W911XK20R0003 0002.pdf

PDF 435 KB Posted

Attached to
Upstream Approach Wall Construction for the Soo Lock Complex, Sault Ste. Marie, MI.
Solicitation number
W911XK20R0003
Issued by

About this file

This federal solicitation seeks proposals for the construction of upstream approach walls at the Soo Lock Complex in Sault Ste. Marie, Michigan. The scope of work includes constructing soldier pile walls, sheet pile cells, concrete caps, fender systems, and mooring structures. The period of performance is 793 calendar days from notice to proceed with completion required by October 2023 for base work and option items. Proposals are due by June 17, 2020 with award intended within 30 days thereafter. The contract is a firm fixed price construction project with no set aside issued by the U.S. Army Corps of Engineers Detroit District.

View the file

Other files

File Type Posted
Amendment 0001 SL_APPROACH_SS115.pdf PDF
Amendment 0001 Railroad Bridge Drawings.pdf PDF
W911XK20R0003-0001_20May2020.pdf PDF
Amendment 0001 SL_APPROACH_SS509.pdf PDF
Amendment 0001 IBA Bridge Drawings.pdf PDF
Amendment 0001 North Canal Wall Survey Data 1.zip ZIP file
Amendment 0001 SL_APPROACH_ST500D.pdf PDF
Amendment 0001 Site Visit Videos.zip ZIP file
Amendment 0001 Summary of Changes to Specifications.pdf PDF
Pre-Proposal Site Visit - Presentation.pdf PDF
Amendment 0001 Drawings of Existing Bridge.pdf PDF
Amendment 0001 North Canal Wall Survey Data.zip ZIP file
Amendment 0001 Unit 10 Sluiceway Drawing.pdf PDF
Amendment 0001 Report for the Determination of Ground Vibration Limits_Final.pdf PDF
Chippewa County Health Department COVID-19 Screening Tool.pdf PDF
COVID-19 Guidance (Face Covering Guidance and Resources).pdf PDF
Amendment 0001 SL_APPROACH_SS301C.pdf PDF
Amendment 0001 SL_APPROACH_SS303.pdf PDF
Amendment 0001 Upstream Approach Wall Historic Drawings.pdf PDF
W911XK20R0003_27Apr2020.pdf PDF
01 99 90 - Bedrock Profiles.pdf PDF
01 99 90 - Electrical Conduit Systems.pdf PDF
01 99 90 - Subsurface Investigation Data_Part1.pdf PDF
UAW Certified Final Plans.pdf PDF
UAW Certified Final Specs.pdf PDF
01 99 90 - Project and Safety Signs.pdf PDF
01 99 90 - Pictures of Potential Hazardous Material.pdf PDF
01 99 90 - Subsurface Investigation Data_Part2.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W56MES91578279

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation No. W911XK20R0003 for the Construction of the Upstream Approach Walls at the Soo Lock Complex, Sault Ste. Marie, Michigan is amended to provide follow up responses to the Requests for Clarif ication (RFC), update Site Visit Attendees, update the DoDAACs, and change the delivery date for CLIN 0004. Please see follow ing pages for details.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 14

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK20R0003

X 9B. DATED (SEE ITEM 11)

27-Apr-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-May-2020

CODE

U.S.ARMY ENGINEER DISTRICT, DETROIT

477 MICHIGAN AVENUE, 7TH FLOOR

DETROIT MI 48226-4523

W911XK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911XK20R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

CONTRACTOR Q&A

Requests for Clarification (RFC):

1. Due to complexity of the work, RFP criteria, and small business participation requirements, and in consideration of the current social and economic environment, we request a 2 week extension to the bid date.

GOVERNMENT RESPONSE: The Government hereby grants additional time for submittal of proposals. Per Amendment 0001, the proposal due date will now be 17 June 2020 at the same time as indicated in the solicitation.

ADDED

GOVERNMENT RESPONSE: The Government will not be extending the proposal due date based on the issuance of Amendment 0002. Per Amendment 0001: proposals will be due 17 June 2020 at the same time as indicated in the solicitation.

