September 2020 Building 1680 Replace Lighting in Sleeping Quarters
SPECIFICATIONS
FOR
BUILDING 1680
REPLACE LIGHTING
IN SLEEPING QUARTERS
PROJECT NAME: BUILDING 1680 REPLACE LIGHTING
IN SLEEPING QUARTERS, FORT MCCOY WI
PROJECT NUMBER: 47-018-1728
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
SECTION NUMBER SECTION TITLE
00 01 10 Table of Contents
DIVISION 1 - GENERAL REQUIREMENTS
01 10 10 General Requirements 01 12 10 Contract Considerations 01 33 00 Submittals 01 35 26 Special Safety Requirements 01 42 13 Industry Standard Abbreviations and Codes
DIVISION 26 - ELECTRICAL
26 05 00 Basic Electrical Requirements 26 05 19 Conductors and Cables 26 05 33 Conduits 26 05 34 Boxes and Enclosures 26 24 16 Panelboards 26 27 26 Wiring Devices 26 51 00 Interior and Exterior Lighting
END OF DOCUMENT
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 1
SECTION 01 10 10
GENERAL REQUIREMENTS
PART 1 GENERAL
1.01 SUMMARY OF THE WORK
A. GENERAL
1. Provide new luminaires, panelboard, circuit breakers, controls, devices, equipment, power and connected components at Building 1680 in the older sleeping quarters including demolition and proper disposal of existing luminaires in compliance with approved Specifications and Drawings, and as specified herein.
2. The 100% design Specifications and Drawings are provided by the Government and form part of the Contract documents. The Contractor must use the approved, 100% design, Government-provided, complete sets of Specifications and Drawings dated September 2020 for this project. The Contractor must not submit or use any other design specifications or drawings for this project. All references to Specifications and Drawings are equivalent to the approved, 100% design Specifications and Drawings provided by the Government.
3. Provide all work, labor, equipment and materials in compliance with federal, state, and local laws, regulations, statutes, codes, and ordnances.
4. Provide daily cleaning of construction areas including disposal of refuse and debris.
5. Provide storage and secure all materials, equipment, tools and items at the end of each work day as specified herein. Storage must be offsite unless the COR approves a request for on-site storage.
6. Provide all new products and items for installation as specified in the Specifications and as indicated on Drawings. All items for installation must be new. Do not re-use items identified for replacement including but not limited to panelboard, circuit breakers, luminaires, and controls.
7. Provide power from sources and panelboards as indicated on Drawings, and do not use any other panelboards for power to new and existing circuits.
8. Overcurrent protection devices may be referred to as circuit breakers or breakers.
Luminaires may be referred to as lighting or light fixtures. Panelboards may be referred to as panels. Faceplates may be referred to as cover plates.
9. Sleeping Quarters: Building 1680 (including all sleeping quarters) will be occupied during construction. Due to the shift and emergency work performed by building occupants, the sleeping quarters may be in use at any time of the day or night. All work in the sleeping quarters must be carefully coordinated through the COR and with building representatives for the health and safety of the occupants, and must be coordinated to minimize disruptions to both occupant schedules and duty operations. Provide phasing of work to minimize disruptions to building occupants.
10. Do not modify the existing fire alarm systems including all connected devices, fixtures, equipment and connected components.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 2
B. REMOVAL WORK:
1. Provide demolition, complete removal, and proper disposal of all items identified for removal or replacement including but not limited to Panel A (located in Corridor 134), luminaires, controls, equipment, and connected components as indicated on Drawings and in compliance with Specifications.
C. NEW WORK: Contractor must provide all work, labor, equipment, materials, tools, transportation, coordination, and supervision for this project including new luminaires, panelboards, circuit breakers, devices, controls, conductors, conduits, equipment, appurtenances and connected components, terminations and connections, testing and verification, documentation, and related incidental work, and perform all work under this contract for complete, useable systems in compliance with Specifications and Drawings, and as specified herein.
1. Provide new luminaires including emergency lighting, light sources, drivers, controls, devices, and power (refer to Drawings for light fixture schedule, (luminaires), lighting plan, physical locations, power and circuiting details).
a. Re-use conduits and conductors for existing lighting circuits where luminaires are identified for replacement unless otherwise indicated on Drawings.
b. Provide new power for all new luminaires including circuit breakers, conductors, conduits, controls, and connected equipment and components.
c. Provide transfer devices (internal and external) and circuiting for all luminaires designated for emergency lighting as indicated on Drawings.
d. Provide new, fully dimmable rocker type light switches in each sleeping room for lighting control as indicated on Drawings. Re-use existing wall boxes for new dimmable switches. Provide metal type wall cover plates and dark brown dimmable switches to match existing materials and finishes in older sleeping quarters, and as indicated on Drawings. Do not use finishes and materials from other areas of the facility.
e. Power for all new circuits must originate from Panel A (located in Corridor 134). All new and existing branch circuits listed on the Panel A Directory must be fed from Panel A (refer to Drawing E1.3 for directory).
