FY17 CLINTON RIVER MOUTH - HABITAT RESTORATION - RTA FY17CLINTONRIVER

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 10 REAL ESTATE

01 22 00.00 10 PRICE AND PAYMENT PROCEDURES

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 13.10 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 38 00 CONSTRUCTION PHOTOGRAPHS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.10 10 QUALITY CONTROL SYSTEM (QCS)

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 99 90 LISTING OF ENCLOSED DOCUMENTS, EXHIBITS AND OTHER

ATTACHMENT

DIVISION 31 - EARTHWORK

31 13 19 SELECTIVE TREE AND SHRUB CLEARING, REMOVAL AND GRUBBING

31 23 00.00 20 EXCAVATION AND FILL

31 31 19.13 CHEMICAL VEGETATION CONTROL

31 31 19.16 PRESCRIPTION BURNING

31 32 11 SOIL SURFACE EROSION CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 90 ESTABLISHMENT ACTIVITIES

32 93 01 NATIVE PLANTS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 10

REAL ESTATE

03/01

PART 1 GENERAL

1.1 SUBMITTALS

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

1.2.2 Additional Real Estate Rights

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

1.3.2 Survey Markers

1.3.2.1 Semipermanent Markers

1.3.2.2 Temporary Markers

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 10 10 Page 1

SECTION 01 10 10

REAL ESTATE

03/01

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Additional Property Agreements; G-RED.

Copies of any agreements for Contractor-acquired real estate rights for this project shall be furnished before entering thereon.

Certified Survey Results

Furnish a copy of certified results of surveys which verify areas and limits of Contractor-acquired real estate rights.

1.2 REGULATORY REQUIREMENTS

1.2.1 Real Estate Rights

Rights for the use of the work and storage areas have been obtained and the general limits of the areas are shown on the drawings. Copies of instruments conveying rights for use of the work and storage areas shown on the drawings and specified herein are available for inspection in the Engineering, Design, & Construction Office, U.S. Army Corps of Engineers, Detroit District, 477 Michigan Avenue, McNamara Building, Detroit, Michigan. Conformance to all applicable requirements of the instruments conveying rights is required. Two (2) copies of each instrument will be furnished to the Contractor. No other real estate rights have been obtained by the Government for this project.

1.2.2 Additional Real Estate Rights

Any additional property agreements and/or real estate rights desired by the Contractor shall be obtained by the Contractor at its own expense. Such agreements shall clearly relieve the Government of any responsibility for damages or liability resulting from the Contractor's use of such grounds.

1.3 PROJECT/SITE CONDITIONS

1.3.1 Location and Verification

It shall be the Contractor's responsibility to accurately locate the limits

SECTION 01 10 10 Page 2 of all lands utilized under the contract. The corner and angle points of each area for which rights have been obtained shall be marked with semipermanent markers except where there is an approved existing property marker. Temporary markers shall be placed at points on alignment. The points on alignment shall be marked at stations so that intervals between points do not exceed 200 feet.

1.3.2 Survey Markers

All markers shall be installed in an area prior to its use and they shall be available for reference during and upon completion of use of the area.

Where approved existing property markers are found, a witness stake, as specified in Subparagraph, "Semipermanent Markers" below, shall be provided. If the types of markers specified hereinafter cannot be used, other types, as approved by the Contracting Officer, shall be provided.

1.3.2.1 Semipermanent Markers

The markers shall be a steel rod one-half inch in diameter and four (4) feet long. The steel rod shall be driven vertically into the ground so that the top is flush with the finished ground surface. Each marker shall be witnessed by a 2" x 2" yellow stake extending two (2) feet above the ground surface and driven into the ground until stable, with not less than one (1) foot penetration.

