AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY18 St. Louis River AOC Slip 3 and Slip C Remedial Cap
This amendment is issued to change the bid schedule and specifications. The due date has been changed to 17 July 2018 at 2:00pm Eastern. Reference changes on the follow ing pages.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Jul-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911XK18B0007
X 9B. DATED (SEE ITEM 11)
06-Jun-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Jul-2018
CODE
U.S.ARMY ENGINEER DISTRICT, DETROIT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK18B0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 10-Jul-2018 02:00 PM to 17-Jul-2018 02:00 PM.
The Issued By organization has changed from
CONTRACTING BRANCH
USACE DETROIT DISTRICT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
to
U.S.ARMY ENGINEER DISTRICT, DETROIT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
The following have been added by full text:
AMENDMENT 0001
CHANGES TO THE SOLICITATION
1. Bid Schedule
Add item 0012, Debris Removal and Disposal, Qty: 10, Unit of Measure: TON
CHANGES TO THE SPECIFICATIONS
1. SECTION 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
a. Add paragraphs:
“1.3.12 0012 Debris Removal and Disposal
1.3.12.1 Payment
This item shall include debris removal within the cap areas in Slip 3 and Slip C, transport, and disposal of the debris at a Type III landfill approved by the COR. All debris within the designated cap areas that extends more than 2 feet above final leveling grade in Slip 3, or above existing mud line in Slip C, shall be removed by the Contractor and disposed of off-site prior to cap construction in the slips.
1.3.12.2 Unit of Measure
Unit of Measure: Ton (2000 lbs)”
b. Add paragraph:
“3.2 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(a) This clause does not apply to terminations. Federal Acquisition Regulation (FAR) part 49.
b) Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of Engineer Pamphlet (EP) 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region 4. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet. “
2. SECTION 35 20 23 SLIP 3 SEDIMENT LEVELING
Delete paragraph 1.8 Artificial Obstructions Add revised paragraph:
“1.8 Artificial Obstructions Debris is anticipated in placement areas in Slip 3 and Slip C. The Government has no knowledge of cables, pipes, or other artificial obstructions or of any wrecks, wreckage, or other material that would necessitate the employment of additional equipment for economical removal. Any existing channel crossing that is damaged due to the Contractor's operations shall be repaired by the Contractor and at its expense. If actual conditions differ from those stated or shown, or both, an adjustment in contract price or time for completion, or both, will be made in accordance with FAR 52.236-2, Differing Site Conditions."
The following have been modified:
BID SCHEDULE
ITEM SUPPLIES/SERVICES UNIT QTY UNIT PRICE TOTAL
0001 Mobilization & Demobilization JOB 1 $ $
0002 Turbidity Curtain Installation & Maintenance of Slip 3 & C
JOB 1 $ $
0003 Pilot Tests Slip 3 & C JOB 1 $ $
0004 Slip Leveling - Slip 3 JOB 1 $ $
0005 Subaqueous Cap Layer A Construction and Area B - Slip 3
JOB 1 $ $
0006 Subaqueous Cap Layer B Construction Shallow Area, Area B and Transition Area - Slip 3
JOB 1 $ $
0007 Subaqueous Cap Layer B Construction Deep Area and Apron Area - Slip 3
JOB 1 $ $
008 Subaqueous Cap Layer A Construction - Slip C
JOB 1 $ $
0009 Subaqueous Cap Layer B Construction, and Cove, and Apron Area - Slip C
JOB 1 $ $
0010 Subaqueous Cap Layer B Construction at Cove Mouth/Wall Failure Areas - Slip C
JOB 1 $ $
0011 Subaqueous Riprap - Slip 3 & Slip C $ $
0011AA First 310 TON TON 310 $ $
0011AB Over 310 TON TON 130 $ $
0012 Debris Removal and Disposal TON 10 $ $
Total Amount of Bid $
(End of Summary of Changes)
File details come from the government source that posted it.