2. Provide a new 100 Amp, 42 circuit panelboard (referred to as Panel A) including but not limited to the following requirements:
a. Electrical Characteristics: 100 Amp capacity; copper bus; main lugs only;
208Y120V (refer to Panel A Directory on Drawing E1.3).
b. Power: Re-use existing feeder conductors and conduit to provide power to new Panel A.
c. Mount: Flush mounted including adequate means of support (interior and exterior). Enclosure must overlap the exterior wall surface and completely cover the entire opening. Provide enlargement of existing wall opening to accommodate the new panel.
d. Provide arc flash risk assessment and arc flash label.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 3
e. Provide permanent, phenolic type nameplate for panelboard (use “Panel A” for the panel name designation), and provide permanent type circuit breaker labels for all spaces including new and existing circuits.
f. Provide new, typewritten Panel A directory including complete circuit descriptions for all new and existing branch circuits. Descriptions on the panel directory must include the physical location and purpose of each branch circuit (use the Panel A Directory on Drawing E1.3). Use the room numbers as shown on the Panel A Directory and as indicated on Drawing E1.2 (lighting plan). Do not use any other room numbers.
(1) For all new and existing branch circuits fed from Panel A, provide circuit breaker control and functionality checks to verify proper operation, to verify the physical location of each branch circuit, and verify each circuit breaker number. Verify accuracy of new panel directory.
g. Circuit Breakers:
(1) Provide a new, separate circuit breaker and branch circuit for each new lighting circuit.
(2) Provide a new, separate circuit breaker control of power in each sleeping room (receptacles and exhaust fan in each sleeping room must be fed from a separate circuit breaker). Do not feed multiple branch circuits from the same circuit breaker, and do not combine the new lighting circuits on power circuits.
(3) Provide a new, separate circuit breaker and branch circuit for each existing appliance located in Room 135 Lounge (refer to Panel A Directory on Drawing E1.3 for description of existing appliances).
D. REPAIR WORK: Contractor shall provide all tools, labor, equipment, materials, transportation, and supervision necessary to perform repairs and restoration or replacement work under this contract including but not limited to:
1. Provide repairs of ceilings, walls and surfaces to match existing materials and finishes, and provide appropriate firestop at penetrations. Provide repair using matching materials for all openings or gaps larger than ¼” width. Eliminate gaps around wall boxes and enclosure openings using matching materials and finishes.
2. Replace all damaged ceiling tiles in areas of work at Contractor’s expense.
3. Repair any existing surfaces, equipment, utilities, structures, and features disturbed, damaged or altered during any phase of work to match existing materials and finishes, utilities, structures and features.
4. Repair landscaping features damaged or altered during any phase of work to match existing landscaping features including plants, grass, lawns, flowers, trees, and shrubs.
5. Repair vehicle ruts. Level the ruts, place topsoil, and seed the disturbed areas in compliance with Specifications.
6. Repair and reinstall structures designated for temporary removal during the work including survey monuments, bench marks, reference points, and improvements.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 4
7. Provide repair and restoration to original condition or replacement as determined by the KO for any damage that occurs during any phase of work in compliance with requirements as specified herein and at Contractor’s expense.
E. TEMPORARY RELOCATION: Building 1680 Fire Station personnel will provide removal and/or temporary relocation of existing moveable personal property and equipment as necessary for the completion of work. Fixed, permanently installed items must remain in place.
F. PROTECTION
1. Interior and Exterior Protection: Provide protection of existing buildings, structures, utilities, improvements, vegetation and property during all phases of work in compliance with Specifications.
a. Provide safety and protection measures in all areas of work in compliance with safety requirements as specified herein including safeguarding against injury and to prevent damage to existing buildings, structures, utilities, improvements, vegetation, and property.
b. During all phases of work, provide protection against damage as specified herein including but not limited to all of the following:
(1) Buildings and all types of property.
(2) Structures (all types including survey monuments, bench marks, and reference points).
(3) Utilities (all types of utilities, both above ground and underground).
(4) Improvements (all types including fencing, sidewalks, paved areas, roads and curbs).
(5) Vegetation (all types including landscaping, plants, grass, lawns, flowers, trees, and shrubs).
c. Damage may include unnecessary cutting, breaking, bruising, or smothering by equipment or parking of vehicles.
d. Provide protective measures including barriers, signage, coverings, temporary fencing, or other similar types of protection to protect the health and safety of building occupants in compliance with protection and safety requirements.
