contractor's notification process to Miss Utility prior to the start of work. Requirements of the law, procedures to be followed by the Contractor and other pertinent information for the Contractor's use can be found at http://www.missutilityofvirginia.com.

Each "person" as defined in the Underground Utility Damage Prevention Act must provide their own notice of excavation. The Contractor shall allow a minimum of 48 hours after notifying the Miss Utility notification center and begin work only after checking the Positive Response System, and confirm through the Ticket Information Exchange (TIE) System, that all applicable utilities have either marked their underground line locations or reported that no lines are present in the work vicinity. The Contractor shall wait an additional 24 hours before commencing work if any utility operators have failed to respond to the TIE within the first 48 hours.

Section 01 14 00 Page 1

1.3 CONTRACTOR WORK REQUIREMENTS

1.3.1 Environmental Protection

The Contractor shall provide and maintain during the life of the Contract, environmental protective measures, as well as environmental protective measures required to correct conditions, such as oil spills or debris that occur during the dredging operations. Comply with Federal, State, and local regulations pertaining to water, air, and noise pollution (see Section 01 57

20.00 10, ENVIRONMENTAL PROTECTION for additional information).

1.3.2 Security and Public Safety of Work Areas

The work area is not accessible to the general public; however, the Contractor is informed that the Government will not undertake to exclude the public or restrict public access to the work area. The Contractor shall be solely responsible for protection of the public at all times for the duration of the Contract and fully comply with the provisions of Occupational Safety and Health Administration (OSHA) safe working practices, and Safety and Accident Prevention requirements of these specifications.

1.3.3 Noise Control and Abatement

The Contractor shall employ the use of properly installed and maintained mufflers, silencers, and manufacturer's recommended sound suppressors on all plant, machinery, and equipment used on this work. The use of sound signals such as whistles, horns, or bells shall not be used if two-way radio communications can accomplish the required function.

1.3.4 Coordination with Other Contractors

During the period of this Contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this Contract. The Contractor shall arrange his plant (equipment), and shall schedule and perform this work, so as to effectively cooperate with all other contractors and Government agencies. It shall be the responsibility of the Contractor on this Contract to be fully informed of the extent of the limits of work to be performed by other contractors. Should there be conflicts between these limits, the Contractor shall immediately notify the Contracting Officer of the conflict and the Contracting Officer's decision shall be final. Details of known coordination efforts are included in Section 01 11 00 SUMMARY OF WORK, Paragraph 1.4.

1.4 PHYSICAL DATA

1.4.1 Physical Conditions Information

The physical conditions indicated on the drawings and in the specifications are the result of site investigations and surveys. Information and data furnished or referred to below are furnished for the Contractor's information; however, it shall be expressly understood that the Government will not be responsible for any interpretation or conclusion drawn from this information or data by the Contractor. The approximate mean-tide range for the work area is indicated on the drawings.

Section 01 14 00 Page 2

1.4.1.1 Additional Information for Local Physical Conditions

The Contractor shall consult the following publications for additional information on local conditions:

a. U.S. Coast Pilot 3, Atlantic Coast, Sandy Hook to Cape Henry, published annually by the National Ocean Service.

b. Tide Tables, High and Low Water Predictions, East Coast of North and South America, published annually by the National Ocean Service.

c. Tide Current Tables, Atlantic Coast of North America, published annually by the National Ocean Service.

d. Local Notice of Mariners, published by the Fifth U.S. Coast Guard District and the broadcast local notice to mariners.

1.4.2 Site Related Weather Conditions

The location of the work area is in the Southern Branch of the Elizabeth River; accordingly, the Contractor shall anticipate that severe weather conditions may occasionally interfere with the progress of work. The area is tidal with a mean range of tide of approximately 2.86 ft at Money Point (approximately 2 miles upriver/south of the AWI site); however, currents are normally not of a sufficient velocity to interfere with operations. Complete weather forecasts, records, and reports may be obtained from the National Weather Service in Wakefield, Virginia, telephone (757) 899-4200, menu selection service or operator assisted as applicable. The Contractor shall satisfy himself as to the hazards likely to arise from the weather conditions during work period.

1.4.3 Obstructions of Channel

The Government will not undertake to keep the area of channels free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act, approved 3 August 1917.

The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor’s plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved (in less than 2 hours) on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Following safe passage of the commercial ship, the Contractor may re-establish his/her equipment in the work zone. Upon the completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under this Contract in navigable water or on shore.

1.4.4 Responsibility

The Contractor shall hold and save harmless the United States, its officers, and employees from all claims that may arise as a result of the Contractor's negligence in connection with the work performed under the Contract, from noncompliance by the Contractor with the provisions of the contract drawings and specifications, or from the instruction of the Contracting Officer.

