0011912707
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to update the Attachment 2_TE-2 FHL JOC Coefficient Spreadsheet. This amendment w ill extend the bid due date from MAY 1, 2023 @ 11:00AM CDT to MAY 3, 2023 @ 11:00AM CDT. The public bid opening w ill now be on MAY 3, 2023 @
2:00PM CDT.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Apr-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911SA23B2011
X 9B. DATED (SEE ITEM 11)
29-Mar-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Apr-2023
CODE
MICC - FT MCCOY
BLDG 1108 SOUTH R ST
FORT MCCOY WI 54656-5153
W911SA 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911SA23B2011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 01-May-2023 11:00 AM to 03-May-2023 11:00 AM.
The following have been modified:
SUPPLEMENTAL INFORMATION
1) GOVERNMENT POC INFORMATION
Contract Specialist: MAJ Francisco J. Arocho Phone: 608-388-1251 Email: francisco.j.arocho.mil@army.mil
Contracting Officer: Steven Bailey Email: steven.m.bailey2.civ@army.mil Phone: 608-388-4525
2) BID SUBMISSION
Please note: The time the Bid is due is different from the time of the Public Bid Opening. This will allow time for bids to be downloaded from the solicitation module of PIEE to be read aloud during the Public Bid Opening teleconference. Late Bids received after the Bid Due date/ time will not be considered for award, even if they are received before the Public Bid Opening. Screenshots of the submission will be taken to confirm each Contractor bid was received by the bid due date/time.
Refer to the Instructions to Bidders Section for further instruction.
Bid Due Date: 03 May 2023 Bid Due Time: 11:00 AM CDT Bid Opening Time: 2:00 PM CDT
3) CONTRACTOR POC INFORMATION
Name: _________________________________________________
E-mail: _______________________________________________
Unique Entity ID: _______________________________________________
TAXPAYER ID #: ______________________________________
4) CONTRACT INFORMATION
a. JOC MAXIMUM: The maximum value for this contract is $10 Million.
b. GUARANTEED MINIMUM: The guaranteed minimum for the life of this contract will be $250,000.
c. SUBMISSION DEADLINE FOR QUESTIONS
Any questions, concerns, verification, or clarification of information on the documents included in the solicitation package shall be submitted in writing to the Government POC’s identified herein NLT 12 April 2023, 10:00 AM CDT. Include in the subject line of the email the Government’s solicitation number; failure to do so will lessen the Government’s ability to ensure all questions are considered during the bidding process. Provide your company name, POC and contact information in the body of the email.
This deadline is created to ensure the Contracting Officer and Requiring Activity have sufficient time to respond to the questions. Questions will be consolidated from all contractors and responses to all questions will be posted as a separate attachment to the solicitation. NOTE: Contractors are highly encouraged to read the entire solicitation in full.
5) JOINT SCOPING
As needs arise for performance under the terms of this contract, the Government will notify the Contractor, verbally and/or in writing, of the requirement and establish a time for a joint site visit. At a time agreed upon, the Contractor and the designated Government representative shall visit the proposed work site to further define the scope of the requirement. The Contractor and the Government will jointly define the work area and major work items to accomplish the required scope of work: measurements shall be taken, rough sketches made, facility access taken into consideration, estimates made of the performance period, and other special conditions shall be discussed. These scoping details shall be refined and agreed to prior to the issuance of any task order.
The Contractor shall then prepare a cost proposal for accomplishment of the work which shall consist of an itemized listing of all proposed work elements, items of equipment to be installed, quantities of expendable items, prices, total proposed cost, and all supporting documentation (catalog cuts, supplier quotes, price lists, etc.) as outlined in the Scope of Work. The approved UPB cost data and associated software shall be utilized to produce the cost proposal.
The cost proposal should be presented on the Contractor’s letterhead or proprietary format with signature blocks for review by the Government’s representative and Contracting Officer. All pricing documents submitted must contain the marking “CUI” for Controlled Unclassified Information. Upon the Government’s request, the Contractor must be prepared to provide a detailed breakdown of its proposal to include all pricing documentation to demonstrate that it is fair and reasonable.
6) ORDERING OFFICIAL/ OFFICER
a. There will be a designated Ordering Official under this contract, authorized to make purchases up to their designated authority of $25,000.00, per single known requirement, against this JOC contract, as along as Non-Pre- Priced work does not exceed 10% of the pre-Priced work, and no more than $2,500.00 total. Projects under this threshold will not be issued on an individual task order FORM 1155, however, all requirements of the contract award, and all policies and procedures will be applicable to projects ordered by the designated official.