G. SUBMITTALS. Provide submittals in compliance with Section 01 33 00 including Part 4 Schedule of Material Submittals and in compliance with Specifications.
H. EXISTING SITE CONDITIONS. Drawings do not reflect all site conditions, and site conditions may have changed after drawings were drafted. Prior to the ordering of equipment and materials and prior to the start of construction, the Contractor must verify all existing site conditions including but not limited to the following: interior dimensions of facility areas indicated for the installation of equipment and materials; dimensions of products for installation; dimensions and measurements for code required clearances;
dimensions and measurements for equipment pads, conduit, piping, and materials; power and controls (routing as indicated on Drawings), and utility service entrance locations and locates.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 5
1.02 FACILITIES
A. The entire Fire Station complex including Building 1680 will be occupied during construction.
B. Access: The Contractor and all subcontractors must coordinate access through the DPW COR and through the Fire Station facility representative.
1.03 ABBREVIATIONS
A. “KO” = Contracting Officer.
B. “COR” = Contracting Officer’s Representative.
C. Industry Standard Abbreviations: Refer to Specification Section 01 42 13.
1.04 TEMPORARY UTILITIES AND FACILITIES
A. General: The Contractor must provide temporary utilities and temporary construction facilities unless stated otherwise herein.
B. Power: There is 120VAC, 60 Hz electricity and lighting currently in the building(s) and available for use. Contractor must provide means of extending power from an existing source to desired point of use. This electricity used will be provided by the Government at no cost to the Contractor.
1. For all power outages and any power requirements beyond the available supply, the Contractor must provide temporary power using an appropriately sized portable generator system or a temporary power pole, and maintain power for the duration of each outage and as required for the completion of work. The Contractor is responsible for the cost of the temporary power including generator and fuel and/or temporary power pole. If the Contractor provides a temporary power pole, the cost of electricity will be provided by the Government at no cost to the Contractor. The Contractor shall contact Xcel Energy for temporary power.
C. Temporary Heating, Cooling, and Ventilation: Not required for this project.
D. Temporary Telephone Service
1. If the Contractor requires phone service for this project, the Contractor must contact the phone company business office:
Century Telephone 205 5th Avenue LaCrosse, Wisconsin 54601
(800) 872-4017
2. The Contractor shall pay for all telephone installation, maintenance, removal, and usage charges.
3. The Contractor is responsible for providing and paying for any and all subcontractor’s telephone usage and calls.
4. Existing telephones owned or rented by the Government will not be used by the Contractor under any circumstances.
E. Temporary Water
1. Contractor shall provide an electronic written request for temporary water supply to Fort McCoy DPW (Directorate of Public Works).
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 6
2. Water for construction purposes will be furnished by the Government and will be available from an existing water connection in areas where work is scheduled to be performed. Capacity is estimated to be not less than 10 GPM at 45 psi. Water is city water quality and contains sodium hypochlorite.
3. The Contractor shall provide anti-siphon and backflow prevention devices on all temporary water connections at Contractor’s expense. Proof of certification is required.
4. Contractor shall not cause water to be wasted or left running when not in use.
Contractor shall repair leaks immediately. Freeze protection shall be provided by the Contractor at all times when freezing is possible.
F. Temporary Sanitary Facilities
1. Existing sanitary facilities in Government buildings shall not be used by the Contractor’s personnel.
2. The Contractor shall be responsible for providing temporary toilet and sanitary facilities at Contractor’s expense. The Contractor shall pay rental fees and cleaning charges, and shall remove the facilities promptly when the project is completed.
3. The COR or Construction Inspector shall approve the site location for all temporary sanitary facilities.
4. Contractor shall maintain all such temporary sanitary facilities in a clean and sanitary condition at all times.
G. Barriers and Fences
1. Contractor shall provide, install, maintain, and remove suitable barriers to prevent public entry and to protect the work site.
2. Such barriers shall be erected to provide a safety barrier around such portions of the project that could cause injury or destruction of property and to provide general security for the affected project site.
3. Materials to be used are at the Contractor’s option and expense.
4. Barriers and fence shall be posted with appropriate warning signs. Place warning signs at the construction area perimeter designating the presence of construction hazards requiring unauthorized persons to keep out. Signs must be placed on all sides of the project, with at least one sign every 300 feet. All points of entry shall have signs designating the construction site as a hard hat area.
5. Fencing shall be provided along the construction site at all open excavations and tunnels to control access by unauthorized people. Fencing must be installed to restrain a lateral force of at least 200 pounds.
H. Security
1. The Contractor shall provide all materials, labor, and equipment to protect the project site from theft and vandalism.