1.3.2.2 Temporary Markers

Markers shall be 2" x 2", red-colored, wood hub stakes driven into the ground until stable (not less than one (1) foot penetration) with two (2) feet projecting above the ground surface. If the period in which temporary markers are to be in place exceeds one (1) construction season, a more permanent type of marker, as approved, shall be provided.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 10 10 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

PRICE AND PAYMENT PROCEDURES

08/15

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

1.2 BIDDING SCHEDULE

1.2.1 0001 CLEARING, GRUBBING, EXCAVATION, FILL AND GRADING

1.2.1.1 Payment

1.2.1.2 Unit of Measure

1.2.2 0002 ESTABLISHMENT ACTIVITIES

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.3 0003 CALCAREOUS SOIL MIX

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.4 0004 TOPSOIL

1.2.4.1 Payment

1.2.4.2 Unit of Measure

1.2.5 0005 RESTORATION SEEDING AND PLANTING

1.2.5.1 Payment

1.2.5.2 Unit of Measure

1.2.6 0006 TEMPORARY CONSTRUCTION FACILITIES

1.2.7 Unit of Measure

1.2.8 0007 DEMOLITION

1.2.9 Unit of Measure

1.2.10 0008 OPTION 1 PHRAGMITES REMOVAL

1.2.11 Unit of Measure

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 22 00.00 10 Page 1

SECTION 01 22 00.00 10

PRICE AND PAYMENT PROCEDURES

08/15

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2 BIDDING SCHEDULE

1.2.1 0001 CLEARING, GRUBBING, EXCAVATION, FILL AND GRADING

1.2.1.1 Payment

Payment will be made at the contract price for costs associated with clearing, grubbing, removal and hauling offsite trees designated and tree protection, excavation, and fill as shown on the drawings and as specified in Section 31 13 19 SELECTIVE TREE AND SHRUB CLEARING, REMOVAL AND GRUBBING, and section 31 23 00.00 20 EXCAVATION AND FILL. The excavation, grading and fill work will include the work required to grade the upland site. Payment constitutes full compensation for all labor, materials, equipment, tools, and incidentals necessary to complete the work as specified and shown on the contract drawings.

1.2.1.2 Unit of Measure

Unit of measure: Job.

1.2.2 0002 ESTABLISHMENT ACTIVITIES

1.2.2.1 Payment

Payment will be made at the contract price for costs associated with the Contractor's labor, materials, tools, equipment, and other incidentals necessary to complete the work including woody resprout control, herbaceous invasive plant control and establishment of seeded and planted areas as indicated, including herbiciding, mowing, inspections, and other activities as shown on the drawings and described in Sections 31 13 19 SELECTIVE TREE

AND SHRUB CLEARING, REMOVAL AND GRUBBING,31 31 19.13 CHEMICAL VEGETATION

CONTROL, section 31 31 19.16 PRESCRIPTION BURNING and section 32 01 90

ESTABLISHMENT ACTIVITIES, THE MDEQ GUIDE TO PHRAGMITES REMOVAL ATTACHMENT.

Maintenance may require watering, weeding, supplemental mulching, or waterfowl/grazing control. The results of the Establishment Activities will

SECTION 01 22 00.00 10 Page 2 be as outlined in paragraph titled "Performance Criteria and Acceptance" listed in Section 32 01 90 ESTABLISHMENT ACTIVITIES to be accepted for payment by the COR.

1.2.2.2 Unit of Measure

Unit of measure: Job.

1.2.3 0003 CALCAREOUS SOIL MIX

1.2.3.1 Payment

Payment will be made at the contract price for costs associated with purchasing, transportation, and placing three inches layer of calcareous soil mix over the top of the existing armoring only in the south side of the site as shown on the contract drawings and specified in section 32 93 01 NATIVE PLANTS. Payment constitutes full compensation for all labor, materials, equipment, tools and incidentals necessary to complete the work as specified and shown on the contract drawings.

1.2.3.2 Unit of Measure

Unit of measure: Job.

1.2.4 0004 TOPSOIL

1.2.4.1 Payment

Payment will be made at the contract price for costs associated with purchasing, transportation, and placing the compost soil as shown on the contract drawings and specified in section 32 93 01 NATIVE PLANTS. Payment constitutes full compensation for all labor, materials, equipment, tools and incidentals necessary to complete the work as specified and shown on the contract drawing.

1.2.4.2 Unit of Measure

Unit of measure: Job.