Contractor will still be required to fulfill a joint scoping with the Government, and prices/ specification for the project will still require negotiation and agreement/ approval by the ordering official.
Projects awarded through the ordering official may count toward fulfillment of the minimum guarantee amounts. If not, enough projects are processed under the minimum guaranteed task order as described elsewhere in this solicitation and resultant contract, then the Government reserves the right to use any or all project amounts processed through the Ordering Officer to count toward the fulfillment of the required minimum guarantee.
The ordering officials will administer and be the main POC for all orders placed under their authority. The names and contact information for these individuals will be included in the resultant contract.
b. The following describes the procedures to be used for ordering items under this contract by using the Federal Government-wide purchase card. This option to order by use of the Government-wide purchase card is strictly an alternative method of ordering by the Government and may be used in place of ordering by other order forms that comply with FAR 12.204. The Government reserves the right to unilaterally terminate the use of the credit card at any time.
(1) All ordering officers may use the Government-wide purchase card, commonly referred to as the
Government "credit card," as an alternative method of ordering and paying for purchases made under this contract. Purchase card orders are subject to all terms and conditions of this contract, unless otherwise stated in this provision or another provision in this contract.
(2) The purchase card is specifically designed for use by the Federal Government. The purchase card is like a typical commercial credit card. However, the authorization limitations of the purchase card are more specific, i.e., only for a particular contract, monthly limitations, certain categories of products or services, etc. The purchase card will be exclusively used for official Government purchases in accordance with the prices, terms, and conditions of this contract. The purchase card order limitation shall be $25,000. With respect to ordering authority, only designated Ordering Officers may use the purchase card as a means of purchasing items on this contract.
(3) Credit limits for the purchase card for ordering officers is $25,000. These credit limits for the purchase card are the responsibility of the credit card holder and the approving office.
(4) The Contractor shall accept payment via credit card for projects authorized by the ordering officers and that have followed the required policies and procedures within this solicitation and resultant contract.
(5) Invoices for orders placed by the ordering officer will be submitted directly to the ordering officer, and progress payments will still be authorized if applicable, the same as would be authorized for Task Order issued on the Form 1155.
(6) When using the purchase card as the payment method, the Contractor is required to generate a receiving report in Wide Area Work Flow (WAWF), and the Government acceptor is required to accept the receiving report in WAWF. These reports are mandatory to ensure compliance with the Prompt Payment Act requirements for written acceptance. Use of WAWF to create and accept receiving reports is mandatory when the GPC is used as a method of payment against a contract. To ensure proper routing of contract transactions paid with the GPC, use the code "CRCARD" in the Pay Official/ DoDAAC field. The Contractor is required to generate a receiving report in WAWF, and the Government acceptor is required to accept the receiving report in WAWF. The Cardholder is required to verify that acceptance has occurred in WAWF prior to submitting the invoice to the Certifying Official for certification.
7) PRICING/ COEFFICIENTS/UNIT PRICE BOOK (UPB)
a. The Contractor shall obtain at their own expense the most recent version (at time of award) of the approved estimating software with the latest version of the RS Means Facilities Construction and Facilities Maintenance & Repair Cost Data database (s), henceforth referred to as the Unit Price Book (UPB), for their use during this contract, in as many licensed copies as required for their operation of the contract.
b. Annual price adjustments for this contract shall be made in the following manner: Provide a new UPB every year on the anniversary date for the life of the contract. The Contractor shall update at their own expense the most current UPB catalog database (compatible with the previously supplied estimating software) for use during the applicable follow-on year, in as many copies as required for their operation of the contract. A separate equitable adjustment will not be allowed.
c. Bidders shall provide pre-Priced coefficients for the contract entirety on the TE-2 Coefficient Spreadsheet document. The spreadsheet will automatically calculate the weighted average, the Total Price and The Total Evaluated Price which will be the basis determining the apparent successful bidder. (See the Evaluation of Bids section for more information). Coefficients are location-specific multiplier(s), developed and proposed by the Contractor, to be applied against the published UPB cost line items for the purpose of providing consideration to the Contractor for the following in-direct costs: General and administrative and other overhead costs, insurance costs, bonding and alternative payment protection costs, protective clothing, equipment rental, and Contractor’s profit.
