W911WN-10-B-0004-0001.doc.pdf
PDF 32 KB Posted
- Solicitation number
- W911WN10B0004
About this file
Amendment 0001 - Changes made to the specifications and the performance period base on question received at the pre-bid meeting as noted on page two of the amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract 10-B-0004 Tionesta Tower.xlsm | XLSM spreadsheet | |
| BidResults for 10B0004.doc | DOC document | |
| 02 42 00.pdf | ||
| 07 24 00.pdf | ||
| 01 57 20.00 10.pdf | ||
| Reference Drawings.pdf | ||
| W911WN-10-B-0004.pdf | ||
| Technical Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81ET492812587
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
RE: TIONESTA LAKE CONTROL TOWER - INSPECTING, CLEANING, REPAIRING AND RECOATING EXTERIOR INSULATION:
Changes made to the specifications and the performance period base on question received at the pre-bid meeting as noted on page tw o of this amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Dec-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911WN-10-B-0004
X 9B. DATED (SEE ITEM 11)
18-Nov-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Dec-2009
CODE
U.S. ARMY ENGINEER DISTRICT, PITTSBURGH
ATTN CECT-LRP
W S MOORHEAD FEDERAL BUILDING
1000 LIBERTY AVENUE ROOM 2116
PITTSBURGH PA 15222-4186
W911WN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911WN-10-B-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 21-Dec-2009 11:00 AM to 22-Dec-2009 11:00 AM.
The contractor period of performance end date has increased by 60 days from 120 days to 180 days.
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ( 10 ) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than (180) calendar days after the date of the notice to Proceed. * The time stated for completion shall include final cleanup of the premises.
(End of clause)
PROJECT SPECIFICATIONS:
Specification sections 01 57 20.00 10, 02 42 00, 07 24 00 are replaced in there entirety with the revised sections included with this amendment. The specific changes are made to the specifications for Control Tower Exterior Insulation and Finish System Repair, Tionesta Lake, Tionesta River, Pennsylvania
� Section 01 57 20.00 10, paragraph 3.1: The paragraph concerning Pennsylvania Department of Environmental Protection General Permit BWM-GP-11 has been deleted.
� Section 01 57 20.00 10, paragraph 3.3.1: The paragraph concerning Cofferdams, Diversions, and
Dewatering Operations has been deleted.
� Section 01 57 20.00 10, paragraph 3.4.5: The requirement to dispose of waste water offsite has been relaxed for cleaning with environmental-friendly products.
� Section 02 42 00, paragraph 3.1.4: The requirement to dispose of waste water offsite has been relaxed for cleaning with environmental-friendly products.
� Section 02 42 00, paragraph 3.5: Text referring to Task Order has been deleted or revised.
� Section 07 24 00, paragraph 1.2 b: The requirement to remove existing sealant and reseal at doors, windows, and similar penetrations has been clarified.
� Section 07 24 00, paragraph 3.1: The time for completion of the inspection report has been changed to 90 calendar days.
� Section 07 24 00, paragraph 3.6: The requirements for cleaning existing EIFS surfaces have been revised to follow coating manufacturer’s recommendations and to add requirement for cleaning products to be environmentally-friendly or non-polluting.
(End of Summary of Changes)