2. Existing Government buildings and facilities shall be protected by the Contractor during the contract when the work involves openings into existing Government buildings. The degree of protection shall not be less than what currently exists.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 7
3. The Contractor shall provide temporary doors, locks, and barricades to prevent unauthorized access to the construction site and existing buildings.
4. Storage of all types of equipment, tools, construction materials, and personal property is at the risk of the Contractor.
I. Access Roads and Parking Areas
1. Contractor’s private vehicles shall be parked at locations designated by the COR.
2. All construction vehicles and Contractor’s private vehicles will be parked in an orderly manner at all times and will not block normal traffic in the area. Private vehicles belonging to the contract personnel will be parked in designated parking areas and in no case on grass areas, adjacent to buildings, or along streets.
3. Contractor is responsible for any snow removal required for access or site work.
J. Access and General Protection/Security Policy and Procedures
1. The Contractor and all associated subcontractors and subcontractor’s employees shall provide all information required for background checks to comply with installation access requirements to be accomplished by Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. The contractor and all associated subcontractors' employees shall also comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The Government may require monthly participation in the Installation Random Antiterrorism Program.
K. Contractors Requiring Common Access Card (CAC)
1. Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05. The contractor employee will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an initial CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI.
L. Traffic Work
1. All work around or involving roadways including roadway excavations and utility crossings will be conducted in accordance with the Manual on Uniform Traffic Control Devices (MUTCD) – FHWA, Latest Edition.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 8
2. The Contractor shall provide road closure, coordination, signage, and traffic management in compliance with Fort McCoy requirements.
a. The Contractor shall provide a road closure plan for each road closure which depicts the location of the road closure and signage locations.
b. For all road closures, provide an advance written notification (electronic and hard copy) to the Contracting Officer a minimum of twenty (20) calendar days prior to the start of the proposed road closure.
c. Advance written notification shall include the start and end dates for each road closure; purpose of each road closure; a list of all traffic management measure to be implemented for each road closure; full name of superintendent on-site with complete contact information, and alternate point of contact in case of emergency.
d. The Contractor shall provide a road closure plan for each road closure with an advance written notification, and the road closure plan shall include the location of each road closure and locations of signage.
e. The Contractor shall not close any road without prior written authorization from the Contracting Officer.
f. The Contractor shall provide coordination prior to each road closure through the Contracting Officer and Fort McCoy DPW.
g. The Contractor shall provide road closure signage including detour signage as necessary for traffic management, and comply with Fort McCoy safety and traffic requirements.
M. Waste Reporting
1. The Army has established the requirement for a 50% minimum diversion rate by weight of C&D waste from landfill disposal. In order to achieve those results, the Contractor shall submit a solid waste management plan as a required submittal for projects costing over $100,000. At a minimum, the solid waste plan shall include the anticipated waste streams and disposal/recycling facilities. No work shall begin until the Contractor has an approved plan.
2. The Contractor shall submit reports to the Contracting Officer quantifying the total pounds of hazardous, universal, recycled, and non-regulated waste disposed of during the duration of the contract. Contractor shall also submit material(s) disposal location(s).
3. Reporting shall be specific to the month in which waste was disposed of and separated per waste type for Fort McCoy’s reporting requirements.
4. Reporting for recycled waste shall also be specific to how much revenue the Contractor received for each type of recycled material.
N. Refuse Disposal and Recycling
1. Provide all solid waste disposal associated with this contract including but not limited to the container delivery, removal, and disposal fees. Items included under this Section are all solid wastes as defined by Wisconsin State Statute 289.01 (33).
These items shall be disposed in a licensed sanitary landfill or recycling center in compliance with State of Wisconsin Administrative Code Chapter NR500 series.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 9
2. The Contractor is allowed to use Fort McCoy recycling facilities for concrete, mixed paper, plastics (PETE#1 and HDPE#2), cardboard, trees/woody waste, metals, and aluminum cans. If materials are recycled at Fort McCoy, provide all labor and delivery to the designated recycling facilities. Materials shall be weighed and weigh slips provided to the COR to receive credit toward the 50% requirement in “Waste Reporting” above. Materials not weighed can be delivered to the designated recycling facilities, but the material will not count toward the 50% waste reporting requirement.
3. Provide for the recycling of all other construction/demolition debris including drywall, lumber, reinforcing steel, piping, wiring, brick, plaster, wall board, roofing material, insulation, plumbing fixtures, doors, and windows to the greatest extent possible. Utilize only licensed recycling facilities.
4. Provide a certificate of recycling for universal waste as defined in Wisconsin Administrative Code Chapter NR600.
N. Material Sales
1. Materials shall not be stockpiled for sale purposes on Post.
2. Public advertised sales of materials will not be permitted on Post.
3. Prior arranged sale of materials may be permitted on Post.
1.05 QUALITY CONTROL
A. The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with the Contract Clause titled “Inspection of Construction.” The Contractor must provide a Contractor Quality Control (CQC) Plan to cover all design and construction operations (both onsite and offsite) and to comply with requirements as specified herein as a minimum including work by subcontractors, fabricators, and suppliers, and key the CQC plan to the proposed construction sequence.
