DIRECTORATE OF PUBLIC WORKS

ENGINEERING DIVISION

FORT BENNING, GEORGIA Project #: 44042

General Requirements – AR OSUT #4 25 April 2019

Armor OSUT: Oscar 13, 10, 8, 4, 1 Fort Benning, Georgia

PROJECT INCLUDES:

1. Construct Firing Point ½ CTA (260FT) / per range

2. Install Hydro-seed, Dirt, Concrete Block, Target Brackets & Timbers / per range

SCHEDULE:

The Contractor will only be allowed to work on three of the following Ranges at a time. This includes OSCARs 13, 10, 8, 4, and 1. As the Contractor completes one there will be a ten day transition period that the Contractor will have to include in their schedule before receiving control of the next Range.

The total contract time for completing all work on the above Ranges shall not exceed 365 days.

1. REQUIRED BID DOCUMENTS

a. Proposed Schedule

b. Cost Proposal

LIQUIDATED DAMAGES:

In the event the contractor exceeds the completion date established per the Request for Task Order Proposal (RTOP), liquidated damages will be imposed on the contractor. The amount to be paid daily, will be $1,495.68 per day.