W911SD24R0042 Question and Answers.pdf

PDF 614 KB Posted

Attached to
Inspec Triple Chair Lift & Rope Tow at West Point
Solicitation number
W911SD24R0042
Issued by

About this file

This document is an amendment to a solicitation for a service contract to provide annual inspections of the Borvig Triple Chair Lift and Multi-Star Handle Tow at the Victor Constant Ski Slope at the United States Military Academy in West Point, NY. The purpose of the amendment is to add questions and answers from a site visit and email RFI request.

The key details include:

  • The contract is a base plus four option year service contract to perform annual inspections in December each year to certify the safety of the lift and tow in accordance with ANSI B77.1 standards.
  • A site visit was held on April 11, 2024 to address questions about the number of towers, inspection requirements, and timing.
  • An RFI was received on April 11, 2024 regarding accessing inspection reports, which the government stated they could not provide without approval.
  • The solicitation number is W911SD24R0042 and the set-aside is unrestricted.
  • Quotes must be submitted by the date and time stated in the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911SD24R0042

0012059727

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The pupoos of the Amendment is to add questions and answ er from site visit.and email RFI request on 4/11/24.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Apr-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911SD24R0042

X 9B. DATED (SEE ITEM 11)

08-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Apr-2024

CODE

MICC - WEST POINT

681 ROGERS PLACE

WEST POINT NY 10996-1514

W911SD 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Queations form Site visit on 4/11/24 at Victor Constant Ski Slope at West Point Military Academy

Q: How Many Towers?

A:There are 9 towers.

Q: Are you testing cable system, breaks and emergency safety ski lift equipment or is that part of the maintenance contract?

A: Maintenance contractor does test cable system, breaks and emergency safety ski lift equipment. I would say the inspection contractor would have to do whatever is necessary to complete an inspection and certify that its safe for operation per ANSI B77.1-2022, NYS and OSHA.

The inspection contractor is responsible to make sure the ski slope and all components are safe for the public per ANSI B77.1-2022, NYS and OSHA. Whatever they need to do to ensure the safety of employee and patrons.

The inspection contractors need to follow ANSI B77.1-2022, NYS and OSHA. They need to follow all applicable industry rules, regulations and standards.

Q: Is the mechanical equipment sheds housing the lifts and rope tow included in the inspection?

A: Everything with the ski slope is part of the inspection.

Q: Could the inspection take place earlier than the month of December?

A: The inspection could be done second half of November and the latest is December 15 th.

EMAIL REFI received 4/11/24 Q: Would it be possible to receive copy of submitted reports?

A: Requiring Activity did not provided approval to post report.

Report 1 Cover Letter dated 1/11/23 Construction Control Representative/COR Construction Contracts Service Branch Engineering Division DPW, Bldg.

667 USAG West Point, NY

Greetings!

January 11, 2023 Subject: West Point

Ski Lift Inspections Attached please find a final copy of the Lift Inspection Report for the chairlift and wire rope tow at the Victor Constant Ski Slope at West Point.

It is important to note that Item #2 must be addressed and repaired prior to operation.

Regarding item #1 pertaining to torque-testing of the brakes I would like to emphasize that it is an ANSI requirement that the holding power of brakes must be tested periodically throughout the operating season, monthly at a minimum. Your ski area personnel must be trained to perform the required brake testing and test the service brake and emergency brake on a regular basis. Bi- Weekly brake testing seems to be the norm throughout the ski industry. Perhaps and can assist area personnel with the training for this task.

Additionally, the brakes should be carefully inspected and operated before public operation of the lift each day.

Similarly, there are many other features of the lift that require a daily inspection to ensure their proper function.

This daily pre-operational inspection must be done by trained personnel and a daily pre-operational inspection log must be completed and signed and filed with the ski area manager’s permanent records.

With regard to report item #10 it should be noted that the placement of fencing around the top and bottom terminals of the tow is not subjective, meaning that it is not up to your ski area personnel to decide if the fencing (or possibly other equipment) should be installed. It is a requirement. The daily pre-operational inspection of the chairlift and tow at the Victor Constant Ski Slope will help to ensure that these lifts are regularly maintained in conformance with the ANSI Standard and ready for public operation.