Section 01 14 00 Page 3

1.4.5 Condition of Work Area

The Drawings show the condition of the work area at the time of the most recent survey. The Government has knowledge of artificial obstructions in the work area and has identified known obstructions; however, the work area may contain trash, debris, and other obstructions not shown on the Drawings.

1.4.6 Channel Traffic

Local channel traffic consists of a wide variety of types and sizes of vessels, including large deep-draft commercial bulk carriers, tankers, container vessels, Naval vessels, shallow and medium draft commercial seafood vessels, barges, tugs, pleasure crafts, and various other crafts. The Contractor shall expect that the vessel traffic will cause periodic delays and interruptions of operations while working near the channel.

The U.S. Coast Guard Captain of the Port of Hampton Roads (757-483-8565) can provide lists of scheduled commercial ship traffic, which typically includes scheduled traffic 1-2 days in advance. The Contractor is responsible for obtaining this information to schedule the Work. The Contractor shall conduct daily coordination while working in the channel to discuss anticipated traffic.

1.4.7 Oyster Grounds

There are no known oyster grounds in the work area; however, some exist across the River from the site along the eastern bank.

1.4.8 Utility Crossings

There is a known, abandoned fiber optic line beneath the dredging prism. The Contractor is unlikely to encounter the line during dredging, but it can be managed as debris if it is encountered and pieces are pulled up by the dredging equipment.

1.5 PUMPING OF BILGES

Contractors are warned that pumping oil or bilge water containing oil into navigable waters, or into areas which would permit the oil to flow into such waters, is prohibited by Section 13 of the River and Harbor Act of 1899, approved 3 March 1899 (30 Stat. 1152; 33 U.S.C. 407). Violation of this prohibition is subject to the penalties under the referenced Acts.

1.6 FUEL TRANSFER OPERATIONS

In accordance with U.S. Coast Guard regulations 33 CFR 156.120, couplings used in fuel oil transfer operations on any vessel with a capacity of 250 or more barrels of oil shall be either a bolted or full-threaded connection; or a quick-connect coupling approved by the Commandant; or an automatic back-pressure shutoff nozzle used to fuel the vessel. An executed fuel oil transfer (Declaration) form signed by the tanker operator shall be submitted to the Contracting Officer for each refueling operation.

Section 01 14 00 Page 4

1.7 PUMPING OF HEADS

Pumping treated or untreated sewage into navigable waters, or into areas which would permit sewage to flow into such water is prohibited.

1.8 INSPECTION

1.8.1 General Inspection Requirements

The presence of the Contracting Officer, Contracting Officer’s Representative (COR) or any Government construction representative shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor will be required to furnish, on the request of the Contracting Officer, COR or any construction representative, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the marine plant as may be necessary in inspecting and supervising the work.

1.9 SIGNAL LIGHTS

Display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65-ft in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as approved by the Secretary of the Army and the Commandant, U.S. Coast Guard. Also, provide lights for buoys that could endanger or obstruct navigation.

1.10 BRIDGE-TO-BRIDGE RADIO COMMUNICATIONS

In order that radio communications may be made with passing vessels, all self-propelled floating plants shall be radio telephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radio Telephone Act (33 USC 1201 et seq.) The radio telephone equipment shall operate on a single channel very high frequency (VHF), FM, on a frequency of 156.65 megahertz (Channels 13 and

16) with low power output having a communication range of approximately 10 mi.

The Federal Communications Commission has approved this frequency. Tugs and tenders will be considered towing vessels within the meaning of the Act.

1.10.1 Radio

The Contractor shall provide the COR and the Government construction representative portable radios capable of communicating with the floating plant for the duration of work. The Contractor shall maintain the radio as required.

1.11 SPECIAL COAST GUARD REQUIREMENTS

1.11.1 Local Notice to Mariners

The Local Notice To Mariners (LNM) for the Fifth Coast Guard District is available on the Internet at http://www.navcen.uscg.gov/lnm/d5/default.htm;

phone (757) 398-6486; or e-mail to: william.r.jones@uscg.mil.

Section 01 14 00 Page 5 http://www.navcen.uscg.gov/lnm/d5/default.htm%3B mailto:william.r.jones@uscg.mil

The LNM is the primary means for disseminating information concerning aids to navigation, hazards to navigation, and other items of marine information of interest to mariners on the waters of the United States, its territories, and possessions. These notices are essential to all navigators for the purpose of keeping their charts, light lists, Coast Pilots, and other nautical publications up-to-date. These notices are published weekly. They may be obtained free of charge by making application to the Fifth Coast Guard District, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704.

If the Contractor encounters any objects on the channel bottom during excavation, dredging operations, or transport of his plant that could be a hazard to navigation, he shall notify the U.S. Coast Guard immediately as to location and at the same time notify the Contracting Officer.