1.2.5 0005 RESTORATION SEEDING AND PLANTING

1.2.5.1 Payment

Payment will be made at the contract price for costs associated with purchasing, transportation, and placing/planting native seed and plants and installing Hummocks as shown on the contract drawings and specified in section 32 93 01 NATIVE PLANTS. Payment constitutes full compensation for all labor, materials, equipment, tools and incidentals necessary to complete the work as specified and shown on the contract drawing.

1.2.5.2 Unit of Measure

Unit of measure: Job.

1.2.6 0006 TEMPORARY CONSTRUCTION FACILITIES

Payment will be made at the contract price for costs associated with a building a temporary administrative field office, utilities, staging

SECTION 01 22 00.00 10 Page 3 storage area and all associated costs as described in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES, as well as all required erosion and sediment control measures as described in specification section 31 32 11 SOIL SURFACE EROSION CONTROL, and the erection and maintenance of one (1) Project Identification Sign and one (1) Safety Performance Sign in accordance with Section 01 58 00 PROJECT IDENTIFICATION and all other temporary features.

1.2.7 Unit of Measure

Unit of Measure: Job.

1.2.8 0007 DEMOLITION

Payment will be made at the contract price for costs associated with the removal of the chainlink fence around the two ponds, the removal of the structure and large trash from and around the ponds and the removal of large trash piles in the west side of the site and all associated costs as shown on the contract drawings and described in Section 32 93 01 NATIVE PLANTS paragraph titled Site Preparation. Payment constitutes full compensation for all labor, materials, equipment, tools, and incidentals necessary to complete the work.

1.2.9 Unit of Measure

Unit of Measure: Job

1.2.10 0008 OPTION 1 PHRAGMITES REMOVAL

Payment will be made at the contract price for costs associated with the Contractor's labor, materials, tools, equipment, and other incidentals required to the intial removal of Phragmites. Phragmites removal includes herbiciding, mechanical removal, mowing, and other activities as shown on the drawings and described in Sections 31 31 19.13 CHEMICAL VEGETATION CONTROL, section 31 31 19.16 PRESCRIPTION BURNING and THE MDEQ GUIDE TO

PHRAGMITES REMOVAL ATTACHMENT

1.2.11 Unit of Measure

Unit of Measure: Job

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used -- End of Section --

SECTION 01 22 00.00 10 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/08

PART 1 GENERAL

1.1 SUBMITTALS

1.2 SCHEDULE PREPARER

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Completed Project Bar Chart Submittal:

3.1.2 3.1.2 Work Activity/Event Cost Date:

3.1.3 Computer Produced Schedules:

3.1.4 Work Activity/Event Cost Data:

3.1.5 Network Diagram Requirements:

3.2 APPROVED CHANGES VERIFICATION:

3.3 PAYMENT TO THE CONTRACTOR:

3.3.1 Responsibility For Completion:

3.4 REQUEST FOR TIME EXTENSIONS:

3.5 ADJUSTMENT OF CONTRACT COMPLETION:

3.6 DIRECTED CHANGES

3.7 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

SECTION 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/08

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Schedule; G

1.2 SCHEDULE PREPARER

Designate an authorized representative to be responsible for the preparation of the schedule, review and report of progress of the project with, and to, the Contracting Officer. The authorized representative shall be experienced in scheduling projects similar in nature to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar chart schedule demonstrating fulfillment of the contract requirements.

The Contractor shall keep the network up-to-date in accordance with the requirements of this section. The Contractor shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). The Bar chart will be utilized to satisfy both time and cost applications.

The schedule shall provide sufficient detail and clarity so that the contractor can plan and control the work and the Contracting Officer can readily monitor and follow the progress of all portions of the work. The critical activities must be clearly shown and the schedule shall include cost loading and activity coding. The degree of detail must be satisfactory to the Contracting Officer. This schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of

SECTION 01 32 01.00 10 Page 2 progress payments until the required schedule is submitted.

3.1.1 Completed Project Bar Chart Submittal:

Within thirty (30) calendar days after receipt of the Contract Award, the Contractor shall submit for the Contracting Officer's review; an electronic copy of Project Bar chart. Each activity/event on the Bar chart schedule shall contain as a minimum, but not limited to, activity/event description, duration, start dates, finish dates, budget amounts, and predecessor and successor relationships. Work activity/event relationships shall be restricted to finish-to-start, only, without lead or lag constraints. Logic events (non-work) will be permitted where necessary to reflect proper sequence among work events, but must have zero duration.