The Contractor's price coefficient must include, but is not limited to the following:
Contractor's overhead and profit (bare cost will be used in UPB) Subcontractors' overhead and profit Insurance All costs associated with bonding (specifically including bond premiums) Employee payroll taxes, insurance, and fringe benefits Business taxes, contributions, memberships, corporate Headquarters support (legal, financial, etc.)
All waste and excess material Sales tax on material and equipment costs Clean up.
Mobilization and close out for the total contract and each task order Compliance with environmental laws (overhead {indirect} costs associated with performing work in compliance with EPA/OSHA regulations, including obtaining any necessary licenses and permits, reporting requirements, etc.)
Compliance with protection and safety laws (i.e., safety rails, face, and clothing protection, etc.)
Traffic and work site signs and barriers Project management and supervision Protection of and/or moving of Government property Quality control Office management and equipment Depreciation of mobile office(s) Interest associated with funding of equipment and payroll.
Submittal preparation As built drawings.
Permits, licenses and fees.
Other risks of doing business (i.e., risk of a lower-than-expected contract dollar value; risk of a high inflation cost if factors are bid for option years, risk of poor subcontractor performance and reperformance)
UPB costs confidence (to include issues regarding how the cost data are captured and the size/types of projects they reflect)
Contingencies Travel Depreciation of equipment or facilities Variances in subcontractor or worker availability Other local market conditions for each site not addressed by RS MEANS Location Factors Other risks of doing business; acceptance testing; work-site security; etc.
Bidder must specify in their bid if there ___are or ___ are not additional types of costs included in their coefficients, other than those listed above. If there are additional costs, bidders must list them specifically as being included in their coefficients. The coefficient(s) proposed by the bidder and accepted by the Government will be incorporated into the JOC contract.
d. Bidders shall also provide an indirect costs and profit rate (Non-Pre-Priced Coefficient), to be applied to NPP work. This is required for each location, as with the Coefficients for Pre-Priced work, a yearly average will also be automatically calculated on TE-2.
e. Indirect Cost and Profit Rate is defined as all costs associated with performing the tasks, other than direct labor, equipment, and material costs. When a proposal is submitted at the task order level to include NPP work, proposals shall be supported with verifiable documentation supporting competitive quotes minimum of two), catalog price, etc., for all NPP work. NPP items shall be proposed in bare costs only (material, equipment, and labor) multiplied by the quantity and the NPP indirect costs and profit rate to arrive at the total price for the NPP work.
f. The Coefficient Spreadsheet (TE-2) will be incorporated into the resultant contract and utilized by the Government in determining the value of issued task orders throughout the life of the awarded contract. The value of Non-Pre-Priced work under an order must not exceed 10 percent of the value of the pre-Priced work unless approved by the contracting officer. In accordance with AFARS 5117.9004-2 (e), the Government has the unilateral right to withdraw a proposed task order either before or after receipt of the Contractor’s proposal. Typical task orders may include repair and maintenance of real property, repair and replacement of HVAC, water, and sewer systems, paving, roofing, interior and exterior painting, ceiling repairs or replacements, repair or replacement of floor coverings, renovations, refurbishments, civil works, and electrical repairs involving all the building crafts and trades.
8) BONDING/ BID GUARANTEE
a. The successful Bidder must provide a Performance and Payment bond, for the entire sum of the Task Order.
b. Bid guarantee should be based on JOC max of $10,000,000.00.
9) REQUIREMENTS/DELIVERABLES
Completed SF1442 with acknowledgement of all amendments.
Completed TE-2 Coefficient Spreadsheet.
Bid Guarantee.
Any additional verification/requested documents or information.
Appendix A Surety Acknowledgement of Coefficient
ATTACHMENTS
a. All referenced documents for this solicitation are available at the Government Point of Entry at https://sam.gov.
Potential bidders are encouraged to sign into SAM to follow this contract opportunity and to setup notifications to receive email updates from SAM when information has been posted to the website for this solicitation.
b. Attachments listed below will be incorporated into the resultant contract.
1. Technical Exhibits
Number Document Title TE-1 Statement of Work TE-2 Coefficient Spreadsheet_4.28.23 TE-3 AT-OPSEC Coversheet TE-4 Wage Determinations – will be provided 10 or more calendar days before the date of bid opening.