The CQC plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. The site project superintendent is responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract.
B. All electrical work and electrical apprentices shall be supervised full time on site and at all times during the work by a state certified journeyman electrician. Electrical apprentices shall be in a recognized electrical apprenticeship training program. All electrical work shall be overseen by a state certified Master electrician. Proof of current state certification is required prior to the start of construction. The cost of the work shall include all State permit fees and approval for the installation of electrical equipment and devices.
C. Submit product data prior to ordering products and prior to the start of construction.
Obtain approval of all items for installation prior to the start of construction. Provide product data submittals for all products indicated or specified for installation. Product data includes shop drawings, manufacturer warranty, certifications, and documentation.
Refer to Specification Section 01 33 00 Submittals.
1.06 REFERENCED DOCUMENTS
A. References are made in these Specifications to published laws, codes, standards, regulations, ordnances, and specifications, and to manufacturers’ societies, associations, and other standards. All references are included in these Specifications as if written in their entirety.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 10
B. Where referenced documents are not specified by date, the most recent edition published as of the bid or proposal request date shall apply. UFC design guides set a minimum requirement for each standard that may be exceeded by a more recent standard as referenced in specification sections.
C. UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings.
1.07 MANUFACTURER’S PUBLISHED DATA AND MANUALS
A. Provide all product data documentation in compliance with each specification for the specific item of equipment and Section 01 33 00 Submittals.
B. Provide one (1) PDF copy of each type of product data documentation for all items of equipment including complete catalog ordering nomenclature sheet, instructions and checklists, shop drawings, and manuals.
C. Provide one (1) PDF copy of equipment maintenance and operation manuals for all new equipment including CT cabinet, meter socket, main distribution panel, safety disconnect switches, and devices.
D. Drawings:
1. Shop drawings including equipment dimensions, materials and schematics.
2. Supplement product data with drawings as necessary to clearly illustrate:
a. Relations of component parts of equipment and systems.
b. Control and flow diagrams.
3. Coordinate drawings with the information in project record documents to assure correct illustration of completed installation.
E. Written text, as required to supplement product data for the particular installation:
1. Organize in consistent format under separate headings for different procedures.
2. Provide logical sequence of instructions for each procedure.
F. Content, for each unit of equipment and system, as appropriate:
1. Description of unit and component parts;
a. Function, normal operating characteristics, and limiting conditions.
b. Performance curves, engineering data, and test results.
c. Complete nomenclature and commercial number of replaceable parts.
2. Operating procedures;
a. Start-up, break-in, routine, and normal operating instructions.
b. Regulation, control, stopping, shut-down, and emergency instructions.
c. Summer and winter operating instructions.
d. Special operating instructions.
3. Maintenance procedures;
a. Routine operations.
b. Guide to “Trouble-Shooting.”
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 11
c. Disassemble, repair, and reassemble.
d. Alignment, adjusting, and checking.
4. Servicing and lubrication schedule including a list of required lubricants.
5. Manufacturer’s printed operating and maintenance instructions.
6. Description of sequence of operations by control manufacturer.
7. Original manufacturer’s parts list, illustrations, assembly drawings, and diagrams required for maintenance:
a. Predicted life of parts subject to wear.
b. Items recommended to be stocked as spare parts.
8. As-installed control diagrams by controls manufacturer.
9. Each Contractor’s coordination drawings:
a. As-installed color coded piping diagrams.
b. As-installed color coded electrical and systems diagrams.
10. Charts of valve tag numbers, with location and function of each valve.
11. List of manufacturer’s spare parts, manufacturer’s current prices, and recommended quantities to be maintained in storage.
12. Other data as required under pertinent sections of specifications.
G. Provide and prepare additional data upon request of the KO or COR as needed for the training of Government or maintenance personnel.
1.08 DELIVERY AND STORAGE
A. Contractor must ensure that all equipment, materials, and items for installation are stored in an environment that will not cause rusting, warping, staining, or any type of damage or physical breakage.
B. All labor and equipment required for loading, unloading, transporting, and moving materials shall be provided by the Contractor.
C. Storage buildings will not be provided by the Government.
D. If onsite storage is required, the Contractor must submit a written request to the COR for a designated storage area at or near the facility. The Contractor is not authorized to use any other area outside of the designated storage area as directed by the COR for the storage of materials, equipment, tools, and other items. The Contractor, and all contractor and subcontractor employees, are responsible to secure all types of personal property, materials, equipment, tools and items at all times.
