DIRECTORATE OF PUBLIC WORKS
ENGINEERING DIVISION
FORT BENNING, GEORGIA Project #: 44042
General Requirements – AR OSUT #4 25 April 2019
Armor OSUT: Oscar 13, 10, 8, 4, 1 Fort Benning, Georgia
PROJECT INCLUDES:
1. Construct Firing Point ½ CTA (260FT) / per range
2. Install Hydro-seed, Dirt, Concrete Block, Target Brackets & Timbers / per range
SCHEDULE:
The Contractor will only be allowed to work on three of the following Ranges at a time. This includes OSCARs 13, 10, 8, 4, and 1. As the Contractor completes one there will be a ten day transition period that the Contractor will have to include in their schedule before receiving control of the next Range.
The total contract time for completing all work on the above Ranges shall not exceed 365 days.
1. REQUIRED BID DOCUMENTS
a. Proposed Schedule
b. Cost Proposal
LIQUIDATED DAMAGES:
In the event the contractor exceeds the completion date established per the Request for Task Order Proposal (RTOP), liquidated damages will be imposed on the contractor. The amount to be paid daily, will be $1,495.68 per day.