TE-5 SF 24
2. Appendices
Letter Document Title A Surety Acknowledgement of Coefficient
EVALUATION OF BIDS
BASIS OF AWARD
This requirement for the modernization, repair, restoration, and sustainment of facilities located at Fort Hunter Liggett, Camp Parks, and Moffett Field shall be awarded utilizing Sealed Bidding Procedures in accordance with Federal Acquisition Regulation (FAR) Part 14, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS), and the Army Federal Acquisition Regulation Supplement (AFARS). Award will be made with reasonable promptness to the responsible bidder submitting the lowest responsive bid in accordance with requirements and provisions herein.
The Government will evaluate proposed price coefficients for balanced and reasonable pricing, using price analysis techniques. Proposed prices evaluated as unreasonable or unbalanced may be ground for eliminating the bid from award eligibility.
EVALUATION CRITERIA
The Government will evaluate bids received in response to this solicitation solely based on price and price related factors. Award will be made to lowest coefficient.
a. TE-2 document will automatically calculate all other required figures utilizing the following formulas:
Weighted Average = (.95)(Average of all PP Coefficients*) + (.05)(Average of all NPP Indirect Cost)
Bidder's Total Price = (Weighted Average)
INSTRUCTIONS TO BIDDERS
BID PREPARATION INSTRUCTIONS
The following instructions prescribe the format for the bid and describe the approach for the development and presentation of bid data. These instructions are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of bids. In the sealed bidding procedures, the price alone will determine the “Apparent Low Bid;” however the submission of a low bid does not in and of itself determine responsibility of a bidder and therefore it is necessary to require additional information in order that the Contracting Officer may make an award based on the lowest overall priced responsible bidder.
ELECTRONIC SUBMISSION
Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/. Proposals submitted by mail or hand carried will not be evaluated. Proposals sent through proprietary or third-party File Transfer Protocol (FTP) sites or DoD SAFE will not be retrieved. It is the responsibility of the Bidder to confirm receipt of proposals. All proposals received after the exact time specified for receipt shall be treated as late submissions and will not be considered except under facts and circumstances allowed by the FAR. For instructions on how to post an offer, please refer to the Posting Offer demonstration: https://pieetraining.eb.mil/wbt/sol/Posting_Offer.pdf.
It is the Bidder’s responsibility to obtain written confirmation of receipt of all electronic files of the full proposal by emailing the Contract Specialist, MAJ Francisco J. Arocho at francisco.j.arocho.mil@army.mil. If the Solicitation Module is down, the alternate method for proposal submission is via email to the Contracting Officer and Contract Specialist identified in the preceding sentence. The Bidder must obtain prior approval from the Contracting Officer or Contract Specialist to use the alternate submission method. Bidder requests to use the alternate submission method must be received by the Contracting Officer or Contract Specialist no later than 36 hours prior to the proposal submission deadline.
Bidders are responsible for ensuring electronic copies are virus-free and shall run an anti-virus scan before submission. Electronic copies of each volume shall be compatible with Adobe Acrobat Reader 11. Narrative portions of the proposal shall be in Adobe Acrobat portable document file (pdf) searchable text format. The Bidder shall not embed sound or video (e.g., MPEG) files into the proposal files. Electronic files shall be clearly identified for each volume, section, and item.
FILE NAMING CONVENTION
To ensure your submission is received and processed appropriately, it is important that interested parties carefully ensure their electronic files adhere to the following naming convention:
W911SA23B2011-FIRM NAME-Bid W911SA23B2011-FIRM NAME-Amendments W911SA23B2011-FIRM NAME-Bid Bonds
FILE ORGANIZATION
Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger.
UPLOAD COMPLETION & DEADLINE
Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of bid receipt will be the upload completion / delivery time & date recorded within PIEE site. Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Bidders should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Bidders are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 14.304.
ELECTRONIC FILES
Files shall be in their native format (i.e., doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications.
Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked)
PUBLIC BID OPENINGS
The Public Bid Opening for this solicitation will be conducted via teleconference. To attend the Public Bid Opening teleconference, any interested party must submit an email request to the Contract Specialist francisco.j.arocho.mil@army.mil prior to the Bid Opening time to access the teleconference. The Contract Specialist will provide you the phone number and attendee passcode for attendance. Once the teleconference has begun, no access information will be distributed, and no information will be repeated for late attendees.
SYSTEM for AWARD MANAGEMENT (SAM) REGISTRATION
An Active SAM Registration is required of all Department of Defense contractors. SAM registration enables electronic funds transfer of contract payments. If your company is not already actively registered, please register in the SAM database at http://www.sam.gov. If your company is currently registered and close to expiring, begin/complete the process for SAM registration renewal.
a. The unique entity identifier used in SAM.gov has changed.