1.09 TRAILERS OR STORAGE BUILDINGS, INCLUDING OFFICE TRAILERS
A. Trailers or storage buildings will be permitted, where space is available, subject to the approval of the COR. All costs for trailers or storage buildings including loading, unloading, installation, delivery, removal and transportation are the Contractor’s responsibility.
B. The trailers or buildings shall be in good condition, free from visible damage, rust, and deterioration, and comply with all applicable safety requirements. Trailers shall be roadworthy and comply with all appropriate State and local vehicle requirements. Failure
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 12 to maintain storage trailers or buildings to these standards shall result in the removal of non-complying units at the Contractor's expense.
C. A sign not smaller than 2-feet by 2-feet shall be conspicuously placed on the trailer depicting the company name, business phone number, and emergency phone number.
D. Trailers shall be anchored to resist high winds and must comply with applicable state and local standards for anchoring mobile trailers.
E. Provide metal or fiberglass skirting completely around office trailers within thirty (30) calendar days of trailer installation on the lot and after receipt of approval from the COR.
F. Grass and weeds shall be cut weekly or as needed to a height not to exceed three inches.
Trash shall be picked up and disposed of properly on a daily basis.
G. The Contractor shall be responsible for the installation and removal of all temporary utility connections at no cost to the Government.
1.10 STORAGE SITE
A. All stored materials must be stacked or arranged to protect against damage in compliance with manufacturer’s published data and recommendations. Storage equipment and materials must be neatly stacked at all times.
B. Trash shall be picked up and properly disposed of on a daily basis.
C. Grass and weeds shall be cut on a regular basis to a height not to exceed three inches. In the Cantonment, uncut height shall not exceed 6 inches. Outside the Cantonment, uncut height shall not exceed 12 inches.
D. Welding equipment shall be handled and stored in compliance with applicable regulations.
E. Fire extinguishers shall be provided where flammable liquids are stored.
1.11 SCHEDULING AND COORDINATING WORK
A. Contractor shall submit the proposed construction schedule in compliance with the FAR clause entitled Schedule for Construction Contracts and in compliance with Specification Section 01 33 00 Submittals. Attached to the construction schedule shall be a horizontal bar chart with a separate line for each major portion of work, identifying the first work day of each week. Distribute copies of the approved schedule to the project site file, subcontractors, suppliers, and other concerned parties.
1. The Contractor shall prepare and submit a project schedule in the form of a Gantt Chart for review within twenty (20) calendar days of award and prior to a Pre-construction Conference (pre-con) if a pre-con meeting is held. This schedule shall show at a minimum critical path, float, owner of float, milestones, baseline, elements of work, and duration of each significant element of work. The Contractor shall obtain approval for the project schedule prior to the start of construction.
2. The Contractor shall maintain the original schedule/Gantt Chart throughout the life of the project and show actual schedule achievement in tandem with the original schedule and shall update the approved schedule bi-weekly to display time gained or lost against the original schedule. If in the opinion of the Contracting Officer the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve progress, including those steps that may be required by the Contracting Officer, without additional cost to the Government. The Contracting Officer may require the Contractor to increase the number of shifts, overtime
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 13 operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved increased effort shall regain the original schedule of progress. FAR 52.236-15
B. The Contractor shall be specifically responsible for the coordination of all phases of work under this contract within the approved construction schedule. The Contractor must phase the work to minimize disruptions to normal duty operations and to prioritize the new service entrance.
C. The Contractor may be required to allow Government personnel or other Contractors to carry out work within the work site. Such work will be scheduled and coordinated through the COR.
D. The Contractor shall provide a phone number and address where a key, and/or approval, to enter may be obtained for the work sites during the work day for times when the Contractor may not be at the work site.
E. Outages: Unscheduled outages are not authorized. Scheduled outages shall be shown on the schedule provided. Emergency utility outages shall be reviewed by the Contracting Officer/Inspector prior to the start of the utility outage. Expenses and damages caused by unscheduled or unapproved utility outages shall be at Contractor's expense.
1. For all outages, provide an advance written notification (electronic and hard copy) to the KO a minimum of ten (10) calendar days prior to the start of the proposed outage. Written notification must include the date of each proposed outage; type and purpose of each outage; a list of all impacted systems during the outage; full name of on-site outage supervisor with contact information, and the estimated duration of outage.
2. The Contractor shall provide advance coordination for all outages with Fort McCoy DPW and all impacted utilities in compliance with Specifications and as specified herein.
1.12 WARRANTIES
A. All new electrical service entrance equipment, panelboards, and safety disconnect switches must include a manufacturer warranty of not less than five (5) years.