10. Water levels in the US pool and in the Great Lakes in general have been at historic highs. Current water levels at the UAW are at approximately +2 LWD. The bottom of formed concrete caps on the SSP cells is at +1.2 LWD, below current water level even if excluding the wave action that is present. Is this work to be performed in the wet or is the contractor to provide a means by which to ensure construction in the dry?

GOVERNMENT RESPONSE: DSN: Reference Amendment 0001 which revises Specification Section 03 31 01.00 10 to clarify this requirement. Concrete may be placed underwater but it must conform to the guidelines and recommendations of ACI 304R Measuring, Mixing, Transporting and Placing Concrete, Chapter 8 - Concrete Placed Under Water. A specific concrete mixture for underwater placement must be developed for use in the placement. A work plan describing specific equipment and procedures for this work must be submitted for review and approval by the Government).

ADDED

RFC: Please clarify if 03 70 00 Mass Concrete and 03 31 00 Structural Concrete can utilize either Class C and/or Class F fly ash/pozzolan similar to fly ash types allowed for flowable fill and the tremie SCC mix types. This affects concrete supply logistics and RFP Risk Factor 6

GOVERNMENT RESPONSE: Both Class C and Class F fly ash/pozzolan can be utilized for the mass and structural concrete.

11. Sheet SS300 contains a series of Transition Wall Notes regarding the contractor designed SSP wall. Note 2 requires a calculation be performed including full hydrostatic pressure from the land side on the SSP wall.

Is it the Government’s intention to have the contractor perform a full stability analysis of the contractor designed SSP wall in the final as-designed, as-constructed state and assume the design liability for that portion of the project?

GOVERNMENT RESPONSE: The Contractor is responsible for construction of the permanent walls satisfying the minimum requirements of the drawings and specifications. Given that the Contractor’s means and methods of construction will affect the temporary conditions for these walls, the Contractor is responsible for the design of these walls in the temporary stages (i.e. required toe embedment for stability, bracing location and configuration, fill lifts, etc…).

ADDED

RFC: Contractor is responsible to construct the transition walls to the “minimum” requirements of the drawings and specifications. Section 31 41 16 Paragraph 2.1 specifies a minimum section modulus per LF of wall for the sheet piling. Is the specification referring to the plastic or the elastic section modulus?

GOVERNMENT RESPONSE: The referenced specification is referring to the elastic section modulus.

29. Please confirm that all fender wall irons and associated hardware including anchor bolts is to be supplied hot dip galvanized.

GOVERNMENT RESPONSE: Reference Amendment 0001 which revises Specification Section 05 12 00 to clarify this requirement. The structural steel components as identified in Specification Section 05 12 00 do not need to be hot dipped galvanized. As indicated in Specification Section 10 00 01, the threaded fasteners and associated hardware for the timber fenders are to be hot dip galvanized.

ADDED

RFC: Please specifically indicate if the 4” x 4” x 3/4” angles above and below the timber fenders are to be hot dipped galvanized or only the threaded fasteners and associated hardware

GOVERNMENT RESPONSE: Only threaded fasteners and associated hardware are to be hot dipped galvanized. The structural steel angles are to be bare steel.

43. Section 31 00 00 Earthwork. 3.2 SSP Wall Toe Trench Excavation states that the contractor shall clear the drive line including “satisfactory removal and disposal of obstructions such as boulders, bedded deposits, and unstratified masses...” What is the Corps’ definition of a boulder? Please provide an example of the bedded deposits referred to in this section as obstructions.

GOVERNMENT RESPONSE: Reference Amendment 0001 which revises Specification Section 31 00 00 to clarify this requirement. Boulders will be interpreted as pieces of rock of 1/2 cubic yard or more in volume. Additional information on the characteristics of the overburden material can be found in the test pit logs and boring logs located in Section 01 99 90.

ADDED

RFC: How will the government address contract adjustment in the event that obstructions or boulders are encountered when drilling for the soldier pile wall, deadman piers, or drilled mooring bollard foundations in areas where overburden is present above bedrock (such as STA 53-14 to STA 53+52)?