1.11.2 Relocation of Navigation Aids

The Contractor shall not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete work under this Contract, the Contractor shall notify the U.S. Coast Guard in writing at the address above with a copy to the Contracting Officer not less than 21 calendar days prior to such need for movement. The Contractor shall notify the U.S. Coast Guard of the approximate time the navigation aid may be relocated to its original position. All notifications to the U.S. Coast Guard shall be provided at the same time to the Contracting Officer and recorded in the Daily Report of Operations. In the event that the Contractor disturbs or damages any navigation aid during work operations, which includes during mobilization or demobilization of his plant, the Contractor shall immediately stop the activity which disturbed or damaged the navigation aid, take immediate corrective action to prevent further disturbances or damage, and shall notify the U.S. Coast Guard immediately as to location, and at the same time notify the Contracting Officer.

1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.12.1 Costs

Allowable costs for construction, and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule," Region II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.

Section 01 14 00 Page 6

1.12.2 Rentals

Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36 substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase, or sale-leaseback arrangements will be determined using the schedule, except that rental costs leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.

1.12.3 Data

When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet." By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorized representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After pricing agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete, and current.

1.13 PROFIT

1.13.1 Weighted Guidelines

Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this Contract.

The profit factors, expressed as a percent, shall be as follows:

Factor Rate Weight Value

Degree of Risk 20 Relative difficulty of work 15 Size of Job 15 Period of performance 15 Contractor's investment 5 Assistance by Government 5 Subcontracting 25

1.13.2 Values

Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.

1.13.2.1 Degree of Risk

Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work

Section 01 14 00 Page 7 to be conducted by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.

1.13.2.2 Relative Difficulty of Work

If the work is most difficult and complex, the weighting should be .12 and should be proportionally reduced to .03 on the simplest jobs. This factor is tied in some extent with the degree of risk. Some things to consider: the nature of work, by whom it is done, where, and what is the time schedule.

1.13.2.3 Size of Job

All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionally weighted from .12 to .05. Work from $5,000,000 to $10,000,000 shall be weighted at .04. Work in excess of $10,000,000 shall be weighted at .03.

1.13.2.4 Periods of Performance

Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionally weighted to a minimum of .03 for jobs not exceed 30 days. No weight where additional time is not required.

1.13.2.5 Contractor's Investment

To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.

1.13.2.6 Assistance by Government

To be weighted from .12 to .03 on the basis of average to above average.

Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.

1.13.2.7 Subcontracting

Shall be weighted inversely proportional to the amount of subcontracting.

Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionally increased to .12 where all the work is performed by the Contractor's own forces.

PART 2 PRODUCTS

Not used.

Section 01 14 00 Page 8

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

04/06

1.1 LUMP SUM PAYMENT ITEMS – BASE BID

Payment items for the work of this contract for which contract lump sum (LS) payments will be made are listed in Section 00 41 00 BIDDING SCHEDULE, BASE BID ITEMS and described below. All costs for items of work, which are not specifically mentioned to be included in a particular LS or unit price payment item, shall be included in the listed LS item most closely associated with the work involved. The LS price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment; and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization (Bid Item 01)

1.1.1.1 Payment

Payment will be made for work associated with mobilization as defined in Special Clause “PAYMENT FOR MOBILIZATION.” Mobilization shall include:

• Preparation of initial submittals

• Pre-construction surveys

• Environmental sampling required at the beginning of the project (refer to Section 02 32 00 ENVIRONMENTAL SAMPLING)

• Mobilization of equipment and personnel to the site

• Establishment and preparation of staging areas

• Establishment of temporary offices and appropriate signage (refer to

Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS)

• Furnishing and installing erosion and sediment controls (refer to Section 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL)

• Furnishing and installing decontamination pad (refer to Section

01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES, Paragraph 1.16)

• Other miscellaneous elements of work required at the beginning of the project.

1.1.1.2 Unit of Measure

Unit of measure: LS.

Section 01 22 00.00 10 Page 1

1.1.2 Construction of Effluent Treatment System (Bid Item 02)

1.1.2.1 Payment

Payment will be made for work associated with design, furnishing, and construction of the treatment plant(s) required to temporarily treat effluent from the following operations and work areas, as defined in Section 44 40 00, WASTEWATER TREATMENT:

• Containment Area No. 1 Surface Water (Pre-Sediment Placement)

• Dredging Supernatant (decanted from scows)

• Amending Pad Runoff (If Amending Pad Used)

• Equipment Decontamination Washdown Water

• PVD Dewatering Effluent.

If the Contractor elects to utilize the existing, onsite treatment system, payment will be made for work associated with evaluation, design, and upgrades to the system, if required.

1.1.2.2 Unit of Measure

Unit of measure: LS.