B. All materials and workmanship shall be warranted by the Contractor for a period of not less than one year from the date of final acceptance by the Government, except when longer warranties are required from the Contractor as stated in each specification section.
C. For products and materials that are normally warranted by the manufacturer or supplier for more than one year, the Contractor shall provide the Government with a written warranty, or certification, indicating the Manufacturer’s or the supplier’s warranty terms and conditions.
D. The Contractor shall populate and submit a Warranty Item Tracking spreadsheet for materials and workmanship cover under Paragraph 1.12 A. The Contractor shall use PART 4 WARRANTY ITEM TRACKING SHEET located at the end of this Section as a template to prepare and populate the warranty item tracking spreadsheet submittal. The spreadsheet shall include all major equipment units and products for installation and project work, and each equipment product provided with an extended warranty equipment. Extended warranty shall be defined as anything beyond one calendar year from the Beneficial Occupancy Date. Item information will include the following: warranty item, equipment description, make, model, serial number, capacity, capacity unit of measure, warranty start
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 14 date, warranty length, scheduled maintenance to maintain warranty, and warranty requirements.
1.13 CONTRACT SUPERINTENDANT
A. Per FAR 52.236-6, at all times during the performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Contracting Officer, has authority to act for the Contractor, and shall be on-site during any activity being performed on the work site.
1. The Contractor shall provide written designation of a qualified person as the Superintendent five (5) working days before the Preconstruction Meeting.
2. The Contractor shall provide documentation demonstrating the experience and ability of the Contractor's Superintendent submission to successfully manage a contract with a value from between $500,000 to $1,000,000 and of scope similar in complexity to this project. Selectee shall have no less than five years of successful experience in direct supervision of major construction for a General Contractor.
3. The Government reserves the right to reject the Contractor's selection of Superintendent based upon that selectee's qualifications and level, type, depth, scope, or length of experience.
PART 2 PRODUCTS
2.01 EXISTING EQUIPMENT AND MATERIALS
A. Equipment and materials to be demolished:
1. All equipment units, materials, devices, appurtenances and components identified for demolition, removal, or replacement from existing facilities and areas shall be the responsibility of the Contractor to remove completely from Fort McCoy.
2. Under limited conditions and as specified on the plans, deliver scrap metal/materials to a location designated by the COR. Contractor will be responsible for hauling all demolished materials to the designated locations.
B. All items indicated or specified for demolition and proper disposal must not be reused including all luminaires, circuit breakers, devices, appurtenances, and segments of existing wiring identified for removal.
2.02 NEW EQUIPMENT, POWER, APPURTENANCES, AND MATERIALS
A. All new electrical equipment including but not limited to panelboards, luminaires, enclosures, devices, switches, circuit breakers, appurtenances, conduits, cables, conductors, and materials must be the standard products of a manufacturer regularly engaged in the manufacture of those products and all products for installation must comply with requirements of Specifications. Each product for installation must have a minimum history of five years of dependable and satisfactory use.
B. All new electrical equipment including but not limited to panelboards, luminaires, devices, switches, circuit breakers, appurtenances, conduits, cables, conductors, and materials shall be of the latest type or model currently being produced by the manufacturer.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 15
C. All products of the same type shall be from the same manufacturer. All circuit breakers shall be from the same manufacturer as the panelboard. All dimmable lighting switches must be certified as fully compatible with each type of luminaire by the manufacturer.
D. Seconds, refurbished, or otherwise substandard equipment, panelboards, switches, structures, conduits, cables, conductors, appurtenances, materials, devices and components are prohibited on Fort McCoy and are not authorized for installation. Equipment units not manufactured within one year of the contract award date are not authorized for installation.
E. For all new luminaires, provide manufacturer catalog order sheet with complete nomenclature for Government review of product data submittal.
F. Where applicable, proposed items for installation including electrical equipment and luminaires shall be eligible for energy efficiency incentives available through Wisconsin's Focus on Energy program. Provide electrical equipment and luminaires to comply with all Focus on Energy requirements for incentives. Proposals shall include the appropriate corresponding incentive codes, model numbers and cut sheets for each proposed lighting component. Further information concerning Focus on Energy's requirements can be found in their lighting catalog which can be found on-line at https://focusonenergy.com .
G. For additional submittal requirements, refer to Specifications including but not limited to Section 01 33 00.
PART 3 EXECUTION
3.01 INSPECTION
A. The Contractor shall not begin successive phases of work until an inspection has been completed and the work is accepted by the COR. Notify the COR forty eight (48) hours prior to completing a phase requiring inspection.
1. Any work that will be covered by successive work must be inspected prior to performing successive work.
2. Work to be covered includes, but is not limited to, underground utilities, utilities located behind walls, and work located below finish floors.