GOVERNMENT RESPONSE: The channel, at the time of completion of the Upstream Channel Deepening contract, will have a depth of no less than thirty (30) feet below Low Water Datum and may be as deep as thirty-one (31) feet below low water datum or greater. There will be local variations in the actual elevation of the surface between these values that may include instances where the variation is caused by boulders that were left in place. Additionally, the fill material present within the piers consists of fragmented Jacobsville Sandstone from previous channel deepening efforts. The Upstream Approach Wall Contractor must notify USACE of any impediments to installation of the Upstream Approach Walls that directly impact the ability to complete the installation and provide possible solutions to resolve the issue. The Contractor must also provide any cost or schedule impacts that may result from having to remove any impediments as part of the installation. The Government will review all cost and schedule impacts and negotiate possible remedies, as necessary.

47. Section 35 20 23 3.6.2 Wall Tolerances. On the NW Pier the timber cribs begin at station 38+35 and extend westward to the Upstream Limit. Should this area be outside of the stated tolerances, how would the Corps intend to resolve the issue? For example, if a timber crib has been damaged prior to the contractor beginning work onsite and is extending into the deepening A Line limit, would the Corps view that as an issue requiring a contract adjustment?

GOVERNMENT RESPONSE: If timber crib damage extends across the deepening A Limit Line outside of the stated tolerance this will be considered an unforeseen site condition and will be handled with a contract modification.

ADDED

RFC: To avoid damage to existing timber cribs, please specify an assumed allowable equipment loading for this feature.

GOVERNMENT RESPONSE: As indicated on GENERAL NOTE #7 on Sheet G-003, existing timber crib approach walls shall not be loaded at any time during construction.

58. SECTION 03 70 00 2.1.1 Mass Concrete - The definition of Mass Concrete is vague and open to interpretation in regards to the concrete dimension limits that require Mass Concrete. The sheet pile concrete cap has a depth of 5 feet. We have had contracts where this is clearly mass concrete, yet other contracts/clients where that dimension was not large enough to require mass concrete. Can the Corp provide more specifics on the minimum dimensions that require mass concrete?

GOVERNMENT RESPONSE: Areas requiring mass concrete can be found in paragraph 1.2 of Spec section 03 70 00. Mass concrete is limited to the concrete within the Transition Zones and the sheet pile end cells at the downstream limit of the project.

ADDED

RFC: Please clarify if 03 70 00 Mass Concrete and 03 31 00 Structural Concrete can utilize either Class C and/or Class F fly ash/pozzolan similar to fly ash types allowed for flowable fill and the tremie SCC mix types. This affects concrete supply logistics and RFP Risk Factor 6

GOVERNMENT RESPONSE: Both Class C and Class F fly ash/pozzolan can be utilized for the mass and structural concrete.

62. Refer to Spec 31 41 16 and 31 00 00.

a. In the SP cell areas 3A/B deepened by other contracts, specify the tip elevation to determine the sheetpile lengths to be purchased.

b. Spec 31 41 16, Article 3.1.6, specifies Inspection of the sheetpile trench. Are inspection surveys required for SP cell locations?

c. In the SP cell areas deepened by other contracts, what tip elevation surface prep is required, if any.

d. The specifications acknowledge there will be gaps under the SP cells on the rock surface. The excavation tolerance is +/-6”. These gaps shall be reported to the CO.

GOVERNMENT RESPONSE: Reference Amendment 0001 which revises Specification Section 31 00 00 and Section 31 41 16 to clarify the below requirements.

a. A tip elevation of -30.5 Feet below Low Water Datum +/- 6” will be required.

b. Inspection surveys will be required for ssp cell locations.

c. Deepening contracts requirements are -30 feet below Low Water Datum + 1’ allowable overdepth.

d. Inspection survey will be required to ensure maintaining required excavation tolerance and submitted to the COR prior to approval.

