Revised_Technical_Specification _Division_01 _Section_01_22_00.00_10 _Measurement_and_Payment.pdf

PDF 26 KB Posted

Attached to
Repair Bulkhead Hoist at Tygart Dam
Solicitation number
W911WN-16-B-8009
Issued by

About this file

Revised Technical Specification Division 01 Section 01 22 00.00 10 Measurement and Payment

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bulkhead Hoist Repairs

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.1.1 Reimbursement For Actual Performance And Payment Bond Premiums

1.1.2 Mobilization And Demobilization

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.1.2.3 Payment Items

1.1.3 Demolition of Existing Conductor Rail System

1.1.3.1 Payment

1.1.3.2 Unit of Measure

1.1.3.3 Payment Item

1.1.4 Furnish and Install New Conductor Rail System

1.1.4.1 Payment

1.1.4.2 Unit of Measure

1.1.4.3 Payment Item

1.1.5 Furnish and Install New Bulkhead Hoist Beam

1.1.5.1 Payment

1.1.5.2 Unit of Measure

1.1.5.3 Payment Item

1.1.6 New Removable Roof Canopy for Bulkhead Hoist

1.1.6.1 Payment

1.1.6.2 Unit of Measure

1.1.6.3 Payment Items

1.1.7 Relocate Bulkhead Hoist

1.1.7.1 Payment

1.1.7.2 Unit of Measure

1.1.7.3 Payment Items

1.1.8 Replace Hoist Cable on Existing Bulkhead Hoist

1.1.8.1 Payment

1.1.8.2 Unit of Measure

1.1.8.3 Payment Items

1.1.9 Repair of Concrete Corbel

1.1.9.1 Payment

1.1.9.2 Unit of Measure

1.1.9.3 Payment Items

1.1.10 Modifications at Bulkhead Storage Platform

1.1.10.1 Payment

1.1.10.2 Unit of Measure

1.1.10.3 Payment Item

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 Digital Progress Images

1.2.1.1 Payment

1.2.1.2 Measurement

1.2.1.3 Unit of Measure

1.2.1.4 Payment Items

1.2.2 Repaint Anchorages

1.2.2.1 Payment

SECTION 01 22 00.00 10 Page 1 Certified Final Tech. Spec.- RTA W911WN-16-B-8009 Amend 0001

1.2.2.2 Measurement

1.2.2.3 Unit of Measure

1.2.2.4 Payment Items

1.2.3 Repair Of Existing Paint Coating

1.2.3.1 Payment

1.2.3.2 Measurement

1.2.3.3 Unit of Measure

1.2.3.4 Payment Items

1.2.4 Rehabilitation of Bulkheads

1.2.4.1 Payment

1.2.4.2 Measurement

1.2.4.3 Unit of Measure

1.2.4.4 Payment Items

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 22 00.00 10 Page 2

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Reimbursement For Actual Performance And Payment Bond Premiums

Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00800 SPECIAL CONTRACT REQUIREMENTS, clause

PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.

0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS

1.1.2 Mobilization And Demobilization

1.1.2.1 Payment

Payment for mobilization and demobilization will be made in accordance with Section 00800 SPECIAL CONTRACT REQUIREMENTS, DFARS 252.236-7004

PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.

1.1.2.2 Unit of Measure

Unit of measure: Job

1.1.2.3 Payment Items

0002 MOBILIZATION AND DEMOBILIZATION

1.1.3 Demolition of Existing Conductor Rail System

1.1.3.1 Payment

Payment for this item shall constitute full compensation for removal and disposal of the existing conductor rail system as shown on the drawings and as specified in Section 41 22 23.19 BULKHEAD HOIST CONDUCTOR RAIL SYSTEM. The Contractor shall reflect the salvage value of copper materials in this contract line item.

1.1.3.2 Unit of Measure

Unit of measure: Job

SECTION 01 22 00.00 10 Page 3

1.1.3.3 Payment Item

0004 DEMOLITION OF EXISTING CONDUCTOR RAIL SYSTEM

1.1.4 Furnish and Install New Conductor Rail System

1.1.4.1 Payment

Payment for this item shall constitute full compensation for furnishing, installing, and testing the new conductor rail system and collector system and associated electrical work as shown on the drawings and as specified in Section 41 22 23.19 BULKHEAD HOIST CONDUCTOR RAIL SYSTEM. This item shall also include payment for furnishing, maintaining, and removing the temporary power supply for the bulkhead hoist.