The complete working Bar chart shall reflect the Contractor's approach to scheduling the complete project. The final Bar chart in its original form shall contain no contract changes or delays that may have been incurred during the final Bar chart development period. It shall reflect the Contractors "AS BID" or "DAY 1" schedule. Changes and /or delays shall be entered at the first monthly update after the final Bar chart has been approved. The Contractor should provide his requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT COMPLETION.

Within fifteen (15) calendar days after receipt of the complete project network diagram, the Contracting Officer or his representative will do one or both of the following:

a. Notify the Contractor concerning his actions, opinions, and objections.

b. Schedule a meeting with the Contractor at, or near the job site, for joint review, correction or adjustment of the proposed plan, if required.

Within ten (10) calendar days after the joint review, the Contractor shall revise and shall submit an electronic copy of the revised Bar chart. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved. This approved Bar chart shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.

3.1.2 3.1.2 Work Activity/Event Cost Date:

The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Overhead, profit and general conditions shall be pro-rated on all work activities/events for the entire project length. Negative work activity/event cost data will not be acceptable, except on USACE issued contract changes.

The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in the General Conditions.

3.1.3 Computer Produced Schedules:

The Contractor shall provide the Contacting Officer monthly computer processing of all computer produced schedules generated from monthly project updates. The Contractor will provide to Contracting Officer

SECTION 01 32 01.00 10 Page 3 an electronic copy of the updated Bar chart. These must be submitted with and substantively support the contractor's monthly payment request.

The Contractor is responsible for the correctness and timeliness of the computer-produced reports. The Contractor is also responsible for the accurate and timely submittal of the updated project schedule.

The Contracting Officer shall report errors in computer-produced reports to the Contractor's representative within ten (10) calendar days from receipt of reports. The Contractor will reprocess the Bar chart, when requested by the Contracting Officers Representative, to correct errors that affect the schedule for the project.

3.1.4 Work Activity/Event Cost Data:

The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Overhead, profit and general conditions shall be pro-rated on all work activities/events for the entire project length.

The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in the General Conditions.

3.1.5 Network Diagram Requirements:

Show on the Bar chart the sequence and interdependence of work activities/events required for complete performance of all items of work.

In preparing the Bar chart, the Contractor shall show activities/events as:

a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre construction work.

b. Contracting Officer's and Architect Engineer's review and approval of shop drawings, samples, template, or similar items.

c. Interruption of utilities, project phasing and any other specification requirements.

d. Agencies activities including, but not limited to, inspections and utility tie-in.

e. Submissions and approvals of as-builts drawings.

f. Contractor's pre-final inspection.

g. Correction of punch list from Contractor's pre-final inspection.

h. Government's pre-final inspection.

i. Correction of punch list from Government's pre-final inspection.

j. Final Inspection.

Break up the work into activities/events of duration no longer than sixty

(60) work days each. The duration for Contracting Officer's approval of any required submittal, shop drawing, or other submittals shall be fourteen

(14) workdays with seven (7) days for resubmittals. The construction time as determined by the Bar chart schedule from start to finish for any sub-phase, phase or the entire project shall not exceed the contract time(s) specified or shown.

Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled "start," "continue," or "completion," are not specific and will not be allowed.

SECTION 01 32 01.00 10 Page 4

3.2 APPROVED CHANGES VERIFICATION:

Include only those project schedule changes in the schedule submission that have been previously approved by the Contracting Officer. The Narrative Report shall specifically reference, on an activity basis, all documented, approved schedule changes.

3.3 PAYMENT TO THE CONTRACTOR:

Weekly job site progress meetings shall be held on dates mutually agreed to by the Contracting Officer (or Contracting Officer's Representative) and the Contractor. Presence of subcontractors during the progress meeting is optional unless required by the Contracting Officer. Job progress will be reviewed to verify:

a. Actual start and/or finish dates for updated/completed activities/events.

b. Remaining duration, required to complete each activity/event started, or scheduled to start, but not completed.

c. Time and cost data for change orders, and supplemental agreements that are to be incorporated into the Bar chart.

d. Percentage for completed and partially completed activities/events.

e. Logic and duration revisions required by this section of the specifications.

f. Activity/event duration and percent complete shall be updated independently.