ADDED

RFC: Refer to Questions and Answers 62 (b) and (c), and 31 41 16 Part 3.1.6. Follow up question- Please clarify how much debris and fractured rock can be expected in the areas deepened by others.?

GOVERNMENT RESPONSE: The channel, at the time of completion of the Upstream Channel Deepening contract, will have a depth of no less than thirty (30) feet below Low Water Datum and may be as deep as thirty-one (31) feet below low water datum or greater. There will be local variations in the actual elevation of the surface between these values that may include instances where the variation is caused by boulders that were left in place. The Upstream Approach Wall Contractor must notify USACE of any impediments to installation of the Upstream Approach Wall that directly impact the ability to complete the installation and provide possible solutions to resolve the issue. The Contractor must also provide any cost or schedule impacts that may result from having to remove any impediments as part of the installation. The Government will review all cost and schedule impacts and negotiate possible remedies, as necessary.

63. Please clarify the criteria required for a cell to be filled without additional work.

GOVERNMENT RESPONSE: Please clarify where this requirement is located.

ADDED

RFC: Per spec. 3.1.6 inspection surveys are required to ensure maintaining required excavation tolerance and submitted to the COR prior to approval.

Inspection surveys are also required for sheetpile installation prior to filling cells Par 3.1.4. The specification acknowledges there will be gaps between the excavated rock surface and the sheetpile tips.

What will be the approval criteria of these condition surveys in order to commence filling the cells or SSP walls in a timely manner?

GOVERNMENT RESPONSE: Specification Section 31 41 16 paragraphs 3.1.6 and 3.1.8 (added in Amendment #0001) requires the Contractor to perform Inspection Surveys of the sheet pile trench and steel sheet pile cell footprint. The Government will utilize this inspection survey to verify that the steel sheet piles will be founded on “competent rock” by confirming that any loose, fragmented rock or overburden material are not present.

65. Will the attendee list for the virtual site visit be published?

GOVERNMENT RESPONSE: Yes

ADDED

RFC: Refer to Virtual Site Visit Attendees list. Please include Massman Construction Co. on the list.

Massman attendees were: Tom Tavernaro, Steve Macon, Bob Roble, John Kelley. Our group was called during the roll, and all responded

GOVERNMENT RESPONSE: The Attendee List for the Virtual Site Visit is updated to include Massman Construction Co. attendees.

81. Z-Pile walls are specified to be installed in a trench excavated a minimum distance into “competent rock”.

As used in this context in the specifications and drawings, what is the definition of “competent rock” and what will be the method of determining/verifying competent rock?

GOVERNMENT RESPONSE: Competent rock shall be interpreted as rock capable of withstanding the loading it will be subjected to. Additional information on the characteristics of the overburden material as well as the bedrock can be found in the test pit logs and boring logs located in Section 01 99 90. The Contractor is responsible for verifying that the rock trench has the minimum required depth in competent rock.

ADDED

RFC: The government response does not address part of the question, please confirm what method will be used to determine/verify competent rock (i.e that that rock is capable of withstanding the loading it will be subject to).

GOVERNMENT RESPONSE: Specification Section 31 41 16 paragraphs 3.1.6 and 3.1.8 (added in Amendment #0001) requires the Contractor to perform Inspection Surveys of the sheet pile trench and steel sheet pile cell footprint. The Government will utilize this inspection survey to verify that the steel sheet piles will be founded on “competent rock” by confirming that any loose, fragmented rock or overburden material are not present.

95. Solicitation item 11 on page 1 states that work is to be complete within 793 calendar days after NTP. If

NTP is 15 October 2020, project completion would be 17 December 2022. Solicitation section 6.1, Volume I – Factor II states that Construction Completion Date for all CLINS is 15 October 2023. Clause 52.217-7 states that options 4 and 6 -10 shall be completed no later than 15 October 2023. Will a time extension be granted if these options are awarded?

GOVERNMENT RESPONSE: Correct, if Options 4 and 6-10 are exercised, there will be an extension to the Period of Performance for completion of these options.