1.1.4.2 Unit of Measure

Unit of measure: Job

1.1.4.3 Payment Item

0005 FURNISH AND INSTALL NEW BULKHEAD HOIST CONDUCTOR RAIL SYSTEM AND

ASSOCIATED ELECTRICAL WORK

1.1.5 Furnish and Install New Bulkhead Hoist Beam

1.1.5.1 Payment

Payment for this item shall constitute full compensation for furnishing and installing the new section of bulkhead hoist beam as shown on the drawings and as specified.

1.1.5.2 Unit of Measure

Unit of measure: Job

1.1.5.3 Payment Item

0006 FURNISH AND INSTALL NEW BULKHEAD HOIST BEAM

1.1.6 New Removable Roof Canopy for Bulkhead Hoist

1.1.6.1 Payment

Payment shall constitute full compensation for all labor, equipment, material and supply costs to construct the new removable roof canopy at the upper bulkhead hoist storage location on the Service Bridge as shown on the drawings and as specified.

1.1.6.2 Unit of Measure

Unit of measure: Job

1.1.6.3 Payment Items

0007 NEW REMOVABLE ROOF CANOPY, BULKHEAD HOIST

1.1.7 Relocate Bulkhead Hoist

SECTION 01 22 00.00 10 Page 4

1.1.7.1 Payment

Payment shall constitute full compensation for all labor, equipment, material and supply costs to remove the existing bulkhead hoist from the storage location, deliver and install the new Government-furnished bulkhead hoist at the lower storage position, and install the existing bulkhead hoist at the upper storage location as specified.

1.1.7.2 Unit of Measure

Unit of measure: Job

1.1.7.3 Payment Items

0008 RELOCATE BULKHEAD HOIST

1.1.8 Replace Hoist Cable on Existing Bulkhead Hoist

1.1.8.1 Payment

Payment shall constitute full compensation for all labor, equipment, material and supply costs to remove the existing hoist cable from the existing bulkhead hoist and furnish and install new hoist cable as specified.

1.1.8.2 Unit of Measure

Unit of measure: Job

1.1.8.3 Payment Items

0009 REPLACE HOIST CABLE ON BULKHEAD HOIST

1.1.9 Repair of Concrete Corbel

1.1.9.1 Payment

Payment for repair of the existing concrete corbel will be made at the contract Job price. These payments shall constitute full compensation for performing the work and shall include the cost of all labor, equipment and tools, materials and supplies required to remove existing concrete and complete the mortar and concrete work under this contract. No measurement and payment will be made for polymer-modified mortar or concrete, as such, which is placed in structures for which payment is made as a Job.

1.1.9.2 Unit of Measure

Unit of measure: Job

1.1.9.3 Payment Items

0017 REPAIR OF CONCRETE CORBEL

1.1.10 Modifications at Bulkhead Storage Platform

1.1.10.1 Payment

Payment for this item shall constitute full compensation for furnishing

SECTION 01 22 00.00 10 Page 5 and installing the new movable handrails and pipe guards at the bulkhead storage platform as shown on the drawings and as specified.

1.1.10.2 Unit of Measure

Unit of measure: Job

1.1.10.3 Payment Item

0018 MODIFICATIONS AT BULKHEAD STORAGE PLATFORM

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in the PRICE SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.2.1 Digital Progress Images

1.2.1.1 Payment

Payment shall constitute full compensation for all costs in connection with completing this item of work as specified in Section 01 32 33 DIGITAL

PROGRESS IMAGES.

1.2.1.2 Measurement

Measurement shall be based on monthly sets of progress photographs that are approved and accepted by the Contracting Officer.

1.2.1.3 Unit of Measure

Unit of measure: Sets

1.2.1.4 Payment Items

0002 DIGITAL PROGRESS IMAGES

1.2.2 Repaint Anchorages

1.2.2.1 Payment

Payment for cleaning anchorages on the bulkhead hoist, storage platform, and bulkhead guides will be made at the respective contract unit prices per each. These payments shall constitute full compensation for performing the work and shall include the cost of all labor, equipment and tools, materials and supplies required for surface preparation, removal and disposal of debris, and painting the area(s) as approved by the Contracting Officer. Each anchorage shall consist of the anchor bolts and adjacent plate surfaces.

For the bulkhead guides, there are 230 anchorages with 4 bolts and 240 anchorages with 2 bolts. For the bulkhead storage platform below EL 1118, there are anchorages with 4 bolts and 8 anchorages with 2 bolts. The bulkhead hoist supports anchorages have 2, 4 or 6 bolts.

SECTION 01 22 00.00 10 Page 6

1.2.2.2 Measurement

Measurement of repainting anchorages will be made on the number of anchorages which are cleaned and repainted, as approved by the Contracting Officer.

