Braddock Locks Interlock Control System Replacement
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
1.1.1 Reimbursement For Actual Performance And Payment Bond Premiums
1.1.2 Interlock Control System Replacement
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.2.3 Payment Item
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Digital Progress Images
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.1.4 Payment Items
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
-- End of Section Table of Contents --
SECTION 01 22 00.00 08 Page 1 Certified Final Documents - RTA W911WN19B8006 - Amendment 3
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Reimbursement For Actual Performance And Payment Bond Premiums
Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00 73 00 SUPPLEMENTARY CONDITIONS, clause
PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.
0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS
1.1.2 Interlock Control System Replacement
1.1.2.1 Payment
Payment for this item shall constitute full compensation for all labor, equipment, material and supply costs for removal of existing control and hydraulic components and installation of new Contractor-furnished control system and hydraulic components as shown in the drawings and as specified , as well as continuous dewatering and sediment removal in the lock crossover .
1.1.2.2 Unit of Measure
Unit of measure: Job
1.1.2.3 Payment Item
0003 INTERLOCK CONTROL SYSTEM REPLACEMENT
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
SECTION 01 22 00.00 08 Page 2
1.2.1 Digital Progress Images
1.2.1.1 Payment
Payment shall constitute full compensation for all costs in connection with completing this item of work as specified in Section 01 32 33 DIGITAL
PROGRESS IMAGES.
1.2.1.2 Measurement
Measurement shall be based on monthly sets of progress photographs that are approved and accepted by the Contracting Officer.
1.2.1.3 Unit of Measure
Unit of measure: Sets.
1.2.1.4 Payment Items
0002 DIGITAL PROGRESS IMAGES
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 calendar days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. The cost of any element in the cost breakdown should be less than $25,000 for progress tracking. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
-- End of Section --