23-R-0004 MSFTB AMD 2.pdf

PDF 139 KB Posted

Attached to
Mission Systems Flying Test Bed Federal contract opportunity
Solicitation number
W911w623R0004
Issued by
Department of the Army Materiel Command Contracting Command Redstone Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to Mission Systems Flying Test Bed, newest first.
File Type Posted
Q_A Matrix AMD 2_ltrhead_final.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A006) System Integration Guide.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A002) Technical Status Report.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A009) Final Report.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A010) Briefing Materials.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A008) MSUT Integration Model.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A007) GFI Utilization Report.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A005) Test Report.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A002) Technical Status Report.pdf PDF
Q_A Matrix AMD 1_ltrhead_final.pdf PDF
23-R-0004 MSFTB AMD 1.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A001) Work Plan.pdf PDF
CALL MSFTB__AMD 1 27 Apr 2023.docx DOCX document
Contract Data Requirements List (CDRL DD Form 1423) - (A006) System Integration Guide.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A004) Test Plan.pdf PDF
Contract Data Requirements List (CDRL DD Form 1423) - (A003) Cost Status Report.pdf PDF
EXH F (CDRL DD Form 1423) - (A006) System Integration Guide.pdf PDF
EXH A (CDRL DD Form 1423) - (A001) Work Plan.pdf PDF
EXH K (CDRL DD Form 1423) - (A010) Briefing Materials.pdf PDF
EXH H (CDRL DD Form 1423) - (A008) MSUT Integration Model.pdf PDF
EXH D (CDRL DD Form 1423) - (A004) Test Plan.pdf PDF
EXH C (CDRL DD Form 1423) - (A003) Cost Status Report.pdf PDF
EXH G (CDRL DD Form 1423) - (A007) GFI Utilization Report.pdf PDF
EXH B (CDRL DD Form 1423) - (A002) Technical Status Report.pdf PDF
EXH L (CDRL DD Form 1423) - (A011) Small Business Utilization Report.pdf PDF
EXH J (CDRL DD Form 1423) - (A009) Final Report.pdf PDF
EXH E (CDRL DD Form 1423) - (A005) Test Report.pdf PDF
MSFTB TO 1 24 Mar 2023.pdf PDF
W911W6-23-R-0004 Posted 24Mar23.pdf PDF
CALL MSFTB 24 Mar 2023 final.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

SEE PG.2

1. CONTRACT ID CODE PAGE OF PAGES

U 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-May-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911W623R0004

X 9B. DATED (SEE ITEM 11)

24-Mar-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-May-2023

CODE

ARMY CONTRACTING COMMAND (ACC)

REDSTONE/CCAM-MZD-B

BLDG 401 LEE BLVD

FORT EUSTIS VA 23604-5577

W911W6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W911W623R0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

BLOCK 14 CONT.

1. The above numbered solicitation is hereby amended to make required changes. Those changes which are not readily apparent on subsequent pages of this amendment are described below:

a. Questions and Answers dated May 4, 2023 are hereby incorporated by reference.

b. Section H, Special Contract Requirements clause H-4, Organizational Conflicts of Interest is modified.

c. Section I, clauses which are inapplicable to this requirement have been removed and required clause has been added.

d. Section J, Exhibits/Attachments has been revised to replace Contract Data Requirements List (CDRLs)

A002 and A006 which have been revised to include the following changes. This also corrects Amendment

0001 which inadvertently changed the CDRLs to a 2023 date.

A002 – Technical Status Report

Block 9 changed to Distribution Statement C

Note added to not include any cost data

A006 – System Integration Guide

Block 12 and 13 have been revised to align with the Statement of Work with first submission due 120 days after contract award and subsequent submission due 180 days after contract award.

2. This amendment consists of the following documents: Amendment 0002; Questions and Answers; and revised

CDRLs.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

The following have been modified:

H-4 ORG CONFLICT OF INTEREST

H-4 ORGANIZATIONAL CONFLICTS OF INTEREST (OCI)

(a) Definition. Organizational conflicts of interest (OCI), as used in this special contract requirement, is defined in

Title 48 of the Code of Federal Regulations (CFR) (Federal Acquisition Regulation) 2.101, Definitions, and

“…means that because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the Government, or the person's objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage.”