1.2.2.3 Unit of Measure

Unit of measure: each

1.2.2.4 Payment Items

0010 CLEAN AND PAINT ANCHOR BOLTS AND PLATES ON EXISTING BULKHEAD

GUIDE ASSEMBLIES

0012 CLEAN AND PAINT ANCHORAGES OF BULKHEAD STORAGE PLATFORM AT AND

BELOW EL 1118

0013AA CLEAN AND PAINT ANCHORAGES OF BULKHEAD HOIST WALL SUPPORTS

ABOVE EL 1118, FIRST 100 EACH

0013AB CLEAN AND PAINT ANCHORAGES OF BULKHEAD HOIST WALL SUPPORTS

ABOVE EL 1118, ALL OVER 100 EACH

1.2.3 Repair Of Existing Paint Coating

1.2.3.1 Payment

Payment for repair of existing paint coating on the bulkhead hoist system will be made at the respective contract unit prices per square foot.

These payments shall constitute full compensation for performing the work and shall include the cost of all labor, equipment and tools, materials and supplies required for surface preparation, removal and disposal of debris, and painting the area(s) as approved by the Contracting Officer.

1.2.3.2 Measurement

Measurement of repair of coating on bulkhead hoist system structure and bulkhead guide structure will be made on the basis of the actual area of existing coating repaired, as approved by the Contracting Officer. For measurement purposes, the minimum repair area will be considered to be 1 square foot.

1.2.3.3 Unit of Measure

Unit of measure: square feet.

1.2.3.4 Payment Items

0011 CLEAN AND PAINT BOTTOM FLANGE OF EXISTING BULKHEAD MONORAIL BEAM

0014AA TOUCHUP CLEAN AND PAINT SURFACE OF BULKHEAD HOIST BRACKET

MEMBERS, FIRST 550 SF

0014AB TOUCHUP CLEAN AND PAINT SURFACE OF BULKHEAD HOIST BRACKET

MEMBERS, ALL OVER 550 SF

0015AA TOUCHUP CLEAN AND PAINT SURFACE OF BULKHEAD GUIDES, FIRST 300

SF

0015AB TOUCHUP CLEAN AND PAINT SURFACE OF BULKHEAD GUIDES, ALL OVER

300 SF

1.2.4 Rehabilitation of Bulkheads

1.2.4.1 Payment

SECTION 01 22 00.00 10 Page 7

Payment for rehabilitation of existing bulkheads will be made at the respective contract unit prices per each. These payments shall constitute full compensation for performing the work as specified, and shall include the cost of all labor, equipment and tools, materials and supplies required to for installing weepholes, replacing timber seals, installing new steel chairs, and cleaning and painting the bulkheads.

1.2.4.2 Measurement

Measurement will be made on the basis of the number of bulkheads repaired as specified and as shown on the drawings.

1.2.4.3 Unit of Measure

Unit of measure: each.

1.2.4.4 Payment Items

0016 HABILITATION OF BULKHEADS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 22 00.00 10 Page 8

01 22 00.00 10 - MEASUREMENT AND PAYMENT
01 22 00.00 10 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 Reimbursement For Actual Performance And Payment Bond Premiums
1.1.2 Mobilization And Demobilization
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.2.3 Payment Items
1.1.3 Demolition of Existing Conductor Rail System
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.3.3 Payment Item
1.1.4 Furnish and Install New Conductor Rail System
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.4.3 Payment Item
1.1.5 Furnish and Install New Bulkhead Hoist Beam
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.5.3 Payment Item
1.1.6 New Removable Roof Canopy for Bulkhead Hoist
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.6.3 Payment Items
1.1.7 Relocate Bulkhead Hoist
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.7.3 Payment Items
1.1.8 Replace Hoist Cable on Existing Bulkhead Hoist
1.1.8.1 Payment
1.1.8.2 Unit of Measure
1.1.8.3 Payment Items
1.1.9 Repair of Concrete Corbel
1.1.9.1 Payment
1.1.9.2 Unit of Measure
1.1.9.3 Payment Items
1.1.10 Modifications at Bulkhead Storage Platform
1.1.10.1 Payment
1.1.10.2 Unit of Measure
1.1.10.3 Payment Item
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Digital Progress Images
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.1.4 Payment Items
1.2.2 Repaint Anchorages
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.2.4 Payment Items
1.2.3 Repair Of Existing Paint Coating
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.3.4 Payment Items
1.2.4 Rehabilitation of Bulkheads
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.4.4 Payment Items
PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION Not Applicable

File details come from the government source that posted it. Updated .