1.1.3 Containment Area No. 1 Preparation (Bid Item 04)

1.1.3.1 Payment

Payment will be made for work associated with the planning, design, and construction of:

• Temporary berms and other clear water diversion and runoff control measures (refer to Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION);

• Preparation of barge/scow offloading area (refer to Section 02 61 13

HANDLING OF CONTAMINATED MATERIAL);

• Amending pad (if used) (refer to Section 02 61 13 HANDLING OF

CONTAMINATED MATERIAL);

• Moving and leveling existing sediment above elevation 0 feet along the Offshore Sheet Pile Wall within Containment Area No. 1 (refer to Section 02 61 13 HANDLING OF CONTAMINATED MATERIAL);

• Sand drainage layer, associated geotextiles, and sumps required to manage water discharged from the PVDs (refer to Section 31 32 40 PRE-

FABRICATED VERTICAL DRAINS);

• Containment area stormwater management system(s) (refer to Section 44 40 00

WASTEWATER TREATMENT); and

• Other related site features required to prepare Containment Area No. 1.

Section 01 22 00.00 10 Page 2

Installation of PVDs and actual sediment amending and placement will be paid under other bid items as described herein.

1.1.3.2 Unit of Measure

Unit of measure: LS.

1.1.4 Removal of Effluent Treatment System (Bid Item 15)

1.1.4.1 Payment

Payment will be made for work associated with the removal of the effluent treatment system constructed or assumed under Bid Item 02, Construction of Effluent Treatment System. This includes:

• Dismantling and deconstruction of the system (as needed)

• Amending of remaining solids and placement of amended solids in the containment areas (if needed)

• Placement of spent media in Stockpile Area A (if needed)

• Complete removal of the system from the site.

1.1.4.2 Unit of Measure

Unit of measure: LS.

1.1.5 Demobilization (Bid Item 16)

1.1.5.1 Payment

Payment will be made for work associated with demobilization as defined in Special Clause “PAYMENT FOR DEMOBILIZATION.” Demobilization shall include:

• Post-construction surveys

• Environmental sampling required at the completion of the project (refer to Section 02 32 00 ENVIRONMENTAL SAMPLING)

• Demobilization of equipment and personnel to the site

• Removal and restoration of staging areas

• Demobilization of temporary offices and signage (refer to Section 01 50

00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS)

• Removal of erosion and sediment controls (refer to Section

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL)

• Removal of decontamination pad (refer to Section 01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR CONTAMINATED SITES, Paragraph 1.16)

• Preparation of closeout submittals

Section 01 22 00.00 10 Page 3

• Other miscellaneous elements of work required at the end of the project.

1.1.5.2 Unit of Measure

Unit of measure: LS.

1.2 UNIT PRICE PAYMENT ITEMS – BASE BID

Payment items for the work of this contract on which the Contract unit price payments will be made are listed in Section 00 41 00 BIDDING SCHEDULE, BASE BID ITEMS and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports; and for performing all work required for each of the unit price items.

1.2.1 Effluent Treatment and Discharge (Bid Item 03)

1.2.1.1 Payment

Payment will be made for work associated with operating and maintaining the effluent treatment system (identified in Bid Item 02) and any associated discharge sampling, monitoring, solids management, utilities, and fees owed to third parties as detailed in Section 44 40 00, WASTEWATER TREATMENT.

1.2.1.2 Measurement

This item shall be measured based on the time the treatment system is operational and treating effluent. If the system is non-operational due to lack of maintenance or some other fault of the Contractor, the time the system is non-operational will not be measured. If the treatment system is operated in batch mode, this item will be measured continuously while the system is onsite and operational, including standby time between batches.

1.2.1.3 Unit of Measure

Unit of measure: day. This will be measured to the nearest 1 day.

1.2.2 PVD Installation (Bid Item 05)

1.2.2.1 Payment

Payment will be made for work associated with installation of PVDs complete in place as specified in Section 31 32 40 PREFABRICATED VERTICAL DRAINS.

1.2.2.2 Measurement

This item shall be measured based on a vertical linear foot (VLF) basis of each drain from the top surface of the Sand Drainage Layer to the bottom tip of the PVD, based on field records agreed upon by the Contractor and Contracting Officer during installation. Any partial PVD where refusal was encountered and a replacement was approved by the Contracting Officer shall also be measured for payment.

Section 01 22 00.00 10 Page 4

1.2.2.3 Unit of Measure

Unit of measure: VLF. This will be measured to the nearest 1 VLF.

1.2.3 Containment Area No. 1 Stormwater Management (Bid Item 06)

1.2.3.1 Payment

Payment will be made for work associated with operating and maintaining the containment area stormwater treatment system (construction is paid under Bid Item 04) and any associated discharge sampling, monitoring, solids management, and fees owed to third parties as detailed in Section 44 40 00

WASTEWATER TREATMENT.

1.2.3.2 Measurement

This item shall be measured based on the time the treatment system is operating and treating effluent.