(b) Notice:

(1) At time of award of this Contract, the Government does not anticipate the work to be performed in the task orders issued pursuant to this Contract will give rise to an OCI as described in FAR Subpart

9.5, Organizational and Consultant Conflicts of Interest.

(2) This Contract procures Advanced Technology Development (ATD) as defined in the Department of Defense

Financial Management Regulation (DoD FMR), Volume 2B, Chapter 5, paragraph 1.5.3. ATD includes development of subsystems and components and efforts to integrate subsystems and components into system prototypes for field experiments and/or tests in a simulated environment. The contracted development does not lead to subsequent development or procurement phases but has the goal of moving out of Science and Technology (S&T) industrial base technologies and into the acquisition process within the Future Years Defense Program (FYDP).

(3) The objective of the Mission System Flying Test Bed (MSFTB) is to provide an architecture verification environment (AVE) for maturing, implementing, and verifying Model Based Engineering (MBSE) methods and

Modular Open Systems Architecture (MOSA) principles to demonstrate incremental airworthiness and cyber security qualification for infrastructure capabilities enabling affordability and faster to field for innovative integration. The work will include demonstration of integration of third party mission system components in the

MSFTB. Any third party applications, if developed using MBSE methods and in accordance with MOSA principles, should support MSFTB Integrator integration and demonstration in the MSFTB without generating OCIs.

(4) In light of the scope of development, the planned project activities will not likely generate OCIs. There is a potential that work at later stages may begin work to transition from the S&T industrial base and into an acquisition phase.

(c) If the Contractor as the development progresses identifies a potential conflict, the Contractor will submit to the

Contracting Officer the following:

(1) Assessment. Applying the principles of FAR Subpart 9.5, the Contractor assessment of the potential OCI associated with the development;

(2) Information. The relevant information regarding any OCIs, including information about current potential subcontracts; and

(3) Proposed Plan. The Contractor proposed draft mitigation plan.

SECTION I - CONTRACT CLAUSES

The following have been added by reference:

252.245-7004 Reporting, Reutilization, and Disposal DEC 2017

The following have been deleted:

52.203-17 Contractor Employee Whistleblower Rights and Requirement

To Inform Employees of Whistleblower Rights

JUN 2020

252.211-7008 Use of Government-Assigned Serial Numbers SEP 2010

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A A001- WORK PLAN

UPDATE

20-APR-2023

Exhibit B A002- TECHNICAL

STATUS REPORT

UPDATE

20-APR-2023

Exhibit C A003-COST STATUS

REPORT UPDATE

20-APR-2023

Exhibit D A004- TEST PLAN

UPDATE

20-APR-2023

Exhibit E A005- TEST REPORT

UPDATE

20-APR-2023

Exhibit F A006- SYSTEM

INTEGRATION GUIDE

20-APR-2023

Exhibit G A007- GFI

UTILIZATION REPORT

20-APR-2023

Exhibit H A008-MSUT

INTEGRATION MODEL

UPDATE

20-APR-2020

Exhibit J A009- FINAL REPORT

UPDATE

20-APR-2023

Exhibit K A010- BRIEFING

MATERIALS UPDATE

20-APR-2023

Exhibit L CDRL-SMALL

BUSINESS

UTILIZATION REPORT

19-JAN-2023

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A A001- WORK PLAN 16-NOV-2021

Exhibit B A002- TECHNICAL

STATUS PLAN

16-NOV-2021

Exhibit C A003- COST STATUS

REPORT

29-NOV-2021

Exhibit D A004- TEST PLAN 29-NOV-2021

Exhibit E A005- SYSTEM

INTEGRATION TEST

REPORT

29-NOV-2021

Exhibit F A006- SYSTEM

INTEGRATION GUIDE

29-NOV-2021

Exhibit G A007- GFI

UTILIZATION REPORT

29-NOV-2021

Exhibit H A008- MSUT

INTEGRATION MODEL

29-NOV-2021

Exhibit J A009- FINAL REPORT 29-NOV-2021

Exhibit K A0010- BRIEFING

MATERIALS

29-NOV-2021

Exhibit L CDRL-SMALL

BUSINESS

UTILIZATION REPORT

19-JAN-2023

(End of Summary of Changes)