As part of the weekly jobsite progress meeting, the General Contractor, specifically requested subcontractors and the Contracting Officers shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary actions required to maintain project schedule during the reporting period.

3.3.1 Responsibility For Completion:

Whenever it becomes apparent from the weekly progress review meeting or the monthly computer produced Bar chart schedule that phasing or contract completion dates will not be met, the Contractor shall adjust means and methods to eliminate the backlog of work.

Prior to proceeding with any of adjustments, the Contractor shall notify and obtain approval from the Contracting Officer for the proposed schedule changes. If such actions are approved, the revisions shall be incorporated by the Contractor into the Bar chart before the next update, at no additional cost to the Government.

3.4 REQUEST FOR TIME EXTENSIONS:

In the event the Contractor believe it is entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the Contracting Officer: justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals issued by the Government, submit a schedule

SECTION 01 32 01.00 10 Page 5 impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.

3.5 ADJUSTMENT OF CONTRACT COMPLETION:

The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, Bar chart data and supporting evidence as the Contracting Officer may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract. Submission of proof based on revised activity/event logic, durations (in work days) and costs is obligatory to any approvals.

The Contracting Officer's determination as to the total number of days of contract extension will be based upon the current computer produced Bar chart schedule for the time period when the change took place and all other relevant information. The Contracting Officer will, within thirty (30) calendar days after receipt of such justification and supporting evidence, advise the Contractor in writing of his decision on the matter.

The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in accordance with the provisions specified under Article, CHANGES, in the Section, GENERAL CONDITIONS. The Contractor shall include, as a part of each change order proposal, a sketch showing all Bar chart revisions, duration (in work days) changes, and cost changes, for work in question and its relationship to other activities on the approved network diagram.

All delays due to non-work activities/events such as RFIs, WEATHER, STRIKES, and similar non-work activities/events shall be analyzed on a month-by-month basis.

3.6 DIRECTED CHANGES

If the NTP is issued for changes prior to settlement of price and/or time, submit proposed schedule revisions to the Contracting Office within 2 weeks of the NTP being issued. The Contracting Officer will approve proposed revisions to the schedule prior to the inclusion of those changes within the project schedule. If the Contractor fails to submit the proposed revisions, the Contracting Officer may furnish the Contractor with suggested revisions to the project schedule. Include these revisions in the project schedule until revisions are submitted, and final changes and impacts have been negotiated. If the Contractor has any objections to the revisions furnished by the Contracting Officer, advice the Contracting Officer within 2 weeks of receipt of the revisions. Regardless off the objections, continue to update the schedule with the Contracting Officer's revisions until a mutual agreement in the revisions is reached. If the Contractor fails to submit alternate revisions within 2 weeks of recite of the Contracting Officer's proposed revisions, the Contractor will be deemed to have occurred with the Contracting Officer's proposed revisions. The proposed revisions will then be the basis for an equitable adjustment for performance of the work.

a. Government (or as otherwise mutually agreed to) for the purpose of jointly reviewing the actual progress and to review planned activities for the upcoming two weeks. The then current and approved schedule update shall be used shall be used for the purposes of this meeting and for the

SECTION 01 32 01.00 10 Page 6 production and review of reports. The Contractor's Project Manager and the Authorized Representative of the Contracting Officer shall attend. The weekly progress meeting will address the status of the RFI's, RFP's and Submittals.

b. Provide a bar chart produced by the scheduling software, organized by Total Float and sorted by Early Start Date, and a two week "look-ahead" schedule by filtering all schedule activities to show only current ongoing activities and activities scheduled to start during the upcoming two weeks.