B. When the Contractor considers the work complete, submit written certification confirming:
1. Contract documents have been reviewed.
2. All project submittals have been completed and submitted for review including construction redlines properly completed on asbuilt drawings.
3. Work has been inspected by the Contractor for compliance with the contract.
4. Equipment and systems have been tested, balanced, and adjusted for proper operations.
5. Work is complete and ready for final inspection.
6. Contractor shall provide a requested date for punch list inspection to the Contracting Officer, in writing, not less than seven (7) working days prior to the proposed date of inspection. Punch list inspections shall be scheduled and conducted to ensure compliance with the contract completion date.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 16
C. The COR will coordinate with the members of the inspection party and establish the punch list inspection date.
1. Should the COR consider the work incomplete or defective, a written punch list of deficiencies will be provided to the Contractor from the Contracting Officer.
2. The Contractor will be given ten calendar days to remedy all deficiencies and complete corrective actions, unless otherwise determined by the Contracting Officer.
3. The Contractor shall provide a second written certification after remedy of all deficiencies is complete and request re-inspection to be scheduled not later than the ten (10) calendar days from the date of certification, unless otherwise determined by the Contracting Officer. This re-inspection shall also be completed during the contract performance period to be in compliance with the Contract.
4. If any further re-inspections are required the Contractor may be charged the additional cost of the inspections.
5. Final acceptance of the work occurs upon the Contracting Officer’s acceptance of the work subsequent to successful final inspection by the COR and receipt of all contract requirements.
6. If final acceptance does not occur prior to the contract completion date, liquidated damages may be applicable in compliance with the liquidated damaged clause.
D. If the Government requires beneficial occupancy of the facility prior to completion of the work by the Contractor, an inspection shall be conducted by the COR to determine whether or not the completed work complies with requirements, to document all deficiencies and any work that is not complete, and to accept completed work that complies with all requirements without any deficiencies. The Contractor will then complete the remaining work and correct all deficiencies.
3.02 TRANSITIONS FROM EXISTING TO NEW WORK
A. When new work abuts or finishes flush with existing work, make a smooth transition.
Patched work shall match existing adjacent work in texture and appearance including finishes and materials.
B. When finished surfaces are cut in such a way that a smooth transition with new work is not possible, terminate existing surface along a straight line at a natural line of division and provide trim appropriate to the finished surface.
3.03 TESTING AND VERIFICATION
A. Provide all types of inspections, tests, verifications, documentation, and submittals as specified herein and in compliance with Specifications.
B. After all installations of new electrical equipment are completed, the Contractor shall provide and conduct pre-start up visual inspections, functionality and operating tests, and verifications in compliance with Specifications and as specified herein.
C. Tests must demonstrate that the installation, performance, operation, and other testing requirements of Specifications have been met. Tests shall be performed in the presence of the COR.
D. Contractor must provide all work in compliance with the manufacturer’ published data and instructions including pre-operation checks, startup checklist and procedures, inspections, operational checks, and verifications.
September 2020 Building 1680 Replace Lighting in Sleeping Quarters 01 10 10 - 17
E. Provide submittals of all test results with test data.
3.04 ENVIRONMENTAL CONSIDERATIONS
A. Provide removal and proper disposal of all hazardous waste encountered during the work in compliance with local, state and federal laws, statutes and regulations.
3.05 HOT WORK PERMIT
A. Hot work permits are required for all work activities which generate or have the potential to generate heat, sparks, or open flames such as abrasive blasting, burning, brazing, cutting, grinding, powder-actuated tools, hot riveting, soldering, thawing, activities, welding, or any similar operations capable of initiating fires or explosions.
B. The Contractor must obtain a hot work permits prior to performing any of the activities described in Paragraph 3.06 A. Hot work permits may be obtained from the Fire Department in Building 1680. The non-emergency telephone number is 608-388-4151.
C. The Contractor must provide a copy of all hot work permits in compliance with Section 01 33 00.
3.06 CLEANING
A. During Construction:
1. The Contractor shall keep work areas clean at all times, and shall provide daily cleaning to keep work areas clean and free from accumulations of refuse and waste materials. The Contractor shall ensure all affected areas are “broom clean” at the end of each work day. Before completing the work, the Contractor shall remove from the work and premises, any rubbish, tools, scaffolding, equipment, and materials that are not the property of the government. Upon completing the work, the Contractor shall leave the work area in a fully cleaned, neat, and orderly condition, satisfactory to the Contracting Officer. FAR 52.236-12
B. Dust Control
1. Clean interior spaces prior to the start of finish coatings and continue cleaning on an as-needed basis until work is finished.
2. The amount of dust resulting from excavation operations or demolition work shall be controlled to prevent the spread of dust and to avoid creation of a nuisance in the surrounding areas.