ADDED

RFC: Section 52.217-7 (Page 74) of the solicitation states “All work under Contract Line Item (CLIN) 0004 “Option 1: Zones 10 and 11 Work: West Center Pier Rehab” shall be completed no later than 15 October 2021.” The Delivery Information on page 9 of the solicitation indicates CLIN 0004 (Option 1:

Zones 10 & 11) is to be completed by 15 October 22. Please confirm which completion date is correct.

GOVERNMENT RESPONSE: The correct completion date is 15 October 2021. CLIN 0004 has been updated to the correct completion date.

The following have been modified:

SITE VISIT ATTENDEES

Site Visit Attendees:

AECOM - Wade Miller Cody Gordanier Ted Sheehan Patty Olson Jeremy O’Farrell

Alberici - Demon Parker Mike Burke Matt Grieshaber Rick Tockes Fred Biermann Brian King Craig Schmidt

Cashman Dredging & Marine – Stephen Tobin Contracting, LLC Michael Empey Brian Rawston

Contract Drilling and Blasting, LLC - Albert vanNiekerk

GEI Consultants – Chris Abraham

J.F. Brennan Co. - Mike Binsfeld Scott Krall Jeff Steiber Dan Wibralski Zach Pontzer Nick Patterson Rory Alsberg Dan Savoy

J. Ranck Electric, Inc. – Peter Kropf

Kokosing Industrial, Inc. - Mark Henrikson David Vogelheim David Nordquist Aaron Harke Jeffrey Hartman John Adam Bakewell Jesse Smith Andrew Fruehling Binh Nguyen Timothy Britts

Kraemer North America, LLC - Brent Freeman Darrin Stanke

Chuck Phillipp Brian Bellfi

Malcolm Drilling Company - Chad Gray Jim Glider Matt Gettendorf

Massman Construction Co. - Tom Tavernaro Steve Macon Bob Roble John Kelley

Michigan Regional Council of - Jason Reed Carpenters and Millwrights

Morrish Wallace Construction, Inc. – Travis Lake (d.b.a. Ryba Marine Construction Co.) Tom Bajko

Nicholson Construction - Aaron Evans

US Army Corps of Engineers - Isaac Freel Steve Hutchens Gail Hill Steven Pautz Donald Johnson Noah Talentino Bryce Sanderson Maureen Mahoney Kristina Schnettler William Merte Sheetal Malhotra Timothy Smith Corina Trommer Neil Kaczorowski Jacob Carr Clint Dougherty Mark Brewer Darin White Jeremiah Nichols Gary Grunwald Alexander Jiminez

SECTION 00 10 00 - SOLICITATION

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

15-OCT-2022 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

FOB: Destination

H7L8860

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

15-OCT-2022 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

965411

The following Delivery Schedule item for CLIN 0002 has been changed from:

CAGE

15-OCT-2021 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2021 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0003 has been changed from:

CAGE

15-OCT-2022 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2022 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0004 has been changed from:

CAGE

15-OCT-2022 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2021 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0005 has been changed from:

CAGE

15-OCT-2022 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2022 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0006 has been changed from:

CAGE

15-OCT-2022 12 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2022 12 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0007 has been changed from:

CAGE

15-OCT-2023 12 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

15-OCT-2023 12 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0008 has been changed from:

CAGE

15-OCT-2022 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2022 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0009 has been changed from:

CAGE

15-OCT-2023 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2023 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0010 has been changed from:

CAGE

15-OCT-2023 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2023 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0011 has been changed from:

CAGE

15-OCT-2023 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2023 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0012 has been changed from:

15-OCT-2023 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2023 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

The following Delivery Schedule item for CLIN 0013 has been changed from:

CAGE

15-OCT-2023 1 SOO AREA OFFICE

ST. MARY'S FALL CANAL

SAULT STE. MARIE MI 49783

CAGE

15-OCT-2023 1 SOO AREA OFFICE

KEVIN SPRAGUE

312 PORTAGE AVENUE

SAULT STE. MARIE MI 49783-2445

(End of Summary of Changes)