Thank you for your continued interest in and attention to these matters.

Report2:

ENGINEERING REPORT

SKI AREA: Victor Constant Ski Slope DATE OF SURVEY:

January 10, 2023

ENGINEER: ACCOMPANIED BY:

A visual survey of ropeways at this location revealed the following items of nonconformance with the American National Standard for Passenger Tramways - Aerial Tramways, Aerial Lifts, Surface Lifts, and Tows - Safety Requirements, B77.1 – 2017. For referral, each numbered item in this report contains a reference number to a specific section of the ANSI Standard.

The survey is limited to a general review and by the operating condition of the ropeways.

The results of this survey are limited to the items listed in this report. The items listed in this report should be corrected as soon as practical but within 30 davs. Critical items should be corrected prior to any public operation of the ropeway. Please send a written statement of the compliance status of each of the items noted in this report to Stevens Engineering.

LIST OF ROPEWAYS OPERATED FOR REMARKS

THIS SURVEY?

Lift #1 – Borvig Chairlift Yes

Lift #2 – Multi Lift Yes

Victor Constant Ski Slope January 10, 2022

Lift #1, Borvig Triple

1. 4.3.3 – REPEAT ITEM - It is necessary that periodic brake tests are conducted to verify the adequacy of the brake holding power. Bi-weekly testing is highly recommended.

2. 4.3.3 – Align Tower 6 and Tower 9 on the upgoing side prior to operation. Check for any worn parts that would cause the misalignment.

3. ANNEX E – The top inside normal stop plastic button is broken. Please replace the button.

4. 4.3.1.1 - Post all required signs.

5. ANNEX F - Fire extinguishers shall be inspected and tagged annually. Fire extinguisher in the motor room and top station requires inspection.

6. ANNEX E – All emergency stop buttons at the top and bottom station shall have a guard installed per ANSI B77.1-2017 Standard during the summer maintenance in 2023.

7. 4.1.4.5.5 – Per the ANSI B77.1 Standard the work carrier shall be load rated with posted placard, have posted operating instructions, and have provisions for fall protection installed. Please complete this work in the summer of 2023. If more information is needed, please contact us at Stevens Engineering.

8. 4.3.4.4 - Dynamic testing shall be performed at intervals not exceeding seven (7) years. The last dynamic test is unknown. Please locate records of the last dynamic test to determine if a load test is necessary. If more information is needed please contact us at

Lift #2, Multi Lift Tow

9. 6.3.2.1 – Post all operating and emergency procedures in the bottom attendant building.

10. 6.3.3 – Fencing shall be placed around top and bottom terminals prior to operation.

11. 6.3.1.2 - Post all required signs.

Victor Constant Ski Slope January 10, 2023

This is a periodic survey of the passenger ropeways listed in the report and is performed according to the provisions for general inspection as interpreted by the ANSI B77 Standards Committee. This field survey consists of a visual and audible review and is limited in scope to a sampling of the safety requirements pertaining to the equipment appearance, function, operation, maintenance, record keeping and conformity with other specifically required nondestructive inspection and testing procedures. Because of the limited nature of this survey, neither the Inspector nor Contractor can guarantee that additional items of nonconformance do not exist. No examination was made of detailed components or equipment that requires disassembly to view as it is the responsibility of the owner to periodically examine and service the equipment through his established maintenance and operations program. Additionally, it is not within the scope of this general survey to evaluate the physical design requirementsof passenger ropeway components or systems.

This survey report is based upon a spot check of conditions and practices evaluated and of the records, information, and statements your personnel provided at the time of the survey. While this report was made to provide you with current information relating to your passenger ropeways, you may find it appropriate to provide copies to other organizations or agencies with which you are involved. If so provided, we would suggest you provide such entities with copies of your responses to any items of nonconformance.

This report has been discussed with and received by:

Signature Title Signature of Inspector

(End of Summary of Changes)