Additional_questions_were_received_on_11_September.pdf

PDF 47 KB Posted

Attached to
EQUIPMENT RENTAL - SOO AREA OFFICE, SAULT STE MARIE, MI
Solicitation number
W911XK19R0023
Issued by

View the file

Other files

File Type Posted
IMG_0034.JPG JPG image
20180126_101431.jpg JPG image
Additional_Government_Response_to_Questions.pdf PDF
W911XK19R0023-0001.pdf PDF
Government_Response_to_Questions.pdf PDF
Sketch_1_Enclosure_Schematic_Elevation.pdf PDF
Sketch_3_2019_Winter_Work_Site_Plan.pdf PDF
Reference_Drawings.pdf PDF
W911XK19R0023.pdf PDF
Sketch_2_Enclosure_Schematic_Elevation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Additional questions were received on 11 September

Reference CLIN 0016

Question 1. What is the Vertical pumping distance?

Answer. 65 feet

Question 2. What is the Horizontal pumping distance?

Answer. 200 feet

Question 3. What is the Type of Pump set up: cable deployed, deployed off excavator or stand-alone unit?

Answer. Stand-alone Unit

Reference CLIN 0019

Question 4. How close can one park a delivery truck to the scaffolding installation location?

Answer. During the period that the MacArthur Lock temporary bridge is in place, a delivery truck will be able to get within approximately 400 feet of the south end of Poe Lock Gate 1. The truck can park while unloading, but not for extended periods.

Question 5. Will we be parking at the top and lowering the material down into the Lock area?

Answer. Scaffold materials will need to be unloaded from the delivery truck and moved approximately 400 feet to the point where they can be lowered to the Gate 1 sill area.

Small load handling equipment can traverse this area, but it is quite congested.