3.7 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

Download and upload the scheduled data into the Resident Management System (RMS) prior to RMS databases being transferred to the Government and is considered to be additional supporting data in a form and detail required by the Contracting Officer pursuant to FAR 52.232-5 - Payments under Fixed-Price Construction Contracts. The receipt of a proper payment request pursuant to FAR 52.232-2777 - Prompt Payment for Construction Contracts is contingent upon Government receiving both acceptable and approved hard copies and electronic export from QCS of the application for progress payment.

SECTION 01 32 01.00 10 Page 7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 SUMMARY

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Approving Authority

1.2.3 Work

1.3 SUBMITTALS

1.4 SUBMITTAL CLASSIFICATION

1.4.1 Designer of Record Approved (DA)

1.4.2 Government Approved (G)

1.4.3 For Information Only

1.4.4 Sustainability Reporting Submittals (S)

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Source Drawings for Shop Drawings

1.5.2.1 Terms and Conditions

1.5.3 Electronic File Format

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Samples SD-04 Samples

1.7 INFORMATION ONLY SUBMITTALS

1.8 SUBMITTAL REGISTER

1.8.1 Use of Submittal Register

1.8.2 Contractor Use of Submittal Register

1.8.3 Approving Authority Use of Submittal Register

1.8.4 Copies Delivered to the Government

1.9 VARIATIONS

1.9.1 Considering Variations

1.9.2 Proposing Variations

1.9.3 Warranting that Variations are Compatible

1.9.4 Review Schedule Extension

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVEDOR REJECTED SUBMITTALS

1.13 APPROVED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

ATTACHMENTS:

SECTION 01 33 00 Page 1

Appendix A - Submittal Register

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register".

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

SECTION 01 33 00 Page 3

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of prices or Earned Value Report

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SECTION 01 33 00 Page 4

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Approving Authority

Office or designated person authorized to approve submittal.

SECTION 01 33 00 Page 5

1.2.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G, AOF

1.4 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.4.1 Designer of Record Approved (DA)

Designer of Record (DOR) approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings." Contractor to provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The Government may review any or all Designer of Record approved submittals for conformance to the Solicitation, Accepted Proposal and the completed design. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below. Design submittals to be in accordance with Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD). Generally, design submittals should be identified as SD-05 Design Data submittals.

1.4.2 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.4.3 For Information Only

Submittals not requiring Government approval will be for information only.

They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

SECTION 01 33 00 Page 6

1.4.4

Sustainability Reporting Submittals (S)

Submittals for Guiding Principle Validation (GPV) or Third Party Certification (TPC) are indicated with an "S" designation. Submit the information required by the technical sections that demonstrates compliance with the sustainable requirement, and for inclusion in the Sustainability Notebook as required by Section 01 33 29 SUSTAINABILITY REPORTING. A full submittal for an item may be provided under another SD; however, for the "S" submittal, only provide that portion of the submittal that demonstrates compliance with the sustainable requirement. If the sustainable submittal does require Government Approval, it may be tagged under another SD with a "G."

Schedule submittals for these items throughout the course of construction as provided; do not wait until closeout.

1.5 PREPARATION

1.5.1 Transmittal Form

Transmittal forms are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted.

Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Source Drawings for Shop Drawings

The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.

1.5.2.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic Source Drawing files are not construction documents.

Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents

SECTION 01 33 00 Page 7 prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.5.3 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/.

Provide hard copies of submittals when requested by the Contracting Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Samples SD-04 Samples

a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.

b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.

c. Submit one sample installation, where directed.

d. Submit one sample of non-solid materials.

1.7 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

SECTION 01 33 00 Page 8

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.8 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT

SYSTEM CONTRACTOR MODE (RMS CM)).

1.8.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

1.8.2 Contractor Use of Submittal Register

Update the following fields with each submittal throughout contract.

Column (a) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (b) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (c) List date of submittal transmission.

Column (d) List date approval received.

1.8.3 Approving Authority Use of Submittal Register

Update the following fields in the program utilized by Contractor.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.8.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government

SECTION 01 33 00 Page 9 with each invoice request.

1.9 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.9.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.9.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.9.3 Warranting that Variations are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.9.4 Review Schedule Extension

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.10 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing and processing of

SECTION 01 33 00 Page 10 submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.11 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within…