On April 4, 2022, the unique entity identifier used across the federal government changed from the DUNS Number to the Unique Entity ID (generated by SAM.gov).
The Unique Entity ID is a 12-character alphanumeric ID assigned to an entity by SAM.gov. As part of this transition, the DUNS Number has been removed from SAM.gov. Entity registration, searching, and data entry in SAM.gov now require use of the new Unique Entity ID. Existing registered entities can find their Unique Entity ID by following the steps here. New entities can get their Unique Entity ID at SAM.gov and, if required, complete an entity registration.
b. Whether your company is a current or new registrant in the SAM database, your registration must indicate that you are a provider of NAICS 236220 or a NAICS of similar business size, under the Goods – Services section of the registration to be eligible to receive a contract for this solicitation.
c. If the prospective awardee for this request for quotes is not actively registered in the SAM database by close of solicitation, including NAICS 236220, or a NAICS of similar business size, under the Goods – Services section, depending on mission requirements, the government reserves the right to proceed to award to the next otherwise successful actively registered offeror.
SAM REQUIREMENT
Prospective contractors who have not completed electronic annual representations and certifications at www.sam.gov in conjunction with required registration in the SYSTEM for AWARD MANAGEMENT (SAM) database, shall complete and submit 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2019) and 252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JUN 2019) in SAM to be eligible to receive an award for this solicitation.
In accordance with DPAP changes to reporting requirements under FAR 52.223-2, Affirmative Procurement of Biobased Products under Service and Construction Contracts, contractors are now required to submit annual bio-based reports to the new reporting module in the System for Award Management (SAM). SAM can be accessed at https://www.sam.gov.
WAGE DETERMINATIONS
As attached to this solicitation are applicable to this project. In accordance with FAR 22.404-10, the contractor must post a copy of the wage determination and Department of Labor Form WH-1321 in a prominent place where employees working on federal construction contracts can easily see it. The applicable wage determination is incorporated into the contract at Section H. The WH-1321 poster is located at http://www.dol.gov/compliance/guide/index.htm.
REAL ID ACT IMPLEMENTATION
Federal agencies, including the Department of Defense, are prohibited from recognizing driver’s licenses and identification cards that are deemed non-compliant according to the REAL ID Act. Due to the pandemic, its disruption of states abilities to issue the Real ID-compliant driver’s licenses DHS has extended the deadline. The U.S Department of Homeland Security (DHS) will begin enforcing the Real ID law on May 3, 2023.
In accordance with Army Directive 2014-05, all non-DOD ID cardholders must be escorted during their entire time at all Army installations or be vetted by the Physical Security Office for non-escorted access.
To obtain credentials for non-escorted access, the Physical Security Office will run a background check through the FBI National Crime Database. Once favorably vetted, individuals will be issued credentials allowing them access to Fort Hunter Liggett.
The credentials must be kept with the individual at all times.
Military sponsors of contractors can visit the Physical Security/ VCC from 8 a.m. to 3 p.m. Monday through Friday to expedite contractor credentialing. This process takes at least 10 minutes, so plan to arrive early. There can be a longer delay during high volume periods.
ALL access vetting forms are processed at the Visitor Center or the front gate.
Required documents:
Completed Access Vetting forms located at: https://home.army.mil/liggett/index.php/about/visitor-information.
Two forms of ID are required.
Acceptable forms of Identification include:
U.S. Passport or U.S. Passport Card PIV Federally issued PIV-I Cards Driver’s license issued by the U.S. Department of State Border Crossing Card (Form DSP-150) Department of Homeland Security “Trusted Traveler” Cards (Global Entry, NEXUS, SENTRI, FAST) U.S. Permanent Resident Card (Form I-551) U.S. Certificate of Naturalization or Certificate of Citizenship (Form N-550) Employment Authorization Document issued by Department of Homeland Security (Form I-766) U.S. Refugee Travel Document or other travel document of immigration status issued by DHS containing a photograph (Forms I-327 and I-571)
TWIC
Merchant Marine Card issued by DHS/USCG State-issued EDLs issued by: Michigan, Minnesota, New York, Vermont, Washington Native American Tribal Photo ID Foreign government-issued Passport PIV-I cards (issued by non-Federal Government entities) Veteran’s Health Identification Card issued by the U.S. Dept. of Veterans Affairs
(End of Summary of Changes)